EP2488435B1 - Device for creating spaces in an elevator pit and overhead for the execution of maintenance work in conditions of safety - Google Patents
Device for creating spaces in an elevator pit and overhead for the execution of maintenance work in conditions of safety Download PDFInfo
- Publication number
- EP2488435B1 EP2488435B1 EP09807559.1A EP09807559A EP2488435B1 EP 2488435 B1 EP2488435 B1 EP 2488435B1 EP 09807559 A EP09807559 A EP 09807559A EP 2488435 B1 EP2488435 B1 EP 2488435B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- strut
- positioning
- inactive
- arm
- cabin
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B5/00—Applications of checking, fault-correcting, or safety devices in elevators
- B66B5/0043—Devices enhancing safety during maintenance
- B66B5/005—Safety of maintenance personnel
- B66B5/0056—Safety of maintenance personnel by preventing crushing
Definitions
- the present invention relates to safety in the field of elevators and, in particular, to a device for creating temporary spaces, in the pit and overhead of the hoistway, where maintenance work can be carried out in conditions of safety.
- norm EN 81-21 specifically concerns installation of new elevators in existing buildings.
- Figure 1 illustrates a known device for positioning the safety strut inside the pit of an elevator hoistway.
- Figure 1 shows a pillar 1 resting on the bottom of a pit 2, sideways in relation to the ledge 3 of the car sling 4 of an elevator cabin (not shown).
- Lower down on the pillar 1 is a shock-absorber 5 constrained to the elevator guide rail (on the part not visible in the figure) that extends down to ground level.
- the upper part of the pillar 1 supports an electromechanical device comprising a bracket-shaped balancing bar 6 with a shorter arm 6a hinged to a horizontal pin 7, and a longer arm 6b that forms the actual strut itself.
- the pin 7 is in proximity to a plate 8 that limits rotation towards the pit of arm 6a to a very small angle.
- the device includes an electromechanical actuator 9 connected to the longer arm 6b to control its inclination.
- the working (or active) position of said arm 6b is reached by inclining it towards the inside of the pit 2.
- the cabin-car sling unit rests against the free end of arm 6b, whose working position is such as to interfere with cabin travel.
- This device is defective because, for sustaining the weight of the cabin, there is only a limited leaning surface due to laterality of the strut, but chiefly because the greater part of the load is borne by the hinge 6a, 7.
- the hinge 6a, 7 might break causing detachment of the balancing bar 6 which would fall into the pit and become ineffective, or the hinge connection might bend and be unable to sustain the weight above it. In either case the maintenance technician would inevitably suffer serious injury.
- Purpose of the present invention is to overcome the above drawbacks.
- subject of the invention is a device for creating temporary spaces in an elevator hoistway to ensure that maintenance work can be done in conditions of safety, comprising means for positioning a strut, in the pit and/or in the overhead of said hoistway, joinable to the vertical guide rail of the cabin or to a wall of the hoistway, said means being operable and controllable from outside the elevator hoistway, and wherein according to the invention, said means for positioning the strut include:
- the safety space in the overhead is created by placing said device in the pit and fixing it to a vertical guide rail of the counterweight so as to intercept the counterweight when the cabin reaches the limit of said safety space in the overhead.
- a second pivoting arm of a shape preferably the same as that of the first arm, is rigidly joined to the first arm in its vertical position at a previously set distance, the second arm comprising at its free end a second seat bored through for vertical insertion of the strut, to improve its stability when loaded.
- the pivoting arm forms part of a substantially C-shaped bracket which, when the strut is inactive, includes a section of the vertical guide rail for sliding the cabin. This conformation of the arm simplifies application of electromagnetic means to lock the strut in its inactive position.
- brackets In the form for realizing the invention with two brackets, these are rigidly joined at their two ends, one below the other, each rigidly connected to a respective end of a tubular element.
- an inactive or idle position signifies a position of the strut that allows the cabin (or the counterweight) to slide alongside said strut without interference.
- the expression active or operative position signifies a position of the strut that would prevent the cabin (or counterweight) from descending below the level established by the strut's own length, as this would cause the cabin-car sling unit to rest on the head of the strut.
- a respective electrical contact when the strut reaches the active or the inactive position, a respective electrical contact will either close or open.
- the strut is fitted at one of its ends with a shock-absorbing element to decelerate the cabin, or the counterweight, at the moment of impact.
- said means for positioning the strut include elastic means, such as a helical spring (that acts as a retaining pin) to oppose externally controlled rotation of said pivoting arm towards the inactive position of the strut.
- elastic means such as a helical spring (that acts as a retaining pin) to oppose externally controlled rotation of said pivoting arm towards the inactive position of the strut.
- the means for positioning the strut include means for locking it in the inactive position.
- said means can include an electromagnet.
- movement of the strut from the inactive to the active position is done manually by means of cords, as well as moving it from the active to the inactive position.
- the strut is moved from its inactive to its active position is done by means of an electromechanical actuator which also serves to move it from the active to the inactive position.
- the strut is move manually from its inactive to its active position by means of cords, while an electromechanical actuator moves it from its active to its inactive position.
- the strut is moved from its inactive to its active position by an electromechanical actuator, and manually from its active to its inactive position by means of cords.
- strut movement in one direction or the other may also be obtained by the force of gravity, for example by a weight transmitted by a cord.
- the safety strut in its active position, rests vertically on the ground and the cabin car sling (or the counterweight) rests on the strut, the entire weight from above is discharged directly onto the ground without affecting any mechanical parts belonging to the kinematic means for positioning said strut.
- the head of the strut can be larger than is strictly necessary; all that is needed is to lengthen the arms not hinged to the brackets in order to move the strut farther away from the guide rail of the cabin. This is possible because the brackets rotate on a horizontal plane that does not affect the length of the strut, but could not be done with the device as conceived by the known art, where moving the strut to a more central position would also have meant exceeding the minimum height of the pit.
- Figure 2 shows a device 10 fixed to the wall of one guide rail 11 of the two that extend throughout the entire hoistway of an elevator to maintain vertical alignment of the cabin in its upward and downward movement.
- the end of the guide rail 11 is firmly fixed to the bottom 12 of the hoistway in the part known as the pit.
- the lower part of a car sling 13 can be seen that supports the frame of an elevator cabin (not shown),
- a flat ledge 14 is fixed a short distance above the end of the car sling 13.
- the device 10 comprises two special three-armed brackets, 15 and 16 aligned one below the other and more clearly seen in Figure 2A.
- Figure 2A shows the substantially C-shaped bracket 15 with a first curving arm 15a, joined at 90° to a second arm 15b from which a third arm. 15c branches off at 90° opposite to arm 15a.
- Bracket 16 possesses a similar set of arms 16a, 16b and 16c.
- the curved arms 15a and 16a of the two brackets 15 and 16 are joined at their ends by a tubular element 17 into which is inserted a pin 18 supported at the two ends by two short bored shelves 19, 20 connected to the wall of the vertical guide rail 11.
- Pin 18 stands vertically and acts as a hinge for rotation of the two brackets joined together.
- the arms 15b and 16b of the two brackets are joined by a vertical handle 21 placed at the angle with the third arms 15c and 16c.
- Arm 15c of the bracket 15 supports a small plate 22 in which is a square central hole 23 through which passes the safety strut 26, whose cross section is also square ( figure 2 ).
- arm 16c of the bracket 16 supports a plate 24 in which there is a square central hole 25 for passage of the strut safety 26.
- the centres of the two holes 23 and 25 are vertically aligned and keep the strut 26 stable in its vertical position.
- the strut can obviously be of a shape different from the parallelepiped form seen in the figure; for example it could be cylindrical in which case the holes 23 and 25 would be circular.
- the bored plates 22 and 24 are made from a single sheet of metal 22a with a double 90° bend at the two ends.
- a plate 27 matched by a collar 28 fixed to the strut 26 at some distance 26a from the upper plate 27.
- the collar 28 is made from a plate similar to plate 27, with a central hole in it through which the strut 26 passes and is fixed.
- a helical spring 29 includes the upper end of the strut 26 comprised between the collar 28 and upper plate 22.
- An electromagnet 30 is connected to the wall of the vertical slide rail 11, matched (as shown in Figure 5 ) by a magnet 31 connected to an extension 32 of the handle 21.
- On the plate 22 is a contact 33 to control the active position of the strut 26.
- the positioning device 10 in Figure 2 corresponds in this conformation to the active position of the strut 26 but is not loaded by the weight of the cabin.
- the strut 26 is aligned with the ledge 14, and detached from it;
- the weak spring 29 is not compressed and when fully extended keeps the strut 26 detached from the ground 12.
- the device 10 includes a spring that automatically ensures that the active position is reached when the lock for the inactive position is removed from the outside of the hoistway. This lock is worked by the electromagnet 30 on the ferromagnetic disk (or magnet) 31.
- the actuator of rotation overcomes the force exerted by residual magnetism and causes the two brackets, 15 and 16, to rotate at 90° towards the inside of the pit.
- Contact 33 is closed to inform the control centre that the strut 26 has reached its active position.
- the maintenance worker can enter the pit.
- the active conformation of the device 10 in Figure 3 differs from the preceding one only because the strut 26 is now loaded with the weight of the car sling 13 and of the cabin, indicated by the arrow 34. As shown, the weak spring 29 is compressed, the strut 26 rests on the bottom of the pit 12, its length being suitable for keeping the cabin at a distance of safety.
- Figure 4 shows the device 10 in the inactive conformation of the strut 26.
- the actuator that controls rotation of the brackets 15 and 16 has completed a rotation of 90° towards the outside of the pit, moving the strut 26 away from vertical of interception by the ledge 14 and causing the opposing magnetic disc 31 to match with the electromagnet 30. This latter is therefore energised locking the strut 26 in the inactive position.
- the magnetic locking device is better seen in Figure 5B .
- the electric contact that controls the inactive position (not shown) is closed confirming that this position has been reached; the electric contact 33 (not shown) controlling the active position is, however, open.
- the helical spring 29 is decompressed and the strut 26, raised above the ground 12, is out of line with the ledge 14 of the car sling 13.
- Figure 5 shows the rear side of the device 10 in Figure 4 in the inactive conformation. It will be seen from the figure that brackets 15, 16 are hinged on the pin 18 by means of tubular element 17.
- a further look at Figure 5A shows the hinged end of the curved arm 16a of the lower bracket 16 is connected to the shaft of a rotation actuator 40, typically a small DC geared-down electric motor connected to the wall of the guide rail 11 and parallel to it. The above end also comprises an eyehole 41 for fixing a cord in case manual operation is required.
- a rotation actuator 40 typically a small DC geared-down electric motor connected to the wall of the guide rail 11 and parallel to it.
- the above end also comprises an eyehole 41 for fixing a cord in case manual operation is required.
- a spring 42 acting as a retaining pin, is wound round the tubular element 17, with the two ends of the spring placed respectively against the wall of the guide rail 11 and the end of the arm 16a, for automatic return of brackets 15 and 16 to the active position of strut 26 should the electromagnet 30 be no longer energised.
- the spring 42 is kept compressed by the electromagnetic device 30 and 31 for locking the strut 26 in the inactive position, more clearly seen in Figure 5B where the contact for electric feed 43 is visible.
Landscapes
- Maintenance And Inspection Apparatuses For Elevators (AREA)
Description
- The present invention relates to safety in the field of elevators and, in particular, to a device for creating temporary spaces, in the pit and overhead of the hoistway, where maintenance work can be carried out in conditions of safety.
- A good example of the known art is given in
EP 0 725 033 A . - In the field of hoisting means, especially of elevators, the question of safety for passengers and for technical staff engaged on maintenance is of primary importance and many are the regulations in force for this purpose. These rules establish the main technical features of the elevator system and the values associated to the chief variables. Technical staff encounter the greatest risks when they have to work in the hoistway of the elevator. It is well known that the highest and lowest levels reached by the cabin do not coincide with the roof or with the bottom of the hoistway, but allow for permanent safety spaces, both between the roof of the cabin and the upper wall of the hoistway called the "overhead" and similarly below, called the "pit", where work can be carried out after the cabin has been moved to some stopping point between floor levels.
- Continuous technical progress in the field has led to a considerable reduction in the vertical bulk of elevator systems in buildings, such as to include the motor, winch and operating apparatus in a compact form now contained in the hoistway to avoid the need for a separate "engine room". This reduction is particularly useful in cases where a new elevator has to be installed in an existing building, so that the above regulations are not fully applicable.
- On a point of information, norm EN 81-21 specifically concerns installation of new elevators in existing buildings.
- Problems of safety are clearly increased by derogation of the law for elevator systems where spaces in the pit and/or overhead cannot be created in a permanent manner. The invention now to be described particularly relates to safety in the pit and/or overhead, to which the present art mentioned corresponds.
- Present regulations categorically exclude the possibility of a maintenance worker taking with him the means for creating temporary safety spaces. These must be provided in the hoistway and must be operated from outside either automatically or manually.
-
Figure 1 illustrates a known device for positioning the safety strut inside the pit of an elevator hoistway.Figure 1 shows apillar 1 resting on the bottom of a pit 2, sideways in relation to theledge 3 of thecar sling 4 of an elevator cabin (not shown). Lower down on thepillar 1 is a shock-absorber 5 constrained to the elevator guide rail (on the part not visible in the figure) that extends down to ground level. The upper part of thepillar 1 supports an electromechanical device comprising a bracket-shaped balancing bar 6 with a shorter arm 6a hinged to ahorizontal pin 7, and a longer arm 6b that forms the actual strut itself. Thepin 7 is in proximity to aplate 8 that limits rotation towards the pit of arm 6a to a very small angle. The device includes an electromechanical actuator 9 connected to the longer arm 6b to control its inclination. Starting from the idle (or inactive) position of arm 6b when vertically aligned (dashed line), the working (or active) position of said arm 6b is reached by inclining it towards the inside of the pit 2. In that position the cabin-car sling unit rests against the free end of arm 6b, whose working position is such as to interfere with cabin travel. This device is defective because, for sustaining the weight of the cabin, there is only a limited leaning surface due to laterality of the strut, but chiefly because the greater part of the load is borne by thehinge 6a, 7. In the event of a particularly strong impact, thehinge 6a, 7 might break causing detachment of the balancing bar 6 which would fall into the pit and become ineffective, or the hinge connection might bend and be unable to sustain the weight above it. In either case the maintenance technician would inevitably suffer serious injury. - Purpose of the present invention is to overcome the above drawbacks.
- To do this, subject of the invention is a device for creating temporary spaces in an elevator hoistway to ensure that maintenance work can be done in conditions of safety, comprising means for positioning a strut, in the pit and/or in the overhead of said hoistway, joinable to the vertical guide rail of the cabin or to a wall of the hoistway, said means being operable and controllable from outside the elevator hoistway, and wherein according to the invention, said means for positioning the strut include:
- a pin connected to a longitudinal wall of said guide rail by connecting means interposed between the pin and said longitudinal wall, in such a way as to keep the pin vertical;
- at least one arm to pivot round said pin, there being at the free end of said arm a seat through which a hole is bored for vertical insertion of the strut;
- elastic means acting between the upper end of the strut and said seat at the free end of the pivotal arm, said elastic means opposing the weight of the strut only, keeping it raised above the bottom of the pit or separated from the upper wall of the overhead when not loaded, the length of the strut being such that, when loaded, it rests on the bottom of the pit or against the upper wall of the overhead, so creating a space where work can be done in safety, as described in
claim 1. - Further characteristics of the present invention considered innovative are described in the dependent claims.
- In one form of realizing the invention, valid for elevators fitted with counterweights, the safety space in the overhead is created by placing said device in the pit and fixing it to a vertical guide rail of the counterweight so as to intercept the counterweight when the cabin reaches the limit of said safety space in the overhead.
- In one form of realizing the invention, a second pivoting arm, of a shape preferably the same as that of the first arm, is rigidly joined to the first arm in its vertical position at a previously set distance, the second arm comprising at its free end a second seat bored through for vertical insertion of the strut, to improve its stability when loaded.
- In one form of realizing the invention, the pivoting arm forms part of a substantially C-shaped bracket which, when the strut is inactive, includes a section of the vertical guide rail for sliding the cabin. This conformation of the arm simplifies application of electromagnetic means to lock the strut in its inactive position.
- In the form for realizing the invention with two brackets, these are rigidly joined at their two ends, one below the other, each rigidly connected to a respective end of a tubular element.
- Before proceeding with the description, it must be stated that the expression an inactive or idle position signifies a position of the strut that allows the cabin (or the counterweight) to slide alongside said strut without interference. The expression active or operative position signifies a position of the strut that would prevent the cabin (or counterweight) from descending below the level established by the strut's own length, as this would cause the cabin-car sling unit to rest on the head of the strut.
- When the strut assumes an active position a distinction must be made between the condition of the strut 'without load', namely when the car sling does not make contact with the head of the strut, and the condition of the strut when 'loaded' with the weight of the cabin (or counterweight).
- Therefore, according to one aspect of the invention, when the strut reaches the active or the inactive position, a respective electrical contact will either close or open.
- According to one aspect of the invention, the strut is fitted at one of its ends with a shock-absorbing element to decelerate the cabin, or the counterweight, at the moment of impact.
- According to one aspect of the invention, said means for positioning the strut include elastic means, such as a helical spring (that acts as a retaining pin) to oppose externally controlled rotation of said pivoting arm towards the inactive position of the strut.
- According to one aspect of the invention, the means for positioning the strut include means for locking it in the inactive position. Advantageously said means can include an electromagnet.
- According to one aspect of the invention, movement of the strut from the inactive to the active position is done manually by means of cords, as well as moving it from the active to the inactive position.
- According to one aspect of the invention, the strut is moved from its inactive to its active position is done by means of an electromechanical actuator which also serves to move it from the active to the inactive position.
- According to one aspect of the invention, the strut is move manually from its inactive to its active position by means of cords, while an electromechanical actuator moves it from its active to its inactive position.
- According to one aspect of the invention, the strut is moved from its inactive to its active position by an electromechanical actuator, and manually from its active to its inactive position by means of cords.
- According to one aspect of the invention, strut movement in one direction or the other may also be obtained by the force of gravity, for example by a weight transmitted by a cord.
- Compared with the known art previously discussed, the invention offers considerable advantages.
- As the safety strut, in its active position, rests vertically on the ground and the cabin car sling (or the counterweight) rests on the strut, the entire weight from above is discharged directly onto the ground without affecting any mechanical parts belonging to the kinematic means for positioning said strut.
- This greatly simplifies decisions on the size of the cross section of the strut, according to the type of system where it will be installed.
- The head of the strut can be larger than is strictly necessary; all that is needed is to lengthen the arms not hinged to the brackets in order to move the strut farther away from the guide rail of the cabin. This is possible because the brackets rotate on a horizontal plane that does not affect the length of the strut, but could not be done with the device as conceived by the known art, where moving the strut to a more central position would also have meant exceeding the minimum height of the pit.
- Further purposes and advantages of the present invention will be clear from the following detailed description of an example of its realization and by the attached drawings provided solely for explanatory reasons in no way limitative, wherein:
-
Figure 1 is a side view of a device from the known art, for creating temporary spaces in the pit for carrying out maintenance work in the hoistway of the elevator in conditions of safety; -
Figure 2 is front and side view in perspective of a device, according to the present invention for creating temporary spaces where maintenance work can be executed in safety in the pit or in the overhead of the elevator hoistway, placed in the pit showing a strut in its active position but not loaded with the weight of the cabin; -
Figure 2A is an exploded view of a detail inFigure 2 ; -
Figure 3 is a view in perspective that differs from that inFigure 2 in that the strut is loaded with the cabin; -
Figure 4 is a view in perspective of the device inFigure 2 showing the strut in its inactive position; -
Figure 5 is a view in perspective that shows the rear side of the device inFigure 4 ; -
Figures 5A and 5B show enlarged details fromFigure 5 . - In the following description elements that appear in different figures may be marked with the same symbols. In describing a figure reference may be made to parts not expressly shown in that figure but in preceding ones. Scale and proportions of the various elements shown do not necessarily correspond to reality.
-
Figure 2 shows adevice 10 fixed to the wall of oneguide rail 11 of the two that extend throughout the entire hoistway of an elevator to maintain vertical alignment of the cabin in its upward and downward movement. The end of theguide rail 11 is firmly fixed to the bottom 12 of the hoistway in the part known as the pit. Along theguide rail 11 the lower part of acar sling 13 can be seen that supports the frame of an elevator cabin (not shown), Aflat ledge 14 is fixed a short distance above the end of thecar sling 13. Thedevice 10 comprises two special three-armed brackets, 15 and 16 aligned one below the other and more clearly seen inFigure 2A. Figure 2A shows the substantially C-shapedbracket 15 with a firstcurving arm 15a, joined at 90° to asecond arm 15b from which a third arm. 15c branches off at 90° opposite toarm 15a.Bracket 16 possesses a similar set ofarms curved arms brackets tubular element 17 into which is inserted apin 18 supported at the two ends by two shortbored shelves vertical guide rail 11.Pin 18 stands vertically and acts as a hinge for rotation of the two brackets joined together. Thearms vertical handle 21 placed at the angle with thethird arms 15c and 16c.Arm 15c of thebracket 15 supports asmall plate 22 in which is a squarecentral hole 23 through which passes thesafety strut 26, whose cross section is also square (figure 2 ). Similarly, arm 16c of thebracket 16 supports aplate 24 in which there is a squarecentral hole 25 for passage of thestrut safety 26. The centres of the twoholes strut 26 stable in its vertical position. The strut can obviously be of a shape different from the parallelepiped form seen in the figure; for example it could be cylindrical in which case theholes bored plates metal 22a with a double 90° bend at the two ends. - Returning to
Figure 2 it will be seen that at the top of thesafety strut 26 there is aplate 27 matched by acollar 28 fixed to thestrut 26 at some distance 26a from theupper plate 27. Thecollar 28 is made from a plate similar toplate 27, with a central hole in it through which thestrut 26 passes and is fixed. Ahelical spring 29 includes the upper end of thestrut 26 comprised between thecollar 28 andupper plate 22. Anelectromagnet 30 is connected to the wall of thevertical slide rail 11, matched (as shown inFigure 5 ) by amagnet 31 connected to anextension 32 of thehandle 21. On theplate 22 is acontact 33 to control the active position of thestrut 26. There is also a similar contact to control the inactive position of the strut but this is not shown in the Figure. From the functional aspect, thepositioning device 10 inFigure 2 corresponds in this conformation to the active position of thestrut 26 but is not loaded by the weight of the cabin. Here thestrut 26 is aligned with theledge 14, and detached from it; Theweak spring 29 is not compressed and when fully extended keeps thestrut 26 detached from theground 12. As will be explained below, thedevice 10 includes a spring that automatically ensures that the active position is reached when the lock for the inactive position is removed from the outside of the hoistway. This lock is worked by theelectromagnet 30 on the ferromagnetic disk (or magnet) 31. When theelectromagnet 30 is de-energised, the actuator of rotation overcomes the force exerted by residual magnetism and causes the two brackets, 15 and 16, to rotate at 90° towards the inside of the pit.Contact 33 is closed to inform the control centre that thestrut 26 has reached its active position. Whendevice 10 is in the conformation shown, the maintenance worker can enter the pit. - The active conformation of the
device 10 inFigure 3 differs from the preceding one only because thestrut 26 is now loaded with the weight of thecar sling 13 and of the cabin, indicated by thearrow 34. As shown, theweak spring 29 is compressed, thestrut 26 rests on the bottom of thepit 12, its length being suitable for keeping the cabin at a distance of safety. -
Figure 4 shows thedevice 10 in the inactive conformation of thestrut 26. It will be seen that the actuator, that controls rotation of thebrackets strut 26 away from vertical of interception by theledge 14 and causing the opposingmagnetic disc 31 to match with theelectromagnet 30. This latter is therefore energised locking thestrut 26 in the inactive position. The magnetic locking device is better seen inFigure 5B . The electric contact that controls the inactive position (not shown) is closed confirming that this position has been reached; the electric contact 33 (not shown) controlling the active position is, however, open. Thehelical spring 29 is decompressed and thestrut 26, raised above theground 12, is out of line with theledge 14 of thecar sling 13. -
Figure 5 shows the rear side of thedevice 10 inFigure 4 in the inactive conformation. It will be seen from the figure thatbrackets pin 18 by means oftubular element 17. A further look atFigure 5A , shows the hinged end of thecurved arm 16a of thelower bracket 16 is connected to the shaft of arotation actuator 40, typically a small DC geared-down electric motor connected to the wall of theguide rail 11 and parallel to it. The above end also comprises aneyehole 41 for fixing a cord in case manual operation is required. Aspring 42, acting as a retaining pin, is wound round thetubular element 17, with the two ends of the spring placed respectively against the wall of theguide rail 11 and the end of thearm 16a, for automatic return ofbrackets strut 26 should theelectromagnet 30 be no longer energised. In the conformation seen in the figure, thespring 42 is kept compressed by theelectromagnetic device strut 26 in the inactive position, more clearly seen inFigure 5B where the contact forelectric feed 43 is visible. - In the case of elevators with a counterweight, the same device as in the preceding figures can clearly be placed in the pit in order to intercept movement of the counterweight, also stopping the cabin and creating a safety space in the overhead.
- It is also clear that, apart from some small changes, the same device can be positioned in the overhead, stopping the cabin in its upward movement and creating there a place for working in safety.
Claims (13)
- Safety device (10) for creating temporary spaces in an elevator hoistway to ensure that maintenance work can be done in conditions of safety, comprising means for positioning a strut (26), in the pit and/or in the overhead of said hoistway, joinable to the vertical guide-rail (11) of the cabin, or to a wall of the hoistway, said means being operable and controllable from outside the elevator hoistway, characterized in that said means for positioning the strut include:- a pin (18) connected to a longitudinal wall of said guide rail (11) by connecting means (19, 20) interposed between the pin (18) and said longitudinal wall in such a way as to keep the pin (18) vertical;- at least one arm (15) to pivot round said pin, there being at the free end of said arm a seat (22) through which a hole (23) is bored for vertical insertion of the strut (26);- elastic means (29) acting between the upper end (27) of the strut and said seat (22) at the free end of the pivotal arm (15), said elastic means opposing the weight of the strut (26) only, keeping it raised above the bottom (12) of the pit, or separated from the upper wall of the overhead when not loaded, the length of the strut (26) being such that, when loaded, it rests on the bottom of the pit or against the upper wall of the overhead, so creating a space where work can be done in safety.
- Device as in claim 1, characterized in that said pivotal arm (15) is part of an approximately C-shaped bracket that, when the strut (26) is in the inactive position, includes a section of the vertical guide-rail (11) of the cabin.
- Device as in claim 2, characterized in that said means for positioning the strut include a second pivotal arm (16) preferably shaped exactly like the first arm (15), the brackets formed by the two pivotal arms (15, 16) opposed, one to another, each rigidly connected to a respective end or a tubular element (17), the second pivotal arm (16) comprising at its free end a second bored seat (24) for vertical insertion of the strut (26), all of which improves the stability of the vertical position of the strut when loaded.
- Device as in claim 1, characterized in that the positioning means of the strut include elastic means placed between said pin (18) and said guide-rail (11) to oppose rotation of the pivotal arm (15) towards the inactive position of the strut (26).
- Device as in claim 1, characterized in that said means for positioning the strut (26) include means (30, 31) for locking it in the inactive position.
- Device as in claim 5, characterized in that said means (30, 31) for locking the strut (26) in the inactive position include an electromagnet.
- Device as in claim 1, characterized in that said means for positioning the strut (26) include cords workable by hand from a distance to move it from the inactive to the active position, and vice versa.
- Device as in claim 1, characterized in that said means for positioning the strut (26) include an electro-mechanical actuator (40) to move it from the inactive to the active position, and vice versa.
- Device as in claim 1, characterized in that said means for positioning the strut (26) include cords workable by hand to move said strut (26) from the inactive to the active position, and an electro-mechanical actuator (40) for moving it from the active to the inactive position.
- Device as in claim 1, characterized in that said means for positioning the strut (26) include an electro-mechanical actuator (40) to move strut (26) from the inactive position to the active position, and cords workable by hand to move it from the active to the inactive position.
- Device as in claim 1, characterized in that said means for positioning the strut (26) include electric contacts (33) closed and opened mechanically to signal when strut (26) has reached its active or inactive position.
- Device as in claim 1, characterized in that it is so placed in the pit to intercept the counterweight, thus creating the space for working safely in the overhead above the cabin.
- Device as in claim 1, characterized in that the strut (26) is fitted at one end with a shock-absorbing element to decelerate the cabin at the moment of impact.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ITMI2009A001741A IT1395860B1 (en) | 2009-10-12 | 2009-10-12 | DEVICE FOR REALIZING THE SAFETY SPACES FOR MAINTENANCE INTERVENTIONS IN THE FOSSA AND THE ELEVATOR RACING TUBE HEAD |
PCT/IT2009/000589 WO2011045826A1 (en) | 2009-10-12 | 2009-12-29 | Device for creating spaces in an elevator pit and overhead for the execution of maintenance work in conditions of safety |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2488435A1 EP2488435A1 (en) | 2012-08-22 |
EP2488435B1 true EP2488435B1 (en) | 2013-06-05 |
Family
ID=42199394
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP09807559.1A Not-in-force EP2488435B1 (en) | 2009-10-12 | 2009-12-29 | Device for creating spaces in an elevator pit and overhead for the execution of maintenance work in conditions of safety |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP2488435B1 (en) |
IT (1) | IT1395860B1 (en) |
WO (1) | WO2011045826A1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10947087B2 (en) | 2016-12-14 | 2021-03-16 | Otis Elevator Company | Elevator safety system and method of operating an elevator system |
US11591184B2 (en) | 2019-07-05 | 2023-02-28 | Otis Elevator Company | Elevator assembly with counterweight blocking stop |
US11691847B2 (en) | 2019-06-20 | 2023-07-04 | Tk Elevator Corporation | Elevator travel blocking apparatus |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102849561B (en) * | 2011-06-30 | 2015-11-25 | 陈海水 | Energy-storage type lifting structure |
ITVA20120050A1 (en) * | 2012-12-17 | 2014-06-18 | E D Lift Ing David Donadello | DEVICE NECESSARY FOR THE CREATION OF TEMPORARY SPACES, REQUIRED TO CARRY OUT THE MAINTENANCE WORK IN SAFETY CONDITIONS IN THE STAGE AND / OR IN THE HEAD OF THE LIFTING WHEEL. |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2166841C (en) * | 1995-01-31 | 2006-08-22 | Heinrich Foelix | Temporary working space protection |
US5806633A (en) * | 1995-12-22 | 1998-09-15 | Macuga; Henry J. | Elevator safety system incorporating false pit |
NZ532767A (en) * | 2003-05-21 | 2004-12-24 | Inventio Ag | Lift installation with a buffer for creating a zone of protection in a lift installation and a method of creating a zone of protection |
US20060042883A1 (en) * | 2004-09-02 | 2006-03-02 | Gary Scott | Elevator pit safety device |
-
2009
- 2009-10-12 IT ITMI2009A001741A patent/IT1395860B1/en active
- 2009-12-29 EP EP09807559.1A patent/EP2488435B1/en not_active Not-in-force
- 2009-12-29 WO PCT/IT2009/000589 patent/WO2011045826A1/en active Application Filing
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10947087B2 (en) | 2016-12-14 | 2021-03-16 | Otis Elevator Company | Elevator safety system and method of operating an elevator system |
US11691847B2 (en) | 2019-06-20 | 2023-07-04 | Tk Elevator Corporation | Elevator travel blocking apparatus |
US11591184B2 (en) | 2019-07-05 | 2023-02-28 | Otis Elevator Company | Elevator assembly with counterweight blocking stop |
Also Published As
Publication number | Publication date |
---|---|
IT1395860B1 (en) | 2012-10-26 |
ITMI20091741A1 (en) | 2011-04-13 |
EP2488435A1 (en) | 2012-08-22 |
WO2011045826A1 (en) | 2011-04-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2488435B1 (en) | Device for creating spaces in an elevator pit and overhead for the execution of maintenance work in conditions of safety | |
EP2035313B1 (en) | Safety device for securing minimum spaces at the top or bottom of an elevator shaft being inspected, and elevator having such safety devices | |
EP1207129B1 (en) | Arrangement to create safety zones for a hoist | |
CN101472824B (en) | Retractable stopper for maintaining overhead clearance above elevator cage | |
CN104684834B (en) | Low top or the indemnifying measure of low pit elevator | |
CN109476456B (en) | Elevator device and elevator | |
WO2000003941A1 (en) | Controller for elevators | |
CN101486424B (en) | Elevator rope vibration stopping apparatus | |
US3426829A (en) | Relay actuated overhead door safety catch | |
CN101117870A (en) | Elevator gate lock | |
KR101862970B1 (en) | Elevator apparatus | |
WO2006069442A1 (en) | Braking mechanism for moving assemblies | |
EP2075211A1 (en) | Safety device for elevator apparatuses and elevator apparatus comprising said safety device | |
JP4107863B2 (en) | Elevator equipment | |
JP2005521610A (en) | Elevator main rope stretch compensation device | |
KR101277680B1 (en) | An equipment of safe door for elevator | |
CN110054057B (en) | Elevator device | |
CN113295559A (en) | Pendulum bob test system for mechanical strength of elevator door plate | |
JP6301010B2 (en) | Elevator equipment | |
JP2013129493A (en) | Moving cable apparatus for elevator | |
JP4248678B2 (en) | Elevator equipment | |
JPH1087228A (en) | Elevator | |
EP3421406B1 (en) | Safety device for stopping an uncontrolled movement away of an elevator car | |
US8544611B2 (en) | Elevator safety system with bar to prevent shaft entry | |
CN220283456U (en) | Lifting limiting mechanism and double-column lifter |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20120214 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
DAX | Request for extension of the european patent (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 615572 Country of ref document: AT Kind code of ref document: T Effective date: 20130615 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602009016302 Country of ref document: DE Effective date: 20130801 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 615572 Country of ref document: AT Kind code of ref document: T Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130906 Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130916 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130905 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: VDEP Effective date: 20130605 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130905 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20131007 Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20131005 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
26N | No opposition filed |
Effective date: 20140306 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602009016302 Country of ref document: DE Effective date: 20140306 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602009016302 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20131229 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20131229 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20140829 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602009016302 Country of ref document: DE Effective date: 20140701 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131231 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131231 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140701 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131229 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131229 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20131231 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20091229 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20130605 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20181015 Year of fee payment: 10 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20191229 |