EP1153172A1 - A method and an assembly for casting a tower foundation - Google Patents

A method and an assembly for casting a tower foundation

Info

Publication number
EP1153172A1
EP1153172A1 EP00901053A EP00901053A EP1153172A1 EP 1153172 A1 EP1153172 A1 EP 1153172A1 EP 00901053 A EP00901053 A EP 00901053A EP 00901053 A EP00901053 A EP 00901053A EP 1153172 A1 EP1153172 A1 EP 1153172A1
Authority
EP
European Patent Office
Prior art keywords
fixture plate
concrete
pull
anchoring
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP00901053A
Other languages
German (de)
French (fr)
Inventor
Teddy Norre
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Neg Micon AS
Original Assignee
Neg Micon AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Neg Micon AS filed Critical Neg Micon AS
Publication of EP1153172A1 publication Critical patent/EP1153172A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • E04H12/085Details of flanges for tubular masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Definitions

  • the present invention relates to an improved method of casting a foundation for a tower providing a high quality contact surface for the bottom part of the tower
  • the invention is highly suitable for making foundations for towers for wind turbines with substantially horizontal rotor axes because such towers are subjected to a strong horizontal force near the top and are thus very demanding for the foundations
  • the invention also relates to a fixture assembly for fixing the upper ends of anchoring rods during casting of the foundation and making a recess in the concrete of the foundation for accommodating a bottom flange of the tower
  • Tower foundations having anchoring rods protruding upwardly from a concrete block for fastening the tower are commonly made by fixing the upper end of the rods with a fixture plate before the concrete is poured into the excavation in which the anchoring rods are placed
  • the surface of the concrete is levelled by hand and the fixture plate is not in contact with the concrete
  • the fixture plate is removed after hardening of the concrete for reuse
  • the area where the bottom flange of the tower will be placed is covered with a layer of expanding concrete where after the bottom flange is positioned on top of the expanding concrete A proper supporting surface for the bottom flange is provided in this way, but the procedure adds another 2-3 days of work to the making of the foundation
  • the fixture plate may also be cast into the concrete foundation, thereby providing a proper supporting surface for the bottom flange of the tower
  • the very precise manufacture of the fixture plate makes this option costly
  • WO 96/16232 discloses a tower foundation in which a template of a shape similar to the bottom flange of the tower is partly submerged by liquid concrete during casting of the foundation, before and during which the template is supported at the lower surface by nuts on anchoring rods extending through the template and by a structure above the template which structure is supported by feet in abutting contact with the ground away from the template and the foundation
  • the template is subsequent to the hardening of the concrete lifted off the foundation leaving a suitable recess for the bottom flange of the tower
  • the nuts must be either removed or displaced further down below the level of the bottom flange because the nuts would hinder pre-stretching of the anchoring rods if they are in abutment with the bottom flange This leads to large voids in the horizontal surface of the recess and thus a less support of the flange
  • the template is very difficult to detach and lift off without permanently bending the template and hinder the reuse of the template
  • the present invention relates to a method of casting a foundation for a tower, comprising the steps of positioning a plurality of anchoring rods substantially vertical in a ground excavation, positioning a fixture assembly at an upper end of the excavation, the assembly comprising a fixture plate and at least two, preferably at least three, pull-off means, the fixture plate having a number of openings defined therein though which the plurality of anchoring rods extends each through one of said openings so that an upper end of each anchoring rod protrudes upwardly from an upper surface of the fixture plate, the fixture plate being positioned so that a lower surface thereof is situated substantially horizontal at an upper end of the excavation the fixture plate being fully supported in said position by said pull-off means being positioned above the fixture plate and each engaging with said upper end of at least one anchoring rod, pouring liquid concrete into and filling the excavation to a horizontal level so that the fixture plate is partly submerged in the concrete, and allowing the concrete to harden, where after the fixture plate is pulled off from the concrete, leaving a recess formed in
  • anchoring rods usually means steel rods having a circular cross-section but is understood to include rods of other cross-sections, such as I beams, angle bars , tubes of various shapes, such as round, square, triangular, etc , but also steel wires and wires or ropes made from fibre-reinforces elastic or plastic materials, such as carbon fibres, glass fibres and/or Kevlar fibres
  • the fixture plate is preferably, prior to being pulled off, detached from the hardened concrete by means of the pull-off means so that the force for detaching or loosening the fixture plate only is used over a short vertical travelling distance of the fixture plate so as to prevent the plate from becoming permanently deformed
  • the pull-off means are connected to the fixture plate by means of adjustable connecting means that may displace the fixture plate relatively to the individual pull-off means, the detachment being performed by displacing the fixture plate upwardly towards the pull-off means by means of adjusting said connecting means
  • the fixture plate may advantageously subsequent to the pouring of the concrete and when the concrete is still liquid be displaced from the initial position upwards and downwards at least once by means of the pull-off means, ending up substantially at the initial position
  • the method advantageously further comprises the step of vibrating the liquid concrete in the excavation
  • the dimensions of the fixture plate as projected on a horizontal plane preferably exceed the corresponding dimensions of the bottom flange of the tower, so that a vertical groove being 5-40 mm, such as 10-30 mm, preferably 15-25 mm wide will be formed between the edges of the recess formed in the concrete and the vertical sides of the bottom flange of the tower when said flange is positioned in the recess
  • This groove may accommodate a sealing material to prevent water from seeping in between the bottom flange of the tower and the support surface
  • the method may further comprise the step of positioning an anchoring plate at a lower part of the excavation, securing the anchoring plate to another founding structure being positioned below the anchoring plate and securing a lower part of each anchoring rod to the anchoring plate
  • the fixture plate has a conical cross-section as seen in a vertical section so as to allow for the fixture plate to be pulled off from the concrete, and at least some of the sides of the fixture plate may therefore be inwardly inclined 5-45 degrees, such as 8-15 degrees and preferably about 10 degrees to vertical
  • the fixture plate is preferably ring shaped and suitable dimensions for the application of the present invention are an outer diameter of 1 5-12 meters and an inner diameter of 1 1-9 5 meters, the difference between the inner and the outer diameter being in the range from 0 4 to 2 5 meters.
  • the plurality of anchoring rods should be distributed evenly around the fixture plate so that they make take up forces on the tower coming from any side
  • the number of anchoring rods are preferably from 64 to 256, such as from 96 to 200 It is an advantage for symmetry reasons that the number of rods is a multiple of eight
  • the present invention further relates to an assembly comprising a fixture plate having a number of openings defined therein through which a plurality of parallel anchoring rods may extend, each through one of said openings, and at least two, preferably at least three, pull-off means, each having organs for engaging with an upper end of at least one of said anchoring rod extending from an upper surface of the fixture plate, and each having connecting means for connecting to the fixture plate so as to fully support the fixture plate when being arranged in a substantially vertical position
  • This assembly is designed to be used with the method according to the invention as described above and may have the disclosed features
  • Each anchoring rod is advantageously provided with external thread at least at the part protruding above the fixture plate, and the fixture plate may be provided with pull-off means mounted thereon for pulling off the fixture plate from the concrete, said pull-off means being adapted for interacting with some of the anchoring rods during the step in which the fixture plate is pulled off, which step is effected by the turning of nuts being arranged on said anchoring rods and being at an upper surface of said nuts in abutting contact with said pull-off means, so that an upward force is applied to the pull-off means and thereby the fixture plate
  • the anchoring plate may furthermore be fixed to another founding structure being positioned below the anchoring plate, such as a vertical foundation plate made from concrete and placed 1 5-5 meters, such as 2-4 meters, below the surface of the ground and with a side length of 8-25 meters, such as 12-20 meters
  • the underlying foundation may comprise piles that are driven into the ground.
  • FIGs. 1-8 An embodiment of the present invention is shown in Figs. 1-8 of which
  • Fig. 1 shows a vertical cross-section of the assembled fixture plate, anchoring rods and anchoring plate
  • Fig. 2 is a top view of the fixture plate
  • Fig. 3 shows a cross-section of one side of the fixture plate
  • Fig. 4 is a top view and Fig. 5 is a side view of a pull-off device as mounted on the fixture plate and the anchoring rods,
  • Fig. 6 is a side view of a pull-off device with measures
  • Fig. 7 shows a vertical cross-section of one side of the bottom flange of the tower
  • Fig. 8 is a vertical cross-section of the bottom flange of the tower as mounted in the recess in the concrete.
  • a vertical cross-section of the assembled fixture plate 1 , anchoring rods 2 and anchoring plate 3 is shown in Fig. 1.
  • a pull-off device 4 mounted on the fixture plate 1 is shown in the circle and details of the pull-off device 4 are shown in Figs. 4-6.
  • the assembling is placed in an excavation and is ready for the concrete to be poured into the excavation.
  • the anchoring plate 3 is fastened with anchoring means 5 to a vertical 14 x 14 meter foundation plate made from concrete and placed 2.5-3 meters below the surface of the ground.
  • the underlying foundation may comprise piles that are driven into the ground.
  • the anchoring rods 2 are at a lower end fastened to the anchoring plate 3 and are at an upper end provided with external thread so that the fixture plate 1 can be fastened to the rods 2 with nuts 6.
  • the fixture plate 1 is ring shaped as seen from the top as shown in Fig 2
  • the 144 anchoring rods 2 extend through holes 7 that are evenly distributed in two rows in the fixture plate 1
  • the fixture plate 1 is further provided with six holes 8 with internal thread for mounting of the pull-off devices 4
  • a cross-section of one side of the fixture plate is shown in Fig 3 with measures indicating the distance between the given position and the same position on the other side of the fixture ring, so that the outer diameter of the plate 1 is given as 3381 millimetres
  • the height of the fixture plate is 40 millimetres and the plate is submerged 30-40 mm into the concrete during casting of the foundation which has shown to be a suitable dept for the voids in the concrete around the fixture plate 1 to be removed or delimited during vibration of the liquid concrete, and the fixture plate 1 is still possible to remove after hardening of the concrete
  • a deeper submersion dept may be chosen for larger diameters of the fixture plate 1
  • the outer edges 9 of the fixture plate 1 are inwardly inclined 10 degrees to vertical in order to ease the removal of the plate 1 from the hardened concrete
  • Fig 4 is a top view and Fig 5 is a side view of a pull-off device 4 as mounted on the fixture plate 1 and the anchoring rods 2
  • Fig 6 shows a side view of the pull-off device 4 with measures
  • the pull-of device 4 is mounted with a bolt 10 into a hole 8 in the fixture plate 1
  • the hole 8 is provided with internal thread and is closed at the lower end with a plug 11 so that the lower surface of the fixture plate 1 is as smooth as possible
  • the pull- off device 4 has four holes 12 giving room for four anchoring rods 2 to pass
  • the pull-off device is connected to the anchoring rods 2 with one nut 13 above the device 4 and one nut 14 below
  • the fixture plate 1 is pulled off from the foundation by removing the upper nuts 13 and turning of the lower nuts 14 so that the pull-off devices 4 and thereby the fixture plate 1 are lifted relative to the anchoring rods 2
  • the bolt 10 is replaced with a bar having external thread at both ends and a nut situated above the upper surface of the
  • Fig 7 shows a vertical cross-section of one side of the bottom flange 15 of the tower 16
  • Fig 8 is a vertical cross-section of the bottom flange 15 of the tower 16 as mounted in the recess in the concrete 17
  • the recess is wider than the bottom flange 15, leaving a vertical groove 18 of about 20 millimetres between the vertical sides of the bottom flange 15 and the sides of the recess
  • the groove 18 is filled with a resilient filler 19 and sealed with a water tight sealing material
  • the anchoring rods 2 are pre-stretched 2 5 millimetres from their original length of 1 5 meters with a hydraulic tool before the nuts are tightened for fastening the bottom flange 15 to the foundation A pre-stretching of 1-2

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Architecture (AREA)
  • Sustainable Development (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Materials Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Sustainable Energy (AREA)
  • Foundations (AREA)

Abstract

A method and a fixture assembly for casting a foundation for a tower (16), in particular for a wind turbine, providing a high quality contact surface for the bottom flange (15) of the tower (16) is disclosed. The method comprises the positioning a plurality of anchoring rods (2) in a ground excavation and of a fixture assembly at an upper end of the excavation so that the anchoring rods (2) extend through openings in a fixture plate (1), which is fully supported by at least three pull-off means (4) above the fixture plate (1) and each engaging with the upper end of four anchoring rods (2). Liquid concrete (17) is poured into the excavation to a horizontal level so that the fixture plate (1) is partly submerged in the concrete (17), and after hardening, the fixture plate (1) is pulled off from the concrete (17) by means of the pull-off means (4), leaving a recess formed in the concrete (17) being suitable for receiving a bottom flange (15) of the tower (16).

Description

A METHOD AND AN ASSEMBLY FOR CASTING A TOWER FOUNDATION
The present invention relates to an improved method of casting a foundation for a tower providing a high quality contact surface for the bottom part of the tower The invention is highly suitable for making foundations for towers for wind turbines with substantially horizontal rotor axes because such towers are subjected to a strong horizontal force near the top and are thus very demanding for the foundations The invention also relates to a fixture assembly for fixing the upper ends of anchoring rods during casting of the foundation and making a recess in the concrete of the foundation for accommodating a bottom flange of the tower
Background
Tower foundations having anchoring rods protruding upwardly from a concrete block for fastening the tower are commonly made by fixing the upper end of the rods with a fixture plate before the concrete is poured into the excavation in which the anchoring rods are placed The surface of the concrete is levelled by hand and the fixture plate is not in contact with the concrete The fixture plate is removed after hardening of the concrete for reuse The area where the bottom flange of the tower will be placed is covered with a layer of expanding concrete where after the bottom flange is positioned on top of the expanding concrete A proper supporting surface for the bottom flange is provided in this way, but the procedure adds another 2-3 days of work to the making of the foundation
A method similar to the above described known method is disclosed in US 5,505,033
Another method is disclosed in FR 2682982, wherein a plate made at least partly from a material which can be deformed is placed between the foundation and the bottom flange
The fixture plate may also be cast into the concrete foundation, thereby providing a proper supporting surface for the bottom flange of the tower However, the very precise manufacture of the fixture plate makes this option costly
WO 96/16232 discloses a tower foundation in which a template of a shape similar to the bottom flange of the tower is partly submerged by liquid concrete during casting of the foundation, before and during which the template is supported at the lower surface by nuts on anchoring rods extending through the template and by a structure above the template which structure is supported by feet in abutting contact with the ground away from the template and the foundation The template is subsequent to the hardening of the concrete lifted off the foundation leaving a suitable recess for the bottom flange of the tower However, the nuts must be either removed or displaced further down below the level of the bottom flange because the nuts would hinder pre-stretching of the anchoring rods if they are in abutment with the bottom flange This leads to large voids in the horizontal surface of the recess and thus a less support of the flange Furthermore, is has been found that the template is very difficult to detach and lift off without permanently bending the template and hinder the reuse of the template
Description of the invention
It is an object of the present invention to provide a method of casting a foundation for a tower by which a proper supporting surface for the bottom flange of the tower is provided within the same casting process as the casting of the foundation
It is a further object of the invention to provide in which a fixture plate which is partly submerged in the concrete so as to form said supporting surface is suspended from the part of the anchoring rods protruding above the fixture plate so as to avoid the requirement of supporting the fixture plate with extern means, which is less precise, as well as a requirement of voids in the supporting surface for enabling the removal of supporting means, such as nuts
It is a yet further object to provide a method and means for detaching the fixture plate after hardening of the concrete in a controlled way so as to prevent stresses from permanently deforming the fixture plate
Thus, the present invention relates to a method of casting a foundation for a tower, comprising the steps of positioning a plurality of anchoring rods substantially vertical in a ground excavation, positioning a fixture assembly at an upper end of the excavation, the assembly comprising a fixture plate and at least two, preferably at least three, pull-off means, the fixture plate having a number of openings defined therein though which the plurality of anchoring rods extends each through one of said openings so that an upper end of each anchoring rod protrudes upwardly from an upper surface of the fixture plate, the fixture plate being positioned so that a lower surface thereof is situated substantially horizontal at an upper end of the excavation the fixture plate being fully supported in said position by said pull-off means being positioned above the fixture plate and each engaging with said upper end of at least one anchoring rod, pouring liquid concrete into and filling the excavation to a horizontal level so that the fixture plate is partly submerged in the concrete, and allowing the concrete to harden, where after the fixture plate is pulled off from the concrete, leaving a recess formed in the concrete being suitable for receiving a bottom flange of the tower
The term anchoring rods usually means steel rods having a circular cross-section but is understood to include rods of other cross-sections, such as I beams, angle bars , tubes of various shapes, such as round, square, triangular, etc , but also steel wires and wires or ropes made from fibre-reinforces elastic or plastic materials, such as carbon fibres, glass fibres and/or Kevlar fibres
The fixture plate is preferably, prior to being pulled off, detached from the hardened concrete by means of the pull-off means so that the force for detaching or loosening the fixture plate only is used over a short vertical travelling distance of the fixture plate so as to prevent the plate from becoming permanently deformed
This may be performed if the pull-off means are displaced relatively to the anchoring rods during detachment by means of turning nuts being arranged on a treaded part of said anchoring rods and being in abutting contact with said pull-off means at an upper surface of said nuts, so that an upward force is applied to the pull-off means and thereby the fixture plate
According to an alternative and preferred embodiment, the pull-off means are connected to the fixture plate by means of adjustable connecting means that may displace the fixture plate relatively to the individual pull-off means, the detachment being performed by displacing the fixture plate upwardly towards the pull-off means by means of adjusting said connecting means Also, in order to remove air captured under the fixture plate and forming voids in the supporting surface, the fixture plate may advantageously subsequent to the pouring of the concrete and when the concrete is still liquid be displaced from the initial position upwards and downwards at least once by means of the pull-off means, ending up substantially at the initial position In order to diminish the size and number of voids in the concrete around the fixture plate and thus providing an improved contact between the concrete foundation and the bottom flange of the tower, the method advantageously further comprises the step of vibrating the liquid concrete in the excavation
The dimensions of the fixture plate as projected on a horizontal plane preferably exceed the corresponding dimensions of the bottom flange of the tower, so that a vertical groove being 5-40 mm, such as 10-30 mm, preferably 15-25 mm wide will be formed between the edges of the recess formed in the concrete and the vertical sides of the bottom flange of the tower when said flange is positioned in the recess This groove may accommodate a sealing material to prevent water from seeping in between the bottom flange of the tower and the support surface
Furthermore, in order to control the position of the anchoring rods, to fasten the rods in the foundation and to ensure that the rods may be pre-tensioned, the method may further comprise the step of positioning an anchoring plate at a lower part of the excavation, securing the anchoring plate to another founding structure being positioned below the anchoring plate and securing a lower part of each anchoring rod to the anchoring plate
For most purposes it is suitable that the fixture plate has a conical cross-section as seen in a vertical section so as to allow for the fixture plate to be pulled off from the concrete, and at least some of the sides of the fixture plate may therefore be inwardly inclined 5-45 degrees, such as 8-15 degrees and preferably about 10 degrees to vertical
It is preferred that at least 5 millimetres of the height of the fixture plate is submerged in the concrete, preferably at least 10 mm and most preferred within the range of 15-50 mm, such as 30-40 mm For most towers being round or substantially round, the fixture plate is preferably ring shaped and suitable dimensions for the application of the present invention are an outer diameter of 1 5-12 meters and an inner diameter of 1 1-9 5 meters, the difference between the inner and the outer diameter being in the range from 0 4 to 2 5 meters The plurality of anchoring rods should be distributed evenly around the fixture plate so that they make take up forces on the tower coming from any side
The number of anchoring rods are preferably from 64 to 256, such as from 96 to 200 It is an advantage for symmetry reasons that the number of rods is a multiple of eight
The present invention further relates to an assembly comprising a fixture plate having a number of openings defined therein through which a plurality of parallel anchoring rods may extend, each through one of said openings, and at least two, preferably at least three, pull-off means, each having organs for engaging with an upper end of at least one of said anchoring rod extending from an upper surface of the fixture plate, and each having connecting means for connecting to the fixture plate so as to fully support the fixture plate when being arranged in a substantially vertical position
This assembly is designed to be used with the method according to the invention as described above and may have the disclosed features
Each anchoring rod is advantageously provided with external thread at least at the part protruding above the fixture plate, and the fixture plate may be provided with pull-off means mounted thereon for pulling off the fixture plate from the concrete, said pull-off means being adapted for interacting with some of the anchoring rods during the step in which the fixture plate is pulled off, which step is effected by the turning of nuts being arranged on said anchoring rods and being at an upper surface of said nuts in abutting contact with said pull-off means, so that an upward force is applied to the pull-off means and thereby the fixture plate
The anchoring plate may furthermore be fixed to another founding structure being positioned below the anchoring plate, such as a vertical foundation plate made from concrete and placed 1 5-5 meters, such as 2-4 meters, below the surface of the ground and with a side length of 8-25 meters, such as 12-20 meters Alternatively or additionally, the underlying foundation may comprise piles that are driven into the ground.
Brief description of the figures
An embodiment of the present invention is shown in Figs. 1-8 of which
Fig. 1 shows a vertical cross-section of the assembled fixture plate, anchoring rods and anchoring plate,
Fig. 2 is a top view of the fixture plate,
Fig. 3 shows a cross-section of one side of the fixture plate,
Fig. 4 is a top view and Fig. 5 is a side view of a pull-off device as mounted on the fixture plate and the anchoring rods,
Fig. 6 is a side view of a pull-off device with measures,
Fig. 7 shows a vertical cross-section of one side of the bottom flange of the tower, and
Fig. 8 is a vertical cross-section of the bottom flange of the tower as mounted in the recess in the concrete.
Measures on the figures are given in millimetres.
Detailed description of the figures
A vertical cross-section of the assembled fixture plate 1 , anchoring rods 2 and anchoring plate 3 is shown in Fig. 1. A pull-off device 4 mounted on the fixture plate 1 is shown in the circle and details of the pull-off device 4 are shown in Figs. 4-6. The assembling is placed in an excavation and is ready for the concrete to be poured into the excavation. The anchoring plate 3 is fastened with anchoring means 5 to a vertical 14 x 14 meter foundation plate made from concrete and placed 2.5-3 meters below the surface of the ground. Alternatively or additionally, the underlying foundation may comprise piles that are driven into the ground. The anchoring rods 2 are at a lower end fastened to the anchoring plate 3 and are at an upper end provided with external thread so that the fixture plate 1 can be fastened to the rods 2 with nuts 6. The fixture plate 1 is ring shaped as seen from the top as shown in Fig 2 The 144 anchoring rods 2 extend through holes 7 that are evenly distributed in two rows in the fixture plate 1 The fixture plate 1 is further provided with six holes 8 with internal thread for mounting of the pull-off devices 4
A cross-section of one side of the fixture plate is shown in Fig 3 with measures indicating the distance between the given position and the same position on the other side of the fixture ring, so that the outer diameter of the plate 1 is given as 3381 millimetres The height of the fixture plate is 40 millimetres and the plate is submerged 30-40 mm into the concrete during casting of the foundation which has shown to be a suitable dept for the voids in the concrete around the fixture plate 1 to be removed or delimited during vibration of the liquid concrete, and the fixture plate 1 is still possible to remove after hardening of the concrete However, a deeper submersion dept may be chosen for larger diameters of the fixture plate 1 The outer edges 9 of the fixture plate 1 are inwardly inclined 10 degrees to vertical in order to ease the removal of the plate 1 from the hardened concrete
Fig 4 is a top view and Fig 5 is a side view of a pull-off device 4 as mounted on the fixture plate 1 and the anchoring rods 2 Fig 6 shows a side view of the pull-off device 4 with measures The pull-of device 4 is mounted with a bolt 10 into a hole 8 in the fixture plate 1 The hole 8 is provided with internal thread and is closed at the lower end with a plug 11 so that the lower surface of the fixture plate 1 is as smooth as possible The pull- off device 4 has four holes 12 giving room for four anchoring rods 2 to pass The pull-off device is connected to the anchoring rods 2 with one nut 13 above the device 4 and one nut 14 below The fixture plate 1 is pulled off from the foundation by removing the upper nuts 13 and turning of the lower nuts 14 so that the pull-off devices 4 and thereby the fixture plate 1 are lifted relative to the anchoring rods 2 Alternatively, the bolt 10 is replaced with a bar having external thread at both ends and a nut situated above the upper surface of the pull-off device 4, and the fixture plate is moved vertically, so as to e g. detach and to pull-off the fixture plate 1 from the foundation, by turning of said nut In this latter embodiment, the vertical movement is easier obtained but demands more angular moment applied to the nut than in the former embodiment in which two or more nuts are turned at each pull-off device 4 to lift the fixture plate 1 Fig 7 shows a vertical cross-section of one side of the bottom flange 15 of the tower 16, and Fig 8 is a vertical cross-section of the bottom flange 15 of the tower 16 as mounted in the recess in the concrete 17 The recess is wider than the bottom flange 15, leaving a vertical groove 18 of about 20 millimetres between the vertical sides of the bottom flange 15 and the sides of the recess The groove 18 is filled with a resilient filler 19 and sealed with a water tight sealing material The anchoring rods 2 are pre-stretched 2 5 millimetres from their original length of 1 5 meters with a hydraulic tool before the nuts are tightened for fastening the bottom flange 15 to the foundation A pre-stretching of 1-2 per thousand of the original length thus providing a tension in the anchoring rods made from steel, has shown to be advantageous for keeping the bottom flange 15 constantly in close contact with the foundation and for reduce the risk of fatigue fracture of the rods 2 The anchoring rods 2 have been provided with a hard sheath 20 made from a plastic material such as polyvinyl chloride polymer or high density polyethylene in which sheaths 20 the rods 2 may slide, thus preventing the concrete 1 7 from sticking to the rods 2 and hinder the pre-stretching of the rods

Claims

1 A method of casting a foundation for a tower comprising the steps of positioning a plurality of anchoring rods substantially vertical in a ground excavation, positioning a fixture assembly at an upper end of the excavation, the assembly comprising a fixture plate and at least two, preferably at least three, pull-off means, the fixture plate having a number of openings defined therein though which the plurality of anchoring rods extends each through one of said openings so that an upper end of each anchoring rod protrudes upwardly from an upper surface of the fixture plate, the fixture plate being positioned so that a lower surface thereof is situated substantially horizontal at an upper end of the excavation, the fixture plate being fully supported in said position by said pull-off means being positioned above the fixture plate and each engaging with said upper end of at least one anchoring rod, pouring liquid concrete into and filling the excavation to a horizontal level so that the fixture plate is partly submerged in the concrete, and allowing the concrete to harden, where after the fixture plate is pulled off from the concrete, leaving a recess formed in the concrete being suitable for receiving a bottom flange of the tower
2 A method according to claim 1 , wherein the fixture plate prior to being pulled off is detached from the hardened concrete by means of the pull-off means
3 A method according to claim 2, wherein the pull-off means are displaced relatively to the anchoring rods during detachment by means of turning nuts being arranged on a treaded part of said anchoring rods and being in abutting contact with said pull-off means at an upper surface of said nuts, so that an upward force is applied to the pull-off means and thereby the fixture plate
4 A method according to claim 2, wherein the pull-off means are connected to the fixture plate by means of adjustable connecting means that may displace the fixture plate relatively to the individual pull-off means, the detachment being performed by displacing the fixture plate upwardly towards the pull-off means by means of adjusting said connecting means 5 A method according to claim 3 or 4, wherein the fixture plate subsequent to the pouring of the concrete and when the concrete is still liquid is displaced from the initial position upwards and downwards at least once by means of the pull-off means, ending up substantially at the initial position, so as to remove air captured under the fixture plate
5
6 A method according to any of the preceding claims, wherein the extend of the fixture plate as projected on a horizontal plane exceeds the corresponding extend of the bottom flange of the tower, so that a vertical groove being 5-40 mm wide will be formed between the edges of the recess formed in the concrete and the vertical sides of the bottom flange
10 of the tower when said flange is positioned in the recess
7 A method according to any of the preceding claims, further comprising the steps of positioning an anchoring plate at a lower part of the excavation, securing the anchoring plate to another founding structure being positioned below 15 the anchoring plate, and securing a lower part of each anchoring rod to the anchoring plate
8 A method according to any of the preceding claims, wherein the fixture plate has a conical cross-section as seen in a vertical section so as to allow for the fixture plate to be
20 pulled off from the concrete
9. A method according to claim 8, wherein at least some of the sides of the fixture plate are inwardly inclined 5-45 degrees to vertical.
25 10 A method according to any of the preceding claims, wherein the fixture plate is submerged at least 5 millimetres in the concrete
11. A method according to any of the preceding claims, wherein the fixture plate is ring shaped having an outer diameter of 1 5-12 meters and an inner diameter of 1 J -9 5
30 meters, the difference between the inner and the outer diameter being in the range from 0 4 to 2.5 meters, and the plurality of anchoring rods are distributed evenly around the fixture plate
12. A method according to any of the preceding claims, wherein the number of anchoring 35 rods are from 64 to 256
13. An assembly comprising a fixture plate having a number of openings defined therein through which a plurality of parallel anchoring rods may extend, each through one of said openings, and at least two, preferably at least three, pull-off means, each having organs for engaging with an upper end of at least one of said anchoring rod extending from an upper surface of the fixture plate, and each having connecting means for connecting to the fixture plate so as to fully support the fixture plate when being arranged in a substantially vertical position.
14. An assembly according to claim 13, wherein the connecting means connects to an upper part of the fixture plate.
15. An assembly according to claim 13 or 14, wherein the connecting means are adjustable and may displace the fixture plate relatively to the individual pull-off means so as to enable an upwardly displacement of the fixture plate towards the pull-off means by means of adjusting said connecting means.
16. An assembly according to claim 14 or 15, wherein the fixture plate has a conical cross-section as seen in a vertical section so as to allow for the fixture plate to be pulled off from concrete in which it is partly embedded.
17. An assembly according to claim 16, wherein at least some of the sides of the fixture plate are inwardly inclined 5-45 degrees to vertical.
18. An assembly according to any of claims 14-17, wherein the fixture plate is ring shaped of an outer diameter of 1.5-12 meters and an inner diameter of 1 J-9.5 meters, the difference between the inner and the outer diameter being in the range from 0.4 to 2.5 meters, and the openings for anchoring rods are distributed evenly around the fixture plate.
19. An assembly according to any of claims 14-18, wherein the number of openings for anchoring rods are from 64 to 256.
EP00901053A 1999-01-22 2000-01-24 A method and an assembly for casting a tower foundation Withdrawn EP1153172A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DKPA199900082 1999-01-22
DK990082 1999-01-22
PCT/DK2000/000030 WO2000043599A1 (en) 1999-01-22 2000-01-24 A method and an assembly for casting a tower foundation

Publications (1)

Publication Number Publication Date
EP1153172A1 true EP1153172A1 (en) 2001-11-14

Family

ID=8089533

Family Applications (1)

Application Number Title Priority Date Filing Date
EP00901053A Withdrawn EP1153172A1 (en) 1999-01-22 2000-01-24 A method and an assembly for casting a tower foundation

Country Status (3)

Country Link
EP (1) EP1153172A1 (en)
AU (1) AU2093200A (en)
WO (1) WO2000043599A1 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004017006B4 (en) 2004-04-02 2012-03-29 Aloys Wobben Method of erecting a tower
CN100381698C (en) * 2005-03-11 2008-04-16 曾碚凯 Small power vertical axle wind-mill generator
CA2647804A1 (en) * 2008-12-23 2010-06-23 Organoworld Inc. Wind turbine tower and method for building the same
EP2224062B9 (en) * 2009-02-26 2015-10-28 Vestas Wind Systems A/S A foundation for a wind turbine and a method of making a foundation for a wind turbine
ES2405034B1 (en) * 2011-11-17 2014-04-15 Acciona Windpower, S.A. PROCEDURE AND UNIT FOR THE SETTING OF A TOWER FROM AN AIRCRAFT TO A FOUNDATION AND AEROGENERATOR THAT INCLUDES SUCH UNIT
CN106592622A (en) * 2016-12-19 2017-04-26 长安大学 Annular concrete based wind-driven generator foundation structure with vertical prestress
CN106638733A (en) * 2017-03-07 2017-05-10 长安大学 Method for reinforcing fan foundation through additionally-arranged horizontal steel bars
CN110616732B (en) * 2019-09-26 2021-05-04 江苏金风科技有限公司 Fastening and leveling device for anchor bolt cage

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2724398A1 (en) * 1977-05-28 1978-11-30 Ernst August Wezel Anchoring bars for chimney stack foundation - are placed by gauge ring removed after concrete has harden
US5586417A (en) * 1994-11-23 1996-12-24 Henderson; Allan P. Tensionless pier foundation
US5740645A (en) * 1997-01-08 1998-04-21 Raby; David Michael J-bolt form

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO0043599A1 *

Also Published As

Publication number Publication date
AU2093200A (en) 2000-08-07
WO2000043599A1 (en) 2000-07-27

Similar Documents

Publication Publication Date Title
CA2853246C (en) Foundation for a wind turbine
CN110847044B (en) Semi-prefabricated assembled bent cap construction method
EP0793754B1 (en) Tensionless pier foundation
EP2383393A1 (en) Apparatus and method for producing a concrete foundation
EP2981654B1 (en) Tower assembly for a tower structure
JP2009167754A (en) Base frame for setting facility equipment and method of setting the base frame
EP2738322A1 (en) Tower structure
EP2550405B1 (en) A method of laying a foundation
JP2009057713A (en) Wind power generation hybrid tower, and its construction method
WO2000043599A1 (en) A method and an assembly for casting a tower foundation
KR20140097320A (en) Device and method for anchoring a wind turbine
CN109750892B (en) Prefabricated assembly type hybrid fan tower formwork supporting method and device
CN111636433A (en) Adjustable die for manufacturing waist beam and using method thereof
US8220214B1 (en) Prefabricated weight distribution element
CN211571515U (en) Assembled precast concrete anticollision wall component
CN114934517A (en) Foundation pit special-shaped continuous waist beam and construction method thereof
CN212801550U (en) Adjustable die for manufacturing waist beam
CN110359755B (en) Consolidation inhaul cable system of wind tower with mixed structure and manufacturing and mounting method thereof
CN112922361A (en) Bracket positioning and mounting method
AU2010226975A1 (en) Precast Concrete Foundation Block and Foundation
JP7536020B2 (en) Method for manufacturing a gravity foundation for an offshore installation and gravity foundation
AU2021255455B2 (en) Post-tension tube foundation and method of assembling same
CN211872969U (en) Pile foundation reinforcing steel bar prestretches device
CN114060225A (en) Steel-concrete combined tower and construction method thereof
CN117091527A (en) High slope deformation monitoring method

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20010822

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

AX Request for extension of the european patent

Free format text: AL PAYMENT 20010822;LT PAYMENT 20010822;LV PAYMENT 20010822;MK PAYMENT 20010822;RO PAYMENT 20010822;SI PAYMENT 20010822

17Q First examination report despatched

Effective date: 20020320

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20040114