DE908383C DESCH6915A DESC006915A DE908383C DE 908383 C DE908383 C DE 908383C DE SCH6915 A DESCH6915 A DE SCH6915A DE SC006915 A DESC006915 A DE SC006915A DE 908383 C DE908383 C DE 908383C
Authority
DE
Germany
Prior art keywords
stones
wall
ring
machine
stone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DESCH6915A
Other languages
German (de)
Inventor
Willy Schulz
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DESCH6915A priority Critical patent/DE908383C/en
Application granted granted Critical
Publication of DE908383C publication Critical patent/DE908383C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • E21D9/11Making by using boring or cutting machines with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines
    • E21D9/112Making by using boring or cutting machines with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines by means of one single rotary head or of concentric rotary heads

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

Einrichtung zur Herstellung von Stollen und Tunnels, insbesondere von U-Bahn-Tunnels und Luftschutzräumen, in Schürfboden Die Erfindung betrifft eine Einrichtung zum möglichst schnellen und billigen Herstellen von Stollen u. dgl. Für U-Bahn-Tunnels, zwischen den Bahnhöfen z. B., würden durch die Anwendung der Einrichtung nach der Erfindung, durch den Bau kleinerer Tunnels nebeneinander, nicht nur die Erd-und Betonarbeiten erheblich verringert, es würden vor allem beim Bau unter Straßen der Aufbruch und die Wiederherstellung derselben mit allen Nebenarbeiten vermieden und der oberirdische Verkehr nicht gestört.Equipment for the production of galleries and tunnels, in particular of underground tunnels and air raid shelters, in scrape floor The invention relates to a Device for the fastest and cheapest possible manufacture of studs and the like. For subway tunnels, between stations e.g. B., would by applying the Device according to the invention, by building smaller tunnels next to each other, not only the earth and concrete work is reduced considerably, it would especially during construction under streets the departure and the restoration of the same with all ancillary work avoided and the traffic above ground is not disturbed.

Für Luftschutzzwecke kann in sicherer Tiefe auch unter Gebäuden gebaut werden. Eingänge könnten nach der gleichen Bauweise schräg dort angelegt werden, wo dieselben erforderlich und möglich sind. Wegen der Billigkeit der Bauweise könnten viele Ausfahrten nach verschiedenen Richtungen bis weit außerhalb der Gefahrenzone geführt werden.For air defense purposes it is also possible to build under buildings at a safe depth will. Entrances could be placed there diagonally according to the same construction method, where they are necessary and possible. Because of the cheapness of the construction many exits in different directions far beyond the danger zone be guided.

Die besondere Form des Gewölbesteines in Verbindung mit der neuen Fugendichtung bewirkt, daß das Gewölbe sich bei der Herstellung unter Pressendruck ausdehnen möchte, so daß es sich infolgedessen fest an die Bodenwandung anpreßt. Hierdurch wird das Setzen des Gewölbes vermieden, der Boden bleibt in seinem gewachsenen Urzustand und belastet das Gewölbe wenig oder gar nicht; die Auskleidung darf dünner sein (erhebliche Betonersparnis, Eisen gar .nicht erforderlich 1). The special shape of the vault stone in connection with the new joint seal causes the vault to expand under pressure during manufacture, so that it is consequently pressed firmly against the bottom wall. This avoids the setting of the vault, the floor remains in its original state and places little or no load on the vault; the lining may be thinner (considerable savings in concrete, iron at all. not necessary 1).

Eine weitere sehr wesentliche Ersparnis liegt in der fast rein maschinellen Arbeitsweise aller Vorrichtungen hierzu, durch deren Anwendung, bei einem Stollendurchmesser von 5 m z. B., ein Vortrieb von mehr als 2 m in der Stunde ausgemauert erzielt werden soll.Another very substantial saving lies in the almost purely machine-based savings Operation of all devices for this, through their application, with a tunnel diameter of 5 m z. B., an advance of more than 2 m in the Hour bricked should be achieved.

Vorkommende Hindernisse lassen sich durch die Ausschnitte der Brustschildfräse oder durch Abmontieren des jeweiligen Kreisausschnittes leichter beseitigen.Occurring obstacles can be removed through the cutouts of the breastplate milling machine or easier to remove by removing the respective segment of the circle.

Bei Wasser ist der Einbau von Druckkammern durch den runden Querschnitt erleichtert.In the case of water, the installation of pressure chambers is due to the round cross-section relieved.

Die Einrichtung zur Herstellung von Stollen nach der Erfindung besteht aus folgenden Vorrichtungen: der Vortriebmaschine, der Beladevorrichtung, .der Mauermaschine, der Entladevorrichtung, der Krananlage, dem Gewölbestein, der Fugendichtung und der Rohrbuchse.The device for making studs according to the invention consists from the following devices: the jacking machine, the loading device, the masonry machine, the unloading device, the crane system, the arch stone, the joint seal and the pipe socket.

Die volle Wirtschaftlichkeit der Einrichtung wird nur im Zusammenwirken dieser hierfür entwickelten Vorrichtungen erzielt; deshalb müssen auch alle Teile derselben, auch solche, die als bekannt gelten, in diese einbezogen werden.The full cost-effectiveness of the facility is only achieved in cooperation these devices developed for this purpose achieved; therefore all parts must the same, including those that are considered to be known, are included in this.

Die Vortriebmaschine besteht aus einer Brustschildfräse und an sich bekannten Wandringen. Die Brustschildfräse sichert den Boden vor Ort gegen Abrutschen, fräst denselben beim Rotieren ab und leitet den gelösten Boden über das Zentrum gesammelt für die Verladung hinaus. Die Wandringe sichern den Boden bis zur Ausmauerung und tragen die Antriebsmotoren. Die hydraulischen Pressen im letzten Wandring schieben die Maschine vor.The tunneling machine consists of a breastplate cutter and in itself known wall rings. The breastplate cutter secures the ground on site against slipping, mills it off while rotating and guides the loosened soil over the center collected for loading out. The wall rings secure the floor up to the brickwork and carry the drive motors. Push the hydraulic presses into the last wall ring the machine in front.

Die Verladeeinrichtung besteht aus einem bekannten Becherwerk, einem Bodensammler und einer Verladebühne. Das Becherwerk trägt den aus der Brustschildfräse herausrieselnden Boden hinauf zum Bodensammler und ebnet denselben darin ein. Der Bodensammler nimmt den Bodenanfall von je einem Arbeitsturnus auf und entlädt denselben durch Kippen des Bodens in Sekundenschnelle in die auf der Verladebühne bereitstehende Lore.The loading device consists of a known bucket elevator, a Soil collector and a loading platform. The bucket elevator carries the one from the breastplate cutter trickling out soil up to the soil collector and levels the same in it. Of the Soil collector picks up the soil accumulation from each work cycle and unloads the same by tilting the floor in a matter of seconds into the one available on the loading platform Lore.

Die Mauermaschine besteht aus einem Verteilerring, der sich aus Steinkammern und den Antriebvorrichtungen für dieselben zusammensetzt. Durch die hydraulischen Pressen werden alle Steine eines Verbandringes gleichzeitig aus dem Verteilerring ausgestoßen und in:die Mauerverzahnung eingesetzt.The masonry machine consists of a distributor ring made up of stone chambers and the drive devices for the same. By the hydraulic All stones of a bandage ring are pressed out of the distributor ring at the same time ejected and inserted into: the wall teeth.

Die Entladevorrichtung für die Gewölbesteine besteht aus einem Transportband und besonders hierfür eingerichteten Loren.The unloading device for the arch stones consists of a conveyor belt and specially equipped trucks.

Die Krananlage besteht aus am Gewölbe mittels der Rohrbuchsen befestigten Laufträgern mit Laufkatzen zum Abheben und zum Schwebendhalten der auf den Loren hereinkommenden Gleisjoche und anderer Materialien bis zur Verwendung, zum Auswechseln der Zwischenjoche und zum Tragen nachfahrender Arbeitsbühnen. Die Träger sollen nach Ausführung der erforderlichen Arbeiten hinten abgebaut und vorn wieder vorgestreckt werden.The crane system consists of fastened to the vault by means of pipe bushings Girders with trolleys to lift off and to keep floating on the trolleys incoming track sections and other materials to use, to exchange the intermediate yokes and to carry subsequent working platforms. The porters should after completing the required work, dismantled at the rear and stretched forward again at the front will.

Der Gewölbestein ist wie üblich radial keilförmig, aber erfindungsgemäß an den Lagerfugen von der Mitte nach vorn und hinten leicht keilförmig, wodurch in Verbindung mit der als Schmiere wirkenden Fugendichtung das Expansionsbestreben der Ausmauerung erzielt wird.The arch stone is, as usual, radially wedge-shaped, but according to the invention slightly wedge-shaped at the bed joints from the center to the front and back, making in connection with the joint seal, which acts as a grease, the tendency to expand the lining is achieved.

Die Fugendichtung- ist neben der Steinform mit der wichtigste Faktor dieser Bauweise. Die Gewölbesteine aus wasserdichtem Beton erhalten außen und an den Fugenseiten einen Bitumen- oder ähnlichen Anstrich, der, vor der Verladung ausgeführt, wohl eine äußere trockene Haut haben, innerlich aber noch weich sein soll. Dieser Anstrich wirkt zuerst haftend, dann, beim Einpressen als Schmiere, verhindert er das Zerreiben der Lagerfugenflächen und dichtet.The joint sealing is next to the stone shape with the most important factor this design. The arched stones made of waterproof concrete get outside and on the joint sides a bitumen or similar coating, which, before loading, probably have dry skin on the outside, but should still be soft on the inside. This The paint initially has an adhesive effect, then, when pressed in as a grease, it prevents the rubbing of the bed joint surfaces and seals.

Als zusätzliche Dichtung ist die künstliche Fuge vorgesehen, die nach Freiwerden mit wasserdichtem Mörtel innig verstrichen werden soll.The artificial joint is provided as an additional seal Exposure to be spread intimately with waterproof mortar.

Die Rohrbuchsen dienen der sofortigen Befestigungsmöglichkeit für die Kranträger, Kraft- und Lichtleitungen beim Rohbau und später beim Ausbau. Sowohl im Umfang als auch in der Länge des Stollens werden Steine mit einbetonierter Rohrbuchse systematisch so eingebaut, daß alle Meter eine vorbereitete Befestigungsmöglichkeit vorhanden ist.The pipe sockets are used for the immediate attachment option for the crane girders, power and light lines during the shell construction and later during the expansion. As well as in the circumference as well as in the length of the tunnel are stones with a concreted pipe socket systematically installed in such a way that a prepared fastening option is available every meter is available.

In den Zeichnungen sind Ausführungsbeispiele der Erfindung dargestellt.Exemplary embodiments of the invention are shown in the drawings.

Fig. I zeigt einen lotrechten Längsschnitt durch den Stollen mit der hauptsächlichsten Einrichtung und Fig.II einen Grundriß hierzu; Fig. III ist ein Querschnitt der Fig. I und II; Fig. IV zeigt eine Ansicht der Brustschildfräse von hinten; Fig. V zeigt die Mauermaschine in der Ausmauerung; die Fig. VI bis IX zeigen Ansichten der Gewölbesteine; die Fig. X bis XVIII zeigen Einzelheiten der Mauermaschine.Fig. I shows a vertical longitudinal section through the cleat with the main device and Fig.II a plan for this; Fig. III is a Cross section of Figures I and II; FIG. IV shows a view of the breastplate milling machine from FIG rear; Fig. V shows the masonry machine in the lining; Figs. VI to IX show Views of the vaulted stones; FIGS. X to XVIII show details of the masonry machine.

Wie in den Fig. I, 1I und IV gezeigt, besteht die Brustschildfräse A aus der Stirnfläche i, den Speichen z, dem Außenreifen 3, dem Hinterwandring 4, dem Innenring 5 und den Speichenwänden 6.As shown in Figures I, 1I and IV, the breastplate reamer exists A from the end face i, the spokes z, the outer tire 3, the rear wall ring 4, the inner ring 5 and the spoke walls 6.

Je nach Größe des Stollenquerschnittes wird die Stirnwand aus mehreren Teilen gebildet, so daß bei vorliegenden Hindernissen ein Kreisausschnitt abmontiert werden kann, ohne die übrige stehende Wand unnötig zu entblößen.Depending on the size of the tunnel cross-section, the front wall is made up of several Parts formed so that a section of a circle dismantled when there are obstacles without unnecessarily exposing the rest of the standing wall.

In den Stirnwandteilen sind gegeneinander versetzte Ausschnitte 7 mit Messern 8 angeordnet, die beim Rotieren der Brustschildfräse A unter Vortrieb den Boden vor Ort abfräsen, der dann durch die Ausschnitte 7 nach innen fällt. Die Speichen 2, die nur bis zu dem in der Mitte eine Öffnung bildenden Ring 5 geführt werden, versteifen die Stirnwand i und leiten auf ihren Flächen den gelösten Boden im oberen Viertel zur Mitte, im unteren Dreiviertel in die Kammern g, denselben beim Rotieren so weit hebend, bis auch dieser Boden auf den Speichen :2 zur Mitte abrutschen kann. Der Außenreifen 3, in kleinem Abstand vom Rande der Stirnfläche i, verbindet die Speichen :2 außen und bildet den Boden der Kammern 9 und gleichzeitig die Rollfläche, auf der die Brustschildfräse A im Wandring 15 auf Gleitrollen i i ringsherum gelagert ist.In the end wall parts, mutually offset cutouts 7 with knives 8 are arranged which, when the breastplate milling machine A rotates, mill off the ground on site, which then falls through the cutouts 7 inwards. The spokes 2, which are only led up to the ring 5 forming an opening in the middle, stiffen the end wall i and guide the loosened soil on their surfaces in the upper quarter to the middle, in the lower three-quarters into the chambers g, the same when rotating Raising it far, until this bottom can also slide off towards the center on the spokes: 2. The outer tire 3, at a small distance from the edge of the end face i, connects the spokes: 2 outside and forms the bottom of the chambers 9 and at the same time the rolling surface on which the breastplate cutter A is mounted all around in the wall ring 1 5 on sliding rollers ii.

Der Hinterwandring 4 verbindet die Speichen :2 und bildet mit den Teilen i und 3 die Bodenauf fangkammern 9 und gleichzeitig die Fläche, auf die der Vortriebandruck vom ersten Wandring 15 auf die Brustschildfräse A wieder mittels Gleitrollen 12 übertragen wird.The rear wall ring 4 connects the spokes: 2 and forms with the Share i and 3, the Bodenauf collecting chambers 9 and at the same time the area on which the Driving pressure from the first wall ring 15 on the breastplate cutter A again by means of Rollers 12 is transferred.

Der Hinterwandring 5 faßt die Speichen nahe der Mitte zusammen. Das vordere Mittelstück io der Stirnfläche i ist ohne Durchlaß,.aber vorn mit einem Bohrstern versehen, der den hier gelösten Boden zu den Ausschnitten 7 abdrängt. Der Antrieb der Brustschildfräse A erfolgt durch am Wandring 15 oder 16 montierte Motoren 21 über einen Zahnkranz 13, der am Hinterwandring 4 montiert wird.The rear wall ring 5 summarizes the spokes near the center. That front center piece io of the end face i is without a passage, but at the front with a Provided drill star that pushes the loosened soil to the cutouts 7. The breastplate milling machine A is driven by the one mounted on the wall ring 15 or 16 Motors 21 via a ring gear 13 which is mounted on the rear wall ring 4.

In der Mitte der Brustschildfräse A ist nach hinten die Bodenauffangschale 14 halbrund und schräg angeordnet, die den von den Speichen 2 abrutschenden Boden auffängt und auf das Becherwerk B leitet. Der Ständer für die Auffangschale 14 ist auf dem Wandring 15 zu montieren. Der Fuß und der Antrieb des Becherwerks B stehen auf dem Wandring 16.In the middle of the breastplate cutter A is the soil collecting tray to the rear 14 semicircular and obliquely arranged, the bottom slipping off the spokes 2 catches and directs to bucket elevator B. The stand for the drip tray 14 is to be mounted on the wall ring 15. The foot and the drive of the bucket elevator B are at a standstill on the wall ring 16.

Zur Vortriebmaschine gehören die Wandringe 15, 16, 17, 18. Dieselben werden aus gebogenen Stahlblechen i9 gebildet und mit Profileisen 2o versteift. Der als Träger der Antriebmotoren 21 der Brustschildfräse A dienende Wandring 16 ist dadurch einem der Drehrichtung der Brustschildfräse A entgegengesetzten Drehimpuls ausgesetzt und muß durch verstellbare Steuerflossen 22 stabilisiert werden. Die hydraulischen Pressen 23 werden im Wandring 18 eingebaut und der Motor 24 dazu auf dem Wandring 17 befestigt. Zwecks Richtungskorrektur und zum eventuellen Kurvenfahren sind zwischen den Wandringen 15, 16, r7,18 Spannschlösser 25 angeordnet, die, entsprechend gestellt, dem Wandringschlauch eine Biegung geben. Die hydraulischen Pressen 23 arbeiten umschichtig.The wall rings 15, 16, 17, 18 belong to the jacking machine. They are formed from bent steel sheets 19 and stiffened with profile iron 20. The wall ring 16 serving as the carrier of the drive motors 21 of the breastplate milling machine A is thus exposed to an angular momentum opposite to the direction of rotation of the breastplate milling machine A and must be stabilized by adjustable control fins 22. The hydraulic presses 23 are installed in the wall ring 18 and the motor 24 is attached to the wall ring 17 for this purpose. For the purpose of correcting the direction and for possible cornering, turnbuckles 25 are arranged between the wall rings 15, 16, r7, 18, which, appropriately positioned, give the wall ring hose a bend. The hydraulic presses 23 work in shifts.

Während die ersten die Verbandsteine aus der Mauermaschine heraus in den Mauerverband einschieben, werden die zweiten eingezogen. Die ersten Pressen arbeiten dann weiter auf Vortrieb der Wandringe und die Brustschildfräse A fräst jetzt. Während des Einziehens der zweiten Pressen sind auch die Steinkammern 55 der Mauermaschine zurückgezogen und werden sofort nacheinander wieder gefüllt und wieder herausgefahren. Der soeben beschriebene Arbeitsgang wiederholt sich jetzt mit den zweiten Pressen und bildet einen Turnus.During the first the bandage stones out of the masonry machine push into the wall bond, the second will be drawn in. The first presses then continue to work on the advance of the wall rings and the breastplate milling machine A mills now. The stone chambers 55 are also during the drawing-in of the second presses the masonry machine are withdrawn and are filled again immediately one after the other and pulled out again. The process just described is now repeated with the second presses and forms a cycle.

Auf diesen Turnus sind auch die Arbeitsgänge der anderen Vorrichtungen abgestimmt, wie Bodenbeladung, Steinentladung usw. Der während des Fräsens gelöste Boden läuft über die Auffangschale 14 auf das Becherwerk B und wird von diesem zum Bodensammler C hinaufgetragen und darin verteilt. Der Bodensammler C und die Verschiebebühne F dienen der schnellen Beladung und dem Umgleisen der Loren D.The operations of the other devices are also on this rotation coordinated, such as floor loading, stone unloading, etc. The one loosened during milling Bottom runs over the drip tray 14 to the bucket elevator B and is used by this Soil collector C carried up and distributed in it. The bottom collector C and the transfer platform F are used for fast loading and rerouting of the lorries D.

Beide sind auf dem Fahrgestell 29, das auf der Ausmauerung fährt, aufgebaut und mit der Vortriebmaschine gekoppelt. Um diese nicht zu sehr einseitig zu belasten, erhält das Fahrgestell einen Hilfsmotor.Both are on the chassis 29, which runs on the brickwork, set up and coupled with the tunneling machine. So as not to be too one-sided to load, the chassis receives an auxiliary engine.

Der Kippbodenbodensammler C ist ein Behälter mit einem auf einer Längsmittelachse 27 gelagerten, einseitig kippbaren Boden 26 und mit radial gebogenen Längswänden 28, der so groß sein soll, daß derselbe den turnusmäßig anfallenden Boden fassen kann.The tilt floor collector C is a container with a on a longitudinal center axis 27 mounted, one-sided tiltable floor 26 and with radially curved longitudinal walls 28, which should be so big that it can grip the regularly occurring soil can.

Der Kippbodenbodensammler C ist auf den Säulen 31 und 32 hochgestellt, damit eine Lore D darunter durch einseitiges Kippen des Bodens 26 in Sekundenschnelle beladen werden kann. Die seitliche Lorenumgleisung auf der Verschiebebühne F wird durch eine in einer versenkten Wanne im Fußboden seitlich verschiebbare Plattform 30 mit Rillengleisen vorgenommen. Das Ende des Becherwerks B wird von der Verschiebebühne F getragen und ist darüber so zu führen, daß die Schaufeln desselben den sich sonst am Ende häufenden Boden letzten Endes gleichmäßig verteilen.The tilting floor collector C is raised on the pillars 31 and 32 so that a cart D underneath can be loaded in seconds by tilting the floor 26 on one side. The lateral lorry rerouting on the shifting platform F is carried out by a platform 30 with grooved tracks that can be laterally displaced in a sunk trough in the floor. The end of the bucket elevator B is carried by the transfer platform F and is to be guided over it in such a way that the shovels of the same ultimately evenly distribute the soil that otherwise accumulates at the end.

Um für die Zeit zur Auswechselung der Gleisjoche vorn weiterarbeiten zu können und eine Lore bereit zu haben, erhält die Verschiebebühne F nach hinten Verlängerungen 33. Diese müssen zwischen sich in der Mitte einen Zwischenraum frei lassen, so daß das Transportband G für die Zuführung der Gewölbesteine zur Mauermaschine H unter der Verschiebebühne F hindurchgeführt werden kann.In order to continue working for the time to replace the track sections in front To be able to and have a cart ready, the transfer platform F is given to the rear Extensions 33. These must free a space between them in the middle let so that the conveyor belt G for the supply of the arched stones to the masonry machine H can be passed under the shifting platform F.

Auch die obere Plattform 34 um den Bodensammler C herum wird nach hinten verlängert, um für die an der Decke anzubringenden Laufträger 48 und die sonstigen Leitungen als Montagebühne zu dienen und um auch als zeitweilige Ablage der Gleiszwischenjoche zu dienen. Am Ende der unteren Plattformverlängerungen 33 sind Gleisschleppen 35 angeordnet, um die bei jedem Turnus sich verlängernden Gleislücken 41 zwischen dem liegenden und dem ständig vorrückenden Gleis zu überbrücken.The upper platform 34 around the bottom collector C is also increased extended at the rear in order for the running beams 48 to be attached to the ceiling and the to serve other lines as an assembly platform and also as a temporary storage area to serve the track intermediate yokes. At the end of the lower platform extensions 33 are towed tracks 35 are arranged around the track gaps that lengthen with each rotation 41 to bridge between the lying and the constantly advancing track.

Die zweigleisig miteinander verbundenen Zwischenjoche 36 usw. von z. B. i m, 2 m usw. Länge werden so oft gegeneinander ausgewechselt, von der Krananlage aufgehoben, gehalten, abgelegt und eingesetzt, bis die liegenbleibenden Normalgleisjoche 4o auf der Unterbettung verlegt werden können. Die Krananlage soll auch sonstige Arbeitsbühnen zum Verputzen der Fugen 5 i, zum rückwärtigen Abmontieren der nicht mehr benötigten Kranträger usw. nachfahren, so daß der Fahrbetrieb unten nicht behindert wird.The double-track interconnected intermediate yokes 36, etc. from z. B. i m, 2 m, etc. lengths are so often interchanged by the crane system lifted, held, filed and used until the normal track yokes that remained 4o can be laid on the bedding. The crane system should also be used for other purposes Working platforms for plastering the joints 5 i, for dismantling the rear not follow up more required crane girders, etc., so that the operation below is not hindered will.

Zur sofortigen Befestigung der Kranträger 48, der diversen Leitungen usw. werden in regelmäßigem Abstand voneinander sowohl im Umfang als auch in der Länge des Stollens Gewölbesteine mit einbetonierter Rohrbuchse 5o vermauert. In diese Rohrbuchse 5o mit Innengewinde können sowohl im Rohbau als auch für den Ausbau jederzeit Leitungen an- und abmontiert werden; auch die Konsolen 42 als Auflager der Zwischenjochträger werden daran befestigt.For the immediate attachment of the crane girders 48 and the various lines etc. are regularly spaced from each other both in scope and in the Length of the tunnel Vaulted stones walled in with a pipe socket set in concrete 5o. In this pipe socket 5o with internal thread can both in the shell and lines can also be attached and removed at any time for expansion; also the consoles 42 as a support for the intermediate yoke beams are attached to it.

Die Entladeeinrichtung besteht aus dem Transportband G und den besonders dafür eingerichteten Loren D.The unloading device consists of the conveyor belt G and the special Loren D.

Das Transportband G besteht aus vier Teilen: dem zwischen den Plattformverlängerungen 33 nach unten zur Mauermaschine H führenden, gewissermaßen festen Teil 44 und den an den mit den Gewölbesteinen 49 beladenen Loren D vorbeiführenden schwenkbaren Teilen 45, 46, 47.The conveyor belt G consists of four parts: the one between the platform extensions 33 leading down to the masonry machine H, to a certain extent fixed part 44 and the on the lorries D that are loaded with the arched stones 49 can be swiveled Share 45, 46, 47.

Die Loren D sind für die Steinentladung besonders einzurichten. Die bei der Einfahrt innere Längswand wird aus drei übereinander angeordneten kippbaren Wandteilen 42 gebildet. Um go° nach innen umkippbar, tragen dieselben die Gewölbesteine 49 (Fig. VI).The wagons D are to be specially set up for the unloading of stones. the at the entrance the inner longitudinal wall is made up of three tiltable ones arranged one above the other Wall parts 42 formed. Can be tilted inwards by go °, they support the arched stones 49 (Fig. VI).

Zur Entladung der Steine werden die Transportbandteile 45, 46, 47 mittels den an den Laufkatzen 54 einzurichtenden Vorrichtungen nach ihrer Längsachse einerseits gehoben und andererseits gesenkt, so daß dieselben parallel zu den kippbaren Lorenw andteilen 42 liegen bzw. schweben.To unload the stones, the conveyor belt parts 45, 46, 47 by means of the devices to be set up on the trolleys 54 along their longitudinal axis on the one hand raised and on the other hand lowered so that the same parallel to the tiltable Wagon wall parts 42 lie or float.

Jetzt werden durch Arbeiter die kippbaren Wandteile 42 auf allen drei Loren zugleich hochgekippt. Dadurch fallen die Gewölbesteine auf die Transportbandteile 45, 46, 47.Now the tiltable wall parts 42 are on all three by workers Loren tipped up at the same time. This causes the arch stones to fall onto the conveyor belt parts 45, 46, 47.

Alsdann werden diese entgegengesetzt wie vorher gesenkt und gehoben und erhalten Anschluß untereinander und an das feste Transportband 44.Then these are lowered and raised in the opposite direction as before and are connected to one another and to the fixed conveyor belt 44.

Jede Lore soll den Bodenanfall eines Vortriebs gleich einer Verbandschicht aufnehmen. Sie muß deshalb auch die erforderlichen Gewölbesteine für diese mitbringen. Der feste Transportbandteil44 soll lang genug sein, um ebenfalls diese Anzahl Steine aufzunehmen, die nun während der Lorenentladung zur Mauermaschine H abrollen. Nach dem vorbeschriebenen Zusammenschluß allerTransportbandteile rollen nun auch die entladenen Steine ab, und der Vorgang wiederholt sich. Die Transporteinrichtung wird mit der Vortriebmaschine gekoppelt und rückt laufend nach. Die Loren D sind nach der Entladung der dritten, untersten Schicht geschlossen und zur Bodenbeladung fertig.Each cart should equal the amount of soil produced by a drive with a layer of dressing take up. You must therefore also bring the necessary vault stones for this. The fixed conveyor belt part 44 should be long enough to also carry this number of stones take up, which now roll during the unloading of the lorry to the masonry machine H. To the above-described combination of all conveyor belt parts are now also rolling discharged stones and the process is repeated. The transport device is coupled with the tunneling machine and is constantly moving up. The Loren D are after the third, lowest layer has been unloaded, it is closed and ready for floor loading done.

Das ist wieder ein Turnus, der sich zeitlich in den Vortrieb einfügt, wenig Arbeitskräfte erfordert und Trubel vermeidet.This is again a cycle that fits into the advance in terms of time, requires little manpower and avoids the hustle and bustle.

Die Mauermaschine H (Fig. V) zum gleichzeitigen Einschub aller für einen weiteren Mauerring erforderlichen Gewölbesteine in die Verzahnung der zuletzt hergestellten Ausmauerung ist ein Verteilerring, der sich aus den Steinkammern und den Führungsgestellen mit den Antriebvorrichtungen zusammensetzt. Einzelteile hierzu zeigen die Fig. X bis XVIII. Die Steinkammern 55 sind nach innen und seitlich geschlossen, vorn zum Durchstoß der Pressen 28 teilweise offen, hinten zum Einschub und Ausstoß der Gewöibesteine 4g ganz offen. Um das Herausfallen der Gewölbesteine 49 beim Einschub zu verhindern, sind an den inneren Seiten der Steinkammern 55 Leisten 74 angeordnet, auf die sich die Gewölbesteine 49 mit Nuten 75 in denselben aufschieben. Außen an den Steinkammern 55 sind Führungsleisten 56 mit i\Tuten angeordnet, mit denen die Steinkammern 55 an den Führungsgestellen 5g bis 63 heraus- und hereingleiten. Die Führungsgestelle 59 bis 63 bestehen aus den überbrückenden und tragenden Gerüstwänden 59 mit den Führungen 63 und den Rollenträgern 61, 62, die, beiderseits durch die Ringe 6o zusammengefaßt, den Raum zwischen der Aus mauerung und dem letzten Wandring 18, auf diesen rollend, überbrücken. Zum Bewegen der Steinkammern 55 tragen diese Zahnstangen 57, in die die in den Führungsgestellen 59 bis 63 gelagerten, ineinandergreifenden zwei Zahnräder 58 eingreifen. Durch diese Anordnung erhalten die Zahnräder 58 entgegengesetzte Drehrichtungen, .die die Zahnstangen 57 und damit die Steinkammern 55 gleichmäßig und in gleicher Richtung bewegen.The masonry machine H (Fig. V) for the simultaneous insertion of all vault stones required for another wall ring into the toothing of the last brickwork produced is a distributor ring, which is composed of the stone chambers and the guide frames with the drive devices. Individual parts for this are shown in FIGS. X to XVIII. The stone chambers 55 are closed inwardly and laterally, partially open at the front for the presses 28 to pierce, and completely open at the rear for the insertion and ejection of the vaulted stones 4g. In order to prevent the vaulted stones 49 from falling out during insertion, strips 74 are arranged on the inner sides of the stone chambers 55, onto which the vaulted stones 49 slide with grooves 75 in the same. On the outside of the stone chambers 55, guide strips 56 with grooves are arranged, with which the stone chambers 55 slide out and in on the guide frames 5g to 63. The guide frames 59 to 63 consist of the bridging and load-bearing scaffolding walls 59 with the guides 63 and the roller carriers 61, 62 which, on both sides combined by the rings 6o, bridge the space between the masonry and the last wall ring 18, rolling on these . To move the stone chambers 55, they carry toothed racks 57 into which the two interlocking gears 58, which are mounted in the guide frames 59 to 63, engage. This arrangement gives the gears 58 opposite directions of rotation, which move the racks 57 and thus the stone chambers 55 uniformly and in the same direction.

Die gleichzeitige Bewegung aller Steinkammern 55 wird dadurch bewirkt, daß in jedem Führungsgestell 59 bis 63 die gleichen Zahnräder 58 auf ihrer Achse außen nach vorn Zahnräder 67 tragen, welche durch einen auf dem vorderen Rollenträger 62 gleitend angeordneten Zahnkranz 69 angetrieben werden. Zur Füllung der Steinkammern 55 muß der Verteilerring streckenweise weitergedreht werden. Zu diesem Zweck ist auf den vorderen Rollenträgern 62 der Zahnkranz 68 an diesem fest angeordnet. Das streckenweiseWeiterrücken des Verteilerringes erfolgt durch ein vom Motor angetriebenes Zahnrad 7o, welches nur so weit mit Zähnen besetzt ist, wie bei einer Umdrehung desselben der Verteilerring weitergedreht werden soll.The simultaneous movement of all stone chambers 55 is caused by that in each guide frame 59 to 63 the same gears 58 on their axis wear outside forward gears 67, which by one on the front roller carrier 62 slidably arranged ring gear 69 are driven. For filling the stone chambers 55 the distributor ring must be turned further in parts. To that end is on the front roller carriers 62 of the ring gear 68 fixedly arranged thereon. That The distributor ring is moved further in places by a motor-driven one Gear wheel 7o, which is only so far occupied with teeth, as with one revolution of the same the distributor ring is to be turned further.

In gleicher Weise sollen auch die Steinkammern 55 streckenweise hin und her bewegt werden; das Zahnrad 71, ebenfalls nur zum Teil mit Zähnen besetzt, bewegt durch Eingriff in eines der Zahnräder 67 mittels des gleitenden Zahnkranzes 69 alle Zahnräder 67 gleichzeitig und gleichmäßig.In the same way, the stone chambers 55 should also go there in parts and be moved here; the gear 71, also only partially occupied with teeth, moved by engaging one of the gears 67 by means of the sliding ring gear 69 all gears 67 simultaneously and evenly.

Der wechselseitige Antrieb der Zahnräder 70 und 71 vom Motor wird durch eine Kupplung 73 (s. Fig. XVII) bewirkt.The reciprocal drive of the gears 70 and 71 from the engine is effected by a coupling 73 (see Fig. XVII).

Der Gewölbestein 49 kann infolge der Keilform der Lagerfugenseiten auch bei Handvermauerung, selbst an der Decke, ohne Lehrbögen leicht eingesetzt werden und fällt nicht wieder heraus. Hierzu würden aber Arbeitsbühnen und viele Steineinsetzer und Zubringer erforderlich sein und das Tempo des Vortriebs hemmen, auch viel Trubel verursachen.The arch stone 49 can due to the wedge shape of the bearing joint sides Easily used even with manual masonry, even on the ceiling, without teaching sheets will and will not fall out again. For this, however, work platforms and many would be Stone setters and feeders may be required and inhibit the speed of the advance, also cause a lot of hustle and bustle.

Mit Mörtel können die Fugen nie zuverlässig gedichtet werden; deshalb wurde die Fugendichtung gewählt. Bitumen oder eine ähnliche Masse läßt sich unter Pressendruck sehr dünn und dicht einpressen, und das gewollte Ausdehnungsbestreben der Ausmauerung und damit das feste Anpressen derselben an die Bodenwandung wird dadurch erreicht.The joints can never be reliably sealed with mortar; for this reason the joint seal was chosen. Bitumen or a similar mass can be omitted Press in the press pressure very thinly and tightly, and the intended expansion effort the lining and thus the firm pressing of the same against the bottom wall achieved thereby.

Die letzten Ringschichten werden sich unter Pressendruck noch ein wenig verlagern. Die künstlichen Fugen 5 i sollen alsdann die Vermauerung durch inniges Verfugen mit wasserdichtem Mörtel nicht nur festlegen, sondern auch noch zusätzlich dichten.The last ring layers will still be one under pressure relocate little. The artificial joints 5 i should then go through the masonry intimate grouting with waterproof mortar not just set, but also seal additionally.

Das unvermeidliche Verlagern der Vermauerung würde bei der Verwendung von Mörtel unter Pressendruck denselben lockern und undicht werden lassen.The inevitable relocation of the brickwork would occur with use Loosen the mortar under pressure and let it leak.

Claims (1)

PATENTANSPRÜCHE: i. Einrichtung zur Herstellung von Stollen undTunnels, insbesondere vonU-Bahn-Tunnels, Luftschutzräumen u. dgl., in Schürfboden, gekennzeichnet durch a) eine Vortriebmaschine finit der im ersten Wandring (15) auf Rollen (1 i) rotierenden Brustschildfräse (A). mit den im letzten Wandring (18) eingebauten Vorschubpressen (28) und mit den an den Wandringen gelagerten Motoren, b) eine in und hinter der Vortriebmaschine angeordnete Verladevorrichtung für den von der Brustschildfräse (A) gelösten Boden, mit einem Becherwerk (B) und einem von einer mit Loren (D) befahrbaren Verschiebebühne (F) getragenen hochgestellten Bodensammler (C), c) eine Entladeeinrichtung für die Gewölbesteine, die aus den besonders eingerichteten Loren (D) und dem ebenfalls hierzu eingerichteten Transportband (G) besteht, um die Steine bis vor die 'Mauermaschine (H) zu transportieren, d) eine hinter der Vortriebmaschine angeordnete Mauermaschine (H), die aus einem drehbaren Verteilerring besteht, der einerseits auf dem Wandring (18), andererseits auf der fertigen Ausmauerung rollt und mit Hilfe der '"ortriebpressen (28) die hinter dem Wandring (18) frei werdende Bodenwand sofort ausmauert. z. Brustschildfräse (A) für die Einrichtung nach Anspruch i, gekennzeichnet durch eine bei vorkommenden Hindernissen teilweise abnehmbare Stirnwand (i), die mit Ausschnitten (7) und am Rande der Ausschnitte mit Schabemessern (8) versehen ist, auf der Vorderseite in der Mitte einen Bohrstern (io) trägt und an der Hinterseite mit Speichen (2) versteift ist, die an einem eine öffnung an der Rückseite bildenden liittelring (5) endigen, in dem eine Rutsche (14) den durch die Schabemesser und den Bohrstern gelösten und auf den Speichen (2) abgleitenden Boden auffängt und zum Weitertransport auf ein Becherwerk (B) weiterleitet. 3. Wandringe für die Einrichtung nach Anspruch i, dadurch gekennzeichnet, daß a) der die Motoren (21) tragende Wandring (16) einem der Drehrichtung der Brustschildfräse (A) entgegengesetzten Drehimpuls ausgesetzt ist, der durch verstellbare Steuerflossen (22) ausgeglichen werden muß, b) verstellbare Spannschlösser (25) zwischen den Wandringen (15 bis 18), zwecks Richtungskorrektur und zum Kurvenfahren angeordnet sind. 4. Beladevorrichtung für die Einrichtung nach Anspruch i, dadurch gekennzeichnet, daß a) das Becherwerk (B) über dem Bodensammler (C) waagerecht geführt wird, um den sich sonst darin häufenden Boden letzten Endes gleichmäßig zu verteilen, b) bei dem Bodensammler (C) der Boden (26) auf einer Längsmittelachse (27) einseitig kippbar angeordnet ist. 5. Entladevorrichtung für die Einrichtung nach Anspruch i, dadurch gekennzeichnet, daß a) das Transportband (G) im unteren Teil (44) fest, aber in den oberen Teilen (45, 46 und 47) nach der Längsachse kippbar angeordnet ist, b) die Loren (D), deren eine Längswand aus übereinander angeordneten, um 9o° nach innen kippbaren Platten (42) zum Tragen der Gewölbesteine besteht, durch Hochkippen derselben die Steine auf das Transportband entladen. 6. Mauermaschine für die Einrichtung nach Anspruch i, gekennzeichnet durch a) den drehbaren Verteilerring (H), der mittels der Rollen (61 und 62) einerseits auf dem Wandring (18), andererseits auf der fertigen Ausmauerung geführt ist, und die zwischen den Führungsgestellen (59) angeordneten Steinkammern (55), die mittels Zahnstangen (57) durch einen gemeinsamen Antrieb (58, 67, 69 und 71) aus dem Ring heraus- und in diesen wieder zurückbewegt werden können, b) Haltefedern (74) in den Steinkammern (55), welche die mit entsprechenden -Nuten (75) versehenen Gewölbesteine (49) beim Hereinschieben nicht wieder herausfallen lassen, c) die hinten ganz offenen, vorn teilweise offenen Wände der Steinkammern (55) zum Ausstoß der Gewölbesteine durch die Pressen (28). 7. Gewölbestein zur Herstellung der Stollenauskleidung mittels der Mauermaschine (H) nach Anspruch 6, gekennzeichnet durch a) die von der Mitte der Lagerfugenseiten nach beiden Seiten angeordneten Verjüngungen, b) die künstliche Fuge (51) im Mauerverband, die durch einen Absatz an der inneren Seite der Gewölbesteine gebildet wird. B. Fugendichtung bei der V ermauerung der Gewölbesteine nach Anspruch 7, gekennzeichnet durch a) die Verwendung bitumenähnlichen Materials an Stelle von Mörtel, b) Verputzen der künstlichen Fuge mit wasserdichtem Mörtel. 9. Rohrbuchse für die Einrichtung nach Anspruch i, gekennzeichnet durch die bei der Herstellung der Steine einbetonierte, hinten steinschraubenförmig gedrückte, vorn mit Innengewinde versehene Rohrbuchse (5o) zum Befestigen der Laufträger und sonstigen Leitungen.PATENT CLAIMS: i. Equipment for the production of galleries and tunnels, in particular by subway tunnels, air raid shelters and the like in scrap floors by a) a tunneling machine finite in the first wall ring (15) on rollers (1 i) rotating breastplate cutter (A). with the feed presses built into the last wall ring (18) (28) and with the motors mounted on the wall rings, b) one in and behind the Driving machine arranged loading device for the breastplate milling machine (A) loosened soil, with a bucket elevator (B) and one of which can be driven on with a cart (D) Transfer platform (F) carried raised floor collector (C), c) an unloading device for the vaulted stones, the ones from the specially equipped trolleys (D) and the one too there is a conveyor belt (G) set up for this purpose to move the stones up to the front of the masonry machine (H) to transport, d) a masonry machine arranged behind the tunneling machine (H), which consists of a rotatable distributor ring on the one hand on the wall ring (18), on the other hand, rolling on the finished brickwork and using the jacks (28) immediately lined up the floor wall exposed behind the wall ring (18). z. Breastplate milling machine (A) for the device according to claim i, characterized by one occurring in Obstacles partially removable front wall (i) with cutouts (7) and on Edge of the cut-outs with scraping knives (8) on the front in carries a drill star (io) in the middle and stiffened at the rear with spokes (2) which end at a middle ring (5) forming an opening on the rear side, in which a slide (14) is loosened by the scraping knife and the drill star and on the spokes (2) slipping ground and for further transport on a Bucket elevator (B) forwards. 3. Wall rings for the device according to claim i, characterized characterized in that a) the wall ring (16) carrying the motors (21) is one of the direction of rotation the breastplate milling machine (A) is exposed to the opposite angular momentum, which is caused by adjustable control fins (22) must be balanced, b) adjustable turnbuckles (25) between the wall rings (15 to 18), for the purpose of direction correction and cornering are arranged. 4. Loading device for the device according to claim i, characterized characterized in that a) the bucket elevator (B) guided horizontally over the bottom collector (C) in order to ultimately evenly distribute the soil that otherwise accumulates in it, b) in the case of the bottom collector (C), the bottom (26) is on one side on a longitudinal center axis (27) is arranged tiltable. 5. Unloading device for the device according to claim i, characterized in that a) the conveyor belt (G) is fixed in the lower part (44), but in the upper parts (45, 46 and 47) arranged tiltable according to the longitudinal axis is, b) the lorries (D), one of the longitudinal walls of which are arranged one above the other, by 9o ° inwardly tiltable plates (42) for supporting the arched stones are made by tilting them up the same unload the stones onto the conveyor belt. 6. Masonry machine for establishment according to claim i, characterized by a) the rotatable distributor ring (H), the means of the rollers (61 and 62) on the one hand on the wall ring (18), on the other hand on the finished Lining is guided, and arranged between the guide frames (59) Stone chambers (55) which are driven by a common drive by means of racks (57) (58, 67, 69 and 71) can be moved out of the ring and back into it can, b) retaining springs (74) in the stone chambers (55), which with the corresponding - Vaulted stones (49) provided with grooves (75) do not fall out again when pushed in c) the walls of the stone chambers that are completely open at the back and partially open at the front (55) for ejecting the arch stones through the presses (28). 7. Arched stone for production the tunnel lining by means of the masonry machine (H) according to claim 6, characterized by a) those arranged from the center of the horizontal joint sides to both sides Tapers, b) the artificial joint (51) in the wall bond, which is created by a paragraph is formed on the inner side of the vault stones. B. Joint sealing at the V bricking up the arch stones according to claim 7, characterized by a) the use bitumen-like material instead of mortar, b) plastering the artificial joint with waterproof mortar. 9. Pipe socket for the device according to claim i, characterized due to the stone screw-shaped at the back, which was concreted in during the production of the stones Pressed tubular socket (5o) with an internal thread at the front for attaching the running girders and other lines.
DESCH6915A 1951-06-21 1951-06-21 Equipment for the production of galleries and tunnels, in particular underground tunnels and air raid shelters, in Schuerfboden Expired DE908383C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DESCH6915A DE908383C (en) 1951-06-21 1951-06-21 Equipment for the production of galleries and tunnels, in particular underground tunnels and air raid shelters, in Schuerfboden

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DESCH6915A DE908383C (en) 1951-06-21 1951-06-21 Equipment for the production of galleries and tunnels, in particular underground tunnels and air raid shelters, in Schuerfboden

Publications (1)

Publication Number Publication Date
DE908383C true DE908383C (en) 1954-04-05

Family

ID=7425117

Family Applications (1)

Application Number Title Priority Date Filing Date
DESCH6915A Expired DE908383C (en) 1951-06-21 1951-06-21 Equipment for the production of galleries and tunnels, in particular underground tunnels and air raid shelters, in Schuerfboden

Country Status (1)

Country Link
DE (1) DE908383C (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1203300B (en) * 1963-03-14 1965-10-21 Demag Ag Driving shield for tunnel construction
DE1225687B (en) * 1963-11-23 1966-09-29 Demag Ag Device for driving a tunnel or the like.
DE1225686B (en) * 1963-11-30 1966-09-29 Demag Ag Two-part driving shield for tunnel construction
DE1279054B (en) * 1964-12-24 1968-10-03 Habegger Maschf Driving shield for the production of lined tunnels, tunnels or the like.

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1203300B (en) * 1963-03-14 1965-10-21 Demag Ag Driving shield for tunnel construction
DE1225687B (en) * 1963-11-23 1966-09-29 Demag Ag Device for driving a tunnel or the like.
DE1225686B (en) * 1963-11-30 1966-09-29 Demag Ag Two-part driving shield for tunnel construction
DE1279054B (en) * 1964-12-24 1968-10-03 Habegger Maschf Driving shield for the production of lined tunnels, tunnels or the like.

Similar Documents

Publication Publication Date Title
DE1584691A1 (en) Machine and method for producing concrete structural parts
DE1534648A1 (en) Driving machine for tunnels, tunnels, channels or the like.
DE2850990A1 (en) FORMWORK FOR CONCRETE LINING FOR TUNNEL
DE69310411T2 (en) Device for digging tunnels
DE908383C (en) Equipment for the production of galleries and tunnels, in particular underground tunnels and air raid shelters, in Schuerfboden
DE2542778B1 (en) PROCEDURE FOR MECHANIZED INSTALLATION OF ROAD CONSTRUCTION AND EQUIPMENT FOR CARRYING OUT THE PROCEDURE
DE2453281C3 (en) Movable formwork scaffolding
DE3601587C2 (en)
DE2343471A1 (en) PROCESS AND SYSTEM FOR THE PRODUCTION OF REINFORCED CONCRETE ELEMENTS, IN PARTICULAR OF LONG STRUCTURAL STRUCTURES, SUCH AS BEAMS OF VARIOUS DIMENSIONS OR THE LIKE. MADE OF PRE-STRESSED CONCRETE
DE2461251C3 (en) Device for pre-assembly, transport and installation of a route or tunnel extension
DE3627270A1 (en) Driving shield, in particular for driving with a heading face supported by earth pressure, with a screw conveyor for the earth moving
DE2360482B1 (en) Device for introducing a steel line or tunnel lining
DE2747975A1 (en) Mine gallery support frame installation system - has erecting frame with hinged members wedged in position by actuator cylinders
DE79592C (en)
DE2119201C3 (en) Erector trolley for inserting a segment lining in tunnels
DE2112947A1 (en) Vehicle for the transport of boxes or the like. concrete
DE1483948A1 (en) Device for attaching loading devices for shaft sinking
DE3700938A1 (en) MANUFACTURING DEVICE FOR MANUFACTURING A LONG STRETCHED CONSTRUCTION
DE19859821A1 (en) Shield assembly for boring tunnel
AT314587B (en) Device for carrying out a process for the underground production of in-situ concrete channels and tunnels of all kinds
DE1179874B (en) Device for clearing and lining open water ditches or channels
DE1187658B (en) Method for the underground construction of tunnels, galleries or similar elongated structures using a driving shield
DE102004033797B4 (en) Design of working devices and roadways for the delivery and avoidance of functional areas in tunnels
CH671053A5 (en) Existing roadway covering method - uses portal truck on tracks either side and lowering prefab sections onto foundations
DE1683884C (en) Distribution device for aggregates for connection to concrete mixers