EP0353829A1 - A method of transporting, installing or removing a marine object, and a semi-submersible vessel for implementation of the method - Google Patents
A method of transporting, installing or removing a marine object, and a semi-submersible vessel for implementation of the method Download PDFInfo
- Publication number
- EP0353829A1 EP0353829A1 EP89202012A EP89202012A EP0353829A1 EP 0353829 A1 EP0353829 A1 EP 0353829A1 EP 89202012 A EP89202012 A EP 89202012A EP 89202012 A EP89202012 A EP 89202012A EP 0353829 A1 EP0353829 A1 EP 0353829A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- outriggers
- load
- vessel
- buoyancy
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/003—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting very large loads, e.g. offshore structure modules
Definitions
- the unit can be connected to an air system for compensation of the vertical motions of the installation vessel.
- the semi-submersible vessel 1 as represented in the drawings is shown in longitudinal and in plan view in figure 1 and is provided with additional buoyant bodies 2 in the form of a watertight bridge house fore and, embodied as tail ends, outriggers in substantially the extension of the board walls 3 of the loading deck of the vessel 1, which is situated rearwardly of the bridge house.
- additional buoyant bodies 2 in the form of a watertight bridge house fore and, embodied as tail ends, outriggers in substantially the extension of the board walls 3 of the loading deck of the vessel 1, which is situated rearwardly of the bridge house.
- a slide pad 11 consisting of a fluid skate can have a carrying capacity per area dimension of 1 m2 of more than 100 tons.
- a flat jack pad with teflon may carry a still many times higher load.
- the hydraulic jacks 18 as represented in figure 12 may be utilized, which are disposed between the ship structure and the supporting beams 10, and which are also adapted for compensation of the outrigger motion as a result of the water motion such as the swell.
Landscapes
- Engineering & Computer Science (AREA)
- Transportation (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Earth Drilling (AREA)
Abstract
Description
- This invention relates to a method of transporting, installing or removing a marine object by means of a buoyant body, the longitudinal sides of which operate at the sides of the object, and with a transverse structure extending from one transverse side between the longitudinal sides, and the opposed transverse side passing under the object.
- There is such a method known, with at said opposed transverse side a bay being formed in the transverse structure so that the buoyant body has a U-shape, but this transverse structure interrupted by a bay has the drawback that the buoyant body tends to trim aft and must be trimmed level in its starting position already.
- It is intended to obviate this drawback by a novel method wherein the transverse structure is uninterrupted, and buoyancy possessing outriggers as tail ends at the upside substantially in the extension of the longitudinal sides of the buoyant body get into the water under the object. In its starting position the buoyant body lies trimmed level and under the object the outriggers lend thereto an at an increasing rate rearward displacement so that the buoyant body also under the load remains lying trimmed substantially level.
- It concerns here a semi-submersible vessel, characterized by three or more superstructures, particularly fore a buoyancy possessing bridge house and aft the outriggers which under the load carried thereby get into the water. Therewith these superstructures have a sufficiently small waterline area to reduce motions and loads as a result of waves.
- During the transport of the marine object the loading deck of the vessel is sufficiently above water so that the loading deck is free of the wave action.
- At the destined loading or unloading site the vessel is then ballasted and semi-submerged to the extent that the deck under a heavy load would almost entirely disappear underwater. Only the three superstructures still extend above water. The two superstructures comprising the outriggers, embodied as tail ends, which extend over the rear or also the side of the vessel, lend thereto, when submerging, at an in creasing rate carrying capacity rearwardly of the stern.
- In order to compensate the load on the outriggers, the outriggers can be provided with additional buoyant bodies which can be added at the site.
- These buoyant bodies which compensate the load may be open from below so that they are to be trimmed with air pressure.
- The outriggers can be used in two manners for installation purposes:
- A) in combination with one or more gantry cranes,
- B) the direct use of the outriggers to lift objects according to the fork lift principle.
- The combination of outriggers and gantry cranes can in principle be used for the installation at sea of submarine systems and submarine objects, or of objects and systems above water.
- For submarine objects rather low gantry cranes would suffice, for installation of objects above water higher gantry cranes are required.
- The gantry cranes are preferably provided with a hydraulic lifting device which will be described later on.
- The gantry cranes can, however, also be provided with a slide or roll system so that they can place an object from the vessel outboard or reversely inboard.
- The lifting device on the gantry cranes can be a hydraulic device which clamps a plurality of wires. The use of such a system to lift loads offshore is an important aspect of the present invention.
- The hydraulic lifting device is provided with two clamping systems which are attached to a hollow cylinder.
- The movable part (the piston) is provided with a clamping system and the fixed portion is provided with a clamping system. By alternately using the two clamping devices the wires can be hauled through the jack or be payed out.
- Especially the use at sea of this type of wire jack is an important aspect. Therewith, in one embodiment, this jack can also be mounted on a second hydraulic cylinder, whereby the roll and pitch motions of the ship are isolated from the load.
- With the pilot line the compensation motion can be controlled.
- Moreover, the unit can be connected to an air system for compensation of the vertical motions of the installation vessel.
- Loads can offshore also directly be lifted by means of the outriggers.
- As an example the top structure of a drilling platform is here described. Herewith the heavy load to be transported, particularly said top structure of a drilling platfrom, is lifted off the lower structure of the drilling platform according to the fork lift principle and loaded on the outriggers of a vessel, particularly the tail ends which are situated in the extension of the twin boards of a dockship, for the transport, and lifted off the outriggers to be installed on said lower structure, respectively.
- Therewith the problem arises that the load each time should be positioned correctly with respect to the outriggers, and notably the top structure of a drilling platform, to be transported or to be installed, should be very accurately relatively adjusted between the outriggers of the vessel and the lower structure of the drilling platform.
- This problem is solved effectively with the method according to the present invention by accurately positioning the outriggers under the load while utilizing carrier supports, and the preferred embodiment of an arrangement for performing this method is characterized by carrier supports upholding the load on each side, and furthermore by a support beam structure to be arranged on the outriggers under the load, with a position which is adjustable by means of carrier pads, with the carrier pad pressure being fluid-controlled. When the carrier pad pressure is sufficient the load will rest in a somewhat floating manner on the carrier pads so that a relative adjustment with respect to the outriggers which carry the load can be effected and, when the correct adjustment is reached, by reducing the carrier pad pressure a fixation of the adjustment can be obtained.
- When lifting or lowering the top structure of a drilling platform on its lower structure, by slidingly shifting the supporting beams a finer adjustment of the top structure with respect to the lower structure is now obtained.
- Moreover, the cyclic motions as a result of the swell are compensated.
- Therewith is taken care that the relative shifting of the load with respect to the outriggers is steered in the right manner due to the fact that the carrier pads are adjustable in longitudinal alignments on the outriggers, said longitudinal alignments extending onto the gangways of the ship so that the carrier pads with the load carried thereby are displaceable between positions outboard and inboard, and furthermore also by alignments located under the transverse beams of the support beam structure, for self-adjustment of the carrier pads transversely. In this manner a universal adjustability of the load with respect to the outriggers is obtained.
- This shifting of the supporting beams with respect to the outriggers can be effected:
- in that the supporting beams are actively controlled by hydraulic cylinders which control the supporting beams at the rate of the measured motions of the outriggers;
- by cross-wires which are passed from winches aboard the ship to the lower structure of the drilling platform and are secured thereon and/or
- by a homing system between the respective drilling platform legs as will be further described in the following. - Also a combination of the above mentioned systems is possible.
- The choice which system is applicable will depend on the maximum allowable loads on the lower structure and the sea condition to be expected during the installation or removel.
- The invention will be further described in the following in view of illustrative embodiments thereof as represented in the attendant drawings, which should, however, not be interpreted in a restrictive sense as of course other embodiments are feasible within its scope.
- Figures 1, 2 and 3 represent embodiments of a barge with superstructures for installing or dismounting objects at sea under or above water.
- Figure 2 shows possibilities for the connection of the three super structures with working deck and accommodation above water.
- Figure 3 shows an example with continuous dock walls.
- Figure 4 depicts the use of outriggers and gantry cranes in a semi-submersible vessel.
- Figure 5 gives possibilities of adding additional buoyancy to reduce the moments on the outriggers and is a schematice general perspective view of a semi-submersible vessel, such as a dockship, which as illustrated is engaged in loading the top structure of a drilling rig or is lifting off this top structure from its outriggers to install it on the lower structure, the so-called jacket, of the drilling rig.
- Figure 6 gives an example of a low gantry crane for operations under water.
- Figure 7 gives an example of a high gantry crane for the operation above water.
- Figure 8 shows the high gantry cranes which place an object underwater.
- Figure 9 depicts a wire-jack which is to be used on a gantry crane in operations offshore.
- Figure 10 shows the the wire-jack mounted on a hydraulic cylinder for roll, pitch and vertical compensation.
- Figure 11 is a schematic representation of a carrier pad system which is arranged on the outriggers under the load to make its correct positioning possible.
- Figure 12 illustrates the compensation of notably the outrigger motions due to the swell, by means of a hydraulic jack.
- Figure 13A and 13B show in longitudinal view and in rear view resilient cross-wires by which the water motion can be compensated.
- Figure 14 shows the homing of top structure legs on the jacket structure.
- Figure 15A shows supported on the boards of a dockship the top structure of a drilling platform, which is made ready for the transport, in end view as seen from the stern, and figure 15B is a corresponding lateral view of the ship aft.
- The
semi-submersible vessel 1 as represented in the drawings is shown in longitudinal and in plan view in figure 1 and is provided with with additionalbuoyant bodies 2 in the form of a watertight bridge house fore and, embodied as tail ends, outriggers in substantially the extension of theboard walls 3 of the loading deck of thevessel 1, which is situated rearwardly of the bridge house. - As an example it is stated that the
vessel 1 has a length of 180 m, a beam of 40 m and a depth of about 9 m, that the bridge house has a length of 20 m and the outriggers a length of 70 m, and that saidbuoyant bodies 2 extend to a heigth of 20 m above the base line of the vessel. - In figure 2 the transport draft ℓ and the installation draft ℓ′ at sea of the
vessel 1 are indicated. The load 4 depends here, as shown, from a working platform. - In figure 3a semi-submersible vessel or so-called "semi-submersible" 1 is represented, which is provided with fixed
carrier legs 26 in the form of hollow columns, which hollowcolumns 26 extend through thewater surface 29 and are connected at the bottom side, on each side of thevessel 1, by caisson floats 30, and between which the necessary supports in the form of braces and rungs such as 31 are arranged. On saidcarrier legs 26 rests a superstructure of which in figure 3 only the workingdeck 32 is schematically represented. Also thissemi-submersible vessel 1 is provided withoutriggers 2 by which a heavy load which here in this figure is not further represented, is to be controlled. - In figures 4 and 5 a
semi-submersible vessel 1 consisting of a dockship is represented, which hasoutriggers 2 in the form af tail ends projecting in the extension of thetwin boards 3, by which according to the fork lift principle a heavy load 4 which may consist of the top structure of a drilling rig, can be lifted off the jacket, indicated at 5, of the drilling rig, or from which the load 4 can be lifted to be installed on thejacket 5. - It is noted that the
dockship 1 as represented in figures 4 and 5 has a largeunobstructed hold 6 defined between saidtwin boards 3, which is to be closed by means of hatch covers, not represented in these figures, and which, for loading and unloading dry cargo through the hatch opening, is to be served by a gantry crane, generally indicated at 7, which rides on thegangways 8 on thetwin boards 3, whereas in thisship 1 wet cargo may be stowed in thehold 6 through the stern 9 which is to be opened to that effect, and to that end theship 1 will then be semi-submerged. - The heavy load, illustrated in figure 5, which as represented may consist of said top structure 4 of a drilling platform, is stowed on the
outriggers 2 on a support beam structure to be placed under the load 4, comprising a plurality of supportingbeams 10, with the interpositioning offluid pads 11 which are indicated with dotted lines in figure 5 and are shown in more detail in figure 11. With a sufficient fluid pressure in thecarrier pads 11 the load 4 will then arrive at a supporting condition which may be regarded as somewhat "floating" in order to, by slidingly shifting on thecarrier pads 2 on theoutriggers 2, thus be accurately located in a desired position, and upon locating it in the desired position, the fluid pressure may then be lowered and a fixed position be obtained. - This concerns lifting and removing the load 4 for its transport. When installing the topside 4 the operation is reversed, with some further provisions being made to position it on the
jacket 5 as will be further described here in the following. - Positioning the
vessel 1 with respect to the load 4 is in all cases in first instance being effected by trimming thevessel 1 with ballast. - For a universal displaceability of the load 4 with respect to the
vessel 1 saidcarrier pads 11 are adapted to be slidingly shifted inlongitudinal alignments 12 on theoutriggers 2, which extend onto thegangways 8 so that thecarrier pads 11 with the load 4 resting thereon can be slidingly displaced in longitudinal directions between positions outboard and inboard, and thecarrier pads 11 can also be shiftable in a gliding or as said somewhat "floating" manner intransverse alignments 13 which are arranged under the support beams 10. - A carrier pad in the form of a flat jack pad, provided with a top layer of low friction, can also be constructed so large that a slide beam can freely move along it in longitudinal and transverse directions.
- As carrier supports also so-called air or water skates can be used, which are not further represented.
- The
carrier pads 11 as illustrated in figure 11 are adapted to be fluid-pressurized by way of the hydraulic supply line indicated at 14, and are covered by asteel sheet 15, or a composite sandwich of steel and rubber, with thereon a glide lining ofteflon 16 on which the support beams 10 will rest. Accordingly, thecarrier pads 11 as represented in figure 11 are themselves not displaceable as in the here earlier described embodiment but occupy a fixed place while the load 4 may slide thereon for adjustment on theoutriggers 2. To that end aslide shoe 17 of stainless steel can be placed under the load 4. - As a typical example, a
slide pad 11 consisting of a fluid skate can have a carrying capacity per area dimension of 1 m² of more than 100 tons. A flat jack pad with teflon may carry a still many times higher load. - For shifting on or along the carrier or
slide pads 11 thehydraulic jacks 18 as represented in figure 12 may be utilized, which are disposed between the ship structure and the supportingbeams 10, and which are also adapted for compensation of the outrigger motion as a result of the water motion such as the swell. - Figures 13A and 13B depict in longitudinal view and in rear view the transfer of a heavy load 4 in the form of the illustrated topside of a drilling rig between the
outriggers 2 and thejacket 5 of the drilling rig. - As shown, to that end cross-wires are passed from drums of
winches 20 which are arranged aboard theship 1, to their attachments on thelegs 21 of thejack 5, said cross-wires 19 running onguide rollers 22 and comprising resilient means 23 for compensation of the water motion which is discernable aboard theship 1. - When the correct adjustment is obtained, the
legs 24 of the topside 4 of the drilling rig can be accurately threaded in thelegs 24 of thejack 5 by means of a homing trunnion, and herewith the installation of the topside 4 of the drilling rig, which is transported by theship 1, is then completed. - In figure 5 are furthermore shown carrier supports in the form of
support legs 26 which are to be girded-on at the location of theoutriggers 2 on each side of theship 1, and are in the form of hollow columns which are to be trimmed by air pressure. The adjustment of theoutriggers 2 under the load 4 can then be assisted by the regulation of valves, not shown, which are disposed in acontrol box 27, and regulate the air supply and discharge. To facilitate a proper girding-on of thesupport legs 26 onto the ship 1 atransverse beam connection 28 is provided therebetween at the location of the stern of theship 1. Also at the location of the extended rear end of theoutrigger tails 2 such a support ortrim leg 26 can be provided, which is, however, not shown in figure 5 but which is to be connected with the two illustratedsupport legs 26 by a cross-structure of rungs. - Such carrier supports can also be provided for handling the
jacket 5 of a drilling rig. - Figure 6 depicts a
low gantry crane 7 by which submerged objects can be handled. - In view of figures 7-10 the lowering of a submerged system by means of a
novel gripper system 33 will be described in the following: - An especially developed
gripper system 33 will be applied for lowering below the sea level. - This
gripper system 33 comprises a movableupper gripper 34 under themain hooks 35 of theship 1 and a fixedlower gripper 36 which is arranged on anupper landing platform 37 and depends under thetrolleys 38 of the ship'crane 7. - On the
tackles 39 depends alower landing platfrom 40 from which as shown thejacket 5 of a drilling rig is depending. - The
gripper system 33 is designed on a safety factor of the work load of 2.5. - No substantial twisting of the
manifold 2 is possible when using this system ( vide figure 7). Moreover, thehanger wires 39, as shown in figure 8, may be tensioned by transverse or cross-wiseextended coupling wires 41 to obviate any substantial torsion risk. - Figures 9 and 10 show the principle of the roll and pitch compensation. At 42 the swell compensation cylinder and at 43 the lifting cylinder is indicated and at 44 the pilot line. The clamps for alternately clamping and releasing the
tackle wires 39 are indicated at 45. - A more detailed description of the lifting method follows herebelow in view of figures 14 and 15.
- 1.
Brackets 46 are welded or clamped to thelegs 47 of thejacket 5 at a suitable level (vide figure 14).
- The load is introduced via the
diaphragm plates 48 and thus thebrackets 46 are only subjected at a very low rate to bending and mainly shear. - 2.
Supports 49 are welded over the cuttingsplice 50.
- The
legs 47 are cut at thecutting level 50 before the actual lifting (vide figure 15A). - 3. Support beams 51 are brought into position by means of the
outriggers 2 of theship 1 and connected to the drilling platform by rack clamps or slings 52 (vide figure 15B). - 4. The
ship 1 is finally positioned by means of dynamic positioning and/or cross mooring wires to thejacket 5. - 5. When it is in position, the
ship 1 is ballasted and 80% of the weigth of the topsides 4 is taken by ballasting. - 6. Tracks with teflon are provided to compensate the horizontal motions of the
ship 1. - 7. Then the
ship cranes 7 are moved forward on their wheels and the topsides 4 are lifted free from thejacket 5 in approximate half a minute in order to prevent hammering between thejacket 5 and the topsides 4. - 8. The support beams are shimmed on the tracks so that further movement is no longer possible.
- 9. The
ship 1 sails with the topsides 4 to a sheltered area where the topsides 4 are transferred to a barge or a quay.
Claims (12)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NL8801920 | 1988-08-02 | ||
NL8801920A NL8801920A (en) | 1988-08-02 | 1988-08-02 | METHOD FOR TRANSPORTING A HEAVY SEMI-SINKABLE VESSEL LIKE A DECKING SHIP FROM A HEAVY LOAD, AND AN APPARATUS FOR CARRYING OUT THE METHOD |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0353829A1 true EP0353829A1 (en) | 1990-02-07 |
EP0353829B1 EP0353829B1 (en) | 1994-01-12 |
Family
ID=19852699
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP89202012A Expired - Lifetime EP0353829B1 (en) | 1988-08-02 | 1989-08-02 | A method of transporting, installing or removing a marine object, and a semi-submersible vessel for implementation of the method |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP0353829B1 (en) |
DE (1) | DE68912230D1 (en) |
NL (1) | NL8801920A (en) |
NO (1) | NO893114L (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2269138A (en) * | 1992-07-27 | 1994-02-02 | Ralph Downham | Stabilising submersible barges. |
US5807029A (en) * | 1994-06-08 | 1998-09-15 | Cherwora Pty. Ltd. | Offshore construction and vessel |
WO2004087494A3 (en) * | 2003-04-04 | 2004-12-16 | Logima V Svend Erik Hansen | A vessel for transporting wind turbines, methods of moving a wind turbine, and a wind turbine for an off-shore wind farm |
US7234409B2 (en) | 2003-04-04 | 2007-06-26 | Logima V/Svend Erik Hansen | Vessel for transporting wind turbines, methods of moving a wind turbine, and a wind turbine for an off-shore wind farm |
WO2011139732A2 (en) * | 2010-05-02 | 2011-11-10 | Delphi Acquisition Holding I B.V. | System and method for thruster protection during transport |
NL2007282C2 (en) * | 2011-08-19 | 2013-02-21 | Heerema Marine Contractors Nl | Vessel and method for removal and/or installation of at least a part of a sea platform. |
WO2012039619A3 (en) * | 2010-09-24 | 2013-04-25 | Gustomsc Resources B.V. | Vessel comprising a hull with a deck and a cargo area extending in a length direction of the deck, and a gantry type crane with legs moveable on the sides of the cargo area |
CN112027027A (en) * | 2020-08-31 | 2020-12-04 | 华电重工股份有限公司 | Marine engineering module installation device and marine engineering module installation system |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6912965B2 (en) | 2003-03-12 | 2005-07-05 | Kellogg Brown & Root, Inc. | Semisubmersible trimaran |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2812568A1 (en) * | 1977-03-25 | 1978-09-28 | Heusden Verolme Scheeps | DOCK SHIP |
FR2405182A1 (en) * | 1977-10-04 | 1979-05-04 | Metalliques Entrepr Cie Fse | PROCESS AND EQUIPMENT FOR PLACING ON COLUMNS ANCHORED TO THE BOTTOM, FROM A TRANSPORTER VESSEL, LOADS, PLATFORMS OR SIMILAR, FOR INSTALLATIONS OFF THE COAST |
GB2165188A (en) * | 1985-06-05 | 1986-04-09 | Heerema Engineering | Installation and removal vessel |
GB2186527A (en) * | 1986-01-08 | 1987-08-19 | Timothy Arthur Broad | Platform topsides removal vessel |
-
1988
- 1988-08-02 NL NL8801920A patent/NL8801920A/en not_active Application Discontinuation
-
1989
- 1989-08-02 NO NO89893114A patent/NO893114L/en unknown
- 1989-08-02 EP EP89202012A patent/EP0353829B1/en not_active Expired - Lifetime
- 1989-08-02 DE DE89202012T patent/DE68912230D1/en not_active Expired - Lifetime
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2812568A1 (en) * | 1977-03-25 | 1978-09-28 | Heusden Verolme Scheeps | DOCK SHIP |
FR2405182A1 (en) * | 1977-10-04 | 1979-05-04 | Metalliques Entrepr Cie Fse | PROCESS AND EQUIPMENT FOR PLACING ON COLUMNS ANCHORED TO THE BOTTOM, FROM A TRANSPORTER VESSEL, LOADS, PLATFORMS OR SIMILAR, FOR INSTALLATIONS OFF THE COAST |
GB2165188A (en) * | 1985-06-05 | 1986-04-09 | Heerema Engineering | Installation and removal vessel |
GB2186527A (en) * | 1986-01-08 | 1987-08-19 | Timothy Arthur Broad | Platform topsides removal vessel |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2269138A (en) * | 1992-07-27 | 1994-02-02 | Ralph Downham | Stabilising submersible barges. |
GB2269138B (en) * | 1992-07-27 | 1995-10-25 | Ralph Downham | Transfer method and barge for use in the method |
AU666742B2 (en) * | 1992-07-27 | 1996-02-22 | Ralph Downham | Transfer method and barge for use in the method |
US5807029A (en) * | 1994-06-08 | 1998-09-15 | Cherwora Pty. Ltd. | Offshore construction and vessel |
CN100579860C (en) * | 2003-04-04 | 2010-01-13 | 斯文·E·汉森洛吉玛公司 | Vessel for transporting wind turbines, methods of moving wind turbine, and wind turbine for off-shore wind farm |
US7234409B2 (en) | 2003-04-04 | 2007-06-26 | Logima V/Svend Erik Hansen | Vessel for transporting wind turbines, methods of moving a wind turbine, and a wind turbine for an off-shore wind farm |
WO2004087494A3 (en) * | 2003-04-04 | 2004-12-16 | Logima V Svend Erik Hansen | A vessel for transporting wind turbines, methods of moving a wind turbine, and a wind turbine for an off-shore wind farm |
EP2266871A1 (en) * | 2003-04-04 | 2010-12-29 | Logima V/Svend Erik Hansen | A wind turbine with a wind turbine base, and methods of transferring or moving a wind turbine |
WO2011139732A2 (en) * | 2010-05-02 | 2011-11-10 | Delphi Acquisition Holding I B.V. | System and method for thruster protection during transport |
WO2011139732A3 (en) * | 2010-05-02 | 2012-02-09 | Delphi Acquisition Holding I B.V. | System and method for thruster protection during transport |
US8701581B2 (en) | 2010-05-02 | 2014-04-22 | Delphi Acquisition Holding I B.V. | System and method for thruster protection during transport |
WO2012039619A3 (en) * | 2010-09-24 | 2013-04-25 | Gustomsc Resources B.V. | Vessel comprising a hull with a deck and a cargo area extending in a length direction of the deck, and a gantry type crane with legs moveable on the sides of the cargo area |
NL2007282C2 (en) * | 2011-08-19 | 2013-02-21 | Heerema Marine Contractors Nl | Vessel and method for removal and/or installation of at least a part of a sea platform. |
EP2559614A3 (en) * | 2011-08-19 | 2013-09-04 | Heerema Marine Contractors Nederland SE | Vessel and method for removal and/or installation of at least a part of a sea platform |
CN112027027A (en) * | 2020-08-31 | 2020-12-04 | 华电重工股份有限公司 | Marine engineering module installation device and marine engineering module installation system |
Also Published As
Publication number | Publication date |
---|---|
NL8801920A (en) | 1990-03-01 |
NO893114D0 (en) | 1989-08-02 |
EP0353829B1 (en) | 1994-01-12 |
DE68912230D1 (en) | 1994-02-24 |
NO893114L (en) | 1990-02-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10800498B2 (en) | Method and apparatus for supporting a personnel housing in a marine environment | |
AU2009310624B2 (en) | Ocean going transport vessel with docking arrangements | |
EP2089268B1 (en) | Marine lifting apparatus | |
US8240264B2 (en) | Marine lifting apparatus | |
US7131388B2 (en) | Lift boat | |
WO2012075162A2 (en) | Marine lifting apparatus | |
EP1259420A1 (en) | Submersible heavy lift catamaran | |
EP0353829B1 (en) | A method of transporting, installing or removing a marine object, and a semi-submersible vessel for implementation of the method | |
WO2013006041A1 (en) | Shear leg crane and transportation vessel | |
US4864957A (en) | Apparatus and method for launch and recovery of watercraft onto and from the deck of a host vessel | |
US20100263581A1 (en) | Marine Lifting Apparatus | |
GB2168293A (en) | Vessel for the installation of production platforms on fixed jackets | |
EP1492699B1 (en) | Submersible watercraft | |
US20230111176A1 (en) | Marine lifting apparatus | |
GB2163393A (en) | A semi-submersible vessel | |
GB2169859A (en) | Semi-submersible lifting vessels |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): BE DE ES FR GB GR IT NL SE |
|
17P | Request for examination filed |
Effective date: 19900705 |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: DOCK-EXPRESS SHIPPING B.V. |
|
17Q | First examination report despatched |
Effective date: 19911122 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): BE DE ES FR GB GR IT NL SE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRE;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.SCRIBED TIME-LIMIT Effective date: 19940112 Ref country code: SE Effective date: 19940112 Ref country code: FR Effective date: 19940112 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 19940112 Ref country code: DE Effective date: 19940112 Ref country code: ES Free format text: THE PATENT HAS BEEN ANNULLED BY A DECISION OF A NATIONAL AUTHORITY Effective date: 19940112 |
|
REF | Corresponds to: |
Ref document number: 68912230 Country of ref document: DE Date of ref document: 19940224 |
|
RAP2 | Party data changed (patent owner data changed or rights of a patent transferred) |
Owner name: DOCKWISE N.V. |
|
EN | Fr: translation not filed | ||
NLT2 | Nl: modifications (of names), taken from the european patent patent bulletin |
Owner name: DOCKWISE N.V. TE MEER, BELGIE. |
|
NLXE | Nl: other communications concerning ep-patents (part 3 heading xe) |
Free format text: PAT.BUL.12/94 CORR.:DOCKWISE N.V. PAT.BUL.14/94 SHOULD BE DELETED |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
REG | Reference to a national code |
Ref country code: GB Ref legal event code: IF02 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20060802 Year of fee payment: 18 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 20060816 Year of fee payment: 18 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20060831 Year of fee payment: 18 |
|
BERE | Be: lapsed |
Owner name: *DOCKWISE N.V. Effective date: 20070831 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20070802 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20080301 |
|
NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee |
Effective date: 20080301 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070831 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070802 |