EP1856370A1 - Pipe handling equipment - Google Patents

Pipe handling equipment

Info

Publication number
EP1856370A1
EP1856370A1 EP06716758A EP06716758A EP1856370A1 EP 1856370 A1 EP1856370 A1 EP 1856370A1 EP 06716758 A EP06716758 A EP 06716758A EP 06716758 A EP06716758 A EP 06716758A EP 1856370 A1 EP1856370 A1 EP 1856370A1
Authority
EP
European Patent Office
Prior art keywords
pipe
pipes
storage
opening
handler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP06716758A
Other languages
German (de)
French (fr)
Inventor
Erik Zachariasen
Finn Engenes
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sense EDM AS
Original Assignee
Sense EDM AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sense EDM AS filed Critical Sense EDM AS
Publication of EP1856370A1 publication Critical patent/EP1856370A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • E21B19/14Racks, ramps, troughs or bins, for holding the lengths of rod singly or connected; Handling between storage place and borehole

Definitions

  • the present invention relates to devices for handling of pipes on the drilling floor onboard a drilling rig.
  • a derrick In the extraction of petroleum products a derrick is used, which is a part of a rig.
  • the rig can either be placed on land or in water. In water, the rig can be a fixed construction that stands on the ocean bottom, or can be a floating construction, which is either anchored to the ocean bottom or dynamically positioned.
  • the main task for the derrick is to serve as a body for suspension of lifting equipment that lowers drill strings, risers, casings and other continuous pipe strings down to, or in a well, and also to lift the pipe string up from the well.
  • the invention is comprised of several devices that can work together or operate individually.
  • the devices shall firstly be described individually and thereafter the operation between these shall be explained with reference to embodiment examples shown in the enclosed figures, in which:
  • the spinning head 34 is fitted with cylinders 38 that can lift the weight from a stand and at the same time rotate the pipe so that the threads are not damaged.
  • the rollers 39 of the spinner are designed so that they can hold the weight of the stand whilst rotating it. The pipe will thereby be lifted up with a predetermined force.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

System for handling pipes on a drilling deck, comprising a pipe-handler (20) that is rotary around a vertical axis, a storage device (1) which in turn comprises an opening (14) through which pipes can be retrieved and inserted, and an intermediate storage (14) in connection to the opening. The storage (14) having the function of a lock gate dividing the drill floor into two separate pipe handling areas. The pipe-handler (20) is arranged to reach both the intermediate storage (14) in connection to the opening and the drilling centre (15). The storage device (1) comprises a pipe transport device which in turn comprises a gripper (30) that is arranged to grip at least one pipe from above and transport the pipe hanging from the gripper (30) between a storage position and the opening (14). The storage device (1) is surrounded by a closure (13) that prevents pipes from unintentionally getting outside the storage device (1).

Description

Pipe handling equipment
The present invention relates to devices for handling of pipes on the drilling floor onboard a drilling rig.
In the extraction of petroleum products a derrick is used, which is a part of a rig. The rig can either be placed on land or in water. In water, the rig can be a fixed construction that stands on the ocean bottom, or can be a floating construction, which is either anchored to the ocean bottom or dynamically positioned.
The main task for the derrick is to serve as a body for suspension of lifting equipment that lowers drill strings, risers, casings and other continuous pipe strings down to, or in a well, and also to lift the pipe string up from the well.
A time critical factor in the execution of drilling operations and others that involve lowering down and bringing back up a long pipe string (the technical jargon for which is tripping) is transport to and from the derrick. Therefore, there has been a strong wish for making the pipe sections (a pipe section is comprised of 2, 3 or 4 drill pipes) as near to the derrick as possible. However, the available space is very limited as other essential equipment must also be located here. Another argument for moving pipe sections away from the drilling deck itself is to place them at a lower level to lower the centre of gravity. These stores near the derrick can therefore contain only a limited amount.
Much has been done to develop equipment that can transport pipe sections quickly to the derrick, in some cases directly to the drilling centre (the line the drill string follows through the tower). It is just as important to quickly remove pipes that are disconnected from the pipe string.
Much emphasis has also been placed on the safety aspect of the development of this type of equipment for handling of pipes. Therefore, steadily more automated equipment that demands a minimum of crew on the drilling floor has been developed.
Examples of prior art are: GB 1250424 which shows a pipe storage on the drill floor within the derrick. The storage is equipped with finger boards to support the pipes.
US 6513605 which shows a pipe storage similar to the storage of GB 1250424.
Norwegian Patent application no. 2004 5263, by the same applicant, describes equipment for transporting pipes between a main store and a drilling floor. The present invention aims to be a supplement or an alternative to the equipment described in the above mentioned patent application.
The invention is comprised of several devices that can work together or operate individually. In the following, the devices shall firstly be described individually and thereafter the operation between these shall be explained with reference to embodiment examples shown in the enclosed figures, in which:
Figure 1 shows a planar view of a drilling floor inside a derrick having a set-back according to the present invention,
Figure 2 shows a sectional elevation of the derrick in figure 1,
Figure 3 shows a detail of a set-back in an alternative embodiment.
Figure 4 shows a planar view of a drill floor area comprising the set back of figures 1 -3 and further pipe handling equipment,
Figure 5a - 5d show a lifting yoke for simultaneous lifting of several pipes, where Figure 5a shows the lifting yoke in sectional elevation, Figure 5b shows a plane diagram of the lifting yoke,
Figure 5 c shows the lifting yoke in sectional elevation perpendicular to figure 6a, Figure 6d shows the lifting yoke in cross section, Figures 6a - d show a spinner for a pipe handler for simultaneous lifting and screwing and unscrewing of pipes.
The invention will first be explained referring to figures 1 and 2, in which figure 1 shows a plane diagram of a drilling floor area with the pipe arrangement location according to the present invention, and figure 2 shows a sectional elevation of a derrick 18 having legs 19, and with the pipe arrangement area of figure 1. In figure 1 the derrick legs 19 are shown in cross section. Figures 1 and 2 illustrates the combined finger board and pipe storage (set back) 1 according to the invention. This finger board and set-back device (in the following called set-back for simplicity) is set up to store pipes 2 on the drill floor and is fitted with finger boards 3 and 4 in two levels.
An upper level 4 has fingers 5 that separates each row with drill pipes/casings 6, 7, 8, 9, 10 and has a lock 12 for each individual pipe 2. The lower board 3 separates each row from each other, but has no lock.
The two finger boards 3, 4 are enclosed, surrounded by a frame 13. If a pipe-stand falls out of a finger 5 it will be caught by the frame 13 so that it does not fall out into the area for drilling and stops the operation here. In addition, the frame 13 will function as a limiting factor in the transport path on the drilling floor so that pipe transport in areas where there can be people will be reduced to a minimum. In this way, one can easier optimise the equipment that is used inside the set-back.
There is only one opening 14 into the set-back 1, and that is through a so-called "single point entry" 14 opening that is combined with an intermediate storage location for drill pipes/casings 2. By using an intermediate storage 14 one can optimise a system for handling of pipe-stands in the set-back area 1. This gives new possibilities for use of other types of gripping heads and handling of pipes faster and with a reduced lifting height and larger extent of automation, as will be explained in more detail in the following. The intermediate storage 14 at the entrance of the set-back 1 on the drill floor has two fingers 16, 17 that can be adjusted horizontally to take different dimensions of drill pipes/casings. The fingers 16, 17 can be tilted to open the intermediate storage towards the set-back or towards the outside of the set-back, respectively. Thereby the intermediate storage 14 functions as a lock chamber for the pipes, dividing the drill floor into two separate pipe handling areas.
One advantage with the above mentioned device is that the system for a travelling crane to lift and transport the pipes and casing between the setlback area and the intermediate storage 14 can be given defined positions in all three planes, x-y-z, so that one avoids problems in placing of pipes with the travelling crane.
The set-back is formed so that several pipes 2 can be located (drill pipes and/or casings) between each finger 5. This ensures that it is possible to carry more pipes with a travelling crane, which lifts from above. There is no need to support the pipes at their lower end during transport within the set-back since no persons have the possibility to enter the set-back during operation. Consequently, the pipes may be allowed to dingle to a certain degree during transport within the set-back.
From the intermediate storage 14 the pipes 2 are transported individually by a drill floor pipe handler 20, which grips the lower and upper parts of the pipe 2 and moves it to the drill centre 15. Here it can be gripped by a top drive 21 running on rails 22 in the derrick 18.
In figure 1 is also shown a small auxiliary set-back 23, which is used for storing pipes during assembling and disassembling of pipe stands 24. The auxiliary set-back 23 is curved in shape so that the distance from the rotational axis of the pipe handler 20 is substantially the same for all slots in the auxiliary set-back 23. The auxiliary set-back 23 may also be used for storing drill collars or other special elements. Figure 1 also shows a small side-storage 24, which also can act as an intermediate storage when stands are being build up or down or to hold pipes in cases when the pipe handler 20 temporarily must put these down while it carries out other tasks.
The fingers 5 can be directed in two directions, namely towards the drill centre 15 from the one wall of the derrick to the other, as shown in figure 1, or towards each other with an opening 25 between them for transport of pipes, as shown in figure 3. As mentioned, the set-back has two finger boards, an upper finger board 4, and a lower finger board 3. The upper board 4 has a lock 26 for a row of pipes 6, 7, 8, 9, 10.
From two to four pipes 6, 7, 8, 9, 10 are arranged between each finger 5 of the finger boards 4 in figure 3. Between each row of two to four pipes there are locking pins 26 that hold the pipes 6, 7, 8, 9, 10 in place. The locking pins 26 can be swung up or down when pipe rows are to be retrieved or put back.
In the configuration in figure 3, a pipe row will first be led out to the passage 25 and thereafter be led 90° towards the gate 14. This is slightly different form the configuration in figure 1, in which a pipe row (of two or four pipes) will first be led out into the passage 27 and thereafter must be turned 90° and led towards the gate 14. Here in the configuration of figure 3, it must be turned back 90° so that it can be led into the combined gate and intermediate storage 14.
An auxiliary storage 23 for pipe collars and a side storage 24 are also shown in figure 3. As for the figure 1 configuration the intermediate storage 14 is placed at the entrance of the set-back 1 on the drilling floor. It has two fingers 16 and 17 that can be adjusted horizontally to take different dimensions of drill pipes/casings.
Transport to the intermediate storage 14 from the outside of the set-back 1 is be with the pipe handler 20, which can also reach the drilling centre 15 and the catwalk (the catwalk is a transport path that brings pipes to the derrick; which will be explained in connection with figure 4). With the use of the intermediate storage 14, one can release extra possibilities for the pipe transporter (see the description below in connection with figures 5a - d) inside the set-back so that this can perform new tasks and carry out the tasks in a much more rational way. The intermediate storage 14 makes it possible to take and put back more than one pipe at the same time.
Figure 4 shows an overview of the system for pipe handling on the drilling floor. The system comprises a catwalk 27 that transports pipes horizontally in the derrick 18. Here, the pipe can be lifted up into a vertical position by, for example, a V-door lifter (not shown). The pipe is thereafter taken over by a pipe handler 20, which can be in the form of a column machine. Alternatively, the pipe handler 20 can pick up a pipe or other objects directly from the cat walk 27 and lift these up into vertical position (for example, with the help of a lower arm) or bring these directly into the drilling centre 15. The pipe handler 20 has the possibility of placing the pipe in a rotary mouse hole 28. Such a rotary mouse hole 28 is described in Norwegian Patent application no. 2004 5263, which is hereby incorporated in the present application by reference. The pipe can, alternatively after having been put together with several pipes to a pipe stand, be transported further to the intermediate storage 14. However, pipes can also be placed in the small side-storage 24 (see also figure 3), that is arranged to hold pipes in cases when the pipe handler 20 must temporarily put these down while it carries out other tasks.
Pipes can also be led into the drilling centre 15 by the pipe handler 20. To provide a nearby storage of a certain size, where pipes can be quickly retrieved or put back into, for example, in connection with tripping of the drill string, the pipes that are placed in the intermediate storage 14 can be brought further into the set-back 1. A lifting yoke which is described in connection with the figures 5a - d is used for this. As this lifting yoke is arranged to grip the pipes from above, the set-back 1 can be configured with a minimum of distance between the pipes. It is possible to grip the pipes from above only and let the pipes hang freely from the lifting yoke during transport inside the set-back because the set-back is a closed-in area where personnel and other equipment have no access during normal operation. In this way, one will have room for a large number of pipes in a small area and achieve an efficient pipe handling. The lifting yoke can be arranged suspended from a trolley (not shown) that runs on a rail system above the set-back. Such a trolley and rail system are, in themselves, known devices and shall therefore not be described in more detail here.
The intermediate storage 14 is placed on the drilling floor at the same level as the setback 1 and the level at which pipes are led into or taken out of the drilling centre. By having such a buffer of pipes as the intermediate storage 14 provides, it is possible to increase the speed to and from the drilling centre 15 in a safe way without increasing the speed of the pipe handling machine (lifting yoke) inside the set back 1, as the lifting yoke and the pipe handler 20 can operate independently of each other.
Next to the set-back 1, the auxiliary set-back 23 is arranged for drill collars and other special pipes (see also figure 3). This auxiliary set-back 23 is preferably arched with a curvature corresponding to the path which gripping heads of the pipe handler 20, so that the pipe handler 20 can reach the positions in the auxiliary set-back 23 by stretching out the gripping heads the same distance.
The pipe handler 20 can be equipped with a spinner, as shown in figures 8a - d, instead of a conventional gripper. The column machine can thereby both transport pipes into and out of the drilling centre 15 and screw the pipes on and off the pipe string. Thereby, one does not have to change grip on the pipe before this is placed onto the pipe string and removed from this, respectively.
With the above mentioned configuration, the pipe handler 20 will be able to reach all actual positions where it is relevant to collect or put down pipes with a minimum of movement. The pipe handler 20 can thus operate efficiently and, to a large extent, independently of associated equipment
The figures 5a - d show a lifting yoke 29 for lifting of pipes 6 out of the set-back 1 and transport these out to the intermediate storage 14. To lift several pipes simultaneously between the setback 1 and the intermediate storage 14, it is an advantage to have a yoke 29 that can lift several pipes 6 at the same time. Thus, the yoke 29 that transports pipes between the finger boards 3, 4 of the set-back 1 and the intermediate storage 14 operates at a lower speed. The gripping head 30 is formed so that it can take more than one pipe stand at the same time, in parallel or in series. Consequently, the gripping head has grippers 31 forming gripping surfaces, which have a length that span the diameter of two or more pipes. The grippers 31 are fixed to arms 32 that are actuated by a hydraulic cylinder 33 acting through an actuation mechanism 33.
The figures 6a - 6d show a spinner 34 for fitting onto a lifting arm 35 for both lifting/transport and on and off screwing of drill pipes/casings. The lifting arm 35 is rotary connected to a trolley 36 that in turn can move along a column 37 (see figures 1 and 2). This column can be a part of the pipe handler 20.
This spinner 34 can be arranged on the pipe handler 20 that lifts a drill pipe/casing into the drilling centre 15. The spinner 34 can rotate the pipe that hangs in it so that it enters the threads on the pipe that sticks up from the drill floor in the drilling centre 15. This makes a faster operation possible and releases time for the machine that screws together pipes to correct momentum.
The spinning head 34 is fitted with cylinders 38 that can lift the weight from a stand and at the same time rotate the pipe so that the threads are not damaged. The rollers 39 of the spinner are designed so that they can hold the weight of the stand whilst rotating it. The pipe will thereby be lifted up with a predetermined force.
When the pipes are screwed together, the cylinders 38 will yield and sink down as the pipe is screwed together so that the spinner head 34 is gradually lowered.
When one screws pipes from each other, the system will be able to take the weight of the pipe and lift it out of the threads with a predetermined force.

Claims

Claims
1.
Device for storing pipes comprising at least one upper and one lower finger board, characterized in that the device is arranged on the drill floor and is surrounded by a closure (13) that defines a storage area (1) and prevents pipes from unintentionally falling outside the storage area (1), and having a defined opening for feeding pipes into the storage area and for retrieving pipes form the storage area (1), the opening having a lock chamber (14) being adapted to hold one or more pipes, and the lock chamber dividing the drill floor into two separate pipe handling areas.
2.
Device according to claim 1, characterized in that the lock chamber is an intermediate storage (14) where a number of pipes can be placed temporarily whilst waiting to be brought out of the storage area (1) or to be fed into the storage area (1).
3.
Device according to claims 1 or 2, characterized in that it comprises a further temporary storage next to the opening.
4.
Device for lifting pipes, characterised in that it comprises a gripper that is arranged to grip at least one pipe from above and transport this suspended inside a storage area to and from an opening in the storage area.
5.
Device for storing drill collars and other special pipes, characterized in that it comprises a pipe stand (23) which is arched with the centre of the circle sector coinciding with the rotation centre of a rotary pipe-handler, such that the pipe-handler can reach the drill collars and the special pipes at the same distance from the centre of rotation and the pipe slots in the pipe stand (23) is only defined by an angular distance between the pipes.
6.
Device for transporting pipes to and from a drilling centre, characterized in that it comprises a gripping head that is arranged to grip the pipe at its upper end and further comprises a device to rotate the pipe around its own axis, to be able to screw pipes off and on the upper end of another pipe.
7.
System for handling pipes on a drilling deck, characterized in that it comprises a pipe-handler that is rotary about a vertical axis, a storage device which in turn comprises an opening through which pipes can be retrieved and inserted and an intermediate storage in connection with the opening, as the pipe-handler is arranged to reach both the intermediate storage and the drilling centre.
8.
System according to claim 7, characterized in that it further comprises a mouse hole device for building up pipe stands, said mouse hole device comprising several chambers to receive pipes and that the pipe-handler is arranged to reach the mouse hole device.
9.
System according to claims 7 or 8, characterized in that the storage device comprises a pipe transporting means which in turn comprises a gripper that is arranged to grip at least one pipe from above and transport the pipe hanging from the gripper between a storage position and the opening of the pipe storage.
10.
System according to claims 7, 8 or 9, characterized in that the storage device is surrounded by a closure that prevents pipes from unintentionally getting outside the storage device.
EP06716758A 2005-03-07 2006-03-06 Pipe handling equipment Withdrawn EP1856370A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NO20051199A NO324009B1 (en) 2005-03-07 2005-03-07 Device for storing rudder.
PCT/NO2006/000082 WO2006096068A1 (en) 2005-03-07 2006-03-06 Pipe handling equipment

Publications (1)

Publication Number Publication Date
EP1856370A1 true EP1856370A1 (en) 2007-11-21

Family

ID=35253695

Family Applications (1)

Application Number Title Priority Date Filing Date
EP06716758A Withdrawn EP1856370A1 (en) 2005-03-07 2006-03-06 Pipe handling equipment

Country Status (5)

Country Link
US (1) US20090053015A1 (en)
EP (1) EP1856370A1 (en)
CA (1) CA2600406A1 (en)
NO (1) NO324009B1 (en)
WO (1) WO2006096068A1 (en)

Families Citing this family (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7328747B2 (en) * 2004-05-03 2008-02-12 Edo Corporation, Fiber Science Division Integrated buoyancy joint
NO333743B1 (en) * 2005-10-12 2013-09-09 Nat Oilwell Norway As Device at drill floor
CN102191922A (en) * 2010-03-03 2011-09-21 中国石油天然气集团公司 Tubular column migration and centralizing device for drilling machine
BR112013010737B1 (en) 2010-11-02 2020-10-27 National Oilwell Varco Norway As rack unit, method for building a pipe segment, and system for storing one or more tubulars
US9091128B1 (en) * 2011-11-18 2015-07-28 T&T Engineering Services, Inc. Drill floor mountable automated pipe racking system
EP2828468B1 (en) * 2012-03-20 2017-02-22 Itrec B.V. Tubulars storage device
DE102012007402A1 (en) * 2012-04-16 2013-10-17 Herrenknecht Vertical Gmbh Pipe bearing and method for feeding and discharging pipe bodies to a drilling rig
US9410382B2 (en) 2012-05-14 2016-08-09 Nabors Drilling International Limited Drilling rig carriage movable along racks and including pinions driven by electric motors
US9790751B2 (en) 2012-05-14 2017-10-17 Nabors Drilling International Limited Drilling rig employing top drive
ITUD20130038A1 (en) * 2013-03-20 2014-09-21 Fincantieri Cantieri Navali It "TUBULAR ELEMENT HANDLING SYSTEM"
CN103422821A (en) * 2013-09-16 2013-12-04 慕武 Stand column placing space distance adjustable finger boards
DE102013015893A1 (en) * 2013-09-24 2015-03-26 Herrenknecht Vertical Gmbh Handling device for drill pipes of a deep drilling device
US9932783B2 (en) * 2014-08-27 2018-04-03 Nabors Industries, Inc. Laterally moving racker device on a drilling rig
CN104278958B (en) * 2014-10-28 2016-07-06 连云港黄海勘探技术有限公司 Borer drill rod carrying case
CA3005465A1 (en) 2015-11-16 2017-05-26 Schlumberger Canada Limited Tubular delivery arm for a drilling rig
RU2726780C2 (en) * 2015-11-16 2020-07-15 Шлюмбергер Текнолоджи Б.В. Automated pipe feed system
RU2726691C2 (en) 2015-11-17 2020-07-15 Шлюмбергер Текнолоджи Б.В. Drilling rig with high rate of round-trip operations
US11136836B2 (en) 2016-04-29 2021-10-05 Schlumberger Technology Corporation High trip rate drilling rig
US11118414B2 (en) 2016-04-29 2021-09-14 Schlumberger Technology Corporation Tubular delivery arm for a drilling rig
RU2018141596A (en) 2016-04-29 2020-05-29 Шлюмбергер Текнолоджи Б.В. DRILLING RIG WITH HIGH SPEED LIFTING OPERATIONS
US10597954B2 (en) 2017-10-10 2020-03-24 Schlumberger Technology Corporation Sequencing for pipe handling
NO343919B1 (en) 2018-04-20 2019-07-08 Mhwirth As Crane yoke, crane and method for handling tubulars
US10837242B2 (en) * 2018-06-29 2020-11-17 Nabors Drilling Technologies Usa, Inc. Apparatus and method for securing tubulars on a drilling rig
US10890038B2 (en) * 2019-03-29 2021-01-12 Nabors Drilling Technologies Usa, Inc. Double layer racking board and methods of use

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2773605A (en) * 1953-11-12 1956-12-11 Paul A Medearis Pipe racking apparatus
US3561811A (en) * 1968-05-23 1971-02-09 Byron Jackson Inc Well pipe racker
USRE30071E (en) * 1973-12-21 1979-08-14 Atlas Copco Aktiebolag Drill string element handling apparatus
US4269554A (en) * 1979-08-14 1981-05-26 Jackson Lewis B Well pipe handling equipment
US4445579A (en) * 1981-08-10 1984-05-01 Paul Bello Pipe carousel for well-drilling rig
NO891944D0 (en) * 1989-05-12 1989-05-12 Hitec As DEVICE FOR ROD HANDLING SYSTEM.
GB9622480D0 (en) * 1996-10-29 1997-01-08 Weatherford Lamb Apparatus and method for running tubulars
US6068066A (en) * 1998-08-20 2000-05-30 Byrt; Harry F. Hydraulic drilling rig
DE19956840A1 (en) * 1999-11-26 2001-06-07 Deutsche Tiefbohr Ag Method and device for handling pipes in drilling rigs
DE10108696B4 (en) * 2001-02-23 2005-10-13 Deilmann-Haniel Mining Systems Gmbh Drilling machine for double-head and overlay drilling with a circular-arc boom
US6821071B2 (en) * 2002-09-25 2004-11-23 Woolslayer Companies, Inc. Automated pipe racking process and apparatus

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO2006096068A1 *

Also Published As

Publication number Publication date
NO324009B1 (en) 2007-07-30
CA2600406A1 (en) 2006-09-14
NO20051199D0 (en) 2005-03-07
NO20051199L (en) 2006-09-08
WO2006096068A1 (en) 2006-09-14
US20090053015A1 (en) 2009-02-26

Similar Documents

Publication Publication Date Title
US20090053015A1 (en) Pipe Handling Equipment
US10465455B2 (en) Automated tubular racking system
CN106285518B (en) A kind of tubing string automatic processing device discharging four single upright column of small drilling tool
US8052370B2 (en) System for handling pipes between a pipe rack and a derrick, and also a device for assembling and disassembling pipe stands
US10597954B2 (en) Sequencing for pipe handling
KR100747819B1 (en) Horizontal Pipe Handling Device
US6763898B1 (en) Dual hoist system
CN110043203A (en) A kind of automated drilling rig and the method using automated drilling rig progress tubing string movement
RU2746984C2 (en) Method and system for transporting drill pipes
KR20100014551A (en) Simultaneous tubular handling system
NO317594B1 (en) Method and apparatus for extending a bore
EP1836374A2 (en) A device for gripping and transporting pipe lenghts and an intermediate storage facility for storage of pipes
US20220349268A1 (en) High-capacity mast on a drilling rig
US9382767B2 (en) Cantilever contained drilling unit utilizing vertical tubular conveyance and standbuilding system
KR101897849B1 (en) A handling system for drill pipe
JP4088743B2 (en) Tube handling assembly and related methods
RU2444608C2 (en) Mechanisation system for lifting and lowering operations during overhaul and routine maintenance of wells
US20130048310A1 (en) Advanced rig design for automated tubular installation and removal operations
RU2774268C2 (en) Pipe lowering-lifting sequence
US20230053471A1 (en) Spiders capable of handling well components of multiple sizes
BR122023010199B1 (en) LIFTING SYSTEM AND METHOD FOR OPERATING A LIFTING SYSTEM
BR112022000212B1 (en) DRILLING SYSTEM
GB2585681A (en) Drilling rig systems and methods
KR20150144434A (en) A handling system for drill pipe

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20070911

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR

DAX Request for extension of the european patent (deleted)
STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20111001