EA201100677A1 - Способ и установка для подводных работ - Google Patents
Способ и установка для подводных работInfo
- Publication number
- EA201100677A1 EA201100677A1 EA201100677A EA201100677A EA201100677A1 EA 201100677 A1 EA201100677 A1 EA 201100677A1 EA 201100677 A EA201100677 A EA 201100677A EA 201100677 A EA201100677 A EA 201100677A EA 201100677 A1 EA201100677 A1 EA 201100677A1
- Authority
- EA
- Eurasian Patent Office
- Prior art keywords
- bundle
- load
- installation
- lifting
- lowering
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63C—LAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
- B63C11/00—Equipment for dwelling or working underwater; Means for searching for underwater objects
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B27/00—Arrangement of ship-based loading or unloading equipment for cargo or passengers
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/40—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting marine vessels
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B19/00—Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
- E21B19/002—Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables specially adapted for underwater drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B41/00—Equipment or details not covered by groups E21B15/00 - E21B40/00
- E21B41/0007—Equipment or details not covered by groups E21B15/00 - E21B40/00 for underwater installations
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B41/00—Equipment or details not covered by groups E21B15/00 - E21B40/00
- E21B41/04—Manipulators for underwater operations, e.g. temporarily connected to well heads
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/01—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
- B63B35/44—Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
- B63B2035/448—Floating hydrocarbon production vessels, e.g. Floating Production Storage and Offloading vessels [FPSO]
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0039—Methods for placing the offshore structure
Abstract
Заявлены способ и установка для опускания груза на дно водоема и/или подъема со дна. Установка включает в себя устройство плавучести, скомпонованное таким образом, чтобы обеспечить его присоединение к грузу, и имеющее положительную плавучесть, достаточную для подъема груза. На установке для приема управляющего груза, стравливаемого с судна для заглубления или подъема связки предусмотрено по меньшей мере одно грузоприемное устройство. Способ опускания включает в себя формирование связки из устройства плавучести и груза и погружение связки в точку на первой высоте над морским дном. В предпочтительном варианте осуществления изобретения связка погружается при помощи системы буксировки стабилизирующего груза. Управляющий груз стравливается с судна на связку для преодоления положительной плавучести связки и опускает, таким образом, груз с первой высоты на дно. Способ подъема аналогичен способу опускания, только действия выполняются в обратном порядке.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB0819489A GB2464714B (en) | 2008-10-24 | 2008-10-24 | Method and apparatus for subsea installations |
PCT/GB2009/051383 WO2010046686A2 (en) | 2008-10-24 | 2009-10-15 | Method and apparatus for subsea installations |
Publications (2)
Publication Number | Publication Date |
---|---|
EA201100677A1 true EA201100677A1 (ru) | 2012-02-28 |
EA020375B1 EA020375B1 (ru) | 2014-10-30 |
Family
ID=40133735
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EA201100677A EA020375B1 (ru) | 2008-10-24 | 2009-10-15 | Способ опускания груза на дно водоема и установка для его осуществления |
Country Status (10)
Country | Link |
---|---|
US (2) | US8992127B2 (ru) |
EP (1) | EP2350424B1 (ru) |
AU (1) | AU2009306155B2 (ru) |
BR (1) | BRPI0919568A2 (ru) |
CA (1) | CA2770346C (ru) |
DK (1) | DK201100237A (ru) |
EA (1) | EA020375B1 (ru) |
GB (1) | GB2464714B (ru) |
MX (1) | MX2011002875A (ru) |
WO (1) | WO2010046686A2 (ru) |
Families Citing this family (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120315096A1 (en) * | 2010-02-12 | 2012-12-13 | Robert Love Byers | Rigless intervention |
GB201015218D0 (en) * | 2010-09-13 | 2010-10-27 | Aubin Ltd | Method |
NL2007756C2 (en) * | 2011-11-09 | 2013-05-14 | Ihc Holland Ie Bv | Workstation for transporting equipment to an underwater position. |
FR2989106B1 (fr) | 2012-04-04 | 2015-04-10 | Technip France | Procede de positionnement d'un ensemble de fond au fond d'une etendue d'eau, et dispositif associe |
CN105051570B (zh) * | 2012-12-13 | 2018-01-19 | 费尔菲尔德工业股份有限公司 | 运送和回收设备、方法以及应用 |
FR3000720B1 (fr) | 2013-01-08 | 2015-01-16 | Technip France | Barge flottante submersible |
US9254894B2 (en) | 2013-02-19 | 2016-02-09 | Conocophillips Company | Flotable subsea platform (FSP) |
EP3052751B1 (en) * | 2013-09-30 | 2019-11-13 | Saudi Arabian Oil Company | Apparatus and method for producing oil and gas using buoyancy effect |
GB201322860D0 (en) * | 2013-12-23 | 2014-02-12 | Deep Blue Engineering Uk Ltd | Deployment device |
ES2555500B1 (es) | 2014-05-27 | 2016-12-13 | Sea Wind Towers Sl | Obra flotante y procedimiento de instalación de la misma |
ES2804103T3 (es) * | 2014-08-27 | 2021-02-03 | Safe Marine Transfer Llc | Un proceso de múltiples embarcaciones para instalar y recuperar paquetes de equipos submarinos |
GB2532028B (en) * | 2014-11-05 | 2017-07-26 | Subsea 7 Norway As | Transportation and installation of heavy subsea structures |
GB2532753B (en) * | 2014-11-26 | 2021-03-31 | Equinor Energy As | Method of lowering an apparatus |
US9404347B1 (en) * | 2015-05-15 | 2016-08-02 | Baker Hughes Incorporated | Apparatus and method for connecting a riser from an offshore rig to a subsea structure |
CN105298442B (zh) * | 2015-11-02 | 2017-10-03 | 江苏科技大学 | 一种移动旋转式线性覆盖工具 |
US9919771B2 (en) * | 2015-11-18 | 2018-03-20 | Cameron International Corporation | Safety system and method for guiding a dropped suspended load away from equipment and to a safe landing area |
GB2551949A (en) * | 2016-03-29 | 2018-01-10 | Sllp 134 Ltd | Method and apparatus for installation of a subsea tank |
WO2018152106A1 (en) | 2017-02-16 | 2018-08-23 | Shell Oil Company | Submersible autonomous barge |
MX2019012199A (es) * | 2017-04-14 | 2020-01-21 | Safe Marine Transfer Llc | Metodo y aparato para instalar, ajustar y recuperar elementos de flotabilidad de instalaciones submarinas. |
ES2695308B2 (es) * | 2017-06-27 | 2019-07-11 | Univ Madrid Politecnica | Sistema de fondeo y método de instalación de sistema de fondeo en fondo marino |
US10781670B1 (en) * | 2019-10-10 | 2020-09-22 | Trendsetter Engineering, Inc. | Process for non-vertical installation and removal of a subsea structure |
GB2623586A (en) * | 2022-10-21 | 2024-04-24 | Subsea 7 Norway As | Connections to subsea electrical equipment |
Family Cites Families (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3656310A (en) * | 1968-11-14 | 1972-04-18 | Petroles Cie Francaise | Method for laying submarine pipelines |
FR2098691A5 (ru) * | 1970-07-24 | 1972-03-10 | Elf | |
GR59794B (en) * | 1975-03-27 | 1978-02-28 | Doris Dev Richesse Sous Marine | Laying pipes under-water |
NL7511638A (nl) * | 1975-10-03 | 1977-04-05 | Johannes Franciscus Oosterkamp | Werkwijze voor het installeren van pijpleidingen op zeer grote waterdiepte, en inrichting voor het uitvoeren van deze werkwijze. |
NL162609C (nl) * | 1976-05-05 | 1980-06-16 | Ihc Holland Nv | Deinings-compensatie-inrichting voor een hijskraan. |
US4048945A (en) * | 1976-05-07 | 1977-09-20 | Chevron Research Company | Removable anchor having retrievable ballast |
FR2370131A1 (fr) | 1976-11-05 | 1978-06-02 | Expertises Sa Cie Maritime | Procede d'immersion d'un colis flottant et dispositifs pour la mise en oeuvre dudit procede |
GB2200938B (en) * | 1987-02-12 | 1992-01-22 | Heerema Engineering | Control system |
NO172483C (no) * | 1990-08-14 | 1993-07-28 | Norwegian Contractors | Fremgangsmaate og anordning for styrt nedsenkning og plassering av et stort, tungt senkeelement ned paa havbunnen |
US5069580A (en) * | 1990-09-25 | 1991-12-03 | Fssl, Inc. | Subsea payload installation system |
FR2671046B1 (fr) * | 1990-12-28 | 1995-08-11 | Inst Francais Du Petrole | Systeme de chargement pour milieux aquatiques. |
US5190107A (en) * | 1991-04-23 | 1993-03-02 | Shell Oil Company | Heave compensated support system for positioning subsea work packages |
US5316509A (en) * | 1991-09-27 | 1994-05-31 | Sofec, Inc. | Disconnectable mooring system |
NO305608B1 (no) | 1994-07-13 | 1999-06-28 | Kv Rner Concrete Construction | FremgangsmÕte til installasjon av en undersj°isk konstruksjon |
GB2324779A (en) * | 1996-02-16 | 1998-11-04 | Petroleum Geo Services As | Tension-leg platform with flexible tendons and process for installatio |
NO994094D0 (no) * | 1999-08-24 | 1999-08-24 | Aker Riser Systems As | Stigerörsanordning |
US6817809B2 (en) * | 2001-03-27 | 2004-11-16 | Conocophillips Company | Seabed oil storage and tanker offtake system |
NO316168B1 (no) * | 2002-03-06 | 2003-12-22 | Aker Marine Contractors As | Fremgangsmåte for transport og installasjon av objekter til havs |
US6752100B2 (en) * | 2002-05-28 | 2004-06-22 | Shell Oil Company | Apparatuses and methods of deploying and installing subsea equipment |
WO2004012990A1 (en) * | 2002-07-30 | 2004-02-12 | Single Buoy Moorings Inc | Floating lowering and lifting device |
SG134996A1 (en) * | 2003-10-08 | 2007-09-28 | Deepwater Technology Group Pte | Extended semi-submersible vessel |
WO2006000919A1 (en) * | 2004-06-23 | 2006-01-05 | Sbm-Imodco, Inc. | Floating lowering and lifting device |
GB2439902B (en) | 2005-05-27 | 2008-12-31 | Shell Int Research | Method for installing oilfield equipment at the water bottom |
BRPI0502113B1 (pt) | 2005-06-01 | 2015-08-25 | Petroleo Brasileiro Sa | Estrutura auxiliar de içamento e transporte e método pendular de instalação de equipamentos submarinos utilizando dita estrutura |
US7416025B2 (en) * | 2005-08-30 | 2008-08-26 | Kellogg Brown & Root Llc | Subsea well communications apparatus and method using variable tension large offset risers |
GB2454660A (en) | 2007-11-13 | 2009-05-20 | Technip France | Method and apparatus for lowering a subsea structure between the surface and the seabed |
WO2009070034A2 (en) | 2007-11-26 | 2009-06-04 | Subsea 7 Norway Nuf | Method for picking up and towing a structure under water |
GB2463697B (en) | 2008-09-22 | 2012-06-27 | Technip France | Method of locating a subsea structure for deployment |
-
2008
- 2008-10-24 GB GB0819489A patent/GB2464714B/en not_active Expired - Fee Related
-
2009
- 2009-10-15 BR BRPI0919568-8A patent/BRPI0919568A2/pt active Search and Examination
- 2009-10-15 EA EA201100677A patent/EA020375B1/ru not_active IP Right Cessation
- 2009-10-15 US US13/061,691 patent/US8992127B2/en not_active Expired - Fee Related
- 2009-10-15 MX MX2011002875A patent/MX2011002875A/es active IP Right Grant
- 2009-10-15 AU AU2009306155A patent/AU2009306155B2/en not_active Ceased
- 2009-10-15 EP EP09748456.2A patent/EP2350424B1/en not_active Not-in-force
- 2009-10-15 CA CA2770346A patent/CA2770346C/en not_active Expired - Fee Related
- 2009-10-15 WO PCT/GB2009/051383 patent/WO2010046686A2/en active Application Filing
-
2011
- 2011-03-31 DK DKPA201100237A patent/DK201100237A/en not_active Application Discontinuation
-
2015
- 2015-02-23 US US14/629,137 patent/US20150167268A1/en not_active Abandoned
Also Published As
Publication number | Publication date |
---|---|
AU2009306155A1 (en) | 2010-04-29 |
CA2770346A1 (en) | 2010-04-29 |
WO2010046686A3 (en) | 2010-06-24 |
BRPI0919568A2 (pt) | 2020-10-27 |
EA020375B1 (ru) | 2014-10-30 |
AU2009306155B2 (en) | 2015-06-11 |
EP2350424A2 (en) | 2011-08-03 |
CA2770346C (en) | 2017-01-31 |
US20110164926A1 (en) | 2011-07-07 |
GB0819489D0 (en) | 2008-12-03 |
GB2464714B (en) | 2010-09-08 |
WO2010046686A2 (en) | 2010-04-29 |
US20150167268A1 (en) | 2015-06-18 |
MX2011002875A (es) | 2011-05-25 |
GB2464714A (en) | 2010-04-28 |
EP2350424B1 (en) | 2014-04-16 |
DK201100237A (en) | 2011-03-31 |
US8992127B2 (en) | 2015-03-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EA201100677A1 (ru) | Способ и установка для подводных работ | |
DK2436593T3 (en) | Ship and method of transport and installation of offshore structures | |
EP2251254A1 (en) | Installation vessel for offshore wind turbines | |
RU2010130496A (ru) | Нефтехранилище с беспричальным наливом с отсоединяемой конструкцией корпуса | |
US20050152748A1 (en) | Method for underwater transportation and installation or removal of objects at sea | |
US20150217838A1 (en) | Method for lowering and hoisting of a load to or from an ocean floor | |
CN104032718B (zh) | 一种轻型、具有自浮功能、并可人力架设的高架结构 | |
WO2009070034A3 (en) | Method for picking up and towing a structure under water | |
GB2582718A (en) | Fish farm | |
EP2465764A3 (en) | Spar hull load out method | |
WO2011139650A3 (en) | Boom mooring system | |
NO177723B (no) | Fremgangsmåte ved styring av den vertikale posisjon til et legeme med positiv oppdrift i vann | |
CN209567062U (zh) | 自由站立式水下基站支持系统 | |
RU2309221C2 (ru) | Комплекс для монтажа морской ледостойкой переставной платформы и способ ее транспортировки и монтажа посредством комплекса для монтажа | |
CN103963931A (zh) | 大型构件半潜式水上出运安装系统及施工方法 | |
MY143906A (en) | Slipway lift system | |
CN113415398B (zh) | 易于布放回收的模块化防淤积海床基系统及其应用方法 | |
AU2010250147B2 (en) | Method for installing a topside module on an offshore support structure | |
CN113772016A (zh) | 一种大吨位重力式锚固基础的安装辅助系统及方法 | |
CN202609028U (zh) | 一种用于海洋工程的双体船 | |
NL2004402C2 (en) | Semisubmersible and method of its operation. | |
KR101183740B1 (ko) | 영구자석을 통해 반목의 중량을 부가하여 침수되도록 하는 탠덤 건조공법 | |
FI128358B (en) | Arrangement and method for installing weights in underwater pipes | |
KR20160007026A (ko) | 해상 크레인 및 이를 계류하는 방법 | |
KR20100057399A (ko) | 해양구조물의 상부블록 운동저감장치 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
MM4A | Lapse of a eurasian patent due to non-payment of renewal fees within the time limit in the following designated state(s) |