EP1978181A2 - Procedure to inspect the condition of construction scaffolding systems on site and tool for the execution of the procedure - Google Patents
Procedure to inspect the condition of construction scaffolding systems on site and tool for the execution of the procedure Download PDFInfo
- Publication number
- EP1978181A2 EP1978181A2 EP08462003A EP08462003A EP1978181A2 EP 1978181 A2 EP1978181 A2 EP 1978181A2 EP 08462003 A EP08462003 A EP 08462003A EP 08462003 A EP08462003 A EP 08462003A EP 1978181 A2 EP1978181 A2 EP 1978181A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- frame
- scaffolding
- tool
- site
- procedure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000010276 construction Methods 0.000 title claims abstract description 9
- 238000009434 installation Methods 0.000 claims abstract description 10
- 238000005259 measurement Methods 0.000 claims abstract description 10
- 229910052751 metal Inorganic materials 0.000 claims abstract description 7
- 239000002184 metal Substances 0.000 claims abstract description 7
- 230000000903 blocking effect Effects 0.000 claims description 3
- 238000007689 inspection Methods 0.000 description 20
- 238000012360 testing method Methods 0.000 description 5
- 229910052782 aluminium Inorganic materials 0.000 description 3
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 3
- 230000000712 assembly Effects 0.000 description 3
- 238000000429 assembly Methods 0.000 description 3
- 238000009533 lab test Methods 0.000 description 3
- 239000004411 aluminium Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000003116 impacting effect Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000000737 periodic effect Effects 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
Definitions
- the subject of the invention is how to inspect the condition of construction scaffolding systems, especially facade scaffold systems before installation or periodically on site, possibly already erected, and the tool for the execution of the procedure.
- the invention's task is to implement such a procedure and construct such supporting equipment that enables a reliable and accurate on site safety inspection of construction or other types of scaffolding systems, especially on shape and dimension discrepancies of erected scaffold frames, possibly already in use.
- joint and surface quality inspection as another part of the safety inspection of scaffolding can be carried out by on site survey or with help of a manual measuring equipment which can be combined with lab tests that provide more accurate data if needed.
- the key to task completion is the recognition of the fact that a quick, accurate and reliable on site safety inspection can only be executed if there is an equipment available that is easy to carry and can be precisely set at the same time.
- the invention that solves the task is a procedure on the course of which we install a tool inside the inspected scaffolding frame that follows the inner line of the frame by a gap.
- the procedure can even be used if the frame is to be inspected on site but already erected.
- the inspected deformations and discrepancies from the specified tolerance that may occur are to be compared to the installed tool by survey and measurements.
- the tool enabling the execution of the procedure is a rectangular pattern frame with two longer and two shorter side units that attach to the inner line of the inspected scaffolding frame by a gap.
- One of the two longer units of this pattern frame has at least two stable brackets installed that can be attached to the inspected scaffolding frame.
- brackets should have swivel joint to allow the closing-opening motion of the pattern frame.
- the rectangular pattern frame A that is suitable for the execution of the procedure consists of two longer and two shorter side units 1 that can possibly be made of light metal mainly aluminium hollow sections welded together, where the longer side units 1 of pattern frame A are connected by cross braces 2 in order to obtain higher level of stability.
- Pattern frame A can be made of other materials (e.g. plastics) provided their ability to maintain shape is comparable to light metal so side panels 1 of pattern frame A can be connected in other ways accordingly.
- Pattern frame A is sized the way that its outer line follows the inner line of scaffolding frame B to be inspected with a gap where the gap between scaffolding frame B and the pattern frame A installed to it falls in the interval of 1 to 10 cm.
- the size of the gap should enable quick and accurate measurements on the inner circumference of scaffolding frame B and survey that can detect the possible deformations easily.
- Two quick locks 3 allowing a practical closing-opening motion are fixed to one of the longer side units 1 under each other in order to obtain easier use. Their detailed structure and the way of installation are shown by Figure 2 and Figure 3 .
- the procedure to inspect mainly metal, especially aluminium made construction scaffolding systems before installation or periodically on site should be executed as already described in the introduction.
- These inspections must include the dimension and shape tolerance of the vertical parts of scaffolding frames B that are the main parts of the scaffolding system, moreover the dimension and shape tolerance of other elements of the scaffolding system such as planking, guardrail members, cross braces, end gate assemblies, toeboards or access units, in addition, the condition of male bases, wall ties, clamps or eye bolts, as well as the quality of joints and the surface condition.
- the on site inspection of the associated accessories consists of surveying and measuring length but it can also include the inspection of diameters when needed.
- the joint and surface quality inspection of scaffolding units can be carried out by manual measuring equipment which can be supported by lab tests in reasonable cases if more accurate data are required.
- pattern frame A that can be easily delivered to the site of the inspection due to its light weight where it can be installed accurately and quickly to the current inspected scaffolding frame B with its proper connecting parts, meaning quick locks 3 fixed by eccentric 10.
- the quick lock 3 has a swivel joint 8
- the pattern frame that is fixed on one of the longer side of the scaffolding frame can be folded onto the inspected scaffolding frame.
- the pattern frame is leveled with the scaffolding frame B in a position defined by the blockers 4.
- pattern frames A is to be installed one by one to each scaffolding frame B to be inspected, starting on the lower levels, prior to which the removal of the handrail end assemblies is required. If the rate of damaged frames exceeds 20% of the inspected scaffolding frames B, the scaffolding system is not safe any more and has to be dismantled. If the on site inspection is executed on not installed scaffold units, on the ground, the inspected scaffolding frame B and pattern frame A have to be practically placed on a spiny palette laid down on the ground.
- the procedure and tool, namely pattern frame, detailed in the invention's description above makes it possible to inspect the condition of different types of scaffolding systems, especially metal made façade scaffolding systems in an economic, efficient and accurate way before installation or periodically, possibly when already erected.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)
Abstract
Description
- The subject of the invention is how to inspect the condition of construction scaffolding systems, especially facade scaffold systems before installation or periodically on site, possibly already erected, and the tool for the execution of the procedure.
- Obligatory inspection before installation and periodic labor safety inspections on installation of metal made construction scaffold systems, primarily aluminum are specified by decree standards. These inspections must be done by qualified competent experts on labor safety regulations according to the parameters specified by the producers. According to the relevant standards, these inspections must include first of all the dimension and shape allowance of the vertical units of the scaffolding frames that are the main parts of the scaffolding system, moreover the dimension and shape allowance of other elements of the scaffolding system such as planking, guardrail members, cross braces, end gate assemblies, toeboards or access units, in addition, the condition of male bases, wall ties, clamps or eye bolts, as well as the quality of the joints and the surface condition. Of course, the results of the inspections are recorded in a protocol and the inspected scaffolding frames are marked accordingly.
- On the course of the above mentioned inspection of the scaffolding system, the following must be checked if
- horizontal units are not deformed or twisted to such an extent that tilting occurs,
- joints are not cracked,
- vertical scaffolding frames are plumb and a proper fit can be made without force,
- handrail brackets are not deformed, the toeboards are not damaged, and the outriggers are working well,
- the cross braces are not deformed,
- the components of the scaffolding system are within the tolerance specified by the producer.
- The above listed inspection tasks, primarily the inspection of scaffolding frames could not be carried out on site so far, especially when scaffolding systems had already been erected. So practically the test of conformity could be performed only under lab circumstances similarly to 102752-15100 Sps/str
the new production of scaffolding units. Due to this fact, on site safety inspections were restricted mostly to surveys. - Beside commonly used measuring instruments and testing equipment for checking joints and surface quality on different types of scaffolding systems, special testing patterns with impacting units attached to a solid, mostly fixed plate base were constructed. Components of scaffolding systems are to be attached to the patterns that measure the possible discrepancies from the specified measurements, the angles of related components, twisting, buckling and other irregularities that could endanger the safety of the scaffolding. Although this lab test pattern gives accurate test results, only few specified scaffolding types can be measured with it. Its general application is not possible, and due to its dimensions and weight, on site tests cannot be performed with it.
- The invention's task is to implement such a procedure and construct such supporting equipment that enables a reliable and accurate on site safety inspection of construction or other types of scaffolding systems, especially on shape and dimension discrepancies of erected scaffold frames, possibly already in use. With reference to that, we have to note that joint and surface quality inspection as another part of the safety inspection of scaffolding can be carried out by on site survey or with help of a manual measuring equipment which can be combined with lab tests that provide more accurate data if needed.
- The key to task completion is the recognition of the fact that a quick, accurate and reliable on site safety inspection can only be executed if there is an equipment available that is easy to carry and can be precisely set at the same time.
- Based on this recognition, the invention that solves the task is a procedure on the course of which we install a tool inside the inspected scaffolding frame that follows the inner line of the frame by a gap. The procedure can even be used if the frame is to be inspected on site but already erected. The inspected deformations and discrepancies from the specified tolerance that may occur are to be compared to the installed tool by survey and measurements.
- The tool enabling the execution of the procedure is a rectangular pattern frame with two longer and two shorter side units that attach to the inner line of the inspected scaffolding frame by a gap. One of the two longer units of this pattern frame has at least two stable brackets installed that can be attached to the inspected scaffolding frame.
- To be able to fit the pattern frame precisely leveled with the inspected scaffolding frame and in order to clearly demonstrate the deformation of the scaffolding frame, according to the invention, it is advantageous to clip blockers on one out of the two longer side units that is opposite to the side unit having the brackets. These overhanging blockers, practically blocking plates must be of perpendicular position and enable the pattern frame to fit into and precisely level with the inspected scaffolding frame.
- In order to achieve faster and more efficient inspection results, it is also advantageous to use eccentric quick locks that connect easily to the scaffolding frame.
- For an easier application of the pattern frame, for practical reasons the brackets should have swivel joint to allow the closing-opening motion of the pattern frame.
- At last, in order to provide a better stability and to maintain the shape of the pattern frame, it is advisable to connect the longer side units with cross braces.
- The invention is explained in details by the enclosed diagram of the construction drawing.
In the diagram -
Figure 1 shows a sketch of the pattern frame to carry out the procedure of the invention installed in the scaffolding frame inspected, -
Figure 2 shows the vertical section of fixing the pattern frame to the scaffolding frame by quick lock and -
Figure 3 shows the horizontal section ofFigure 2 - As it is shown by
Figure 1 , the rectangular pattern frame A that is suitable for the execution of the procedure consists of two longer and twoshorter side units 1 that can possibly be made of light metal mainly aluminium hollow sections welded together, where thelonger side units 1 of pattern frame A are connected bycross braces 2 in order to obtain higher level of stability. Pattern frame A can be made of other materials (e.g. plastics) provided their ability to maintain shape is comparable to light metal soside panels 1 of pattern frame A can be connected in other ways accordingly. Pattern frame A is sized the way that its outer line follows the inner line of scaffolding frame B to be inspected with a gap where the gap between scaffolding frame B and the pattern frame A installed to it falls in the interval of 1 to 10 cm. Anyhow, the size of the gap should enable quick and accurate measurements on the inner circumference of scaffolding frame B and survey that can detect the possible deformations easily. Twoquick locks 3 allowing a practical closing-opening motion are fixed to one of thelonger side units 1 under each other in order to obtain easier use. Their detailed structure and the way of installation are shown byFigure 2 and Figure 3 . - At the same time, on the longer side unit that lies opposite to the longer side unit that has installed
quick locks 3, there are three evenly spaced overhangingperpendicular blockers 4, possibly blocking plates. These plates fit to one side of the inspected scaffolding frame or are laid onto it providing a leveled and precise fit of pattern frame A into B, furthermore, lack of even spacing between theblockers 4 is a definite sign of deformation. Thelevel 5 placed on the upper shorter side unit of the pattern frame shows clearly if the inclination angle of the erected scaffolding frame exceeds the acceptable limit.Figure 2 and Figure 3 show clearly thatquick locks 3 are fixed byscrews 6 and bolts 7 to pattern frame A and by atube brace 9 fixed by eccentric 10 to scaffolding frame B. As aswivel joint 8 connects the bolt of thequick lock 3 and thetube brace 9, this point allows pattern frame A to make a closing-opening motion related to scaffolding frame B, providing easier use. - Based on the invention, the execution of the procedure with help of the above described pattern frame A is as follows:
- The procedure to inspect mainly metal, especially aluminium made construction scaffolding systems before installation or periodically on site should be executed as already described in the introduction. These inspections must include the dimension and shape tolerance of the vertical parts of scaffolding frames B that are the main parts of the scaffolding system, moreover the dimension and shape tolerance of other elements of the scaffolding system such as planking, guardrail members, cross braces, end gate assemblies, toeboards or access units, in addition, the condition of male bases, wall ties, clamps or eye bolts, as well as the quality of joints and the surface condition.
- The on site inspection of the associated accessories consists of surveying and measuring length but it can also include the inspection of diameters when needed. The joint and surface quality inspection of scaffolding units can be carried out by manual measuring equipment which can be supported by lab tests in reasonable cases if more accurate data are required.
- The most important novelty in the procedure to inspect the condition of scaffolding systems on site for safety reasons is the application of pattern frame A that can be easily delivered to the site of the inspection due to its light weight where it can be installed accurately and quickly to the current inspected scaffolding frame B with its proper connecting parts, meaning
quick locks 3 fixed by eccentric 10. As thequick lock 3 has aswivel joint 8, the pattern frame that is fixed on one of the longer side of the scaffolding frame can be folded onto the inspected scaffolding frame. In case there is no occurring deformation, the pattern frame is leveled with the scaffolding frame B in a position defined by theblockers 4. It follows the inner line of scaffolding frame B by a gap and in this position on one hand, the possible deformations can already be determined by survey, on the other hand, discrepancies from the specified shape and dimension tolerance can be easily measured along the inner circumference of scaffolding frame B, usually at 2 points per side. In case the scaffolding system is already erected and installed, the procedure to install pattern frame A to each scaffolding frame B to be inspected is as follows: pattern frames A is to be installed one by one to each scaffolding frame B to be inspected, starting on the lower levels, prior to which the removal of the handrail end assemblies is required. If the rate of damaged frames exceeds 20% of the inspected scaffolding frames B, the scaffolding system is not safe any more and has to be dismantled. If the on site inspection is executed on not installed scaffold units, on the ground, the inspected scaffolding frame B and pattern frame A have to be practically placed on a spiny palette laid down on the ground. - The procedure and tool, namely pattern frame, detailed in the invention's description above makes it possible to inspect the condition of different types of scaffolding systems, especially metal made façade scaffolding systems in an economic, efficient and accurate way before installation or periodically, possibly when already erected.
Claims (6)
- A procedure to inspect construction scaffolding systems, especially, metal made façade scaffolding systems before or even after the installation periodically on site, in the course of which we check the twisting and buckling on the frames of the scaffolding system, the position of the scaffolding frame components related to each other and also the measurement discrepancies from the specification of these components, characterized by the installation of a tool inside the inspected scaffolding frame attached to the frame of a possibly already erected scaffolding system to be checked on site, that follows the inner line of the scaffold frame by a gap and the possible deformations and discrepancies from the specified measurements can be determined by survey or by measurements compared to the installed tool.
- A tool to inspect the condition of construction scaffolding systems, especially facade scaffold systems before installation or periodically on site. In addition, we check the twisting and buckling on the frames of the scaffold system, the position of the scaffolding frame components related to each other and also the measurement discrepancies from the specification of these components. The tool is characterized by a rectangular shaped pattern frame (A) built up from two long and two short side-units (1) that follows the inner line of the inspected scaffold frame (B) by a gap having at least two stably attached clips on one of the longer side unit (1) of the pattern frame (A) that can be connected to the system frame (B).
- A tool according to Patent Requirements 2, characterized by blockers clipped on one out of the two longer side units (1) that is opposite to the one having the brackets. These overhanging blockers (4), practically blocking plates must be of perpendicular position and enable the pattern frame (A) to fit into and precisely level with the inspected scaffolding frame (B).
- A tool according to Patent Requirements 2 or 3, characterized by the application of eccentric quick locks (3) that connect easily to the scaffolding frame (B).
- A tool according to Patent Requirements 2-4, characterized by brackets that have swivel joint (8) to allow the closing-opening motion of the pattern frame (A) compared to the scaffolding frame (B).
- A tool according to Patent Requirements 2-5, characterized by cross braces (2) that connect the longer side units of the pattern frame (A).
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
HU0700267A HU227258B1 (en) | 2007-04-06 | 2007-04-06 | Method and tool for checking of dimensional change and deformation of scaffoldings at surveying process |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1978181A2 true EP1978181A2 (en) | 2008-10-08 |
EP1978181A3 EP1978181A3 (en) | 2009-11-18 |
Family
ID=89987444
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP08462003A Withdrawn EP1978181A3 (en) | 2007-04-06 | 2008-03-28 | Procedure to inspect the condition of construction scaffolding systems on site and tool for the execution of the procedure |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP1978181A3 (en) |
HU (1) | HU227258B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102901528A (en) * | 2012-09-25 | 2013-01-30 | 昆山荣科钣金科技有限公司 | Testing machine frame and manufacture process thereof |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105937864B (en) * | 2016-05-30 | 2019-04-30 | 赛闻(苏州)包装工业有限公司 | A kind of verifying metal cubing substituting motor body |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH102103A (en) | 1996-06-13 | 1998-01-06 | Takenaka Komuten Co Ltd | Side balustrade for standing post framework |
JP2005076445A (en) | 2003-09-03 | 2005-03-24 | Alinco Inc | Safety handrail |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10009227B4 (en) * | 2000-02-28 | 2004-05-19 | Gerüstbau Lothar Pannwitz | locking device |
-
2007
- 2007-04-06 HU HU0700267A patent/HU227258B1/en not_active IP Right Cessation
-
2008
- 2008-03-28 EP EP08462003A patent/EP1978181A3/en not_active Withdrawn
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH102103A (en) | 1996-06-13 | 1998-01-06 | Takenaka Komuten Co Ltd | Side balustrade for standing post framework |
JP2005076445A (en) | 2003-09-03 | 2005-03-24 | Alinco Inc | Safety handrail |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102901528A (en) * | 2012-09-25 | 2013-01-30 | 昆山荣科钣金科技有限公司 | Testing machine frame and manufacture process thereof |
CN102901528B (en) * | 2012-09-25 | 2015-04-29 | 昆山荣科钣金科技有限公司 | Testing machine frame and manufacture process thereof |
Also Published As
Publication number | Publication date |
---|---|
HUP0700267A2 (en) | 2009-03-02 |
HU227258B1 (en) | 2010-12-28 |
EP1978181A3 (en) | 2009-11-18 |
HU0700267D0 (en) | 2007-06-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8919727B2 (en) | Elevated floor and ceiling slab formwork system | |
CN106092036A (en) | A kind of formwork-support deformation remote real time monitoring system and method | |
KR101826007B1 (en) | A Supporting stand for a Bridge Inspection | |
CN112459090B (en) | Novel steel hanging box cofferdam construction method based on Larsen steel sheet pile | |
CN108179868B (en) | Air construction platform device based on steel structure overhanging special-shaped curtain wall | |
CN109457965B (en) | High-efficiency installation method and device of precast concrete wall panel | |
CN105115397B (en) | A kind of scaffold detection ruler | |
CN111424950A (en) | Steel column hoisting device, steel column hoisting construction method and supervision method thereof | |
CN210347331U (en) | Guardrail horizontal load resistance on-site detection device | |
CN115419277A (en) | Construction method of heavy steel box type inclined column | |
EP1978181A2 (en) | Procedure to inspect the condition of construction scaffolding systems on site and tool for the execution of the procedure | |
CN105423880B (en) | A kind of method for hanging main push-towing rope measurement deflection of bridge span | |
CN104213511B (en) | A kind of bridge construction platform structure and building method thereof | |
Jamińska-Gadomska et al. | Verification of the façade scaffolding computer model | |
CN210513104U (en) | Formwork system monitoring device | |
CN113235898A (en) | Overhanging scaffold and construction process thereof | |
CN211060931U (en) | Portable template verticality measuring device | |
WO2021209931A1 (en) | Lift shaft scaffolding and related safety rail installation | |
RU208002U1 (en) | Fence test spreader | |
CN112942809A (en) | Combined template assembling method capable of realizing mechanical construction | |
CN215167840U (en) | Overhanging scaffold | |
CN221052850U (en) | Assembled cable membrane structure | |
KR200275936Y1 (en) | Batter board made by using slide type pole assembly multi-pole of different diameter | |
CN205861036U (en) | A kind of formwork-support deformation remote real time monitoring system | |
JP4782613B2 (en) | Roof bolt testing machine mounting apparatus and installation method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA MK RS |
|
17P | Request for examination filed |
Effective date: 20090407 |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA MK RS |
|
17Q | First examination report despatched |
Effective date: 20100521 |
|
AKX | Designation fees paid |
Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20151001 |