EP2105679A2 EP09003722A EP09003722A EP2105679A2 EP 2105679 A2 EP2105679 A2 EP 2105679A2 EP 09003722 A EP09003722 A EP 09003722A EP 09003722 A EP09003722 A EP 09003722A EP 2105679 A2 EP2105679 A2 EP 2105679A2
Authority
EP
European Patent Office
Prior art keywords
opening closure
heating boiler
boiler according
opening
housing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP09003722A
Other languages
German (de)
French (fr)
Other versions
EP2105679A3 (en
EP2105679B1 (en
Inventor
Roger DÖNGES
Rüdiger Stock
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Viessmann Werke GmbH and Co KG
Original Assignee
Viessmann Werke GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Viessmann Werke GmbH and Co KG filed Critical Viessmann Werke GmbH and Co KG
Priority to PL09003722T priority Critical patent/PL2105679T3/en
Publication of EP2105679A2 publication Critical patent/EP2105679A2/en
Publication of EP2105679A3 publication Critical patent/EP2105679A3/en
Application granted granted Critical
Publication of EP2105679B1 publication Critical patent/EP2105679B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H1/00Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters
    • F24H1/22Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating
    • F24H1/40Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating with water tube or tubes
    • F24H1/43Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating with water tube or tubes helically or spirally coiled
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H9/00Details
    • F24H9/02Casings; Cover lids; Ornamental panels
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H9/00Details
    • F24H9/14Arrangements for connecting different sections, e.g. in water heaters 
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H9/00Details
    • F24H9/14Arrangements for connecting different sections, e.g. in water heaters 
    • F24H9/146Connecting elements of a heat exchanger
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H9/00Details
    • F24H9/18Arrangement or mounting of grates or heating means
    • F24H9/1809Arrangement or mounting of grates or heating means for water heaters
    • F24H9/1832Arrangement or mounting of combustion heating means, e.g. grates or burners
    • F24H9/1836Arrangement or mounting of combustion heating means, e.g. grates or burners using fluid fuel

Definitions

  • the invention relates to a heating boiler according to the preamble of patent claim 1.
  • a boiler of the type mentioned is according to EP 1 562 006 A1 known.
  • This consists of a combustion chamber enclosing housing with an opening portion which is formed closable with an opening closure, wherein the opening closure of a first, annular, attachable to the housing part and a second, a burner head for selectively liquid or gaseous fuels receiving, lid-like part formed is.
  • the boiler is after the EP 1 562 006 A1 in particular from a substantially cylindrical jacket housing, in which a helically coiled heat exchanger (so-called Wendelspalt Shileyer) is used, wherein in the center of the heat exchanger, a combustion chamber and between the heat exchanger and the housing wall an exhaust gas collecting chamber are defined with Abgasabbowan gleich, ie that in the combustion chamber through the Combustion exhaust gas flows through precisely defined flow gaps of the heat exchanger in the exhaust gas collection chamber and from there to a corresponding exhaust port.
  • the heat exchanger in this case has an inlet and a discharge connection for a heat transfer medium (typically heating circuit water), wherein these connections are guided through corresponding through openings on the front-side cover elements of the jacket housing.
  • a heat transfer medium typically heating circuit water
  • this lid member On the burner head opposite side of the housing, this lid member is integrally formed and, so to speak, simply inserted into the cylinder jacket.
  • Brennkopf Wenn consists of the opening closure of the above-mentioned, the first annular part, which in the solution after the EP 1 562 006 A1 initially inserted as a single component in the cylinder jacket and attached to this during assembly of the boiler. The then not yet closed, larger part of the opening area is then closed with a second part, the actual lid.
  • this cover On this cover is the burner head, but for example also (which, however, in the EP 1 562 006 A1 not explicitly shown) the pneumatically connected to the combustion head fan attached.
  • the invention has the object to improve a boiler of the type mentioned in particular with regard to its ease of servicing during maintenance.
  • both parts of the opening closure are designed as a functional unit mounted together on the housing, wherein the first, annular part of the opening closure, a component carrier for the fan is arranged.
  • the boiler according to the invention the in FIG. 1 is shown in principle completely (but without enclosing housing, pipes, etc.) consists first of all in a conventional manner from a combustion chamber 1 enclosing, cylindrical housing 2 with an end-side opening portion 3, which is formed closable with an opening closure 4.
  • the opening closure 4 of a first, annular, attachable to the housing part 2 and a second, a burner head 6 for selectively liquid or gaseous fuels receiving, cover-like part 7 is formed.
  • Said burner head 6 is pneumatically connected to a blower 8 arranged at the opening closure 4.
  • the first part 5 of the opening closure 4 has a through-opening 18 for a connecting piece 19 of the heat exchanger 15.
  • the first part 5 of the opening closure 4 in the opening portion 3 of the housing 2 is designed to be inserted (compare in particular FIG. 5 ), wherein particularly preferably the first and the second part 5, 7 of the opening closure 4 made of aluminum, in particular die-cast aluminum, are formed.
  • the aluminum is there especially for fuel oil combustion applications with a suitable coating or shield against corrosive acid attack.
  • FIG. 3 shows the easily negotiable second part 7 of the opening closure 4.
  • FIGS. 6 and 7 the comparable assembly is shown, but in the absence of a corresponding component carrier on the first part 5 of the opening closure 4, all components on the second part 7 of the opening closure 4 must be attached and make them accordingly heavy and unwieldy.
  • the component carrier 9 is arranged protruding in an extension plane of the opening closure 4 on the housing 2 and at least on the blower side is formed as a flat plate.
  • the component carrier 9 is formed as, for example, L-shaped, with its short leg on the first part 5 of the opening closure 4 and also made of aluminum existing carrier.
  • the component carrier 9 has a passage opening 10, to which on the one hand the Fan arranged peripherally to the housing 2 8 and on the other hand connected to the burner head 6 air duct 11 connects, wherein the air duct 11 is attached to the lid-like part 7 and the component carrier 9 is applied without a connection, which allows easy removal of the second part 7 of the opening closure 4, wherein but then the transition region from the fan 8 via the component carrier 9 to the air duct 11 is formed sealed with corresponding sealing means.
  • At least a second component carrier 13 (structurally corresponding to the first one) is arranged on the first part 5 of the opening closure 4, specifically for receiving an oil pump 14, wherein the two (or more) component carrier 9, 13 are distributed in a structurally favorable manner over the circumference of the housing 2, as it were.
  • a housing facing away from the edge 17 of the first part 5 of the opening closure 4 is approximately aligned with the inner surface of the heat exchanger 15.
  • the combustion chamber 1 and the second part 7 of the opening closure 4 have an approximately equal diameter (for example between 20 cm and 50 cm).
  • a sealed groove and tongue connection is provided between the first and the second part 5, 7 (cf. FIG. 4 ), wherein the second part 7 of the opening closure 4 on the first part 5 is screwed.
  • thermal insulation element 20 For thermal insulation is still on the second part 7 of the opening closure 4 combustion chamber side, a thermal insulation element 20 (see, for example, the DE 196 27 961 A1 ) arranged.
  • an ignition transformer 21 and the air duct 11 for example, an air pressure switch 12 is arranged.

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Air Supply (AREA)
  • Feeding And Controlling Fuel (AREA)
  • Combustion Of Fluid Fuel (AREA)

Abstract

The boiler has a housing (2) enclosing a combustion chamber (1) with an opening portion (3), which is formed with an opening connection (4) in a locked manner. The units of the opening connection are formed as functional unit common mountable at the housing, where a component carrier (9) for a fan (8) is arranged on annular unit (5) of the opening connection. The units of the opening connection are made of aluminum.

Description

Die Erfindung betrifft einen Heizkessel gemäß dem Oberbegriff des Patentanspruchs 1.The invention relates to a heating boiler according to the preamble of patent claim 1.

Ein Heizkessel der eingangs genannten Art ist nach der EP 1 562 006 A1 bekannt. Dieser besteht aus einem eine Brennkammer umschließenden Gehäuse mit einem Öffnungsbereich, der mit einem Öffnungsverschluss verschließbar ausgebildet ist, wobei der Öffnungsverschluss aus einem ersten, ringförmigen, am Gehäuse befestigbaren Teil und einem zweiten, einen Brennerkopf für wahlweise flüssige oder gasförmige Brennstoffe aufnehmenden, deckelartigen Teil gebildet ist.A boiler of the type mentioned is according to EP 1 562 006 A1 known. This consists of a combustion chamber enclosing housing with an opening portion which is formed closable with an opening closure, wherein the opening closure of a first, annular, attachable to the housing part and a second, a burner head for selectively liquid or gaseous fuels receiving, lid-like part formed is.

Wie auch der noch zu erläuternde erfindungsgemäße Heizkessel besteht der Heizkessel nach der EP 1 562 006 A1 insbesondere aus einem im wesentlichen zylinderförmigen Mantelgehäuse, in das ein schraubenförmig gewickelter Wärmetauscher (so genannter Wendelspaltwärmetauscher) eingesetzt ist, wobei im Zentrum des Wärmetauschers eine Brennkammer und zwischen dem Wärmetauscher und der Gehäusewand eine Abgassammelkammer mit Abgasabfuhranschluss definiert sind, d. h. das in der Brennkammer durch die Verbrennung entstehende Abgas strömt durch genau definierte Strömungsspalte des Wärmetauschers in die Abgassammelkammer und von dort zu einem entsprechenden Abgasanschluss. Wie zum Beispiel aus Figur 2 der EP 1 562 006 A1 ersichtlich, weist der Wärmetauscher dabei einen Zu- und einen Abfuhranschluss für ein Wärmeträgermedium (typischerweise Heizkreiswasser) auf, wobei diese Anschlüsse durch entsprechende Durchgriffsöffnungen an den stirnseitigen Deckelelementen des Mantelgehäuses geführt sind.Like the still to be explained boiler according to the invention, the boiler is after the EP 1 562 006 A1 in particular from a substantially cylindrical jacket housing, in which a helically coiled heat exchanger (so-called Wendelspaltwärmetauscher) is used, wherein in the center of the heat exchanger, a combustion chamber and between the heat exchanger and the housing wall an exhaust gas collecting chamber are defined with Abgasabfuhranschluss, ie that in the combustion chamber through the Combustion exhaust gas flows through precisely defined flow gaps of the heat exchanger in the exhaust gas collection chamber and from there to a corresponding exhaust port. Like, for example FIG. 2 of the EP 1 562 006 A1 it can be seen, the heat exchanger in this case has an inlet and a discharge connection for a heat transfer medium (typically heating circuit water), wherein these connections are guided through corresponding through openings on the front-side cover elements of the jacket housing.

Auf der dem Brennerkopf gegenüberliegenden Seite des Gehäuses ist dieses Deckelelement einteilig ausgebildet und gewissermaßen einfach in den Zylindermantel eingeschoben. Brennkopfseitig besteht der Öffnungsverschluss aus dem oben bereits erwähnten, ersten ringförmigen Teil, der bei der Lösung nach der EP 1 562 006 A1 bei der Montage des Kessels zunächst als Einzelbauteil in den Zylindermantel eingeschoben und an diesem befestigt wird. Der dann noch nicht verschlossene, größere Teil des Öffnungsbereichs wird anschließend mit einem zweiten Teil, dem eigentlichen Deckel verschlossen. An diesem Deckel ist der Brennerkopf, aber zum Beispiel auch (was allerdings in der EP 1 562 006 A1 nicht explizit dargestellt ist) das pneumatisch mit dem Brennkopf verbundene Gebläse befestigt.On the burner head opposite side of the housing, this lid member is integrally formed and, so to speak, simply inserted into the cylinder jacket. Brennkopfseitig consists of the opening closure of the above-mentioned, the first annular part, which in the solution after the EP 1 562 006 A1 initially inserted as a single component in the cylinder jacket and attached to this during assembly of the boiler. The then not yet closed, larger part of the opening area is then closed with a second part, the actual lid. On this cover is the burner head, but for example also (which, however, in the EP 1 562 006 A1 not explicitly shown) the pneumatically connected to the combustion head fan attached.

Der Erfindung liegt die Aufgabe zugrunde, einen Heizkessel der eingangs genannten Art insbesondere hinsichtlich seiner Servicefreundlichkeit bei der Wartung zu verbessern.The invention has the object to improve a boiler of the type mentioned in particular with regard to its ease of servicing during maintenance.

Diese Aufgabe ist mit einem Heizkessel der eingangs genannten Art durch die im Kennzeichen des Patentanspruchs 1 aufgeführten Merkmale gelöst.This object is achieved with a boiler of the type mentioned by the features listed in the characterizing part of patent claim 1.

Nach der Erfindung ist also vorgesehen, dass beide Teile des Öffnungsverschlusses als Funktionseinheit gemeinsam am Gehäuse montierbar ausgebildet sind, wobei am ersten, ringförmigen Teil des Öffnungsverschlusses ein Komponententräger für das Gebläse angeordnet ist.According to the invention, it is thus provided that both parts of the opening closure are designed as a functional unit mounted together on the housing, wherein the first, annular part of the opening closure, a component carrier for the fan is arranged.

Mit anderen Worten ausgedrückt, wird erfindungsgemäß nicht mehr zunächst nur der erste, ringförmige Teil am Gehäuse und danach erst der zweite am ersten Teil befestigt, sondern beide Teile werden gemeinsam in einem Arbeitsschritt als Funktions- bzw. Montageeinheit am Gehäuse montiert. Zusammen mit der Maßgabe, dass am ersten Teil auch noch (mindestens) ein Komponententräger für das Gebläse (und gegebenenfalls weitere Komponenten wie eine Ölpumpe oder dergleichen) vorgesehen ist, ergibt sich daraus insgesamt erstmals die Möglichkeit, am zweiten Teil insbesondere nur den Brennerkopf anzuordnen, was bei Wartungsarbeiten den erheblichen Vorteil hat, dass nur der zweite, auf diese Weise deutlich leichtere Teil des Öffnungsverschlusses demontiert und bewegt werden muss. Bei der Lösung nach der EP 1 562 006 A1 sind dagegen am zweiten Teil des Öffnungsverschlusses alle weiteren Komponenten wie Gebläse, Ölpumpe etc. befestigt, d. h. in diesem Fall ist dieser zweite Teil deutlich schwerer und dementsprechend unhandlicher (siehe auch Figur 6 und 7).In other words, according to the invention, it is no longer initially only the first, annular part on the housing and then the second attached to the first part, but both parts are mounted together in one step as a functional or mounting unit on the housing. Together with the proviso that on the first part also (at least) a component carrier for the fan (and optionally other components such as an oil pump or the like) is provided, this results in total for the first time the possibility to arrange on the second part in particular only the burner head, which during maintenance the considerable Advantage is that only the second, in this way much lighter part of the opening closure must be dismantled and moved. In the solution after the EP 1 562 006 A1 On the other hand, on the second part of the opening closure, all other components such as fan, oil pump, etc. are attached, ie in this case, this second part is significantly heavier and accordingly more cumbersome (see also FIGS. 6 and 7 ).

Andere vorteilhafte Weiterbildungen ergeben sich aus den abhängigen Patentansprüchen.Other advantageous developments emerge from the dependent claims.

Der Vollständigkeit halber wird noch auf die DE 101 14 490 C1 hingewiesen.The sake of completeness is still on the DE 101 14 490 C1 pointed.

Der erfindungsgemäße Heizkessel einschließlich seiner vorteilhaften Weiterbildungen gemäß den abhängigen Patentansprüchen wird nachfolgend anhand der zeichnerischen Darstellung eines bevorzugten Ausführungsbeispiels näher erläutert.The boiler according to the invention including its advantageous developments according to the dependent claims will be explained in more detail with reference to the drawing of a preferred embodiment.

Es zeigt jeweils perspektivischIt shows each perspective

Figur 1FIG. 1
den erfindungsgemäßen Heizkessel in zusammengebautem Zustand;the boiler according to the invention in assembled condition;
Figur 2FIG. 2
den Heizkessel gemäß Figur 1 bei demontiertem zweiten, deckelartigen Teil des Öffnungsverschlusses;according to the boiler FIG. 1 with disassembled second, lid-like part of the opening closure;
Figur 3FIG. 3
der deckelartige, zweite Teil des Öffnungsverschlusses in Alleinstellung;the lid-like, second part of the opening closure in isolation;
Figur 4FIG. 4
teilweise geschnitten den erfindungsgemäß als Montageeinheit ausgebildeten Öffnungsverschluss;partially cut the invention designed as a mounting unit opening closure;
Figur 5FIG. 5
den erfindungsgemäßen Heizkessel bei vollständig demontiertem Öffnungsverschluss;the boiler according to the invention with completely disassembled opening closure;
Figur 6FIG. 6
eine brennerkopfseitige Ansicht eines Öffnungsverschlusses gemäß dem Stand der Technik; unda burner head side view of an opening closure according to the prior art; and
Figur 7FIG. 7
eine Ansicht des Öffnungsverschlusses gemäß Figur 6 aus der entgegengesetzten Richtung.a view of the opening closure according to FIG. 6 from the opposite direction.

Der erfindungsgemäße Heizkessel, der in Figur 1 im Prinzip vollständig dargestellt ist (allerdings ohne Umschließungsgehäuse, Leitungen etc.) besteht zunächst einmal in an sich bekannter Weise aus einem eine Brennkammer 1 umschließenden, zylinderförmigen Gehäuse 2 mit einem stirnseitigen Öffnungsbereich 3, der mit einem Öffnungsverschluss 4 verschließbar ausgebildet ist. Dabei ist der Öffnungsverschluss 4 aus einem ersten, ringförmigen, am Gehäuse 2 befestigbaren Teil 5 und einem zweiten, einen Brennerkopf 6 für wahlweise flüssige oder gasförmige Brennstoffe aufnehmenden, deckelartigen Teil 7 gebildet. Der genannte Brennerkopf 6 ist pneumatisch mit einem am Öffnungsverschluss 4 angeordneten Gebläse 8 verbunden.The boiler according to the invention, the in FIG. 1 is shown in principle completely (but without enclosing housing, pipes, etc.) consists first of all in a conventional manner from a combustion chamber 1 enclosing, cylindrical housing 2 with an end-side opening portion 3, which is formed closable with an opening closure 4. In this case, the opening closure 4 of a first, annular, attachable to the housing part 2 and a second, a burner head 6 for selectively liquid or gaseous fuels receiving, cover-like part 7 is formed. Said burner head 6 is pneumatically connected to a blower 8 arranged at the opening closure 4.

Mit Verweis auf Figur 2 ist im Gehäuse 2 ein die Brennkammer 1 umschließender, schraubenförmig gewickelter Wärmetauscher 15 und zwischen diesem und dem Gehäuse 2 eine Abgassammelkammer 16 angeordnet. Der erste Teil 5 des Öffnungsverschlusses 4 weist eine Durchgriffsöffnung 18 für einen Anschlussstutzen 19 des Wärmetauschers 15 auf. Außerdem ist der erste Teil 5 des Öffnungsverschlusses 4 in den Öffnungsbereich 3 des Gehäuses 2 einsteckbar ausgebildet (vergleiche hierzu insbesondere Figur 5), wobei besonders bevorzugt der erste und der zweite Teil 5, 7 des Öffnungsverschlusses 4 aus Aluminium, insbesondere Aluminiumdruckguss, gebildet sind. Das Aluminium ist dabei insbesondere für Anwendungen mit Heizölverbrennung mit einer entsprechenden Beschichtung oder Abschirmung gegen korrosiven Säureangriff versehen.With reference to FIG. 2 is in the housing 2 a combustion chamber 1 enclosing, helically wound heat exchanger 15 and disposed between the latter and the housing 2, an exhaust gas collection chamber 16. The first part 5 of the opening closure 4 has a through-opening 18 for a connecting piece 19 of the heat exchanger 15. In addition, the first part 5 of the opening closure 4 in the opening portion 3 of the housing 2 is designed to be inserted (compare in particular FIG. 5 ), wherein particularly preferably the first and the second part 5, 7 of the opening closure 4 made of aluminum, in particular die-cast aluminum, are formed. The aluminum is there especially for fuel oil combustion applications with a suitable coating or shield against corrosive acid attack.

Wesentlich für den erfindungsgemäßen Heizkessel ist nun, dass beide Teile 5, 7 des Öffnungsverschlusses 4 als Funktions- bzw. Montageeinheit gemeinsam am Gehäuse 2 montierbar ausgebildet sind, wobei am ersten, ringförmigen Teil 5 des Öffnungsverschlusses 4 ein Komponententräger 9 für das Gebläse 8 angeordnet ist.Essential for the boiler according to the invention is now that both parts 5, 7 of the opening closure 4 as a function or assembly unit are mounted together mounted on the housing 2, wherein the first, annular part 5 of the opening closure 4, a component carrier 9 is arranged for the fan 8 ,

Der Vorteil der Erfindung wird besonders deutlich, wenn man Figur 3 und Figur 6 bzw. 7 miteinander vergleicht: Figur 3 zeigt den leicht handlebaren zweiten Teil 7 des Öffnungsverschlusses 4. In den Figuren 6 und 7 ist die vergleichbare Baugruppe dargestellt, bei der aber mangels eines entsprechenden Komponententrägers am ersten Teil 5 des Öffnungsverschlusses 4 alle Komponenten am zweiten Teil 7 des Öffnungsverschlusses 4 befestigt sein müssen und diesen entsprechend schwer und unhandlich machen.The advantage of the invention becomes particularly clear when one FIG. 3 and FIG. 6 or 7 compared: FIG. 3 shows the easily negotiable second part 7 of the opening closure 4. In the FIGS. 6 and 7 the comparable assembly is shown, but in the absence of a corresponding component carrier on the first part 5 of the opening closure 4, all components on the second part 7 of the opening closure 4 must be attached and make them accordingly heavy and unwieldy.

Wie sich insbesondere aus Figur 2 deutlich ergibt, ist weiterhin vorgesehen, dass der Komponententräger 9 in einer Erstreckungsebene des Öffnungsverschlusses 4 über das Gehäuse 2 hinausragend angeordnet und mindestens gebläseseitig als ebene Platte ausgebildet ist. Konkret ist der Komponententräger 9 als zum Beispiel L-förmiger, mit seinem kurzen Schenkel am ersten Teil 5 des Öffnungsverschlusses 4 befestigter und ebenfalls aus Aluminium bestehender Träger ausgebildet.As can be seen in particular FIG. 2 clearly shows, is further provided that the component carrier 9 is arranged protruding in an extension plane of the opening closure 4 on the housing 2 and at least on the blower side is formed as a flat plate. Specifically, the component carrier 9 is formed as, for example, L-shaped, with its short leg on the first part 5 of the opening closure 4 and also made of aluminum existing carrier.

Bezüglich der Anbindung des Gebläses 8 hat es sich als besonders vorteilhaft erwiesen, wenn der Komponententräger 9 eine Durchgangsöffnung 10 aufweist, an die sich einerseits das peripher zum Gehäuse 2 angeordnete Gebläse 8 und andererseits ein mit dem Brennerkopf 6 verbundener Luftführungskanal 11 anschließt, wobei der Luftführungskanal 11 am deckelartigen Teil 7 befestigt ist und am Komponententräger 9 verbindungsmittelfrei anliegt, was ein leichtes Abnehmen des zweiten Teils 7 des Öffnungsverschlusses 4 ermöglicht, wobei dann aber der Übergangsbereich vom Gebläse 8 über den Komponententräger 9 zum Luftführungskanal 11 mit entsprechenden Dichtmitteln abgedichtet ausgebildet ist.With regard to the connection of the blower 8, it has proved to be particularly advantageous if the component carrier 9 has a passage opening 10, to which on the one hand the Fan arranged peripherally to the housing 2 8 and on the other hand connected to the burner head 6 air duct 11 connects, wherein the air duct 11 is attached to the lid-like part 7 and the component carrier 9 is applied without a connection, which allows easy removal of the second part 7 of the opening closure 4, wherein but then the transition region from the fan 8 via the component carrier 9 to the air duct 11 is formed sealed with corresponding sealing means.

Um weiterhin auch bei Ölbrennern die Ölpumpe nicht am zweiten Teil 7 des Öffnungsverschlusses 4 anordnen zu müssen, ist am ersten Teil 5 des Öffnungsverschlusses 4 mindestens ein zweiter Komponententräger 13 (baulich dem ersten entsprechend), und zwar insbesondere zur Aufnahme einer Ölpumpe 14, angeordnet, wobei die beiden (oder mehr) Komponententräger 9, 13 gewissermaßen in baulich günstiger Weise über den Umfang des Gehäuses 2 verteilt angeordnet sind.In order, furthermore, not to have to arrange the oil pump on the second part 7 of the opening closure 4 in the case of oil burners, at least a second component carrier 13 (structurally corresponding to the first one) is arranged on the first part 5 of the opening closure 4, specifically for receiving an oil pump 14, wherein the two (or more) component carrier 9, 13 are distributed in a structurally favorable manner over the circumference of the housing 2, as it were.

Um den Heizkessel bei Bedarf gut reinigen zu können (also der oben genannte Wartungsfall) ist vorgesehen, dass ein gehäuseabgewandter Rand 17 des ersten Teils 5 des Öffnungsverschlusses 4 etwa zur inneren Oberfläche des Wärmetauschers 15 fluchtet. Etwas anders ausgedrückt, ist vorgesehen, dass die Brennkammer 1 und der zweite Teil 7 des Öffnungsverschlusses 4 einen etwa gleichen Durchmesser (zum Beispiel zwischen 20 cm und 50 cm) aufweisen.In order to clean the boiler well when needed (ie the above maintenance case) is provided that a housing facing away from the edge 17 of the first part 5 of the opening closure 4 is approximately aligned with the inner surface of the heat exchanger 15. In other words, it is provided that the combustion chamber 1 and the second part 7 of the opening closure 4 have an approximately equal diameter (for example between 20 cm and 50 cm).

Um den Öffnungsbereich 3 ordnungsgemäß abzudichten, ist zwischen dem ersten und dem zweiten Teil 5, 7 eine abgedichtet ausgebildete Nut- und Federverbindung vorgesehen (siehe hierzu Figur 4), wobei der zweite Teil 7 des Öffnungsverschlusses 4 am ersten Teil 5 anschraubbar ausgebildet ist.In order to properly seal the opening area 3, a sealed groove and tongue connection is provided between the first and the second part 5, 7 (cf. FIG. 4 ), wherein the second part 7 of the opening closure 4 on the first part 5 is screwed.

Zur wärmetechnischen Isolation ist weiterhin am zweiten Teil 7 des Öffnungsverschlusses 4 brennkammerseitig ein Wärmedämmelement 20 (siehe hierzu zum Beispiel die DE 196 27 961 A1 ) angeordnet.For thermal insulation is still on the second part 7 of the opening closure 4 combustion chamber side, a thermal insulation element 20 (see, for example, the DE 196 27 961 A1 ) arranged.

Schließlich ist am zweiten Teil 7 des Öffnungsverschlusses 4 zum Beispiel ein Zündtransformator 21 und am Luftführungskanal 11 zum Beispiel ein Luftdruckwächter 12 angeordnet.Finally, on the second part 7 of the opening closure 4, for example, an ignition transformer 21 and the air duct 11, for example, an air pressure switch 12 is arranged.

BezugszeichenlisteLIST OF REFERENCE NUMBERS

11
Brennkammercombustion chamber
22
Gehäusecasing
33
Öffnungsbereichopening area
44
Öffnungsverschlussopening closure
55
erster Teil des Öffnungsverschlussesfirst part of the opening closure
66
Brennerkopfburner head
77
zweiter Teil des Öffnungsverschlussessecond part of the opening closure
88th
Gebläsefan
99
Komponententrägercomponent support
1010
DurchgangsöffnungThrough opening
1111
LuftführungskanalAir duct
1212
LuftdruckwächterAir pressure switch
1313
Komponententrägercomponent support
1414
Ölpumpeoil pump
1515
Wärmetauscherheat exchangers
1616
AbgassammelkammerExhaust gas collection chamber
1717
Randedge
1818
DurchgriffsöffnungThrough opening
1919
Anschlussstutzenspigot
2020
Wärmedämmelementthermal insulation element
2121
Zündtransformatorignition transformer

Claims (15)

Heizkessel, umfassend ein eine Brennkammer (1) umschließendes Gehäuse (2) mit einem Öffnungsbereich (3), der mit einem Öffnungsverschluss (4) verschließbar ausgebildet ist, wobei der Öffnungsverschluss (4) aus einem ersten, ringförmigen, am Gehäuse (2) befestigbaren Teil (5) und einem zweiten, einen Brennerkopf (6) für wahlweise flüssige oder gasförmige Brennstoffe aufnehmenden, deckelartigen Teil (7) gebildet ist, wobei der Brennerkopf (6) pneumatisch mit einem am Öffnungsverschluss (4) angeordneten Gebläse (8) verbunden ist,
dadurch gekennzeichnet,
dass beide Teile (5, 7) des Öffnungsverschlusses (4) als Funktionseinheit gemeinsam am Gehäuse (2) montierbar ausgebildet sind, wobei am ersten, ringförmigen Teil (5) des Öffnungsverschlusses (4) ein Komponententräger (9) für das Gebläse (8) angeordnet ist.
A heating boiler, comprising a housing (2) enclosing a combustion chamber (1) and having an opening region (3) which is closable with an opening closure (4), wherein the opening closure (4) consists of a first, annular, fastened to the housing (2) Part (5) and a second, a burner head (6) for selectively liquid or gaseous fuels receiving, lid-like part (7) is formed, wherein the burner head (6) is pneumatically connected to a at the opening closure (4) fan (8) .
characterized,
in that both parts (5, 7) of the opening closure (4) are designed to be mounted together as a functional unit on the housing (2), wherein a component carrier (9) for the fan (8) is provided on the first, annular part (5) of the opening closure (4). is arranged.
Heizkessel nach Anspruch 1,
dadurch gekennzeichnet,
dass der Komponententräger (9) in einer Erstreckungsebene des Öffnungsverschlusses (4) über das Gehäuse (2) hinausragend angeordnet ist.
Heating boiler according to claim 1,
characterized,
that the component carrier (9) in an extension plane of the opening closure (4) over the housing (2) is arranged, projecting.
Heizkessel nach Anspruch 1 oder 2,
dadurch gekennzeichnet,
dass der Komponententräger (9) mindestens gebläseseitig als ebene Platte ausgebildet ist.
Heating boiler according to claim 1 or 2,
characterized,
that the component carrier (9) is at least fan side is formed as a flat plate.
Heizkessel nach einem der Ansprüche 1 bis 3,
dadurch gekennzeichnet,
dass der Komponententräger (9) eine Durchgangsöffnung (10) aufweist, an die sich einerseits das Gebläse (8) und andererseits ein mit dem Brennerkopf (6) verbundener Luftführungskanal (11) anschließt, wobei vorzugsweise der Luftführungskanal (11) am deckelartigen Teil (7) befestigt ist, wobei vorzugsweise ein Übergangsbereich vom Gebläse (8) über den Komponententräger (9) zum Luftführungskanal (11) abgedichtet ausgebildet ist, wobei vorzugsweise der Luftführungskanal (11) am Komponententräger (9) verbindungsmittelfrei anliegt.
Heating boiler according to one of claims 1 to 3,
characterized,
in that the component carrier (9) has a passage opening (10) to which the fan (8) on the one hand and an air guide channel (11) connected to the burner head (6) adjoin, preferably the air guide channel (11) on the cover-like part (7) ), wherein preferably a transition region from the fan (8) via the component carrier (9) to the air duct (11) is formed sealed, preferably the air duct (11) on the component carrier (9) rests without a connection.
Heizkessel nach Anspruch 4,
dadurch gekennzeichnet,
dass am Luftführungskanal (11) ein Luftdruckwächter (12) angeordnet ist.
Heating boiler according to claim 4,
characterized,
in that an air pressure monitor (12) is arranged on the air duct (11).
Heizkessel nach einem der Ansprüche 1 bis 5,
dadurch gekennzeichnet,
dass am ersten Teil (5) des Öffnungsverschlusses (4) mindestens ein zweiter Komponententräger (13) insbesondere zur Aufnahme einer Ölpumpe (14) angeordnet ist.
Heating boiler according to one of claims 1 to 5,
characterized,
in that at least one second component carrier (13), in particular for receiving an oil pump (14), is arranged on the first part (5) of the opening closure (4).
Heizkessel nach einem der Ansprüche 1 bis 6,
dadurch gekennzeichnet,
dass das Gehäuse (2) mindestens öffnungsbereichsseitig, vorzugsweise vollständig, zylinderförmig ausgebildet und der Öffnungsbereich (3) stirnseitig angeordnet ist.
Heating boiler according to one of claims 1 to 6,
characterized,
is that the housing (2) at least the opening region side, preferably completely cylindrical and is arranged, the opening area (3) end face.
Heizkessel nach einem der Ansprüche 1 bis 7,
dadurch gekennzeichnet,
dass im Gehäuse (2) ein die Brennkammer (1) umschließender, schraubenförmig gewickelter Wärmetauscher (15) und zwischen diesem und dem Gehäuse (2) eine Abgassammelkammer (16) angeordnet ist, wobei vorzugsweise ein gehäuseabgewandter Rand (17) des ersten Teils (5) des Öffnungsverschlusses (4) etwa zur inneren Oberfläche des Wärmetauschers (15) fluchtet, wobei vorzugsweise der erste Teil (5) des Öffnungsverschlusses (4) eine Durchgriffsöffnung (18) für einen Anschlussstutzen (19) des Wärmetauschers (15) aufweist.
Heating boiler according to one of claims 1 to 7,
characterized,
in that a combustion chamber (1) enclosing, helically wound heat exchanger (15) and between this and the housing (2) an exhaust gas collection chamber (16) is arranged in the housing (2), wherein preferably a housing-facing edge (17) of the first part (5 ) of the opening closure (4) approximately to the inner surface of the heat exchanger (15) is aligned, wherein preferably the first part (5) of the opening closure (4) has a passage opening (18) for a connecting piece (19) of the heat exchanger (15).
Heizkessel nach einem der Ansprüche 1 bis 8,
dadurch gekennzeichnet,
dass der erste Teil (5) des Öffnungsverschlusses (4) in den Öffnungsbereich (3) des Gehäuses (2) einsteckbar ausgebildet ist.
Heating boiler according to one of claims 1 to 8,
characterized,
that the first part (5) of the opening closure (4) into the opening portion (3) of the housing (2) is inserted.
Heizkessel nach einem der Ansprüche 1 bis 9,
dadurch gekennzeichnet,
dass die Brennkammer (1) und der zweite Teil (7) des Öffnungsverschlusses (4) einen etwa gleichen Durchmesser aufweisen.
Heating boiler according to one of claims 1 to 9,
characterized,
that the combustion chamber (1) and the second part (7) of the opening closure (4) have an approximately same diameter.
Heizkessel nach einem der Ansprüche 1 bis 10,
dadurch gekennzeichnet,
dass am zweiten Teil (7) des Öffnungsverschlusses (4) brennkammerseitig ein Wärmedämmelement (20) angeordnet ist.
Heating boiler according to one of claims 1 to 10,
characterized,
in that a heat-insulating element (20) is arranged on the combustion chamber side on the second part (7) of the opening closure (4).
Heizkessel nach einem der Ansprüche 1 bis 11,
dadurch gekennzeichnet,
dass am zweiten Teil (7) des Öffnungsverschlusses (4) ein Zündtransformator (21) angeordnet ist.
Heating boiler according to one of claims 1 to 11,
characterized,
in that an ignition transformer (21) is arranged on the second part (7) of the opening closure (4).
Heizkessel nach einem der Ansprüche 1 bis 12,
dadurch gekennzeichnet,
dass zwischen dem ersten und dem zweiten Teil (5, 7) des Öffnungsverschlusses (4) eine abgedichtet ausgebildete Nut- und Federverbindung vorgesehen ist.
Heating boiler according to one of claims 1 to 12,
characterized,
in that a sealed groove and tongue connection is provided between the first and the second part (5, 7) of the opening closure (4).
Heizkessel nach einem der Ansprüche 1 bis 13,
dadurch gekennzeichnet,
dass der zweite Teil (7) des Öffnungsverschlusses (4) am ersten Teil (5) anschraubbar ausgebildet ist.
Heating boiler according to one of claims 1 to 13,
characterized,
in that the second part (7) of the opening closure (4) is screwed on the first part (5).
Heizkessel nach einem der Ansprüche 1 bis 14,
dadurch gekennzeichnet,
dass wahlweise der erste und/oder zweite Teil (5, 7) aus Aluminium, insbesondere Aluminiumdruckguss, gebildet ist/ sind, wobei vorzugsweise das Aluminium wahlweise beschichtet oder abgeschirmt ausgebildet ist.
Heating boiler according to one of claims 1 to 14,
characterized,
in that optionally the first and / or second part (5, 7) is / are made of aluminum, in particular aluminum die casting, wherein preferably the aluminum is optionally coated or shielded.
EP09003722A 2008-03-28 2009-03-16 Boiler Not-in-force EP2105679B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PL09003722T PL2105679T3 (en) 2008-03-28 2009-03-16 Boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102008016313A DE102008016313A1 (en) 2008-03-28 2008-03-28 boiler

Publications (3)

Publication Number Publication Date
EP2105679A2 true EP2105679A2 (en) 2009-09-30
EP2105679A3 EP2105679A3 (en) 2009-12-09
EP2105679B1 EP2105679B1 (en) 2012-08-15

Family

ID=40755615

Family Applications (1)

Application Number Title Priority Date Filing Date
EP09003722A Not-in-force EP2105679B1 (en) 2008-03-28 2009-03-16 Boiler

Country Status (3)

Country Link
EP (1) EP2105679B1 (en)
DE (1) DE102008016313A1 (en)
PL (1) PL2105679T3 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19627961A1 (en) 1996-07-11 1998-01-15 Viessmann Werke Kg Refractory moulding especially for boiler combustion chamber base
DE10114490C1 (en) 2001-03-24 2002-08-01 Viessmann Werke Kg Wall heater, using a liquid fuel, has a coiled tube giving an increased heat exchange surface for a larger volume of available water requiring fewer burner actions and giving reduced exhaust emissions
EP1562006A1 (en) 2004-01-30 2005-08-10 Viessmann Werke GmbH & Co KG Heating device

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3841273A (en) * 1973-09-27 1974-10-15 Sioux Steam Cleaner Corp Multi-pass heating apparatus with expandable air cooled jacket
EP0498748B1 (en) * 1991-02-07 1994-04-27 De Dietrich Thermique Cast iron gas-fixed sectional boiler with total premixing
DE102006001590A1 (en) * 2006-01-11 2007-07-12 Viessmann Werke Gmbh & Co Kg boiler

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19627961A1 (en) 1996-07-11 1998-01-15 Viessmann Werke Kg Refractory moulding especially for boiler combustion chamber base
DE10114490C1 (en) 2001-03-24 2002-08-01 Viessmann Werke Kg Wall heater, using a liquid fuel, has a coiled tube giving an increased heat exchange surface for a larger volume of available water requiring fewer burner actions and giving reduced exhaust emissions
EP1562006A1 (en) 2004-01-30 2005-08-10 Viessmann Werke GmbH & Co KG Heating device

Also Published As

Publication number Publication date
EP2105679A3 (en) 2009-12-09
EP2105679B1 (en) 2012-08-15
PL2105679T3 (en) 2013-01-31
DE102008016313A1 (en) 2009-10-01

Similar Documents

Publication Publication Date Title
EP1562006B1 (en) Heating device
EP2739928B1 (en) Heat exchanger assembly
EP3108194B1 (en) Exhaust gas heat exchanger
DE102008004790B4 (en) Refrigerant compressor arrangement
DE102014102358A1 (en) exhaust-gas distributor
EP3719379B1 (en) Device for reducing flow noise
DE10261966B4 (en) Air heater for integration into an air-conducting housing arrangement
WO2007079730A1 (en) Boiler
DE102013111561A1 (en) turbocharger
EP2105679B1 (en) Boiler
DE102017129559B4 (en) Connection head for a filter candle, set with a connection head and filter candle
DE10060705B4 (en) Engine-independent heater of a motor vehicle
DE10327481A1 (en) Casing-free plate heat exchanger with collecting box
EP1985956A2 (en) Tube plate for residual heat exchanger
DE19838588A1 (en) Connecting clamp for pipe connection between manifold of road vehicle heat exchangere and pipe conduit feeding heat exchange fluid to manifold or pipe conduit leading fluid away from manifold
EP2306112B1 (en) Heating device
DE102013111773A1 (en) boiler
DE102008031424B4 (en) heat exchangers
DE102013008773A1 (en) Heat exchanger, in particular exhaust gas heat exchanger or intercooler
AT523245B1 (en) Heating device, in particular gas condensing device
DE202012101622U1 (en) Heat exchanger
DE102021100469B4 (en) boiler
DE10349887A1 (en) Exhaust gas reconducting system cooler in internal combustion engine, has flow channel encased by pipe that is shaped based on channel profile to let coolant to flow between chambers, where channel has chambers of rectangular cross section
DE19516688C1 (en) Heating unit for vehicles, with outlet deflection sheet
DE102019135085B4 (en) Treatment device for the treatment of, in particular, liquid fluids as well as connection head of a treatment device

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA RS

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA RS

RIC1 Information provided on ipc code assigned before grant

Ipc: F24H 1/43 20060101AFI20090622BHEP

Ipc: F24H 9/14 20060101ALI20091103BHEP

Ipc: F24H 9/18 20060101ALI20091103BHEP

Ipc: F24H 9/02 20060101ALI20091103BHEP

17P Request for examination filed

Effective date: 20100602

AKX Designation fees paid

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR

17Q First examination report despatched

Effective date: 20110909

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RIC1 Information provided on ipc code assigned before grant

Ipc: F24H 9/02 20060101ALI20120229BHEP

Ipc: F24H 1/43 20060101AFI20120229BHEP

Ipc: F24H 9/14 20060101ALI20120229BHEP

Ipc: F24H 9/18 20060101ALI20120229BHEP

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 571054

Country of ref document: AT

Kind code of ref document: T

Effective date: 20120815

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502009004371

Country of ref document: DE

Effective date: 20121011

REG Reference to a national code

Ref country code: NL

Ref legal event code: VDEP

Effective date: 20120815

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20121115

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20121215

REG Reference to a national code

Ref country code: PL

Ref legal event code: T3

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20121217

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20121116

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20121126

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20130516

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20121115

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 502009004371

Country of ref document: DE

Effective date: 20130516

BERE Be: lapsed

Owner name: VIESSMANN WERKE G.M.B.H. & CO. KG

Effective date: 20130331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130331

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130331

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130316

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130331

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 571054

Country of ref document: AT

Kind code of ref document: T

Effective date: 20140316

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20090316

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20120815

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130316

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140316

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 8

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 9

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20190213

Year of fee payment: 11

Ref country code: GB

Payment date: 20190318

Year of fee payment: 11

Ref country code: FR

Payment date: 20190329

Year of fee payment: 11

Ref country code: PL

Payment date: 20190220

Year of fee payment: 11

Ref country code: IT

Payment date: 20190321

Year of fee payment: 11

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 502009004371

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20201001

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200331

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20200316

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200316

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200316

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200316