EP2071262A1 - Method for heating in an industrial furnace - Google Patents

Method for heating in an industrial furnace Download PDF

Info

Publication number
EP2071262A1
EP2071262A1 EP08171076A EP08171076A EP2071262A1 EP 2071262 A1 EP2071262 A1 EP 2071262A1 EP 08171076 A EP08171076 A EP 08171076A EP 08171076 A EP08171076 A EP 08171076A EP 2071262 A1 EP2071262 A1 EP 2071262A1
Authority
EP
European Patent Office
Prior art keywords
heating
furnace
heating power
temperature
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP08171076A
Other languages
German (de)
French (fr)
Other versions
EP2071262B1 (en
Inventor
Tomas Ekman
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
AGA AB
Original Assignee
AGA AB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by AGA AB filed Critical AGA AB
Publication of EP2071262A1 publication Critical patent/EP2071262A1/en
Application granted granted Critical
Publication of EP2071262B1 publication Critical patent/EP2071262B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D19/00Arrangements of controlling devices
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D11/00Process control or regulation for heat treatments
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/0081Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor for slabs; for billets
    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21DMODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING
    • C21D9/00Heat treatment, e.g. annealing, hardening, quenching or tempering, adapted for particular articles; Furnaces therefor
    • C21D9/70Furnaces for ingots, i.e. soaking pits
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D19/00Arrangements of controlling devices
    • F27D2019/0028Regulation
    • F27D2019/0034Regulation through control of a heating quantity such as fuel, oxidant or intensity of current

Definitions

  • the present invention relates to batch heating of billets or ingots in industrial furnaces.
  • a final homogeneous temperature throughout the heated material is often the objective.
  • the difference between the surface temperature of the material and the temperature at its centre must in many cases not exceed a particular predetermined value.
  • the required final temperature of the material can be achieved by controlling the temperature of the furnace atmosphere so that it asymptotically converges to the required final temperature. This convergence is normally controlled by means of a control regulator which controls the heating power introduced into the furnace and which uses the temperature of the furnace atmosphere as an input variable. This provides effective control of the furnace temperature for the purpose of obtaining the required final temperature in the material quickly.
  • the present invention solves the above problems.
  • the present invention thus relates to a method for heating billets or ingots in an industrial furnace by means of at least one burner, in which furnace the heating power continuously introduced into the furnace is controlled by means of a regulator whose input parameter is the temperature of the furnace atmosphere, which temperature is measured by means of a temperature measuring device, wherein the regulator is caused to control the heating in at least one first heating step and a subsequent second temperature equalising step, and is characterised in that the instantaneous heating power is measured continuously, in that the derivative of the heating power with respect to time is calculated continuously, and in that the heating is interrupted when a primary condition, namely that this derivative falls within a predetermined interval, is met, provided that the heating at this time is in the subsequent second temperature equalising step.
  • Figure 1 shows an industrial furnace 1 in which an ingot 2 is arranged to be heated batchwise.
  • the method of the invention can also be used in furnaces where slabs and billets of different types are heated.
  • the method of the invention is advantageously also used for batch heating of a plurality of ingots, billets or slabs simultaneously.
  • the industrial furnace 1 comprises at least one burner 3, which heats the atmosphere of the furnace 1.
  • the burner or burners 3 may, for example, be driven by means of a gaseous or liquid fuel and air or oxygen gas as oxidant, but other operating configurations may also be used.
  • a particularly preferred burner is a so-called oxyfuel burner whose oxidant consists of at least 80% oxygen gas.
  • At least one temperature measuring device 4 which measures the temperature of the furnace atmosphere and feeds it as an input parameter to a regulator 5 of the PID type (Proportional, Integral, Derivative), is also arranged in the furnace 1.
  • This regulator 5 generates an output signal in the form of a desired heating power of the burner or burners 3.
  • the output signal is fed to a flow regulator 6 which converts the required heating power to a certain flow of fuel and oxidant, which flow is fed from the flow regulator 6 to the burner or burners 3.
  • the output signal from the regulator 5 is generally less volatile than the resultant flow from the flow regulator 6, since the flow regulator 6, unlike the regulator 5, must take into consideration, among other things, the operating limitations of the burner or burners 3.
  • the flow resulting from the flow regulator 6 thus constitutes an approximation of the ideal output signal of the regulator 5.
  • the burner or burners 3 heat(s) the furnace atmosphere, which in turn heats the ingot 2.
  • Figure 2 shows four principal and simplified, explanatory graphs in which the scale of the X-axis is identical for all four graphs and indicates the time.
  • T 0 the ingot 2 is fed into the furnace 1.
  • the heat treatment is divided into two steps, herein referred to as a first heating step and a second heating step, or alternatively a second temperature equalising step, respectively.
  • a first heating step the power of the burner 3 is relatively high, the purpose of which is to heat the furnace atmosphere quickly.
  • the temperature equalising step the power is continuously controlled by means of the PID regulator 5 for the purpose of achieving a sufficiently uniform temperature distribution in the ingot 2 as quickly as possible.
  • the top graph shows the time development for the temperature T furnace in the atmosphere of the furnace 1, the temperature T surface on the surface of the ingot 2, and the temperature T centre in the centre of the ingot 2.
  • the desired final temperature T ref is also shown as a dotted horizontal line.
  • the temperature T furnace of the furnace atmosphere is higher than the surface temperature T surface of the ingot 2 when the ingot 2 is introduced into the furnace 1.
  • the temperature T furnace of the furnace atmosphere initially drops as a result of the cooling effect of the ingot 2, then increases again after a certain time as a consequence of the heating power from the burner or burners 3.
  • the top but one graph shows the time development for the power P instantaneously discharged by the burner or burners 3, and a straight horizontal line P cond that represents an interruption condition.
  • the heating power P of the burner or burners 3 is set during the heating step to a relatively high, constant level. The purpose of this is to increase the temperature T furnace and the temperatures of the ingot 2 quickly before the temperature equalising step, which begins at the time T 1 .
  • T furnace is controlled by the PID regulator 5, with T furnace as input parameter, which in turn controls through its output signal the flow regulator 6, in turn controlling the flow of fuel and oxidant to the burner or burners 3 for the purpose of obtaining the desired final temperature T ref as quickly as possible.
  • T furnace has stabilised sufficiently close to T ref , it may be concluded that the surface temperature T surface of the ingot 2 and its centre temperature T centre have also reached sufficient, and sufficiently homogeneous, temperatures.
  • T furnace is therefore measured and fed as an input parameter to the PID regulator 5, which in turn, by controlling the flow regulator 6, indirectly controls the heating power P.
  • the purpose of this control is, in a conventional manner, to cause T furnace to approach the desired final temperature T ref as effectively as possible.
  • the bottom graph shows the time development for the accumulated thermal energy PAck given by the burner or burners 3, together with a straight horizontal line PAck cond , which represents an interruption condition.
  • the top graph shows that the surface temperature T surface of the ingot 2 and its centre temperature T centre increase at different rates during the heating. Due to heat conduction, T surface increases more quickly than does T centre . Due among other things to different furnace configurations and different dimensions of the heated material, this difference in heating is of varying preponderance. However, a common feature is that at the time T 2 , when the ingot 2 is removed from the furnace 1, it is desirable for the difference between T surface and T centre to be less than a certain predetermined value to avoid the problems described above in subsequent machining steps.
  • the present invention solves this problem by examining the behaviour of the curve P.
  • the instantaneously discharged power P of the burner or burners 3 can be measured in several different ways.
  • P can be measured indirectly by observing the output signal of the regulator 5.
  • an ideal, desired value is obtained for P, which does not necessarily correspond to the power actually discharged instantaneously at a certain moment.
  • this ideal value is a measure of the desired burner power given the current development of furnace temperature T furnace .
  • this method of measuring P in certain embodiments is therefore preferred according to the present invention.
  • the power P can be measured by measuring the flow from the flow regulator 6, either by means of a flow meter or by reading off the flow directly from the flow regulator 6.
  • This alternative measuring method gives a measured value which more closely corresponds to the power actually discharged instantaneously from burner or burners 3, but on the other hand contains more noise relative to the desired power calculated by the regulator 5.
  • next but bottom graph shows the time development for dP/dt, as well as two straight horizontal lines dP/dP cond 1 , dP/dP cond 2 , which together represent an interruption condition.
  • dP/dt is initially approximately zero in the present exemplary embodiment, then passes from the first heating step and into the PID control phase, i.e. the second heating step, via a not necessarily continuous transition at the time T 1 . During this phase the derivative dP/dt will vary according to the PID control of P.
  • time T 2 is selected according to the present invention as the time at which a primary condition is met, in other words the time at which dP/dt falls within a certain predetermined interval [dP/dP cond 1 , dP/dP cond 2 ], determined on the basis of experience and dependent on a number of factors such as the dimensions and shape of the heated material, the furnace type, the number of burners, the characteristics of the regulator 5 and the flow regulator 6, desired maximum temperature difference between T surface and T centre and so on.
  • this can be done by ensuring that two secondary conditions are met simultaneously.
  • a first secondary condition is that the absolute value of P must be below a certain first predetermined value P cond . It is preferable for this first predetermined value P cond to be selected so that it is below the value of P during the initial phase or an early phase, between T 0 and T 1 , to prevent the heating process from being interrupted already during the first heating step.
  • a second secondary condition is that the total thermal energy supplied, PAck, must exceed a certain second predetermined value PAck cond .
  • This second predetermined value PAck cond is selected to prevent premature interruption of the heating process, preferably so that it exceeds the minimum quantity of energy which is theoretically required to heat the ingot 2 to the desired final temperature distribution with the desired minimum temperature homogeneity and with a heating efficiency suitable for the system.
  • the purpose of the second secondary condition is to prevent premature interruption of the heating process and that this purpose is achieved by not allowing such interruption to take place before a minimum quantity of thermal energy has been supplied.
  • Approximate and/or indirect measures of PAck can thus be used to determine whether the second secondary condition has been met or not. For example, the time from the beginning of the heating process may be measured, and given that P, as a function of time, is approximately known, this time can be used as an approximate and indirect measure of PAck.
  • many other metrics can be used to determine, approximately and/or indirectly, whether the second secondary condition has been met, for example the position of fuel valves, measured fuel pressures, etc.
  • the total thermal energy supplied, PAck is preferably measured indirectly by measuring the total quantity of fuel introduced into the furnace 1 since heating began.
  • the heating method is in the temperature equalising phase between T 1 and T 2 , i.e. in the second temperature equalising step.
  • the furnace 1 is in a form of dynamic thermal equilibrium.
  • the temperature of the furnace wall has thus been largely stabilised, as has the degree of thermal losses through the wall.
  • the flue gases maintain a constant temperature and flow.
  • the ingot 2 that changes temperature during this temperature equalising phase.
  • the dependence between P and T centre is relatively direct, which is why the PID control of P has a relatively clear, and delayed, effect on the variation of T centre .
  • d P tot d t d P material d t + d P losses d t ⁇ F ⁇ ⁇ T + k 1 ⁇ d P tot d t ⁇ d P tot d t ⁇ k 2 ⁇ ⁇ ⁇ T ⁇ T centre ⁇ T surface - 1 k 2 ⁇ d P tot d t , in which k 1 and k 2 are constants and since F( ⁇ T) is an approximately linear function. Since T surface is known and constant when the dynamic equilibrium described above prevails, the time derivative of P tot can thus be used to approximately calculate the temperature T centre in the centre of the heated material.
  • the dotted surface illustrates the area in which both secondary conditions are met. At the time T 2 the primary condition is also met, and the heating may thus be interrupted.
  • the PID control of P will have a relatively high variance. As described above, this variance will be somewhat higher if P is measured at the flow regulator 6 rather than at the regulator 5.
  • P will generally vary as a relatively smooth function as the negative derivative increases during the period between T 1 and T 2 , but with a noise component of varying intensity.
  • this noise component can be filtered off by averaging P over a number of measuring points that depends on the current application, preferably at least 10 measuring points.
  • the number of points used in the formation of the mean value vary as a function of how high the variance of P currently is.
  • the variance may be lower during the beginning of the temperature equalising second heating step and higher during its final stage.
  • a mean value has been formed over 10 historical measuring points for P in the next but bottom graph of dP/dt.
  • the flow regulator 6 controls the burner or burners 3, in certain applications, to heat the furnace 1 by an on/off procedure. This may, for example, depend on the fact that the burner or burners 3 has (have) a minimum power which exceeds the heating power prescribed by the PID regulator 5, which heating power is to be discharged to the furnace atmosphere at a certain given occasion.
  • the flow regulator 6 controls the burner or burners 3 to be switched on for a certain period of time after which it (they) are switched off and then repeat(s) this process so that the mean power emitted will be that prescribed by the PID regulator 5 during each given period of time.
  • This method is called pulse width modulation.
  • the flow regulator 6 it is also possible for the flow regulator 6 to use constant times for the switched-on/switched-off position, respectively, and instead to vary the power of the burner or burners 3 during the switched-on position, thereby achieving the same correct average heating power. This is called pulse height modulation.
  • modulation techniques are also possible, for example a combination of pulse width modulation and pulse height modulation, to achieve an average instantaneous heating power which corresponds to that prescribed by the PID regulator 5 during a certain given period of time.
  • the regulator 5 is of the PID type, but it should be realised that also other types of regulators can be used when applying the method of the present invention.
  • the criteria of the present invention for interrupting the heating may need to be modified to suit the prevailing conditions.
  • the present invention thus provides a method that enables a heating process to be interrupted with greater certainty in an industrial furnace when there is sufficient temperature uniformity in the material, without the need to continue the heating process for an unnecessarily long period, with the associated drawbacks in terms of long heating times, high energy costs and material damage.
  • the investment cost for applying the present invention to existing industrial furnaces is low, because sensors or corresponding devices required to measure or observe emitted power and furnace temperature are often already installed. In these cases it is therefore sufficient to implement the actual interruption condition, which can be achieved at relatively low cost.

Abstract

A method for heating billets or ingots in an industrial furnace by means of at least one burner, in which furnace the heating power (P) continuously introduced into the furnace is controlled by means of a regulator whose input parameter is the temperature (Tfurnace) of the furnace atmosphere, which temperature (Tfurnace) is measured by means of a temperature measuring device, wherein the regulator is caused to control the heating in at least one first heating step and a subsequent second temperature equalising step.
The invention is characterised in that the instantaneous heating power (P) is measured continuously, in that the derivative of the heating power (P) with respect to time (dP/dt) is calculated continuously, and in that the heating is interrupted when a primary condition, namely that this derivative (dP/dt) falls within a predetermined interval ([dP/dPcond 1, dP/dPcond 2]), is met, provided that the heating at this time is in the subsequent second temperature equalising step.

Description

  • The present invention relates to batch heating of billets or ingots in industrial furnaces.
  • In such heating a final homogeneous temperature throughout the heated material is often the objective. For example, to ensure that subsequent machining is effective and to avoid damage to the material due, among other things, to shearing forces during such machining, the difference between the surface temperature of the material and the temperature at its centre must in many cases not exceed a particular predetermined value.
  • The required final temperature of the material can be achieved by controlling the temperature of the furnace atmosphere so that it asymptotically converges to the required final temperature. This convergence is normally controlled by means of a control regulator which controls the heating power introduced into the furnace and which uses the temperature of the furnace atmosphere as an input variable. This provides effective control of the furnace temperature for the purpose of obtaining the required final temperature in the material quickly.
  • However, it is difficult to know the time at which the temperature is sufficiently homogeneous throughout the heated material. The reason for this is that on the one hand the surface of the material comparatively quickly assumes approximately the same temperature as the furnace atmosphere. On the other hand, the centre temperature of the material takes a longer time to approach the temperature of the furnace atmosphere, due to heat conduction. Since no cheap and at the same time effective method of measuring the temperature in the centre of the material is known, empirically determined heating times have hitherto had to be relied upon to ensure that the temperature differences in the billet or ingot are not too large when the heating process is interrupted.
  • The drawback of such an approach is that a very good margin must be provided to ensure that temperature differences inside the material do not become too large, which is why the heating time often becomes unnecessarily long. The reason for this is, among other things, that the actual conducting of the process gives rise to several sources of uncertainty and that the original temperature distribution in the material is often not fully known. This results in increased energy and time consumption, with the accompanying increases in costs and environmental pollution. Moreover, suSch long heating times may result in damage to the material, e.g. due to exaggerated oxidation, which naturally increases the cost of the method and complicates it.
  • The present invention solves the above problems.
  • The present invention thus relates to a method for heating billets or ingots in an industrial furnace by means of at least one burner, in which furnace the heating power continuously introduced into the furnace is controlled by means of a regulator whose input parameter is the temperature of the furnace atmosphere, which temperature is measured by means of a temperature measuring device, wherein the regulator is caused to control the heating in at least one first heating step and a subsequent second temperature equalising step, and is characterised in that the instantaneous heating power is measured continuously, in that the derivative of the heating power with respect to time is calculated continuously, and in that the heating is interrupted when a primary condition, namely that this derivative falls within a predetermined interval, is met, provided that the heating at this time is in the subsequent second temperature equalising step.
  • The invention will now be described in detail with reference to an exemplary embodiment of the invention and the attached drawings, in which:
    • Figure 1 shows a general view of an industrial furnace in which the method of the invention is applied; and
    • Figure 2 shows a collection of four explanatory and simplified graphs which explain the method of the invention.
  • Figure 1 shows an industrial furnace 1 in which an ingot 2 is arranged to be heated batchwise. However, it should be realised that the method of the invention can also be used in furnaces where slabs and billets of different types are heated. The method of the invention is advantageously also used for batch heating of a plurality of ingots, billets or slabs simultaneously.
  • The industrial furnace 1 comprises at least one burner 3, which heats the atmosphere of the furnace 1. The burner or burners 3 may, for example, be driven by means of a gaseous or liquid fuel and air or oxygen gas as oxidant, but other operating configurations may also be used. A particularly preferred burner is a so-called oxyfuel burner whose oxidant consists of at least 80% oxygen gas.
  • At least one temperature measuring device 4, which measures the temperature of the furnace atmosphere and feeds it as an input parameter to a regulator 5 of the PID type (Proportional, Integral, Derivative), is also arranged in the furnace 1. This regulator 5 generates an output signal in the form of a desired heating power of the burner or burners 3. The output signal is fed to a flow regulator 6 which converts the required heating power to a certain flow of fuel and oxidant, which flow is fed from the flow regulator 6 to the burner or burners 3.
  • The output signal from the regulator 5 is generally less volatile than the resultant flow from the flow regulator 6, since the flow regulator 6, unlike the regulator 5, must take into consideration, among other things, the operating limitations of the burner or burners 3. The flow resulting from the flow regulator 6 thus constitutes an approximation of the ideal output signal of the regulator 5.
  • The burner or burners 3 heat(s) the furnace atmosphere, which in turn heats the ingot 2.
  • Figure 2 shows four principal and simplified, explanatory graphs in which the scale of the X-axis is identical for all four graphs and indicates the time. At the time T0, the ingot 2 is fed into the furnace 1.
  • The heat treatment is divided into two steps, herein referred to as a first heating step and a second heating step, or alternatively a second temperature equalising step, respectively. During the heating step the power of the burner 3 is relatively high, the purpose of which is to heat the furnace atmosphere quickly. During the temperature equalising step, the power is continuously controlled by means of the PID regulator 5 for the purpose of achieving a sufficiently uniform temperature distribution in the ingot 2 as quickly as possible.
  • The top graph shows the time development for the temperature Tfurnace in the atmosphere of the furnace 1, the temperature Tsurface on the surface of the ingot 2, and the temperature Tcentre in the centre of the ingot 2. The desired final temperature Tref is also shown as a dotted horizontal line. In the present embodiment the temperature Tfurnace of the furnace atmosphere is higher than the surface temperature Tsurface of the ingot 2 when the ingot 2 is introduced into the furnace 1. Thus, the temperature Tfurnace of the furnace atmosphere initially drops as a result of the cooling effect of the ingot 2, then increases again after a certain time as a consequence of the heating power from the burner or burners 3.
  • The top but one graph shows the time development for the power P instantaneously discharged by the burner or burners 3, and a straight horizontal line Pcond that represents an interruption condition. As shown in the graph, the heating power P of the burner or burners 3 is set during the heating step to a relatively high, constant level. The purpose of this is to increase the temperature Tfurnace and the temperatures of the ingot 2 quickly before the temperature equalising step, which begins at the time T1.
  • During the temperature equalising step, P is controlled by the PID regulator 5, with Tfurnace as input parameter, which in turn controls through its output signal the flow regulator 6, in turn controlling the flow of fuel and oxidant to the burner or burners 3 for the purpose of obtaining the desired final temperature Tref as quickly as possible. When Tfurnace has stabilised sufficiently close to Tref, it may be concluded that the surface temperature Tsurface of the ingot 2 and its centre temperature Tcentre have also reached sufficient, and sufficiently homogeneous, temperatures.
  • Tfurnace is therefore measured and fed as an input parameter to the PID regulator 5, which in turn, by controlling the flow regulator 6, indirectly controls the heating power P. The purpose of this control is, in a conventional manner, to cause Tfurnace to approach the desired final temperature Tref as effectively as possible.
  • The bottom graph shows the time development for the accumulated thermal energy PAck given by the burner or burners 3, together with a straight horizontal line PAckcond, which represents an interruption condition.
  • The top graph shows that the surface temperature Tsurface of the ingot 2 and its centre temperature Tcentre increase at different rates during the heating. Due to heat conduction, Tsurface increases more quickly than does Tcentre. Due among other things to different furnace configurations and different dimensions of the heated material, this difference in heating is of varying preponderance. However, a common feature is that at the time T2, when the ingot 2 is removed from the furnace 1, it is desirable for the difference between Tsurface and Tcentre to be less than a certain predetermined value to avoid the problems described above in subsequent machining steps.
  • Instead of allowing the heating process to run for such a long time as to guarantee adequate temperature equalisation, the present invention solves this problem by examining the behaviour of the curve P.
  • Accordingly, the value P is observed continuously and its time derivative dP/dt is calculated.
  • The instantaneously discharged power P of the burner or burners 3 can be measured in several different ways. Firstly, P can be measured indirectly by observing the output signal of the regulator 5. In this case an ideal, desired value is obtained for P, which does not necessarily correspond to the power actually discharged instantaneously at a certain moment. On the other hand, this ideal value is a measure of the desired burner power given the current development of furnace temperature Tfurnace. For reasons described in detail below, this method of measuring P in certain embodiments is therefore preferred according to the present invention. Secondly, the power P can be measured by measuring the flow from the flow regulator 6, either by means of a flow meter or by reading off the flow directly from the flow regulator 6. This alternative measuring method gives a measured value which more closely corresponds to the power actually discharged instantaneously from burner or burners 3, but on the other hand contains more noise relative to the desired power calculated by the regulator 5.
  • The next but bottom graph shows the time development for dP/dt, as well as two straight horizontal lines dP/dPcond 1, dP/dPcond 2, which together represent an interruption condition. As will be realised from the combination of the next but top and next but bottom graphs, dP/dt is initially approximately zero in the present exemplary embodiment, then passes from the first heating step and into the PID control phase, i.e. the second heating step, via a not necessarily continuous transition at the time T1. During this phase the derivative dP/dt will vary according to the PID control of P.
  • Surprisingly, it has been found that empirically based conditions for dP/dt can be formulated, thus making it possible to estimate, very accurately, the time T2 at which the heating process can be interrupted and the ingot 2 can be removed from the furnace 1 for subsequent machining steps without heating ingot 2 for an unnecessarily long time, whilst at the same time achieving sufficient temperature homogeneity in the ingot 2.
  • Correspondingly, time T2 is selected according to the present invention as the time at which a primary condition is met, in other words the time at which dP/dt falls within a certain predetermined interval [dP/dPcond 1, dP/dPcond 2], determined on the basis of experience and dependent on a number of factors such as the dimensions and shape of the heated material, the furnace type, the number of burners, the characteristics of the regulator 5 and the flow regulator 6, desired maximum temperature difference between Tsurface and Tcentre and so on. The interval [dP/dPcond 1, dP/dPcond 2] is preferably symmetrical around dP/dt = 0.
  • To prevent the heating process from being interrupted too early, it must also be ensured that the method has reached the temperature equalising second heating step. According to an exemplary embodiment this can be done by ensuring that two secondary conditions are met simultaneously.
  • A first secondary condition is that the absolute value of P must be below a certain first predetermined value Pcond. It is preferable for this first predetermined value Pcond to be selected so that it is below the value of P during the initial phase or an early phase, between T0 and T1, to prevent the heating process from being interrupted already during the first heating step.
  • A second secondary condition is that the total thermal energy supplied, PAck, must exceed a certain second predetermined value PAckcond. This second predetermined value PAckcond is selected to prevent premature interruption of the heating process, preferably so that it exceeds the minimum quantity of energy which is theoretically required to heat the ingot 2 to the desired final temperature distribution with the desired minimum temperature homogeneity and with a heating efficiency suitable for the system.
  • It is realised that the purpose of the second secondary condition is to prevent premature interruption of the heating process and that this purpose is achieved by not allowing such interruption to take place before a minimum quantity of thermal energy has been supplied. Approximate and/or indirect measures of PAck can thus be used to determine whether the second secondary condition has been met or not. For example, the time from the beginning of the heating process may be measured, and given that P, as a function of time, is approximately known, this time can be used as an approximate and indirect measure of PAck. Similarly, many other metrics can be used to determine, approximately and/or indirectly, whether the second secondary condition has been met, for example the position of fuel valves, measured fuel pressures, etc.
  • The total thermal energy supplied, PAck, is preferably measured indirectly by measuring the total quantity of fuel introduced into the furnace 1 since heating began.
  • When both secondary conditions are met, it is certain that the heating method is in the temperature equalising phase between T1 and T2, i.e. in the second temperature equalising step. During this phase, the furnace 1 is in a form of dynamic thermal equilibrium. The temperature of the furnace wall has thus been largely stabilised, as has the degree of thermal losses through the wall. In principle, the flue gases maintain a constant temperature and flow. In practice it is mainly the ingot 2 that changes temperature during this temperature equalising phase. In other words, the dependence between P and Tcentre is relatively direct, which is why the PID control of P has a relatively clear, and delayed, effect on the variation of Tcentre. Conversely, because the PID control is a predictable process under uniform conditions, the variation in P induced by the PID control will depend on the variation over time in Tcentre, and also on the instantaneous value of Tcentre. Because of these relations, it has been found that it is possible to use the value of dP/dt to predict when the value of Tcentre will exceed a certain value.
  • This can be realised by considering a somewhat simplified expression of the total power supplied Ptot expressed as a function of the surface area A of a heated ingot, the thermal conductivity of the heated material λ, the distance ΔD between the surface of the material and its centre, and the temperature difference ΔT between the surface and the centre, and at the above described dynamic equilibrium, i.e. when the surface temperature of the heated material has reached the final temperature in the furnace: P tot = P material + P losses = A λ Δ T Δ D + P losses ,
    Figure imgb0001

    in which Pmaterial and Plosses, respectively, are those proportions of the total power supplied that are transferred to the material in the form of thermal energy and that disappear from the system in form of losses, respectively.
  • In the case of dynamic equilibrium, Plosses is built up from two components. Firstly, losses occur in the form of thermal energy in the outgoing flue gases. These are approximately linear as a function of Ptot. Secondly, other losses occur which are approximately constant over time where there is dynamic equilibrium, since the temperature conditions are approximately constant over time in the furnace, besides inside the heated material itself, as described above.
  • Furthermore, A, λ and ΔD are approximately constant throughout the heating process, which is why Pmaterial is essentially a function of ΔT. In fact, it has been found that in the case of the dynamic equilibrium described above, the derivative of Pmaterial with respect to time is approximately a linear function of ΔT, referred to below as F(ΔT).
  • In other words, the following applies under dynamic equilibrium: P tot t = P material t + P losses t F Δ T + k 1 P tot t P tot t k 2 Δ T T centre T surface - 1 k 2 P tot t ,
    Figure imgb0002

    in which k1 and k2 are constants and since F(ΔT) is an approximately linear function. Since Tsurface is known and constant when the dynamic equilibrium described above prevails, the time derivative of Ptot can thus be used to approximately calculate the temperature Tcentre in the centre of the heated material.
  • Finally, since the specific operating conditions may vary somewhat, it has been found that it is easier to use empirically based interruption conditions than mathematically calculated conditions. The above derivation is therefore intended mainly to explain the principle behind the present invention.
  • In Figure 2, the dotted surface illustrates the area in which both secondary conditions are met. At the time T2 the primary condition is also met, and the heating may thus be interrupted.
  • Because of the operating conditions, that actually vary, and the generally varying conditions that prevail during heating of material in industrial furnaces, the PID control of P will have a relatively high variance. As described above, this variance will be somewhat higher if P is measured at the flow regulator 6 rather than at the regulator 5.
  • In other words, P will generally vary as a relatively smooth function as the negative derivative increases during the period between T1 and T2, but with a noise component of varying intensity. Whenever applicable, this noise component can be filtered off by averaging P over a number of measuring points that depends on the current application, preferably at least 10 measuring points. It is also possible, and preferable, to have the number of points used in the formation of the mean value vary as a function of how high the variance of P currently is. Thus, more points are used in the formation of the mean value at high instantaneous variance, and reversely fewer points at low instantaneous variance. For example, the variance may be lower during the beginning of the temperature equalising second heating step and higher during its final stage. For the sake of clarity, and to give an example, a mean value has been formed over 10 historical measuring points for P in the next but bottom graph of dP/dt.
  • Moreover, there may be greater justification, for example, in forming a mean value over more points if P is measured at the flow regulator 6. The flow of fuel and oxidant controlled by the flow regulator 6 contains a further noise component relative to the output signal generated by the regulator 5, as described above. One reason for this is that the flow regulator 6 controls the burner or burners 3, in certain applications, to heat the furnace 1 by an on/off procedure. This may, for example, depend on the fact that the burner or burners 3 has (have) a minimum power which exceeds the heating power prescribed by the PID regulator 5, which heating power is to be discharged to the furnace atmosphere at a certain given occasion. In this case, for example, the flow regulator 6 controls the burner or burners 3 to be switched on for a certain period of time after which it (they) are switched off and then repeat(s) this process so that the mean power emitted will be that prescribed by the PID regulator 5 during each given period of time. This method is called pulse width modulation.
  • It is also possible for the flow regulator 6 to use constant times for the switched-on/switched-off position, respectively, and instead to vary the power of the burner or burners 3 during the switched-on position, thereby achieving the same correct average heating power. This is called pulse height modulation.
  • Other modulation techniques are also possible, for example a combination of pulse width modulation and pulse height modulation, to achieve an average instantaneous heating power which corresponds to that prescribed by the PID regulator 5 during a certain given period of time.
  • When such a modulation is used, combined with measurement of P at the flow regulator 6, it is also possible, advantageously, to average the curve P over a number of measuring points in order to arrive at a corresponding continuous function from which dP/dt can be determined. In the same manner as above, at least 10 measuring points are preferably used for the mean value formation, but it is also preferable to vary the number of measuring points as a function of the variance of P. For example, the modulation will very likely be greater or more prevalent during the final stage of the heating process, when Tcentre approaches its desired final temperature.
  • In the present exemplary embodiment, the regulator 5 is of the PID type, but it should be realised that also other types of regulators can be used when applying the method of the present invention. In such cases the criteria of the present invention for interrupting the heating may need to be modified to suit the prevailing conditions. For example, it may also be necessary to examine the second derivative with respect to time of the heating power curve in the case where a regulator used can bring about a build-up of the furnace temperature, where the derivative of the heating power is zero once or several times before the furnace temperature eventually approaches its final value.
  • The present invention thus provides a method that enables a heating process to be interrupted with greater certainty in an industrial furnace when there is sufficient temperature uniformity in the material, without the need to continue the heating process for an unnecessarily long period, with the associated drawbacks in terms of long heating times, high energy costs and material damage. Moreover, the investment cost for applying the present invention to existing industrial furnaces is low, because sensors or corresponding devices required to measure or observe emitted power and furnace temperature are often already installed. In these cases it is therefore sufficient to implement the actual interruption condition, which can be achieved at relatively low cost.
  • Exemplary embodiments have been described above. However, the invention may be varied without departing from the concept of the invention. The present invention must not therefore be considered to be limited by these exemplary embodiments but can be varied within the scope of the attached claims.

Claims (13)

  1. A method for heating billets or ingots (2) in an industrial furnace (1) by means of at least one burner (3), in which furnace (1) the heating power (P) continuously introduced into the furnace (1) is controlled by means of a regulator (5) whose input parameter is the temperature (Tfurnace) of the furnace atmosphere, which temperature (Tfurnace) is measured by means of a temperature measuring device (4), wherein the regulator (5) is caused to control the heating in at least one first heating step and a subsequent second temperature equalising step, characterised in that the instantaneous heating power (P) is measured continuously, in that the derivative of the heating power (P) with respect to time (dP/dt) is calculated continuously, and in that the heating is interrupted when a primary condition, namely that this derivative (dP/dt) falls within a predetermined interval ([dP/dPcond 1, dP/dPcond 2]), is met, provided that the heating at this time is in the subsequent second temperature equalising step.
  2. A method according to Claim 1, characterised in that the heating is considered to be in the subsequent second temperature equalising step if both a first secondary condition, namely that the absolute instantaneous heating power (P) is below a first predetermined value (Pcond), and a second secondary condition, namely that the total thermal energy (PAck) introduced into the furnace (1) since the beginning of the heating exceeds a second predetermined value (PAckcond), are met at the same time as the said primary condition.
  3. A method according to Claim 1 or 2, characterised in that the instantaneous heating power (P) at any time is determined indirectly by continuously measuring the quantity of fuel per unit time introduced into the industrial furnace (1).
  4. A method according to Claim 1 or 2, characterised in that the instantaneous heating power (P) at any time is determined as an ideal and desired heating power calculated by the regulator (5).
  5. A method according to Claim 1 or 2, characterised in that the regulator (5) is caused to control a flow regulator (6), which in turn is caused to control the heating power supplied to the industrial furnace (1), and in that the instantaneous heating power (P) is determined at any time as the heating power modulated by the flow regulator (6).
  6. A method according to Claims 2, 3, 4 or 5, characterised in that the first predetermined value (Pcond) consists of the heating power emitted into the furnace (1) during an early stage, or a lower value.
  7. A method according to any one of Claims 2 - 6, characterised in that the second predetermined value (PAckcond) consists of the theoretical energy which is at least required to heat the material (2) to the required final temperature distribution or higher with a heating efficiency suitable for the system.
  8. A method according to any one of the preceding claims, characterised in that the variance over time of the heating power (P) is caused to be reduced by means of a first mean value formation over several consecutive measuring points, before calculation of the derivative of the heating power with respect to time (dP/dt).
  9. A method according to any one of the preceding claims, characterised in that when pulse width modulation, pulse height modulation or combinations of these are used to control the heating power (P) introduced continuously into the furnace (1), a corresponding continuous heating power function is calculated by means of a second mean value formation over several consecutive measuring points of the heating power (P), and in that the corresponding continuous heating power function is used to calculate the derivative (dP/dt).
  10. A method according to Claim 8 or 9, characterised in that the first and/or second mean value formation over several consecutive measuring points make(s) use of at least 10 consecutive points.
  11. A method according to Claim 8 or 9, characterised in that the first and/or second mean value formation over several consecutive measuring points make(s) use of a number of consecutive points where the number of points varies depending on the instantaneous variance of the heating power over time.
  12. A method according to any one of the preceding claims, characterised in that the interval ([dP/dPcond 1, dP/dPcond 2]) is symmetrical around 0.
  13. A method according to any one of the preceding claims, characterised in that the burner (3) is an oxyfuel burner.
EP08171076.6A 2007-12-13 2008-12-09 Method for heating in an industrial furnace Not-in-force EP2071262B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SE0702774A SE532567C2 (en) 2007-12-13 2007-12-13 Procedure for heating in an industrial oven

Publications (2)

Publication Number Publication Date
EP2071262A1 true EP2071262A1 (en) 2009-06-17
EP2071262B1 EP2071262B1 (en) 2016-08-03

Family

ID=40456992

Family Applications (1)

Application Number Title Priority Date Filing Date
EP08171076.6A Not-in-force EP2071262B1 (en) 2007-12-13 2008-12-09 Method for heating in an industrial furnace

Country Status (3)

Country Link
EP (1) EP2071262B1 (en)
RU (1) RU2008149158A (en)
SE (1) SE532567C2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011131802A1 (en) * 2010-04-23 2011-10-27 Sidenor Investigación Y Desarrollo, S.A. Control method for heating ovens
ES2415560R1 (en) * 2010-04-23 2014-01-24 Gerdau Investigación Y Desarrollo Europa, S.A. HEATING OVEN CONTROL PROCEDURE
US10648738B2 (en) 2015-06-24 2020-05-12 Novelis Inc. Fast response heaters and associated control systems used in combination with metal treatment furnaces

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2788175A (en) * 1955-05-12 1957-04-09 James G Murray Jr Furnace control system
DE2808771A1 (en) * 1978-03-01 1979-09-06 Hoesch Werke Ag PROCEDURE FOR CONTROLLING A HEATING FURNACE FOR STEEL BLOCKS

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2788175A (en) * 1955-05-12 1957-04-09 James G Murray Jr Furnace control system
DE2808771A1 (en) * 1978-03-01 1979-09-06 Hoesch Werke Ag PROCEDURE FOR CONTROLLING A HEATING FURNACE FOR STEEL BLOCKS

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011131802A1 (en) * 2010-04-23 2011-10-27 Sidenor Investigación Y Desarrollo, S.A. Control method for heating ovens
ES2415560R1 (en) * 2010-04-23 2014-01-24 Gerdau Investigación Y Desarrollo Europa, S.A. HEATING OVEN CONTROL PROCEDURE
US10648738B2 (en) 2015-06-24 2020-05-12 Novelis Inc. Fast response heaters and associated control systems used in combination with metal treatment furnaces
US11268765B2 (en) 2015-06-24 2022-03-08 Novelis Inc. Fast response heaters and associated control systems used in combination with metal treatment furnaces

Also Published As

Publication number Publication date
SE0702774L (en) 2009-06-14
EP2071262B1 (en) 2016-08-03
RU2008149158A (en) 2010-06-20
SE532567C2 (en) 2010-02-23

Similar Documents

Publication Publication Date Title
RU2553783C2 (en) Method and device of pressure control in continuous annealing furnace
CN103397171B (en) Method for determining furnace-temperature set value of billet heating furnace
JP4949192B2 (en) Operation method of dental kiln and combustion kiln
JPH01260213A (en) Fuel burner control method and control device
EP2071262B1 (en) Method for heating in an industrial furnace
CN105018718A (en) Heating furnace process furnace temperature control method based on thermal load distribution
US6104744A (en) Regulation or control of a fusion process in a three-phase current arc furnace
JP2011099608A (en) Boiler combustion control device
JP6424725B2 (en) Boiler system
JP3231601B2 (en) Electric furnace temperature control method and apparatus
US20070238061A1 (en) Method for heating a metal material
JP2003521623A (en) Turbine operating method and turbine plant
CN104508371A (en) Boiler system
KR20030016715A (en) Mtehod and apparatus for automatic control of gas combustion in the hot stove for operating blast furnace
JP5648789B2 (en) boiler
TWI512258B (en) Energy saving method of setting the furnace pressure
JP5742311B2 (en) Method and apparatus for preventing warpage of rolled material in hot rolling line
KR101996255B1 (en) Control panel for burner
JPS61141787A (en) Control of oven temperature in coke oven
KR101205069B1 (en) Apparatus and method for controlling injection of fuel-gas
CN116857983A (en) Feedforward control method and system for improving control precision of heating furnace
Andreev et al. Obtaining reliable information on energy-saving regimes for the heating of continuous-cast semifinished products prior to rolling
KR101808420B1 (en) Damper control apparatus for heat insulation device of rolled materials and method thereof
JP2507406Y2 (en) Boiler operation control device
IL300443A (en) Method and system for providing variable ramp-down control for an electric heater

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA MK RS

17P Request for examination filed

Effective date: 20091209

AKX Designation fees paid

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

17Q First examination report despatched

Effective date: 20100330

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20160510

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

Ref country code: AT

Ref legal event code: REF

Ref document number: 817610

Country of ref document: AT

Kind code of ref document: T

Effective date: 20160815

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602008045409

Country of ref document: DE

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 9

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20160803

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 817610

Country of ref document: AT

Kind code of ref document: T

Effective date: 20160803

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161203

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161103

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161205

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161104

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602008045409

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161103

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20170504

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161231

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161231

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161209

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 10

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161209

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20081209

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20160803

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161209

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20181127

Year of fee payment: 11

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20181123

Year of fee payment: 11

Ref country code: GB

Payment date: 20181205

Year of fee payment: 11

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602008045409

Country of ref document: DE

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20191209

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191209

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191231

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20200701