EP2185331B1 - Device for working workpieces made of wood, plastic and the like and method for working said workpieces - Google Patents

Device for working workpieces made of wood, plastic and the like and method for working said workpieces Download PDF

Info

Publication number
EP2185331B1
EP2185331B1 EP08801576A EP08801576A EP2185331B1 EP 2185331 B1 EP2185331 B1 EP 2185331B1 EP 08801576 A EP08801576 A EP 08801576A EP 08801576 A EP08801576 A EP 08801576A EP 2185331 B1 EP2185331 B1 EP 2185331B1
Authority
EP
European Patent Office
Prior art keywords
workpiece
clamping
workpieces
clamped
carriages
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Not-in-force
Application number
EP08801576A
Other languages
German (de)
French (fr)
Other versions
EP2185331A1 (en
Inventor
Uwe Motzkau
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Michael Weinig AG
Original Assignee
Michael Weinig AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Michael Weinig AG filed Critical Michael Weinig AG
Priority to SI200830258T priority Critical patent/SI2185331T1/en
Publication of EP2185331A1 publication Critical patent/EP2185331A1/en
Application granted granted Critical
Publication of EP2185331B1 publication Critical patent/EP2185331B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B27WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
    • B27MWORKING OF WOOD NOT PROVIDED FOR IN SUBCLASSES B27B - B27L; MANUFACTURE OF SPECIFIC WOODEN ARTICLES
    • B27M1/00Working of wood not provided for in subclasses B27B - B27L, e.g. by stretching
    • B27M1/08Working of wood not provided for in subclasses B27B - B27L, e.g. by stretching by multi-step processes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B27WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
    • B27FDOVETAILED WORK; TENONS; SLOTTING MACHINES FOR WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES
    • B27F1/00Dovetailed work; Tenons; Making tongues or grooves; Groove- and- tongue jointed work; Finger- joints
    • B27F1/02Making tongues or grooves, of indefinite length

Definitions

  • the invention relates to a device for processing workpieces made of wood, plastic and the like according to the preamble of claim 1 and a method for processing such workpieces according to the preamble of claim 6 and 12 respectively.
  • EP-A-1 810 802 the workpiece is clamped on one side by individual collets, which can be positioned independently of one another along the workpiece.
  • the clamping device consists of two feed elements, which are limited relative to each other adjustable to adjust the length of the clamping device to the length of the workpiece to be clamped.
  • the invention has the object of providing the generic device and the generic method in such a way that the workpieces can be clamped reliably and flexibly, without the need for a complex adjustment is required.
  • the tensioning device consists of the first and the second tensioning carriages, which can each be positioned independently of one another.
  • the workpieces can be flexibly tensioned with the tensioning carriages, depending on the length and the area in which machining is to take place.
  • the individual clamping carriages can be moved to the desired position of the workpieces in the longitudinal direction, so that the workpieces can be optimally tensioned for subsequent processing. This makes it easy to position the clamping carriages and clamp the workpiece with them so that a workpiece area is accessible for machining.
  • the workpiece can be clamped with the first and second clamping carriages from two sides to about half the width.
  • the first tensioning carriages are arranged in mirror image to the second tensioning carriages. This makes it very easy to keep the workpieces always clamped in the transfer of the first to the second tensioner.
  • the clamping carriages each have an upper and a lower collet, which clamp the workpiece at the top and at the bottom. As a result, the workpiece can be clamped securely with the clamping carriage, so that it is held reliably during processing.
  • At least one of the first clamping carriages, with which the workpiece is clamped is provided with at least one stop for the workpiece, it can be clamped with exact position.
  • the stop is adjustable transversely to the direction of movement of the clamping carriage.
  • a simple adaptation of the clamping carriage to different widths workpieces is possible.
  • the clamping carriages are moved synchronously with the clamped workpiece.
  • the workpiece to be machined is first clamped transversely to the feed direction to about half the width. Then the workpiece is machined on one side. Then the workpiece is stretched so that it is clamped from the opposite side to about half the width. In the further course, the workpiece is then further processed.
  • the workpiece always remains clamped during re-clamping.
  • the first tensioning carriages clamp the workpiece while it is engaged by the second tensioning carriages. Only when the second clamping carriages have clamped the workpiece, the collets of the first clamping carriages are released. In this way it is ensured that the workpiece during transfer or when re-clamping its intended for a high-quality processing position.
  • the workpiece is guided through two successive processing stations and processed there each.
  • different processing methods can be used.
  • the workpiece is machined differently in at least one, but preferably in both processing stations.
  • sawing, milling or drilling operations can be performed on the workpiece.
  • At least one workpiece is simultaneously processed in each case in two processing stations.
  • Each workpiece is clamped with corresponding clamping carriages.
  • workpieces 1 made of wood are processed in a manner to be described on at least two opposite sides.
  • the elongate workpieces 1 are fed transversely to their longitudinal direction via a transverse conveyor 2.
  • the workpieces 1 may previously be planed or otherwise processed, for example.
  • the workpieces 1 pass from the cross conveyor 2 on clamping carriage 3, on which the workpieces 1 are tightened.
  • the device has several tensioning carriages 3, each for can be moved and positioned individually. Depending on the length of the workpiece 1, a corresponding number of clamping carriage 3 is used to clamp the workpiece 1.
  • the clamping carriage 3 can be moved individually in the longitudinal direction of the workpieces 1 and in the feed direction 6, the workpieces 1 can be stretched flexibly, depending on the length and depending on the area where machining is to be performed on the workpiece.
  • the tensioning carriage 3 are then moved with the tensioned workpiece 1 at a synchronous speed.
  • the workpiece 1 for example, processed longitudinally or positioned for processing.
  • the tensioning carriage 3 On the tensioning carriage 3, the workpieces are transported along a transport path 4.
  • the workpieces 1 are stretched on the tensioning carriage 3 so that they are transported in their longitudinal direction through the device.
  • a first processing station 5 the workpieces are processed at least on their right in the direction of transport 6 long side.
  • a transfer area 7 in which the workpieces 1 are taken over by second tensioning carriage 8, which are arranged approximately in mirror image to the first tensioning carriage 3.
  • second tensioning carriage 8 On the second clamping carriage 8, the machined on the right longitudinal side workpieces 1 are recorded so that they can be processed in a second processing station 9 at least on its left in the transport direction 6 longitudinal side.
  • the processed on both sides of the workpieces 1 1 handed over a cross conveyor 10, which transports the workpieces 1 transversely to its longitudinal direction from the device and optionally supplies a downstream processing.
  • the clamping carriage 8 are as well as the clamping carriage 3 independently moved and positioned individually.
  • the workpieces 1 are taken over in a manner to be described by the clamping carriage 8 so that they can be further processed in the processing station 9.
  • the tensioning carriage 8 are also moved with the tensioned workpiece 1 at a synchronous speed.
  • the tensioning carriage 3 travel on a rail 11, which is located on the left in the transport direction 6 longitudinal side of the transport path.
  • the tensioning carriage 8 run on a rail 12 which is provided on the right in the transport direction 6 longitudinal side of the transport path 4. In the transfer area 7, the rails 11, 12 overlap each other. This makes it possible that the clamping carriage 3, 8 can be positioned side by side so that the workpiece 1 can be taken over without change in position of the second clamping carriage 8.
  • part of the tensioning carriage 3 is initially in a parking position 13.
  • a different number of tensioning carriages 3 is used.
  • Each tensioning carriage 3 has an upper and a lower collet 14, 15 (FIG. Fig. 6 ), with which the workpiece 1 at the top and bottom 18, 19 can be clamped.
  • At least the upper collet 14 is vertically adjustable to the transport direction 6, so that the workpiece 1 can easily get on the clamping carriage 3 and can be stretched on it.
  • the adjustment is preferably pneumatic, but can also be done hydraulically or by electric motor.
  • the lower collet 15 is height-adjustable to pass the workpiece 1 in a manner to be described to the second clamping carriage 8 can.
  • a support could be provided, which is advantageous height adjustable or easily lowered.
  • each clamping carriage 3 is advantageous with at least one stop 17 (FIG. Fig. 6 ), which is adjustable transversely to the transport direction 6.
  • the stop 17 By means of the stop 17, the workpieces 1 can be accurately aligned with the tensioning carriage 3, before being tensioned with the collets 14, 15 on the tensioning carriage 3.
  • the upper collets 14 are height adjustable.
  • the lower collets 15 serve as a support for the workpiece 1.
  • the upper and the lower collets 14, 15 are mutually adjustable in opposite directions.
  • the two collets 14, 15 extend on the top and the bottom 18, 19 of the workpiece 1 only so far that they do not interfere with or affect the processing of the workpiece 1 in the processing station 5.
  • the stop 17 may also be provided as a separate unit in the device, that is not on the clamping carriage 3. Even then, the workpieces 1 can be clamped exactly on the clamping carriage 3.
  • the processing station 5 has a plurality of processing units, in the embodiment a saw 20, a drilling unit 21 and a milling unit 22.
  • the saw 20 With the saw 20, the workpiece 1 is first sawed transversely to its longitudinal direction to the required length. It is possible to design the saw 20 or the circular saw blade so that they can be set at an angle, so that the workpiece can be sawn at the end face also at an angle.
  • the drilling unit 21 has at least one drill 23, with which the required holes can be mounted in the workpiece.
  • the drill 23 on the right in the transport direction 6 longitudinal side 24 of the workpiece 1 introduce the holes.
  • the drilling unit 21 is advantageously pivotable about different axes, so that the holes can not only be introduced vertically into the longitudinal side 24, but also at different angles and / or inclined. It is also possible to adjust the drilling unit 21 so that holes can be made with the drill 23 in the upper side 18 of the workpiece 1. These holes can be perpendicular to the workpiece top 18, but also at different angles to her. Since the clamping carriage 3 are each arranged at greater distances from each other, the holes can be provided easily in the area between. Also in the end faces of the workpiece 1 holes can be attached.
  • the right longitudinal side 24 of the workpiece 1 is processed.
  • the workpiece 1 does not have to be machined over the entire length of the longitudinal side 24. It is possible to make only at certain points on the long side 24 milling, as determined by the Fig. 2 to 5 will be explained in one embodiment.
  • the workpieces can be processed 1 to about half the cross section on the entire longitudinal side with high accuracy and quality in the flow.
  • each tensioning carriage 8 After passing through the processing station 5, the tensioning carriage 3 reach the rail 11 in the transfer area 7. Here are the second tensioning carriage 8.
  • Each tensioning carriage 8 also has collets 25, 26 (FIG. Fig. 1 and 6 ), which are arranged according to the collets 14, 15 in pairs one above the other. With the collets 25, 26, the workpiece 1 is clamped to the top 18 and bottom 19. The collets 25, 26 extend from the right longitudinal side 24 in the direction of the left in the direction of transport 6 longitudinal side 27 of the workpiece. 1
  • the machined in the processing station 5 workpiece 1 is passed to the clamping carriage 8.
  • the clamping carriage 3, 8 are arranged in the transfer area 7 to each other so that the collets 25, 26 of the clamping carriage 8 are opposite to the collets 14, 15 of the clamping carriage 3.
  • This has the advantage that the workpiece 1 may initially remain clamped on the tensioning carriage 3 when the collets 25, 26 are applied to the workpiece 1.
  • the collets 14, 15 of the clamping carriage 3 are lifted so that the clamping carriage 3 can go back to the starting position to clamp in the region of the cross conveyor 2, the next workpiece 1.
  • the workpiece 1 With the clamping carriage 8, the workpiece 1 is transported through the processing station 9. It has several processing units, in the embodiment a drilling unit 28 with at least one drill 29, then a milling unit 30 and finally a saw unit 31. With the drill 29 of the drilling unit 28 holes can be mounted in the workpiece. In the in Fig. 1 shown position, a bore in the left in the transport direction 6 longitudinal side 27 of the workpiece 1 is introduced with the drill 29.
  • the drilling unit 28 is advantageously adjustable about different axes, so that the drill 29 can be brought into different positions with respect to the workpiece 1. Thus, with the drill 29 on the top 18 of the workpiece 1 a bore can be introduced.
  • this hole not only perpendicular to the transport direction 6, but depending on the setting of the drilling unit 28 in different angles of inclination. Also in the longitudinal side 27 and in the end face 36, 37 can be introduced in different directions extending bores, depending on the position of the drill 29th
  • corresponding milling work on the workpiece 1 are made, for example, on the longitudinal side 27 or at the end face.
  • the cutting unit 31 following the milling unit 30 has a chain saw 32, with which slots in the workpiece 1 can be produced.
  • the saw unit 31 or the chain saw 32 can be set in different positions so that slits running on the workpiece 1 in different directions can be attached.
  • the chainsaw 32 can also be adjusted so that, for example, at the end face of the workpiece 1, a corresponding slot can be sawn.
  • the tensioning carriages 8 After leaving the processing station 9, the tensioning carriages 8 reach the area of the transverse conveyor 10. After loosening the collets 25, 26, the machined workpiece 1 is transferred to the transverse conveyor 10. Then the tensioning carriage 8 drive back into the transfer area, to take over the next, in the meantime in the processing station 5 machined workpiece 1.
  • the transfer of the workpiece 1 in the transfer area 7 is advantageously carried out automatically.
  • the clamping carriage 3, 8 are independently adjustable in the transport direction 6, the workpiece 1 can be optimally clamped.
  • the Fig. 2 to 5 show by way of example a workpiece 1, which has been processed in the two processing stations 5, 9.
  • the exemplified workpiece 1 is a Kehlsparren having the longitudinal sides 24 and 27. Near the two ends, a groove 33, 34 is provided in the longitudinal side 24, which has been introduced by the milling unit 22 of the processing station 5. In the area between the grooves 33, 34, which extend over the thickness of the workpiece 1, the longitudinal side 24 is flat.
  • the end faces 36, 37 are bevelled and profiled.
  • the end face 36 is roof-shaped in cross section, while the end face 37 has a V-shaped recess 38 over its length.
  • the profiling of the previously obliquely sawn end faces 36, 37 can be performed with the milling unit 22 or 30.
  • the end face 36 can also be processed by two saw cuts in two different pivot positions of the saw.
  • the workpiece 1 according to the Fig. 2 to 5 is to be understood only as an example. From the machining of this workpiece results that in the respective processing stations 5, 9 not all processing units must be used. Depending on the processing task, only one or only two or also all three units are used in the processing stations 5, 9.
  • the number of processing units in the processing stations 5, 9 is also only exemplary.
  • the processing stations may have fewer or more processing units, as exemplified in Fig. 1 is shown.
  • the processing stations 5, 9 may contain different numbers and / or different types of processing units, in addition to the described example, a marking unit, with which the workpieces 1 itself or any reference lines for the later use of the workpieces can be marked.
  • the processing units in the processing stations 5, 9 are advantageously interchangeable, so that it is possible, depending on the processing task, to load the corresponding processing units into the respective processing station 5 and / or 9.
  • various tools can be substituted, depending on the type of processing task.
  • the necessary tools are available in tool magazines near the respective processing units, from which they can be removed automatically and quickly and loaded into the processing unit.
  • the workpieces 1 are processed in two steps from the right and left, with the workpieces are clamped during these operations.
  • the workpieces 1 can be processed in the pass on the entire longitudinal side with high accuracy and quality.
  • the clamping carriage 3 and 8 can be easily moved next to each other in the transfer area 7, the support and the lower collet 15, 26 of the clamping carriage 3, 8 slightly downwards adjustable. To transfer the pads or the lower collets 15 of those clamping carriage, which do not tension the workpiece, lowered. Likewise, it is also possible to slightly raise the still clamped with the clamping carriage 3 workpiece when entering the transfer area, so that the clamping carriage 3, 8 can be easily moved next to each other.
  • the workpieces 1 can first be sawn at both end faces 36, 37. Subsequently, the one longitudinal side of the workpieces is partially or over their entire length machined by milling and / or drilling.
  • the device can also be designed mirror-inverted to the X and / or Y axis.
  • the workpieces are in plan view accordingly FIG. 1 seen from the bottom right fed, the passage direction through the device is from right to left and the removal advantageous to the top left.
  • the feeder In a mirror-inverted arrangement to the Y axis, the feeder would be from top left, the direction of passage from left to right, and the bottom right removal; and finally, in a mirror-inverted arrangement to the X and Y axes, the feeder would be from the bottom left, the pass direction would also be from left to right, and the top right.
  • the first tensioning carriages 3 are always opposite the feeder provided and executed with the stops, or in the area of the first tensioning carriage, a separate stop for the workpieces is provided opposite the feed.
  • only one processing station is provided in the device in which the workpiece can be processed completely and on all sides.
  • the transfer of the workpieces can be done in the processing station or in the area before or after this processing station, the removal before or after this processing station.
  • the production capacity is significantly limited in such training.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Forests & Forestry (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • Adornments (AREA)
  • Electrical Discharge Machining, Electrochemical Machining, And Combined Machining (AREA)
  • Diaphragms For Electromechanical Transducers (AREA)
  • Chemical And Physical Treatments For Wood And The Like (AREA)
  • Veneer Processing And Manufacture Of Plywood (AREA)

Abstract

The device comprises a clamping device for the workpieces (1), comprising a collet chuck (14). With said method, the workpiece (1) is clamped, transported in the feed direction and worked. In order to design the device and the method such that the workpieces (1) can be clamped in a reliable and flexible manner, without requiring an extensive adjustment device, the clamping device comprises two first clamping carriages (3) that can be positioned independently from each other and two second clamping carriages (8) that can be positioned independently from each other and clamp the workpiece (1) from the other side than the first clamping carriages (3). With the method, the workpiece (1) is clamped transversely to the feed direction to approximately half the width, then one side of the workpiece (1) is worked, and the workpiece (1) is then reclamped such that it is clamped from the opposite side to approximately half the width. Then the workpiece (1) is worked further. The device and the method ensure optimum and reliable working of the workpieces (1).

Description

Die Erfindung betrifft eine Vorrichtung zum Bearbeiten von Werkstücken aus Holz, Kunststoff und dergleichen nach dem Oberbegriff des Anspruches 1 sowie ein Verfahren zur Bearbeitung solcher Werkstücke nach dem Oberbegriff des Anspruches 6 bzw. 12.The invention relates to a device for processing workpieces made of wood, plastic and the like according to the preamble of claim 1 and a method for processing such workpieces according to the preamble of claim 6 and 12 respectively.

Es sind Vorrichtungen bekannt ( EP-A-1 281 491 ), bei denen die Werkstücke in Vorschubeinheiten eingespannt werden, die mit Spannzangen zum Einspannen der Werkstücke versehen sind. Die Spannzangen liegen zumindest über den größten Teil der Länge des Werkstückes nebeneinander. Üblicherweise werden alle Spannzangen zum Einspannen des Werkstückes eingesetzt. Sollen an bestimmten Bereichen des Werkstückes Bearbeitungen vorgenommen werden, können die üblicherweise dort liegenden Spannzangen abgesenkt werden, so dass der entsprechende Werkstückbereich für die Bearbeitung zugänglich ist. Die Vorschubeinheiten sowie die Verstelleinrichtungen für die Spannzangen sind aufwändig und verteuern die Herstellung der Vorrichtung.Devices are known ( EP-A-1 281 491 ), in which the workpieces are clamped in feed units, which are provided with collets for clamping the workpieces. The collets lie next to each other at least over most of the length of the workpiece. Usually, all collets are used for clamping the workpiece. If machining operations are to be carried out on specific areas of the workpiece, the collets usually located there can be lowered so that the corresponding workpiece area is accessible for machining. The feed units and the adjustment for the collets are complex and expensive to manufacture the device.

Bei einer anderen bekannten Vorrichtung ( EP-A-1 810 802 ) wird das Werkstück an einer Seite durch einzelne Spannzangen eingespannt, die längs des Werkstückes unabhängig voneinander positionierbar sind.In another known device ( EP-A-1 810 802 ), the workpiece is clamped on one side by individual collets, which can be positioned independently of one another along the workpiece.

Bei einer anderen bekannten Vorrichtung ( EP-A-1 600 254 ) besteht die Spanneinrichtung aus zwei Vorschubelementen, die begrenzt relativ zueinander verstellbar sind, um die Länge der Spanneinrichtung an die Länge des zu spannenden Werkstückes anzupassen.In another known device ( EP-A-1 600 254 ) The clamping device consists of two feed elements, which are limited relative to each other adjustable to adjust the length of the clamping device to the length of the workpiece to be clamped.

Der Erfindung liegt die Aufgabe zugrunde, die gattungsgemäße Vorrichtung und das gattungsgemäße Verfahren so auszubilden, dass die Werkstücke zuverlässig und flexibel eingespannt werden können, ohne dass hierfür eine aufwändige Verstelleinrichtung erforderlich ist.The invention has the object of providing the generic device and the generic method in such a way that the workpieces can be clamped reliably and flexibly, without the need for a complex adjustment is required.

Diese Aufgabe wird bei der gattungsgemäßen Vorrichtung erfindungsgemäß mit den kennzeichnenden Merkmalen des Anspruches 1 und beim gattungsgemäßen Verfahren erfindungsgemäß mit den kennzeichnenden Merkmalen des Anspruches 6 bzw. 12 gelöst.This object is achieved according to the invention in the generic device with the characterizing features of claim 1 and in the generic method according to the invention with the characterizing features of claim 6 and 12.

Bei der erfindungsgemäßen Vorrichtung besteht die Spanneinrichtung aus den ersten und den zweiten Spannwagen, die jeweils unabhängig voneinander positioniert werden können. Dadurch können die Werkstücke je nach Länge und je nach Bereich, in dem eine Bearbeitung erfolgen soll, mit den Spannwagen flexibel gespannt werden. Die einzelnen Spannwagen lassen sich an die gewünschte Stelle der Werkstücke in deren Längsrichtung verfahren, so dass die Werkstücke für die nachfolgende Bearbeitung optimal gespannt werden können. So ist es problemlos möglich, die Spannwagen so zu positionieren und mit ihnen das Werkstück so einzuspannen, dass ein Werkstückbereich für eine Bearbeitung zugänglich ist. Das Werkstück kann mit den ersten und zweiten Spannwagen von zwei Seiten aus bis etwa auf halbe Breite gespannt werden.In the apparatus according to the invention, the tensioning device consists of the first and the second tensioning carriages, which can each be positioned independently of one another. As a result, the workpieces can be flexibly tensioned with the tensioning carriages, depending on the length and the area in which machining is to take place. The individual clamping carriages can be moved to the desired position of the workpieces in the longitudinal direction, so that the workpieces can be optimally tensioned for subsequent processing. This makes it easy to position the clamping carriages and clamp the workpiece with them so that a workpiece area is accessible for machining. The workpiece can be clamped with the first and second clamping carriages from two sides to about half the width.

Vorteilhaft sind die ersten Spannwagen spiegelbildlich zu den zweiten Spannwagen angeordnet. Dadurch ist es sehr einfach möglich, die Werkstücke bei der Übergabe von den ersten zu den zweiten Spannwagen stets eingespannt zu halten.Advantageously, the first tensioning carriages are arranged in mirror image to the second tensioning carriages. This makes it very easy to keep the workpieces always clamped in the transfer of the first to the second tensioner.

Die Spannwagen haben jeweils eine obere und eine untere Spannzange, die das Werkstück an der Ober- und an der Unterseite spannen. Dadurch kann das Werkstück mit den Spannwagen sicher eingespannt werden, so dass es bei der Bearbeitung zuverlässig gehalten wird.The clamping carriages each have an upper and a lower collet, which clamp the workpiece at the top and at the bottom. As a result, the workpiece can be clamped securely with the clamping carriage, so that it is held reliably during processing.

Wenn zumindest einer der ersten Spannwagen, mit denen das Werkstück eingespannt wird, mit wenigstens einem Anschlag für das Werkstück versehen ist, lässt es sich positionsgenau einspannen.If at least one of the first clamping carriages, with which the workpiece is clamped, is provided with at least one stop for the workpiece, it can be clamped with exact position.

Vorteilhaft ist der Anschlag quer zur Verfahrrichtung der Spannwagen einstellbar. Dadurch ist eine einfache Anpassung der Spannwagen an unterschiedlich breite Werkstücke möglich.Advantageously, the stop is adjustable transversely to the direction of movement of the clamping carriage. As a result, a simple adaptation of the clamping carriage to different widths workpieces is possible.

Die Spannwagen werden mit dem eingespannten Werkstück synchron verfahren.The clamping carriages are moved synchronously with the clamped workpiece.

Beim erfindungsgemäßen Verfahren wird das zu bearbeitende Werkstück quer zur Vorschubrichtung zunächst bis auf etwa halbe Breite eingespannt. Anschließend wird das Werkstück an einer Seite bearbeitet. Dann wird das Werkstück so gespannt, dass es von der gegenüberliegenden Seite aus bis etwa auf halbe Breite eingespannt wird. Im weiteren Verlauf wird dann das Werkstück weiter bearbeitet.In the method according to the invention, the workpiece to be machined is first clamped transversely to the feed direction to about half the width. Then the workpiece is machined on one side. Then the workpiece is stretched so that it is clamped from the opposite side to about half the width. In the further course, the workpiece is then further processed.

Vorteilhaft ist es, wenn das Werkstück beim Umspannen stets eingespannt bleibt. So halten beispielsweise die ersten Spannwagen das Werkstück eingespannt, während es von den zweiten Spannwagen erfasst wird. Erst wenn die zweiten Spannwagen das Werkstück eingespannt haben, werden die Spannzangen der ersten Spannwagen gelöst. Auf diese Weise ist gewährleistet, dass das Werkstück bei der Übergabe bzw. beim Umspannen seine für eine qualitativ hochwertige Bearbeitung vorgesehene Lage beibehält.It is advantageous if the workpiece always remains clamped during re-clamping. For example, the first tensioning carriages clamp the workpiece while it is engaged by the second tensioning carriages. Only when the second clamping carriages have clamped the workpiece, the collets of the first clamping carriages are released. In this way it is ensured that the workpiece during transfer or when re-clamping its intended for a high-quality processing position.

Zweckmäßig wird das Werkstück an der einen Seite, in Vorschubrichtung gesehen, eingespannt und an der gegenüberliegenden Seite bearbeitet.Appropriately, the workpiece on one side, seen in the feed direction, clamped and machined on the opposite side.

Es ist aber auch möglich, dass das Werkstück an der einen Seite, in Vorschubrichtung gesehen, eingespannt und an dieser Seite bearbeitet wird.But it is also possible that the workpiece on one side, seen in the feed direction, clamped and machined on this side.

Bei einer vorteilhaften Ausführungsform wird das Werkstück durch zwei hintereinander liegende Bearbeitungsstationen geführt und dort jeweils bearbeitet. Dadurch können unterschiedliche Bearbeitungsverfahren eingesetzt werden.In an advantageous embodiment, the workpiece is guided through two successive processing stations and processed there each. As a result, different processing methods can be used.

Vorteilhaft wird das Werkstück in zumindest der einen, vorzugsweise aber in beiden Bearbeitungsstationen unterschiedlich bearbeitet. So können am Werkstück beispielsweise Säge-, Fräs- oder Bohroperationen durchgeführt werden.Advantageously, the workpiece is machined differently in at least one, but preferably in both processing stations. For example, sawing, milling or drilling operations can be performed on the workpiece.

Bei einer Verfahrensweise wird gleichzeitig jeweils mindestens ein Werkstück in zwei Bearbeitungsstationen bearbeitet. Dabei ist jedes Werkstück mit entsprechenden Spannwagen eingespannt.In one procedure, at least one workpiece is simultaneously processed in each case in two processing stations. Each workpiece is clamped with corresponding clamping carriages.

Weitere Merkmale der Erfindung ergeben sich aus den weiteren Ansprüchen, der Beschreibung und den Zeichnungen.Further features of the invention will become apparent from the other claims, the description and the drawings.

Die Erfindung wird nachstehend anhand eines in den Zeichnungen dargestellten Ausführungsbeispieles näher erläutert. Es zeigen

Fig. 1
in schematischer Darstellung eine erfindungsgemäße Vorrichtung zur Bearbeitung von Werkstücken,
Fig. 2
ein in der Vorrichtung gemäß Fig. 1 bearbeitetes Werkstück in per- spektivischer Darstellung,
Fig. 3
das Werkstück gemäß Fig. 2 in Seitenansicht,
Fig. 4
das Werkstück gemäß Fig. 2 in Stirnansicht,
Fig. 5
einen Schnitt längs der Linie V-V in Fig. 3,
Fig. 6
in schematischer Darstellung die Spanneinrichtung zweier Spann- wagen der erfindungsgemäßen Vorrichtung gemäß Fig. 1.
The invention will be explained in more detail with reference to an embodiment shown in the drawings. Show it
Fig. 1
a schematic representation of an inventive device for machining workpieces,
Fig. 2
a in the device according to Fig. 1 machined workpiece in perspective view,
Fig. 3
the workpiece according to Fig. 2 in side view,
Fig. 4
the workpiece according to Fig. 2 in front view,
Fig. 5
a section along the line VV in Fig. 3 .
Fig. 6
in a schematic representation of the clamping device of two tensioning carriages of the device according to the invention Fig. 1 ,

In der Vorrichtung werden Werkstücke 1 aus Holz in noch zu beschreibender Weise an zumindest zwei einander gegenüberliegenden Seiten bearbeitet. Die länglichen Werkstücke 1 werden über einen Querförderer 2 quer zu ihrer Längsrichtung zugeführt. Die Werkstücke 1 können zuvor beispielsweise gehobelt oder auf andere Weise bearbeitet sein. Die Werkstücke 1 gelangen vom Querförderer 2 auf Spannwagen 3, auf denen die Werkstücke 1 festgespannt werden. Die Vorrichtung hat mehrere Spannwagen 3, die jeweils für sich einzeln verfahr- und positionierbar sind. Je nach Länge des Werkstückes 1 wird eine entsprechende Zahl von Spannwagen 3 verwendet, um das Werkstück 1 festzuspannen. Da die Spannwagen 3 einzeln in Längsrichtung der Werkstücke 1 bzw. in Vorschubrichtung 6 verfahren werden können, können die Werkstücke 1 je nach Länge und je nach Bereich, wo eine Bearbeitung am Werkstück durchgeführt werden soll, flexibel gespannt werden. Die Spannwagen 3 werden dann mit dem gespannten Werkstück 1 mit synchroner Geschwindigkeit verfahren. Hierbei kann das Werkstück 1 beispielsweise längsbearbeitet oder für eine Bearbeitung positioniert werden. Auf den Spannwagen 3 werden die Werkstücke längs einer Transportbahn 4 transportiert. Die Werkstücke 1 sind so auf den Spannwagen 3 gespannt, dass sie in ihrer Längsrichtung durch die Vorrichtung transportiert werden. In einer ersten Bearbeitungsstation 5 werden die Werkstücke zumindest an ihrer in Transportrichtung 6 rechten Längsseite bearbeitet.In the device, workpieces 1 made of wood are processed in a manner to be described on at least two opposite sides. The elongate workpieces 1 are fed transversely to their longitudinal direction via a transverse conveyor 2. The workpieces 1 may previously be planed or otherwise processed, for example. The workpieces 1 pass from the cross conveyor 2 on clamping carriage 3, on which the workpieces 1 are tightened. The device has several tensioning carriages 3, each for can be moved and positioned individually. Depending on the length of the workpiece 1, a corresponding number of clamping carriage 3 is used to clamp the workpiece 1. Since the clamping carriage 3 can be moved individually in the longitudinal direction of the workpieces 1 and in the feed direction 6, the workpieces 1 can be stretched flexibly, depending on the length and depending on the area where machining is to be performed on the workpiece. The tensioning carriage 3 are then moved with the tensioned workpiece 1 at a synchronous speed. Here, the workpiece 1, for example, processed longitudinally or positioned for processing. On the tensioning carriage 3, the workpieces are transported along a transport path 4. The workpieces 1 are stretched on the tensioning carriage 3 so that they are transported in their longitudinal direction through the device. In a first processing station 5, the workpieces are processed at least on their right in the direction of transport 6 long side.

In Transportrichtung 6 hinter der Bearbeitungsstation 5 befindet sich ein Übergabebereich 7, in dem die Werkstücke 1 von zweiten Spannwagen 8 übernommen werden, die etwa spiegelbildlich zu den ersten Spannwagen 3 angeordnet sind. Auf den zweiten Spannwagen 8 werden die an der rechten Längsseite bearbeiteten Werkstücke 1 so aufgenommen, dass sie in einer zweiten Bearbeitungsstation 9 zumindest an ihrer in Transportrichtung 6 linken Längsseite bearbeitet werden können. Nach Durchlaufen der Bearbeitungsstation 9 werden die an beiden Längsseiten bearbeiteten Werkstücke 1 einem Querförderer 10 übergeben, der die Werkstücke 1 quer zu ihrer Längsrichtung aus der Vorrichtung abtransportiert und gegebenenfalls einer nachgelagerten Bearbeitung zuführt. Auch die Spannwagen 8 sind ebenso wie die Spannwagen 3 unabhängig voneinander einzeln verfahr- und positionierbar. Die Werkstücke 1 werden in noch zu beschreibender Weise von den Spannwagen 8 übernommen, damit sie in der Bearbeitungsstation 9 weiter bearbeitet werden können. Die Spannwagen 8 werden ebenfalls mit dem gespannten Werkstück 1 mit synchroner Geschwindigkeit verfahren.In the transport direction 6 behind the processing station 5 is a transfer area 7, in which the workpieces 1 are taken over by second tensioning carriage 8, which are arranged approximately in mirror image to the first tensioning carriage 3. On the second clamping carriage 8, the machined on the right longitudinal side workpieces 1 are recorded so that they can be processed in a second processing station 9 at least on its left in the transport direction 6 longitudinal side. After passing through the processing station 9, the processed on both sides of the workpieces 1 1 handed over a cross conveyor 10, which transports the workpieces 1 transversely to its longitudinal direction from the device and optionally supplies a downstream processing. Also, the clamping carriage 8 are as well as the clamping carriage 3 independently moved and positioned individually. The workpieces 1 are taken over in a manner to be described by the clamping carriage 8 so that they can be further processed in the processing station 9. The tensioning carriage 8 are also moved with the tensioned workpiece 1 at a synchronous speed.

Die Spannwagen 3 fahren auf einer Schiene 11, die sich an der in Transportrichtung 6 linken Längsseite der Transportbahn befindet. Die Spannwagen 8 laufen auf einer Schiene 12, die an der in Transportrichtung 6 rechten Längsseite der Transportbahn 4 vorgesehen ist. Im Übergabebereich 7 überlappen die Schienen 11, 12 einander. Dadurch ist es möglich, dass die Spannwagen 3, 8 so nebeneinander positioniert werden können, dass das Werkstück 1 ohne Lageveränderung von den zweiten Spannwagen 8 übernommen werden kann.The tensioning carriage 3 travel on a rail 11, which is located on the left in the transport direction 6 longitudinal side of the transport path. The tensioning carriage 8 run on a rail 12 which is provided on the right in the transport direction 6 longitudinal side of the transport path 4. In the transfer area 7, the rails 11, 12 overlap each other. This makes it possible that the clamping carriage 3, 8 can be positioned side by side so that the workpiece 1 can be taken over without change in position of the second clamping carriage 8.

Ein Teil der Spannwagen 3 befindet sich im Ausführungsbeispiel zunächst in einer Parkstellung 13. Je nach Länge und/oder Querschnitt der Werkstücke 1 wird eine unterschiedliche Zahl von Spannwagen 3 eingesetzt. Jeder Spannwagen 3 hat eine obere und eine untere Spannzange 14, 15 (Fig. 6), mit denen das Werkstück 1 an der Ober- und Unterseite 18, 19 eingespannt werden kann. Zumindest die obere Spannzange 14 ist senkrecht zur Transportrichtung 6 höhenverstellbar, damit das Werkstück 1 problemlos auf den Spannwagen 3 gelangen und auf ihm gespannt werden kann. Die Verstellung erfolgt vorzugsweise pneumatisch, kann aber auch hydraulisch oder elektromotorisch erfolgen. Vorteilhaft ist auch die untere Spannzange 15 höhenverstellbar, um das Werkstück 1 in noch zu beschreibender Weise an die zweiten Spannwagen 8 übergeben zu können. Anstelle der unteren Spannzange 15 könnte auch eine Auflage vorgesehen sein, die vorteilhaft höhenverstellbar oder leicht absenkbar ist.In the exemplary embodiment, part of the tensioning carriage 3 is initially in a parking position 13. Depending on the length and / or cross section of the workpieces 1, a different number of tensioning carriages 3 is used. Each tensioning carriage 3 has an upper and a lower collet 14, 15 (FIG. Fig. 6 ), with which the workpiece 1 at the top and bottom 18, 19 can be clamped. At least the upper collet 14 is vertically adjustable to the transport direction 6, so that the workpiece 1 can easily get on the clamping carriage 3 and can be stretched on it. The adjustment is preferably pneumatic, but can also be done hydraulically or by electric motor. Advantageously, the lower collet 15 is height-adjustable to pass the workpiece 1 in a manner to be described to the second clamping carriage 8 can. Instead of the lower collet 15 and a support could be provided, which is advantageous height adjustable or easily lowered.

Die Werkstücke 1 werden im Bereich des Querförderers 2 auf den Spannwagen 3 gespannt. Damit das Werkstück 1 eine genaue Ausrichtung hat, ist jeder Spannwagen 3 vorteilhaft mit wenigstens einem Anschlag 17 (Fig. 6) versehen, der quer zur Transportrichtung 6 verstellbar ist. Mittels des Anschlags 17 können die Werkstücke 1 genau auf den Spannwagen 3 ausgerichtet werden, bevor sie mit den Spannzangen 14, 15 auf den Spannwagen 3 gespannt werden. Grundsätzlich reicht es aus, wenn nur die oberen Spannzangen 14 höhenverstellbar sind. Dann dienen die unteren Spannzangen 15 als Auflage für das Werkstück 1. Es ist aber auch möglich, dass die oberen und die unteren Spannzangen 14, 15 gegensinnig zueinander verstellbar sind. Die beiden Spannzangen 14, 15 erstrecken sich auf der Ober- und der Unterseite 18, 19 des Werkstückes 1 nur so weit, dass sie die Bearbeitung des Werkstückes 1 in der Bearbeitungsstation 5 nicht stören bzw. beeinträchtigen.The workpieces 1 are clamped in the region of the transverse conveyor 2 on the tensioning carriage 3. So that the workpiece 1 has an exact alignment, each clamping carriage 3 is advantageous with at least one stop 17 (FIG. Fig. 6 ), which is adjustable transversely to the transport direction 6. By means of the stop 17, the workpieces 1 can be accurately aligned with the tensioning carriage 3, before being tensioned with the collets 14, 15 on the tensioning carriage 3. Basically, it is sufficient if only the upper collets 14 are height adjustable. Then, the lower collets 15 serve as a support for the workpiece 1. It is also possible that the upper and the lower collets 14, 15 are mutually adjustable in opposite directions. The two collets 14, 15 extend on the top and the bottom 18, 19 of the workpiece 1 only so far that they do not interfere with or affect the processing of the workpiece 1 in the processing station 5.

Der Anschlag 17 kann auch als separate Einheit in der Vorrichtung vorgesehen sein, das heißt nicht am Spannwagen 3. Auch dann lassen sich die Werkstücke 1 exakt auf dem Spannwagen 3 festspannen.The stop 17 may also be provided as a separate unit in the device, that is not on the clamping carriage 3. Even then, the workpieces 1 can be clamped exactly on the clamping carriage 3.

Die Bearbeitungsstation 5 hat mehrere Bearbeitungseinheiten, im Ausführungsbeispiel eine Säge 20, ein Bohraggregat 21 und eine Fräseinheit 22. Mit der Säge 20 wird das Werkstück 1 zunächst quer zu seiner Längsrichtung auf die erforderliche Länge gesägt. Es ist möglich, die Säge 20 bzw. das Kreissägeblatt winklig einstellbar auszubilden, so dass das Werkstück stirnseitig auch unter einem Winkel gesägt werden kann.The processing station 5 has a plurality of processing units, in the embodiment a saw 20, a drilling unit 21 and a milling unit 22. With the saw 20, the workpiece 1 is first sawed transversely to its longitudinal direction to the required length. It is possible to design the saw 20 or the circular saw blade so that they can be set at an angle, so that the workpiece can be sawn at the end face also at an angle.

Das Bohraggregat 21 hat wenigstens einen Bohrer 23, mit dem die erforderlichen Bohrungen im Werkstück angebracht werden können. So kann der Bohrer 23 an der in Transportrichtung 6 rechten Längsseite 24 des Werkstückes 1 (Fig. 6) die Bohrungen einbringen. Das Bohraggregat 21 ist vorteilhaft um verschiedene Achsen schwenkbar, so dass die Bohrungen nicht nur senkrecht in die Längsseite 24 eingebracht werden können, sondern auch unter verschiedenen Winkeln und/oder geneigt. Es ist auch möglich, das Bohraggregat 21 so einzustellen, dass mit dem Bohrer 23 in der Oberseite 18 des Werkstückes 1 Bohrungen eingebracht werden können. Diese Bohrungen können senkrecht zur Werkstückoberseite 18, aber auch unter unterschiedlichen Winkeln zu ihr liegen. Da die Spannwagen 3 jeweils mit größeren Abständen voneinander angeordnet sind, können auch im Bereich dazwischen die Bohrungen problemlos vorgesehen werden. Auch in den Stirnseiten des Werkstückes 1 können Bohrungen angebracht werden.The drilling unit 21 has at least one drill 23, with which the required holes can be mounted in the workpiece. Thus, the drill 23 on the right in the transport direction 6 longitudinal side 24 of the workpiece 1 (FIG. Fig. 6 ) introduce the holes. The drilling unit 21 is advantageously pivotable about different axes, so that the holes can not only be introduced vertically into the longitudinal side 24, but also at different angles and / or inclined. It is also possible to adjust the drilling unit 21 so that holes can be made with the drill 23 in the upper side 18 of the workpiece 1. These holes can be perpendicular to the workpiece top 18, but also at different angles to her. Since the clamping carriage 3 are each arranged at greater distances from each other, the holes can be provided easily in the area between. Also in the end faces of the workpiece 1 holes can be attached.

Mit der Fräseinheit 22 wird die rechte Längsseite 24 des Werkstückes 1 bearbeitet. Hierbei muss das Werkstück 1 nicht über die gesamte Länge der Längsseite 24 bearbeitet werden. Es ist möglich, nur an bestimmten Stellen der Längsseite 24 Fräsarbeiten vorzunehmen, wie dies anhand der Fig. 2 bis 5 an einem Ausführungsbeispiel noch erläutert werden wird.With the milling unit 22, the right longitudinal side 24 of the workpiece 1 is processed. In this case, the workpiece 1 does not have to be machined over the entire length of the longitudinal side 24. It is possible to make only at certain points on the long side 24 milling, as determined by the Fig. 2 to 5 will be explained in one embodiment.

Besonders vorteilhaft durch die Art der Werkstückspannung und die Verfahrensweise ist, dass die Werkstücke 1 bis etwa zum halben Querschnitt an der kompletten Längsseite mit hoher Genauigkeit und Qualität im Durchlauf bearbeitet werden können.Particularly advantageous due to the nature of the workpiece clamping and the procedure is that the workpieces can be processed 1 to about half the cross section on the entire longitudinal side with high accuracy and quality in the flow.

Nach dem Durchlauf durch die Bearbeitungsstation 5 gelangen die Spannwagen 3 auf der Schiene 11 in den Übergabebereich 7. Hier befinden sich die zweiten Spannwagen 8. Jeder Spannwagen 8 hat ebenfalls Spannzangen 25, 26 (Fig. 1 und 6), die entsprechend den Spannzangen 14, 15 paarweise übereinander angeordnet sind. Mit den Spannzangen 25, 26 wird das Werkstück 1 an der Oberseite 18 und an der Unterseite 19 gespannt. Die Spannzangen 25, 26 erstrecken sich von der rechten Längsseite 24 aus in Richtung auf die in Transportrichtung 6 linke Längsseite 27 des Werkstückes 1.After passing through the processing station 5, the tensioning carriage 3 reach the rail 11 in the transfer area 7. Here are the second tensioning carriage 8. Each tensioning carriage 8 also has collets 25, 26 (FIG. Fig. 1 and 6 ), which are arranged according to the collets 14, 15 in pairs one above the other. With the collets 25, 26, the workpiece 1 is clamped to the top 18 and bottom 19. The collets 25, 26 extend from the right longitudinal side 24 in the direction of the left in the direction of transport 6 longitudinal side 27 of the workpiece. 1

Im Übergabebereich 7 wird das in der Bearbeitungsstation 5 bearbeitete Werkstück 1 den Spannwagen 8 übergeben. Die Spannwagen 3, 8 sind im Übergabebereich 7 so zueinander angeordnet, dass die Spannzangen 25, 26 der Spannwagen 8 gegenüberliegend zu den Spannzangen 14, 15 der Spannwagen 3 liegen. Dies hat den Vorteil, dass das Werkstück 1 zunächst auf den Spannwagen 3 eingespannt bleiben kann, wenn die Spannzangen 25, 26 an das Werkstück 1 angelegt werden. Sobald das Werkstück 1 mit den Spannzangen 25, 26 eingespannt ist, werden die Spannzangen 14, 15 der Spannwagen 3 abgehoben, so dass die Spannwagen 3 zurück in die Ausgangsstellung fahren können, um im Bereich des Querförderers 2 das nächste Werkstück 1 einzuspannen.In the transfer area 7, the machined in the processing station 5 workpiece 1 is passed to the clamping carriage 8. The clamping carriage 3, 8 are arranged in the transfer area 7 to each other so that the collets 25, 26 of the clamping carriage 8 are opposite to the collets 14, 15 of the clamping carriage 3. This has the advantage that the workpiece 1 may initially remain clamped on the tensioning carriage 3 when the collets 25, 26 are applied to the workpiece 1. Once the workpiece 1 is clamped with the collets 25, 26, the collets 14, 15 of the clamping carriage 3 are lifted so that the clamping carriage 3 can go back to the starting position to clamp in the region of the cross conveyor 2, the next workpiece 1.

Mit den Spannwagen 8 wird das Werkstück 1 durch die Bearbeitungsstation 9 transportiert. Sie hat mehrere Bearbeitungseinheiten, im Ausführungsbeispiel ein Bohraggregat 28 mit wenigstens einem Bohrer 29, anschließend eine Fräseinheit 30 und schließlich eine Sägeeinheit 31. Mit dem Bohrer 29 des Bohraggregates 28 können im Werkstück 1 Bohrungen angebracht werden. In der in Fig. 1 dargestellten Stellung wird mit dem Bohrer 29 eine Bohrung in der in Transportrichtung 6 linken Längsseite 27 des Werkstückes 1 eingebracht. Das Bohraggregat 28 ist vorteilhaft um unterschiedliche Achsen einstellbar, so dass der Bohrer 29 in unterschiedliche Lagen bezüglich des Werkstückes 1 gebracht werden kann. So kann mit dem Bohrer 29 auf der Oberseite 18 des Werkstückes 1 eine Bohrung eingebracht werden. Dabei kann diese Bohrung nicht nur senkrecht zur Transportrichtung 6 liegen, sondern je nach Einstellung des Bohraggregates 28 auch in unterschiedlichen Neigungswinkeln. Auch in der Längsseite 27 und in der Stirnseite 36, 37 können in unterschiedlichen Richtungen verlaufende Bohrungen eingebracht werden, je nach Stellung des Bohrers 29.With the clamping carriage 8, the workpiece 1 is transported through the processing station 9. It has several processing units, in the embodiment a drilling unit 28 with at least one drill 29, then a milling unit 30 and finally a saw unit 31. With the drill 29 of the drilling unit 28 holes can be mounted in the workpiece. In the in Fig. 1 shown position, a bore in the left in the transport direction 6 longitudinal side 27 of the workpiece 1 is introduced with the drill 29. The drilling unit 28 is advantageously adjustable about different axes, so that the drill 29 can be brought into different positions with respect to the workpiece 1. Thus, with the drill 29 on the top 18 of the workpiece 1 a bore can be introduced. In this case, this hole not only perpendicular to the transport direction 6, but depending on the setting of the drilling unit 28 in different angles of inclination. Also in the longitudinal side 27 and in the end face 36, 37 can be introduced in different directions extending bores, depending on the position of the drill 29th

Mit der anschließenden Fräseinheit 30 werden entsprechende Fräsarbeiten am Werkstück 1 vorgenommen, beispielsweise an dessen Längsseite 27 oder auch an dessen Stirnseite.With the subsequent milling unit 30 corresponding milling work on the workpiece 1 are made, for example, on the longitudinal side 27 or at the end face.

Die der Fräseinheit 30 nachfolgende Sägeeinheit 31 hat eine Kettensäge 32, mit der Schlitze im Werkstück 1 hergestellt werden können. Die Sägeeinheit 31 bzw. die Kettensäge 32 lässt sich in unterschiedliche Lagen einstellen, so dass am Werkstück 1 in unterschiedlichen Richtungen verlaufende Schlitze angebracht werden können. Die Kettensäge 32 lässt sich auch so einstellen, dass beispielsweise an der Stirnseite des Werkstückes 1 ein entsprechender Schlitz gesägt werden kann.The cutting unit 31 following the milling unit 30 has a chain saw 32, with which slots in the workpiece 1 can be produced. The saw unit 31 or the chain saw 32 can be set in different positions so that slits running on the workpiece 1 in different directions can be attached. The chainsaw 32 can also be adjusted so that, for example, at the end face of the workpiece 1, a corresponding slot can be sawn.

Nach Verlassen der Bearbeitungsstation 9 gelangen die Spannwagen 8 in den Bereich des Querförderers 10. Nach Lösen der Spannzangen 25, 26 wird das bearbeitete Werkstück 1 dem Querförderer 10 übergeben. Anschließend fahren die Spannwagen 8 wieder zurück in den Übergabebereich, um das nächste, in der Zwischenzeit in der Bearbeitungsstation 5 bearbeitete Werkstück 1 zu übernehmen.After leaving the processing station 9, the tensioning carriages 8 reach the area of the transverse conveyor 10. After loosening the collets 25, 26, the machined workpiece 1 is transferred to the transverse conveyor 10. Then the tensioning carriage 8 drive back into the transfer area, to take over the next, in the meantime in the processing station 5 machined workpiece 1.

Die Übergabe des Werkstückes 1 im Übergabebereich 7 erfolgt vorteilhaft automatisch.The transfer of the workpiece 1 in the transfer area 7 is advantageously carried out automatically.

Da die Spannwagen 3, 8 unabhängig voneinander in Transportrichtung 6 einstellbar sind, kann das Werkstück 1 optimal eingespannt werden. Die Fig. 2 bis 5 zeigen beispielhaft ein Werkstück 1, das in den beiden Bearbeitungsstationen 5, 9 bearbeitet worden ist. Das beispielhaft dargestellte Werkstück 1 ist ein Kehlsparren, der die Längsseiten 24 und 27 aufweist. Nahe den beiden Enden ist in der Längsseite 24 jeweils eine Nut 33, 34 vorgesehen, die durch die Fräseinheit 22 der Bearbeitungsstation 5 eingebracht worden ist. Im Bereich zwischen den Nuten 33, 34, die sich über die Dicke des Werkstückes 1 erstrecken, ist die Längsseite 24 eben.Since the clamping carriage 3, 8 are independently adjustable in the transport direction 6, the workpiece 1 can be optimally clamped. The Fig. 2 to 5 show by way of example a workpiece 1, which has been processed in the two processing stations 5, 9. The exemplified workpiece 1 is a Kehlsparren having the longitudinal sides 24 and 27. Near the two ends, a groove 33, 34 is provided in the longitudinal side 24, which has been introduced by the milling unit 22 of the processing station 5. In the area between the grooves 33, 34, which extend over the thickness of the workpiece 1, the longitudinal side 24 is flat.

An der gegenüberliegenden Längsseite 27 ist eine über deren Länge sich erstreckende Vertiefung 35 vorgesehen, die mit der Fräseinheit 30 der Bearbeitungsstation 9 am Werkstück 1 angebracht worden ist.On the opposite longitudinal side 27 is provided over its length extending recess 35 which has been attached to the milling unit 30 of the processing station 9 on the workpiece 1.

Die Stirnseiten 36, 37 sind abgeschrägt und profiliert. Die Stirnseite 36 ist im Querschnitt dachförmig ausgebildet, während die Stirnseite 37 über ihre Länge eine V-förmige Vertiefung 38 aufweist. Die Profilierung der vorher schräg gesägten Stirnseiten 36, 37 kann mit der Fräseinheit 22 oder 30 ausgeführt werden. Die Stirnseite 36 kann auch durch zwei Sägeschnitte in zwei unterschiedlichen Schwenkstellungen der Säge bearbeitet sein.The end faces 36, 37 are bevelled and profiled. The end face 36 is roof-shaped in cross section, while the end face 37 has a V-shaped recess 38 over its length. The profiling of the previously obliquely sawn end faces 36, 37 can be performed with the milling unit 22 or 30. The end face 36 can also be processed by two saw cuts in two different pivot positions of the saw.

Das Werkstück 1 gemäß den Fig. 2 bis 5 ist nur als Beispiel zu verstehen. Aus der Bearbeitung dieses Werkstückes ergibt sich, dass in den jeweiligen Bearbeitungsstationen 5, 9 nicht jeweils alle Bearbeitungseinheiten eingesetzt werden müssen. Je nach Bearbeitungsaufgabe werden in den Bearbeitungsstationen 5, 9 nur eine oder nur zwei oder auch alle drei Einheiten eingesetzt.The workpiece 1 according to the Fig. 2 to 5 is to be understood only as an example. From the machining of this workpiece results that in the respective processing stations 5, 9 not all processing units must be used. Depending on the processing task, only one or only two or also all three units are used in the processing stations 5, 9.

Die Anzahl der Bearbeitungseinheiten in den Bearbeitungsstationen 5, 9 ist ebenfalls nur beispielhaft. Die Bearbeitungsstationen können weniger oder auch mehr Bearbeitungseinheiten aufweisen, als beispielhaft in Fig. 1 dargestellt ist. Die Bearbeitungsstationen 5, 9 können unterschiedliche Zahlen und/oder unterschiedliche Arten von Bearbeitungseinheiten enthalten, neben den beschriebenen beispielsweise auch eine Markiereinheit, mit der die Werkstücke 1 selbst oder irgendwelche Bezugslinien für den späteren Einsatz der Werkstücke gekennzeichnet werden können. Vorteilhaft sind die Bearbeitungseinheiten in den Bearbeitungsstationen 5, 9 auswechselbar, so dass es möglich ist, je nach Bearbeitungsaufgabe die entsprechenden Bearbeitungseinheiten in die jeweilige Bearbeitungsstation 5 und/oder 9 einzuwechseln.The number of processing units in the processing stations 5, 9 is also only exemplary. The processing stations may have fewer or more processing units, as exemplified in Fig. 1 is shown. The processing stations 5, 9 may contain different numbers and / or different types of processing units, in addition to the described example, a marking unit, with which the workpieces 1 itself or any reference lines for the later use of the workpieces can be marked. The processing units in the processing stations 5, 9 are advantageously interchangeable, so that it is possible, depending on the processing task, to load the corresponding processing units into the respective processing station 5 and / or 9.

Ebenso können in einzelne Bearbeitungseinheiten, wie zum Beispiel die Fräseinheiten 22, 30 oder die Bohraggregate 21, 28, verschiedene Werkzeuge eingewechselt werden, je nach Art der Bearbeitungsaufgabe. Vorteilhaft stehen die notwendigen Werkzeuge in Werkzeugmagazinen nahe den jeweiligen Bearbeitungseinheiten zur Verfügung, aus denen sie automatisch und schnell entnommen und in die Bearbeitungseinheit eingewechselt werden können.Likewise, in individual processing units, such as the milling units 22, 30 or the drilling units 21, 28, various tools can be substituted, depending on the type of processing task. Advantageously, the necessary tools are available in tool magazines near the respective processing units, from which they can be removed automatically and quickly and loaded into the processing unit.

Mit der Vorrichtung ist eine flexible Bearbeitung von großen Holzbauteilen, zum Beispiel im Holzbau, möglich. Die Werkstücke 1 werden in zwei Schritten von rechts und links bearbeitet, wobei die Werkstücke während dieser Bearbeitungen jeweils eingespannt sind. Die Werkstücke 1 können im Durchlauf an der kompletten Längsseite mit hoher Genauigkeit und Qualität bearbeitet werden.With the device, a flexible processing of large wooden components, for example in timber construction, possible. The workpieces 1 are processed in two steps from the right and left, with the workpieces are clamped during these operations. The workpieces 1 can be processed in the pass on the entire longitudinal side with high accuracy and quality.

Da die Werkstücke 1 bei der Übergabe in der beschriebenen Weise immer eingespannt bleiben, ist ein vollautomatischer Ablauf und eine hohe Bearbeitungsgenauigkeit gewährleistet.Since the workpieces 1 always remain clamped in the transfer in the manner described, a fully automatic process and a high processing accuracy is guaranteed.

Damit die Spannwagen 3 und 8 im Übergabebereich 7 problemlos nebeneinander verfahren werden können, ist die Auflage bzw. die untere Spannzange 15, 26 der Spannwagen 3, 8 geringfügig nach unten verstellbar. Zur Übergabe werden die Auflagen bzw. die unteren Spannzangen 15 derjenigen Spannwagen, die das Werkstück nicht spannen, abgesenkt. Ebenso ist es auch möglich, das mit den Spannwagen 3 noch eingespannte Werkstück beim Einfahren in den Übergabebereich geringfügig anzuheben, damit die Spannwagen 3, 8 problemlos nebeneinander gefahren werden können.Thus, the clamping carriage 3 and 8 can be easily moved next to each other in the transfer area 7, the support and the lower collet 15, 26 of the clamping carriage 3, 8 slightly downwards adjustable. To transfer the pads or the lower collets 15 of those clamping carriage, which do not tension the workpiece, lowered. Likewise, it is also possible to slightly raise the still clamped with the clamping carriage 3 workpiece when entering the transfer area, so that the clamping carriage 3, 8 can be easily moved next to each other.

In der Vorrichtung können die Werkstücke 1 zunächst an beiden Stirnseiten 36, 37 gesägt werden. Anschließend wird die eine Längsseite der Werkstücke teilweise oder über ihre gesamte Länge durch Fräsen und/oder Bohren bearbeitet.In the apparatus, the workpieces 1 can first be sawn at both end faces 36, 37. Subsequently, the one longitudinal side of the workpieces is partially or over their entire length machined by milling and / or drilling.

Bei einem anderen Verfahrensablauf ist es möglich, beispielsweise nur die in Vorschubrichtung 6 vordere Stirnseite der Werkstücke 1 zu sägen und anschließend eine gewünschte Bearbeitung durchzuführen. Danach kann die in Vorschubrichtung rückwärtige Stirnseite der Werkstücke 1 gesägt werden.In another method, it is possible, for example, only to saw in the feed direction 6 front end of the workpieces 1 and then perform a desired processing. Thereafter, the rear in the feed direction end side of the workpieces 1 can be sawn.

Auf jeden Fall kann eine Fräsoperation auch an beiden Stirnseiten 36, 37 der Werkstücke 1 vorgenommen werden.In any case, a milling operation on both end faces 36, 37 of the workpieces 1 can be made.

Die Vorrichtung kann abweichend vom dargestellten Ausführungsbeispiel auch spiegelbildlich zur X- und/oder Y-Achse ausgebildet sein. Bei einer Ausführung spiegelbildlich zur X-Achse werden die Werkstücke in Draufsicht entsprechend Figur 1 gesehen von rechts unten zugeführt, die Durchlaufrichtung durch die Vorrichtung ist von rechts nach links und die Entnahme vorteilhaft nach links oben. Bei einer Anordnung spiegelbildlich zur Y-Achse wäre die Zuführung von links oben, die Durchlaufrichtung von links nach rechts und die Entnahme rechts unten; und schließlich wäre bei einer Anordnung spiegelbildlich zur X- und Y-Achse die Zuführung von links unten, die Durchlaufrichtung ebenfalls von links nach rechts und die Entnahme nach rechts oben. Die ersten Spannwagen 3 sind immer gegenüber der Zuführung vorgesehen und mit den Anschlägen ausgeführt, bzw. im Bereich der ersten Spannwagen ist gegenüber der Zuführung ein separater Anschlag für die Werkstücke vorgesehen.Deviating from the illustrated embodiment, the device can also be designed mirror-inverted to the X and / or Y axis. In an embodiment mirror image of the X-axis, the workpieces are in plan view accordingly FIG. 1 seen from the bottom right fed, the passage direction through the device is from right to left and the removal advantageous to the top left. In a mirror-inverted arrangement to the Y axis, the feeder would be from top left, the direction of passage from left to right, and the bottom right removal; and finally, in a mirror-inverted arrangement to the X and Y axes, the feeder would be from the bottom left, the pass direction would also be from left to right, and the top right. The first tensioning carriages 3 are always opposite the feeder provided and executed with the stops, or in the area of the first tensioning carriage, a separate stop for the workpieces is provided opposite the feed.

In einer weiteren, vom dargestellten Ausführungsbeispiel abweichenden Ausführung ist in der Vorrichtung nur eine Bearbeitungsstation vorgesehen, in der das Werkstück komplett und auf allen Seiten bearbeitet werden kann. Die Übergabe der Werkstücke kann in der Bearbeitungsstation oder im Bereich vor oder nach dieser Bearbeitungsstation erfolgen, die-Entnahme vor oder nach dieser Bearbeitungsstation. Allerdings ist die Produktionsleistung bei einer solchen Ausbildung wesentlich eingeschränkt.In another, deviating from the illustrated embodiment embodiment, only one processing station is provided in the device in which the workpiece can be processed completely and on all sides. The transfer of the workpieces can be done in the processing station or in the area before or after this processing station, the removal before or after this processing station. However, the production capacity is significantly limited in such training.

Claims (12)

  1. Device for working of oblong workpieces (1) made of wood, plastic and the like with a clamping device comprising chucks for the workpieces (1) having an upper side and an under side (18, 19), on which an upper and a lower chuck (14, 15; 25, 26) abut in a clamping position, characterised in that the clamping device is composed of at least two first clamping carriages (3), which are positionable independently from each other and of at least two second clamping carriages (8) which are positionable independently from each other, that the clamping carriages (3, 8) comprise the upper and the lower chuck (14, 15; 25, 26) respectively which clamp the workpiece (1) between the upper and the underside (18, 19), and that the chucks (14, 15) of the first clamping carriages (3) clamp the workpiece (1) from the one longitudinal side and the chucks (25, 26) of the second clamping carriages (8) from the other longitudinal side.
  2. Device according to claim 1,
    characterised in that the first clamping carriages (3) are arranged inversely to the second clamping carriages (8).
  3. Device according to claim 1 or 2,
    characterised in that at least one of the clamping carriages (3, 8) is provided with at least one stop (17) for the workpiece (1).
  4. Device according to claim 3,
    characterised in that the stop (17) is adjustable transversely to a transport direction (6) of the clamping carriages (3, 8).
  5. Device according to one of the claims 1 to 4,
    characterised in that the clamping carriages (3, 8) with the clamped workpiece (1) are transportable synchronously.
  6. Method for working workpieces made of wood, plastic and the like with a device according to one of the claims 1 to 5, where by the workpiece is clamped, is transported in the feed direction and is worked,
    characterised in that the workpiece (1) is clamped transversely to the feed direction (6) to approximately half width, that subsequently one side of the workpiece (1) is worked, that next the workpiece (1) is reclamped in such a way that it is clamped from the opposite side to approximately half width, and that subsequently the workpiece (1) is worked further.
  7. Method according to claim 6,
    characterised in that the workpiece (1) remains clamped continuously during reclamping.
  8. Method according to claim 6 or 7,
    characterised in that the workpiece (1) is clamped at one side in the feed direction (6) and is worked at the opposite side.
  9. Method according to claim 6 or 7,
    characterised in that the workpiece (1) is clamped at one side in the feed direction (6) and worked on this side.
  10. Method according to one of the claims 6 to 9,
    characterised in that the workpiece (1) is transported through two working stations (5, 9) for working.
  11. Method according to claim 10,
    characterised in that the workpiece (1) is worked differently in at least one of the working stations (5, 9).
  12. Method for working workpieces made of wood, plastic and the like with a device according to one of the claims 1 to 5, where by the workpiece is clamped, is transported in feed direction and is worked,
    characterised in that at two working stations (5, 9) simultaneously at least one workpiece (1) is worked respectively.
EP08801576A 2007-08-28 2008-08-14 Device for working workpieces made of wood, plastic and the like and method for working said workpieces Not-in-force EP2185331B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SI200830258T SI2185331T1 (en) 2007-08-28 2008-08-14 Device for working workpieces made of wood, plastic and the like and method for working said workpieces

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102007040580A DE102007040580B3 (en) 2007-08-28 2007-08-28 Device for processing workpieces made of wood, plastic and the like, and method for processing such workpieces
PCT/EP2008/006677 WO2009030348A1 (en) 2007-08-28 2008-08-14 Device for working workpieces made of wood, plastic and the like and method for working said workpieces

Publications (2)

Publication Number Publication Date
EP2185331A1 EP2185331A1 (en) 2010-05-19
EP2185331B1 true EP2185331B1 (en) 2011-03-02

Family

ID=39865126

Family Applications (1)

Application Number Title Priority Date Filing Date
EP08801576A Not-in-force EP2185331B1 (en) 2007-08-28 2008-08-14 Device for working workpieces made of wood, plastic and the like and method for working said workpieces

Country Status (5)

Country Link
EP (1) EP2185331B1 (en)
AT (1) ATE500042T1 (en)
DE (2) DE102007040580B3 (en)
SI (1) SI2185331T1 (en)
WO (1) WO2009030348A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102528864B (en) * 2012-01-16 2013-11-13 佛山市顺德区新马木工机械设备有限公司 Numerical-control multi-shaft seat mortising machine
DE102014222423A1 (en) 2014-11-03 2016-05-04 Homag Holzbearbeitungssysteme Gmbh jig
DE102020002319A1 (en) * 2020-04-09 2021-10-14 Michael Weinig Aktiengesellschaft Clamping device for workpieces made of wood, plastic, aluminum and the like as well as system with such a clamping device

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19752685A1 (en) * 1997-11-28 1999-07-01 Ima Maschinenfabriken Klessmann Gmbh Machine for processing window frame spars
DE10137839C5 (en) * 2001-08-02 2012-06-21 Michael Weinig Ag Machine for machining workpieces made of wood, plastic and the like
DE102004027888B4 (en) * 2004-05-27 2007-01-04 Michael Weinig Ag Feed unit for a machine for processing workpieces made of wood, plastic or the like, and method for processing such workpieces
ITMO20060021A1 (en) * 2006-01-20 2007-07-21 Scm Group Spa MACHINE TOOL

Also Published As

Publication number Publication date
SI2185331T1 (en) 2011-07-29
WO2009030348A1 (en) 2009-03-12
ATE500042T1 (en) 2011-03-15
DE502008002754D1 (en) 2011-04-14
DE102007040580B3 (en) 2009-04-09
EP2185331A1 (en) 2010-05-19

Similar Documents

Publication Publication Date Title
EP1281491B1 (en) Apparatus and method for machining wooden, plastic or similar workpieces
EP1600254B1 (en) Conveying unit for machine for working workpieces and method for machining such workpieces
DE10305570B4 (en) Method and processing plant for processing wood workpieces
EP0922547B1 (en) Apparatus for manufacturing window frame members
EP1688227B1 (en) Method of operation of a wood working machine and wood working machine
WO2016045968A1 (en) Machining device
EP2127829A1 (en) Board separation assembly
EP2165811A2 (en) Machine and method for machining workpieces made of wood, plastic and similar
EP2193895B1 (en) Board partitioning device and method for operating same
EP2185331B1 (en) Device for working workpieces made of wood, plastic and the like and method for working said workpieces
EP2810754B1 (en) Method and apparatus for processing a tree trunk
DE3533404A1 (en) Woodworking machine
DE202006001351U1 (en) Sawing machine for sawing workpiece has bandsaw as sawing tool, with at least two diverting pulleys in vertical plane
DE3307809A1 (en) Wood-working machine
DE102006009421A1 (en) moulder
EP0292864B1 (en) Wood-working machine
DE3536221C2 (en)
EP0813941B2 (en) Machine tool for working elongated material
CH658016A5 (en) WOODWORKING MACHINE FOR TAPPING AND LENGTH PROFILING OF WOODS, ESPECIALLY WINDOWWOODS.
WO2019115009A1 (en) Method for cutting elongate workpieces made of wood, plastic and the like into slats, and machine tool for carrying out such a method
DE2749546A1 (en) Wooden window component cutting and shaping machine - has two workpieces fed through side by side, with profile cut unit added
DE3717411C2 (en)
DE19721521C2 (en) Numerically controlled tenoning machine
DE19703240B4 (en) Device for handling and processing preferably plate-shaped workpieces
DE19927742C1 (en) Device for cutting tree trunks in a quarter cut and associated saw station

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20100329

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA MK RS

RIN1 Information on inventor provided before grant (corrected)

Inventor name: MOTZKAU, UWE

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

DAX Request for extension of the european patent (deleted)
GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REF Corresponds to:

Ref document number: 502008002754

Country of ref document: DE

Date of ref document: 20110414

Kind code of ref document: P

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502008002754

Country of ref document: DE

Effective date: 20110414

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: PATENTANWALTSBUERO JEAN HUNZIKER AG

REG Reference to a national code

Ref country code: NL

Ref legal event code: VDEP

Effective date: 20110302

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110602

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110603

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110613

LTIE Lt: invalidation of european patent or patent extension

Effective date: 20110302

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110602

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

REG Reference to a national code

Ref country code: IE

Ref legal event code: FD4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110704

Ref country code: IE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110702

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20111205

BERE Be: lapsed

Owner name: MICHAEL WEINIG A.G.

Effective date: 20110831

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 502008002754

Country of ref document: DE

Effective date: 20111205

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20110831

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20110831

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 502008002754

Country of ref document: DE

Effective date: 20120301

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20120814

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20110814

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20120301

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20120814

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20110302

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 9

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 10

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20200715

Year of fee payment: 13

REG Reference to a national code

Ref country code: CH

Ref legal event code: PFUS

Owner name: MICHAEL WEINIG AG, DE

Free format text: FORMER OWNER: MICHAEL WEINIG AG, DE

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SI

Payment date: 20200715

Year of fee payment: 13

Ref country code: AT

Payment date: 20200812

Year of fee payment: 13

Ref country code: IT

Payment date: 20200805

Year of fee payment: 13

Ref country code: CH

Payment date: 20200717

Year of fee payment: 13

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 500042

Country of ref document: AT

Kind code of ref document: T

Effective date: 20210814

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210814

REG Reference to a national code

Ref country code: SI

Ref legal event code: KO00

Effective date: 20220406

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210814

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20210831