EP2585747A2 - Enveloppe magnétique appliquée de régulation d'écoulement - Google Patents

Enveloppe magnétique appliquée de régulation d'écoulement

Info

Publication number
EP2585747A2
EP2585747A2 EP11798886.5A EP11798886A EP2585747A2 EP 2585747 A2 EP2585747 A2 EP 2585747A2 EP 11798886 A EP11798886 A EP 11798886A EP 2585747 A2 EP2585747 A2 EP 2585747A2
Authority
EP
European Patent Office
Prior art keywords
flow
bridging
control method
materials
flow control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP11798886.5A
Other languages
German (de)
English (en)
Inventor
Douglas C. Cabot
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Greenward Co LLC
Original Assignee
Greenward Co LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Greenward Co LLC filed Critical Greenward Co LLC
Publication of EP2585747A2 publication Critical patent/EP2585747A2/fr
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/10Means for stopping flow from or in pipes or hoses
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • E21B33/06Blow-out preventers, i.e. apparatus closing around a drill pipe, e.g. annular blow-out preventers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/10Means for stopping flow from or in pipes or hoses
    • F16L55/1003Means for stopping flow from or in pipes or hoses by introduction of paste, powder, particles, or the like

Definitions

  • This invention relates to the field of controlling fluid flow and more specifically to the field of reducing fluid flow through a flow system such as a pipe or blowout preventer.
  • blowout preventers There is an increasing need for obstructing flow in pipes. For instance, underwater blowouts while drilling for oil wells have provided a particular need for improved methods of stopping oil flow out of the well after a blowout. Conventional means include use of blowout preventers. Drawbacks to blowout preventers include instances in which the blowout preventers fail.
  • a flow control method for a flow system that includes creating a flow regulating applied magnetic envelope at a targeted point in the flow system.
  • the method further includes introducing bridging and obstructing materials to the flow system.
  • the method includes capturing the bridging and obstructing materials with the flow regulating applied magnetic envelope to create a framework at the targeted point.
  • Figure 1 illustrates various embodiments of bridging and obstructing materials
  • Figure 2 illustrates an embodiment of a flow control method having a series of flow regulating applied magnetic envelopes
  • Figure 3 illustrates an embodiment of a flow control method having reinforcements and pre-attached delivery lines
  • Figure 4 illustrates an embodiment of a flow control method having a flow regulating applied magnetic envelope and cartridges
  • Figure 5 illustrates an embodiment of a flow control method having reloadable cartridges.
  • a flow control method includes creating a flow regulating applied magnetic envelope, which includes constructing a magnetic field at targeted points in a flow system.
  • the flow control method also includes introducing magnetic bridging and obstructing materials into the flow system.
  • the flow control method obstructs or substantially stops the flow of fluid through the flow system.
  • the magnetic bridging and obstructing materials create at least one obstruction (i.e., framework) in the flow system for the purposeful regulation of the flow of materials and/or fluids, the reduction of the flow of materials and/or fluids, and/or the elimination of the flow of materials and/or fluids in the flow system.
  • the flow system may be any type of system through which fluid flows.
  • the flow system is a pipe, riser, blowout preventer, or the like. In some embodiments, the flow system is disposed in a nuclear cooling plant.
  • the fluid may be any fluid. In an embodiment, the fluid includes oil. In other embodiments, the fluid is a gas flowing in a flow system.
  • the flow regulating applied magnetic envelope is employed in response to a flow through a flow system. In other embodiments, the flow regulating applied magnetic envelope is disposed on the flow system prior to the flow. In some embodiments, the flow regulating applied magnetic envelope is disposed in preparation (i.e., on standby) for deployment to a flow system when desired. For instance, in an embodiment, the flow regulating applied magnetic envelope is an integrated part of a blowout preventer at manufacture. In other embodiments, the flow regulating applied magnetic envelope is a modification to an existing blow out preventer. For instance, in embodiments, a blank may be provided where a ram may typically be disposed on a blowout preventer to allow the magnets to be disposed thereon.
  • the flow regulating applied magnetic envelope provides flow regulation to a flow system where the intended flow control point may not be easily or readily reached or in instances in which access to the exterior of a pipe or system may be obstructed.
  • examples of such instances of use of the flow regulating applied magnetic envelope include sub-surface applications, well casing rupture, debris obstruction, physical hazards (i.e., fire, electrical, nuclear, chemical, and the like).
  • the flow regulating applied magnetic envelope includes targeted choke points of the desired structure that are locally magnetized with the focus envelope of the magnetic field, which include the internal portion of the targeted structure.
  • the flow regulating applied magnetic envelope facilitates installment of magnets or cross-pieces of magnets (i.e., a quick hook up of magnets/magnet cross pieces). For instance, in embodiments, a robot is disposed to install the magnets.
  • any type and configuration of magnet suitable for use with the flow regulating applied magnetic envelope are suitable.
  • any suitable magnet for creating a magnetic field may be used.
  • suitable magnets include permanent magnets and electromagnets.
  • the permanent magnets may have any suitable configuration.
  • the magnets are adjustable and configurable for irregular surfaces.
  • embodiments include the permanent magnets having square or curved configurations.
  • the permanent magnets may have any desirable irregular shape.
  • the magnets may be applied by any suitable method.
  • the magnets may be physically placed on the desired structure or by the placement and/or wrapping of the wires of an electromagnet around the desired structure.
  • the magnets may be attached to a structure with any type of surface such as a flat, curved, or irregular surface.
  • the magnets may also be composed of any elemental composition and blend suitable for regulation of flows and electron flow management in and around the flow regulating applied magnetic envelope.
  • the permanent magnets may be composed of any suitable material.
  • the permanent magnets are composed of neodymium, boron, graphene, other suitable materials, or any combinations thereof.
  • the permanent magnets may be composed of any suitable amount of boron.
  • the permanent magnets have between about 50 wt.% and about 60 wt.% boron.
  • boron absorbs neutrons and has a suitable curie point.
  • stretching of graphene creates a magnetic field.
  • permanent magnets that include graphene may be wrapped around the outside of a pipe to provide the magnetic field.
  • embodiments of the flow regulating applied magnetic envelope include locally magnetizing targeted choke points of the superstructure with the focus envelope of the magnetic field including the internal portion of the targeted structure (e.g., risers, blowout preventers, pipes, and the like).
  • the magnets may be attached at any suitable attachment points on the superstructure (i.e., blowout preventer) of the flow system.
  • suitable attachment points include flip or fold out attachment points (i.e., the magnets are flipped or folded out in the blowout preventer), the attachment points are pre-wired, and/or the attachment points are pre-drilled points in which the magnets are inserted or disposed.
  • the magnet is a manually deployed cross-piece that is swung down into the superstructure (i.e., pipe).
  • the flow control method includes bridging and obstructing materials.
  • the bridging and obstructing materials may be composed of any desirable materials.
  • the bridging and obstructing materials include any materials composed of various chemical and elemental combinations that have the electrical charge and atomic structures to achieve the intended flow regulation and electron management in and around the flow regulating applied magnetic envelope environment.
  • the bridging and obstructing materials include materials that are attracted to magnets.
  • the bridging and obstructing materials include ferromagnetic materials.
  • the magnets include rare earth materials or neodymium materials.
  • the bridging and obstructing materials include boron, copper, or any combinations thereof.
  • the copper may be accelerated and/or decelerated from the outside or from within the flow system. Further, without limitation, the copper and/or boron absorb radioactivity (i.e., when disposed in a nuclear cooling plant).
  • the bridging and obstructing materials may have any suitable strengths of magnetism. In addition, the bridging and obstructing materials may include any suitable configuration.
  • Suitable configurations include two crossed portions ( Figure 1(a)), a plurality of crossed portions ( Figure 1(c)), curved portions (i.e., curved for hydrodynamic lift) ( Figure 1(e)), in the configuration of an H ( Figure 1(b)), two angled sides with a side connecting the ends of the two angled sides closest to each other ( Figure 1(d)), or any combinations thereof.
  • the bridging and obstructing materials include stacks of about equal sized cubes.
  • the stacks include three blocks high by four blocks wide (such as the embodiment of Figure 1(f)), four blocks high by four blocks wide (such as the embodiment of Figure 1(g)), three blocks high by four blocks wide (such as the embodiment of Figure 1 (h)), or any combinations thereof.
  • the two crossed portions may be perpendicular.
  • the plurality of crossed sections may have a solid circular end on the end opposite that of the ends that cross each other.
  • the bridging and obstructing materials may also have any suitable dimensions. In embodiments, for example, the bridging and obstructing materials have the dimensions of 1.92 inch x 1.44 inch or 1.92 inch x 1.92 inch.
  • the bridging and obstructing materials may be tailored to the flow system (e.g., pipe) size, characteristics, and/or objectives thereof.
  • multiple types of bridging and obstructing materials i.e., different configurations, compositions, and strengths
  • the bridging and obstructing materials are tailored to the flow system and are designed to minimize damage to the superstructures (i.e., pipe and systems) and reduce the possibility of a spark or excess heat.
  • the hydrodynamic flow, lift, buoyancy, and pairing characteristic of the materials are considered in selection.
  • selection of the materials may be intended to encourage or discourage hydrate formations within the flow system, and also has consideration for minimizing brittle characteristics of the materials.
  • the bridging and obstructing materials are functionalized.
  • the bridging and obstructing materials may be functionalized for any suitable purpose.
  • functionalized bridging and obstructing materials include functionalization for thermal activated/adjusted bridging and obstructing materials, crush activated/accumulating bridging and obstructing materials, shear thickening bridging and obstructing materials, magnetically activated bridging and obstructing materials, Kelvin-Helmholtz instability facilitating bridging and obstructing materials, capsule deployed bridging and obstructing materials, timer activated bridging and obstructing materials, remote activated bridging and obstructing materials, ROV activated bridging and obstructing materials, sensor feedback activated bridging and obstructing materials, foam, glue, and/or elemental bridging and obstructing materials.
  • Capsule deployed bridging and obstructing materials include one or more bridging and obstructing materials encapsulated in a material.
  • the material may be any material suitable for encapsulating the bridging and obstructing materials.
  • the encapsulating material may be activated by any suitable means (i.e., electrical signal, dissolution, and the like) to release the encapsulated bridging and obstructing materials.
  • delivery capsules and/or modules may systematically fracture.
  • such capsules and/or modules may deliver structural pieces of themselves to become a port of the flow regulating applied magnetic envelope.
  • the bridging and obstructing materials are released when in a suitable position within the environment of the flow regulating applied magnetic envelope.
  • the bridging and obstructing materials include functionalized magnetorheological and electro rheological fluids as well as colloidal solutions, Ferro fluids, and paramagnetic fluids.
  • the flow control method includes injecting the bridging and obstructing materials into the flow system and delivery thereof to the flow regulating applied magnetic envelope.
  • Any suitable injection method may be used.
  • the injection methods include manifold injection, hose injection, drill pipe injection, and any specialized implements configurable for injection.
  • delivery of the bridging and obstructing materials to the flow regulating applied magnetic envelope is accomplished by disposing the bridging and obstructing materials in cartridges.
  • the flow control method includes delivering the cartridges to the desired position at which the cartridges are activated to release the bridging and obstructing materials. The cartridges may be activated by any suitable means such as by an electrical signal.
  • one or more cartridges are disposed on a drill pipe and delivered to the desired position.
  • An electrical signal is then sent through the drill pipe to active the cartridges and release the bridging and obstructing materials.
  • the magnets then capture the bridging and obstructing materials to provide a framework.
  • the cartridges have different types of bridging and obstructing materials. For instance, the first cartridge has larger bridging and obstructing materials with each successive cartridge having smaller bridging and obstructing materials.
  • various bridging and obstructing materials are inserted into the flow system.
  • the bridging and obstructing materials may then be attracted to and captured by the magnetic field created by the magnets, and therefore become magnetically attracted, attached, and/or held to the inside of the structures of the flow system (e.g., superstructures within the scope of the targeted magnetic field envelope) to provide framework.
  • the bridging and obstructing materials are designed to flow in the flow system and minimize the possibility of damage to the flow system (e.g., pipe).
  • embodiments include the bridging and obstructing materials composed of a composition that reduces the possibility of spark or excess heat.
  • the hydrodynamic flow, lift, buoyancy, and pairing characteristics of the materials are considered in selection.
  • the intended encouragement or discouragement of hydrate formations within the system and considerations for minimizing brittle characteristics of the materials are also factored into the materials selection.
  • the flow control method includes follow up bridging and obstructing materials.
  • the follow up bridging and obstructing materials may be added subsequent to the initial insertion of the bridging and obstructing materials.
  • Such follow up bridging and obstructing materials may be of any suitable composition.
  • the follow up bridging and obstructing materials are ferrous materials, non ferrous materials, or any combinations thereof.
  • the follow up bridging and obstructing materials may also include additional bridging and obstructing materials.
  • the additional bridging and obstructing materials may be more specifically designed to fill in and fully obstruct, choke, and/or clog any remaining small openings that may remain at the targeted choke point (i.e., in the framework).
  • Follow up bridging and obstructing materials may include custom capsule/functionalized elements (i.e., copper and/or boron), materials may be of one uniform construction, or combined into one piece of varying composition, small particles suspended in solution, shear thickening fluids, ground and shredded materials of varying sizes, steel wool, wire, foam capsule, rubber material/adhesive, materials exhibiting Kelvin-Helmholtz instability, materials packed together that separate when disposed in a desired position, or any combinations thereof.
  • the flow control method includes creating the flow regulating applied magnetic envelope having a desired choke point at which the flow is desired to be obstructed or stopped. In other embodiments, the flow control method includes multiple choke points in the flow regulating applied magnetic envelope. In some embodiments, the flow control method includes multiple in-line targeted magnetic choke points that may be upstream or downstream of each other.
  • Figure 2 illustrates an embodiment of the flow control method having multiple flow regulating applied magnetic envelopes 5 with targeted choke and obstruction points. As shown, the flow control method includes inserting a series of integrated attachment points in a blowout preventer 20 at which magnetic fields attract and capture bridging and obstructing materials.
  • the bridging and obstructing materials are inserted into the flow system 40 at injection point 30, which is upstream of the blowout preventer 20.
  • Remaining bridging and obstructing materials continue to flow downstream to the second magnetic field 50 at which the magnetic field is created by a magnet disposed at an attachment point 35 at the intersection of the blowout preventer and pipe 65 (e.g., a catch and release magnetic field).
  • remaining bridging and obstructing materials flow downstream to the third magnetic field 55 that is created by electromagnets 10 wrapped around the outside of the blowout preventer 20 (e.g., a capture and hold magnetic field).
  • the remainder of the bridging and obstructing materials flow downstream to the fourth magnetic field 60 that is created by the blowout preventer with rams that have been made electromagnetic 10 (e.g., a reverse hold magnetic field).
  • the flow control method is not limited to the flow regulating applied magnetic envelopes 5 shown, but instead may have any desirable number of integrated attachment points created by any desired type of created attachment points and magnetic fields.
  • the flow control method has a backup secondary injection point 25.
  • the flow control method includes a control panel for the flow regulating applied magnetic envelope for electromagnets, which controls reactivation of the magnets, how long the magnets are activated, and the power at which the magnets are activated.
  • the control panel includes control categories for shapes of the magnets, catch/release speed, capture/hold power, reverse hold power, and the like, or any combinations thereof.
  • each category has a hi/low power control (e.g., analog power).
  • the control panel also includes computer control sequences (i.e., pulses and timed sequences).
  • cross materials may also be added to the flow system (e.g., pipe) by the flow control method.
  • the cross materials may include any suitable design to assist with the capture and retention of the bridging and obstructing materials.
  • the cross materials assist with the bridging and capture at about the mid channel of the flow.
  • the cross materials include an insert, a cross rod, a cross latticework or scaffolding that may be added to the interior (i.e., midchannel) of the targeted flow system (e.g., pipe).
  • the flow control method includes a bridging and obstructing material insertion procedure for high pressure systems.
  • a line is attached to an anchor point.
  • the line may be of any suitable material and configuration such as a chain, cable, or the like.
  • the line comprises ferrous materials.
  • measured lengths of bridging and obstructing materials are metered out.
  • the line is first inserted through a fluid lock valve and secured to an anchor point (i.e., attachment point) within the flow system.
  • the bridging and obstructing material on the line When introduced to the fluid flow (e.g., oil flow), the bridging and obstructing material on the line is delivered to the desired region for optimal capture probability to form basic framework upon which more bridging and obstructing materials may be inserted, attracted to, and captured by the magnetic field.
  • the line may also be released to provide further framework (i.e., when captured by the magnetic field).
  • the bridging and obstructing materials may be inserted by pipe and/or on a pipeline pig instead of or in addition to the line.
  • the flow control method is used in the instance of an overpressure of the flow system.
  • the magnets may be rapidly demagnetized or turned off, which may allow materials to pass downstream and thereby reduce the possibility of damage to the flow system.
  • the flow control method includes flow wheels that measure flow and comparative flow for accurate placement of the flow regulating applied magnetic envelope.
  • the flow wheels may be disposed by any suitable method.
  • the flow wheels are disposed on a line or pipe.
  • the flow control method includes placing the flow regulating applied magnetic envelope onto/over or inside a ruptured casing.
  • the flow regulating applied magnetic envelope spans the breach of the rupture and regulates flow through the casing and prevents flow out of the casing through the breach.
  • the flow regulating applied magnetic envelope provides reinforcements to the flow system (i.e., pipe) for a reduced bulge or slip.
  • Figures 3(a), (b) show reinforcements and delivery of the flow regulating applied magnetic envelope 5.
  • Figure 3(b) is an embodiment of the flow control method showing the pre-attached delivery lines 110 disposed in the embodiment shown in Figure 3(a).
  • a delivery manifold 75 is disposed at a proper depth. Reinforcements 90 are added to the pipe 100 on sides at delivery manifold 75 and downstream for placement of the magnet 95.
  • Pre-attached delivery lines 110 are attached to the delivery manifold 75 and provide the bridging and obstructing material and/or the cross-bridging structure 105.
  • Flow diverter 80 diverts flow through the delivery manifold 75. Delivery manifold 75 delivers cross-bridging structure 105 to flow regulating applied magnetic envelope 5 created by magnet 95 by pre-attached delivery lines 110.
  • the flow control method includes attaching two valves in the delivery manifold.
  • Valve one separates the delivery manifold from the flow system (e.g., pipe), and valve two separates the delivery manifold into two chambers.
  • the delivery manifold then includes a first chamber between valve one and valve two, and a second chamber distal to the pipe and that includes the access panel.
  • valve one is opened, filled to pressure, and closed. Bridging and obstructing materials are added through the access panel in the second chamber.
  • Valve two is opened to combine the two chambers. Valve one is then opened to feed the bridging and obstructing materials to the flow system.
  • Figure 4 illustrates another embodiment of the flow control method.
  • the flow regulating applied magnetic envelope 5 is lowered downstream on a pipe 120 along with cartridges 125.
  • the flow regulating applied magnetic envelope 5 is lowered until disposed in a breach of casing 130.
  • the flow regulating applied magnetic envelope 5 may include feedback sensors of the flow rate through the flow regulating applied magnetic envelope 5 for accurate depth placement of the flow regulating applied magnetic envelope 5.
  • the flow regulating applied magnetic envelope 5 spans the breach for structural support.
  • the flow regulating applied magnetic envelope 5 has orifices 135 through which material may flow until the electromagnets in the flow regulating applied magnetic envelope 5 are magnetized.
  • the primary delivery of bridging and obstructing materials through the pipe 120 provides framework within the flow regulating applied magnetic envelope 5. Secondary and/or primary delivery of the bridging and obstructing materials may be through the cartridges 125.
  • FIG. 5 illustrates an embodiment of the flow control method for introducing functionalized bridging and obstructing materials to the flow system (e.g., casing 130).
  • reloadable cartridges 125 are disposed in a panel with an injection pump 150 that provides the functionalized bridging and obstructing materials to the reloadable cartridges 125.
  • a main pump 145 provides a one way flow to the casing 130 through the connection 140 (e.g., the connection to the blow out preventer/stack).
  • the panel may include any suitable number of reloadable cartridges 125.
  • a power/control panel 115 controls the panel of reloadable cartridges 125 and release of the functionalized bridging and obstructing materials. The bridging and obstructing materials when released flow through the one way flow and the connection 140 to the flow system in casing 130 and to the flow regulating applied magnetic envelope (not illustrated).
  • a module that spans a breech may functionally distort or crush as part of the flow regulating applied magnetic envelope construction.
  • the flow and/or movement of nonferrous and/or non magnetized material may be maintained and regulated through a pipe within the flow regulating applied magnetic envelope.
  • fluid movement may be separately regulated and controlled through a pipe and may be regulated with mechanical and/or electrical valves and flow control systems.
  • the flow control method includes a capture apparatus.
  • the capture apparatus may include any structure suitable for capturing vented materials near the end flow or vent for the recapture and use of any vented bridging and obstruction materials.
  • the capture apparatus is a net.
  • the capture apparatus is magnetically charged.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physical Or Chemical Processes And Apparatus (AREA)
  • Flow Control (AREA)
  • Paper (AREA)
  • Magnetically Actuated Valves (AREA)
  • Pipe Accessories (AREA)
  • Soft Magnetic Materials (AREA)

Abstract

L'invention porte sur un procédé de commande d'écoulement qui commande l'écoulement dans un système d'écoulement. Dans un mode de réalisation, un procédé de commande d'écoulement pour un système d'écoulement comprend la création d'une enveloppe magnétique appliquée de régulation d'écoulement au niveau d'un point ciblé dans le système d'écoulement. Le procédé comprend en outre l'introduction de matériaux de colmatage et d'obstruction dans le système d'écoulement. En outre, le procédé comprend la capture des matériaux de colmatage et d'obstruction au moyen de l'enveloppe magnétique appliquée de régulation d'écoulement afin de créer une charpente au niveau du point ciblé.
EP11798886.5A 2010-06-23 2011-06-22 Enveloppe magnétique appliquée de régulation d'écoulement Withdrawn EP2585747A2 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US35796010P 2010-06-23 2010-06-23
PCT/US2011/041529 WO2011163419A2 (fr) 2010-06-23 2011-06-22 Enveloppe magnétique appliquée de régulation d'écoulement

Publications (1)

Publication Number Publication Date
EP2585747A2 true EP2585747A2 (fr) 2013-05-01

Family

ID=45372094

Family Applications (1)

Application Number Title Priority Date Filing Date
EP11798886.5A Withdrawn EP2585747A2 (fr) 2010-06-23 2011-06-22 Enveloppe magnétique appliquée de régulation d'écoulement

Country Status (7)

Country Link
US (1) US20130199650A1 (fr)
EP (1) EP2585747A2 (fr)
AU (1) AU2011270879A1 (fr)
CA (1) CA2840172A1 (fr)
MX (1) MX2013000147A (fr)
NZ (2) NZ606094A (fr)
WO (1) WO2011163419A2 (fr)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
MX2016006386A (es) 2013-12-19 2016-08-01 Halliburton Energy Services Inc Herramienta de intervencion para suministrar un fluido de reparacion de autoensamblaje.
US9850733B2 (en) * 2013-12-19 2017-12-26 Halliburton Energy Services, Inc. Self-assembling packer
MX2016004757A (es) 2013-12-30 2016-07-22 Halliburton Energy Services Inc Herramienta de ferrofluido para mejorar los campos magneticos en un pozo.
WO2015102563A1 (fr) 2013-12-30 2015-07-09 Halliburtion Energy Services, Inc. Outil à ferrofluide pour influencer les chemins électro-conducteurs dans un puits de forage
MX2016006952A (es) 2013-12-30 2016-09-27 Halliburton Energy Services Inc Herramienta de ferrofluido para el aislamiento de objetos en un pozo.
SG11201708149PA (en) 2015-06-30 2017-11-29 Halliburton Energy Services Inc Outflow control device for creating a packer
DE102019206330B4 (de) * 2019-05-03 2021-08-19 Technische Universität Dresden Magnetorheologisches Ventil
CN113884167B (zh) * 2021-09-15 2024-03-01 湖南库特智能科技有限公司 一种移动式破碎机工作产能计量方法及系统

Family Cites Families (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4463502A (en) * 1982-03-08 1984-08-07 Fitzgerald Thomas J Magnetic distributor-downcomer for fluidized beds and magnetic valve to control the flow of solids
CH665369A5 (de) * 1984-03-07 1988-05-13 Concast Standard Ag Verfahren zur regelung des durchflusses einer metallschmelze beim stranggiessen, und eine vorrichtung zur durchfuehrung des verfahrens.
US4691774A (en) * 1985-11-15 1987-09-08 Dowell Schlumberger Incorporated Novel ferrofluids for use in cementing wells
MX170398B (es) * 1989-11-14 1993-08-19 Hylsa Sa Metodo y aparato mejorados para regular el flujo de solidos ferromagneticos particulados
DE29607363U1 (de) * 1996-04-23 1996-08-22 Bürkert Werke GmbH & Co., 74653 Ingelfingen Gasdurchströmtes Ventil
DE19816208B4 (de) * 1998-04-09 2009-04-23 Knorr-Bremse Systeme für Schienenfahrzeuge GmbH Steuerventil
US6375901B1 (en) * 1998-06-29 2002-04-23 Agilent Technologies, Inc. Chemico-mechanical microvalve and devices comprising the same
CA2259776C (fr) * 1999-01-21 2001-07-31 Ian B. Zeer Assemblage magnetique pour perforateur de tubage de puits
BR0214130A (pt) * 2001-11-19 2004-10-13 Shell Int Research Método para perfurar um furo de sondagem em uma formação de terra
US7428922B2 (en) * 2002-03-01 2008-09-30 Halliburton Energy Services Valve and position control using magnetorheological fluids
US6817415B2 (en) * 2002-11-05 2004-11-16 Schlumberger Technology Corporation Method of sealing an annulus surrounding a slotted liner
KR100668335B1 (ko) * 2005-04-02 2007-01-12 삼성전자주식회사 자성 왁스 플러그를 구비한 마이크로 밸브 및 자성 왁스를이용한 유동 제어 방법
DE112007001932T5 (de) * 2006-08-24 2009-07-30 Lord Corp. Steuerbares Ventil für eine magnetorheologische Flüssigkeit, Vorrichtung und Verfahren
US8343416B2 (en) * 2008-08-07 2013-01-01 Tmt Tapping-Measuring-Technology Gmbh Methods and devices for regulating the flow rate and for slowing down non-ferromagnetic, electrically conductive liquids and melts
US20100229955A1 (en) * 2009-03-13 2010-09-16 Douglas Bell Increasing Fluidity of a Flowing Fluid
US20110005628A1 (en) * 2009-07-13 2011-01-13 Elmer Mason Magnetohydrodynamic Fluid Conditioner
US8286705B2 (en) * 2009-11-30 2012-10-16 Schlumberger Technology Corporation Apparatus and method for treating a subterranean formation using diversion
WO2011153524A2 (fr) * 2010-06-05 2011-12-08 Jay Vandelden Bloc d'obturation de puits magnétorhéologique
US9008257B2 (en) * 2010-10-06 2015-04-14 Terrapower, Llc Electromagnetic flow regulator, system and methods for regulating flow of an electrically conductive fluid
KR101184282B1 (ko) * 2010-11-29 2012-09-21 현대자동차주식회사 Mr유체가 봉입된 엔진마운트용 오리피스플레이트의 구조

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO2011163419A3 *

Also Published As

Publication number Publication date
NZ705599A (en) 2016-06-24
MX2013000147A (es) 2015-12-07
AU2011270879A1 (en) 2013-02-07
US20130199650A1 (en) 2013-08-08
CA2840172A1 (fr) 2011-12-29
WO2011163419A2 (fr) 2011-12-29
NZ606094A (en) 2015-04-24
WO2011163419A3 (fr) 2013-04-04

Similar Documents

Publication Publication Date Title
US20130199650A1 (en) Flow Regulating Applied Magnetic Envelope
US9605789B2 (en) Magneto-cryogenic valves, systems and methods for modulating flow in a conduit
US6817415B2 (en) Method of sealing an annulus surrounding a slotted liner
CA2992712C (fr) Deploiement de dispositif de colmatage
US20170130545A1 (en) Closing of Underwater Oil Spills with the Help of Magnetic Powders
US20080053662A1 (en) Electrically operated well tools
EP2859178A1 (fr) Systèmes et procédés d'étanchéité secondaire d'une perforation dans un tubage de puits de forage
US10309174B2 (en) Automated remote actuation system
EP3196402A1 (fr) Colmatage de trous de forage à abandonner dans la terre
WO2008058209A3 (fr) Système universel de colonnes montantes en haute mer
US9163475B2 (en) Closing of underwater oil spills with the help of magnetic powders
CA2506458A1 (fr) Tampon recuperable renforce amortisseur de vibrations pour puits tubes
CN111810077A (zh) 用于向海底防喷器提供液压流体的歧管以及相关方法
US9476277B2 (en) Magnetic leak management apparatus and methods
US9488034B2 (en) Opening a conduit cemented in a well
BR112020010003A2 (pt) conjunto de cabeça de disparo, aparelho de completação de poço e método para usar um conjunto de cabeça de disparo
WO2011156326A2 (fr) Soupape de sûreté à activation magnétique pouvant se fermer en réponse à une rupture
ES2310828T3 (es) Aparato de control de fluido hidraulico.
WO2011151730A2 (fr) Appareil de coiffage électrodynamique d'urgence de tuyaux et de puits
DE102010025227A1 (de) Vorrichtung, die eine defekte Ölquelle schließen kann
Zhang et al. Developing New-Generation Disintegrable Material to Improve Efficiency of Multistage Fracturing Treatment in Cased-Hole Completions
AU2018408876B2 (en) Kaapaali bowls and tunnels - the Tsunami diverter
CN101705836B (zh) 喷流控制装置及方法
CN118880813A (zh) 一种堤坝管涌快速封堵抢险装置及方法
ITCT20020006U1 (it) Elettro valvola di protezione sismica per impianti a gas

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20130122

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

R17D Deferred search report published (corrected)

Effective date: 20130404

DAX Request for extension of the european patent (deleted)
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20160105