DE747634C - Process for the production of concrete pavements - Google Patents

Process for the production of concrete pavements

Info

Publication number
DE747634C
DE747634C DEE53094D DEE0053094D DE747634C DE 747634 C DE747634 C DE 747634C DE E53094 D DEE53094 D DE E53094D DE E0053094 D DEE0053094 D DE E0053094D DE 747634 C DE747634 C DE 747634C
Authority
DE
Germany
Prior art keywords
concrete
der
cover
magazine
issue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DEE53094D
Other languages
German (de)
Inventor
Dr-Ing Habil Karl Eberle
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
EBERLE KARL DR ING HABIL
Original Assignee
EBERLE KARL DR ING HABIL
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by EBERLE KARL DR ING HABIL filed Critical EBERLE KARL DR ING HABIL
Priority to DEE53094D priority Critical patent/DE747634C/en
Application granted granted Critical
Publication of DE747634C publication Critical patent/DE747634C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Description

Verfahren zur Herstellung von Betonstraßendecken Die Erfindung betrifft die Herstellung von Betonstraßen und Betonflächen mit einem Weichbeton mit 6 °/o bis 8 °/o Mlassergehalt und einem Zement mittlerer Mahlfeinheit und einem Tonerdemodul zwischen 0,5 und 2,5. Die mit Weichbeton dieser Art hergestellten Kaukörper haben bisher im allgemeinen die Grite und Festigkeit von Baukörpern aus erdfeuchtem Beton nicht erreicht. Zweck der Erfindung ist es, auch mit Weichbeton Bauwerke, insbesondere Betonstraßendecken, zu erhalten, die allen an sie gestellten Güteanforderungen entsprechen. Gemäß der Erfindung soll der Weichbeton unter Beachtung bestimmter Verarbeitungsregeln und Berücksichtigung der Zementbeschaffenheit und Zuschlagstoffzusammensetzung nebst der Benutzung von geeigneten Verdichtungsgeräten nicht nur technisch gleichwertige Betondecken ergeben, sondern auch eine wesentliche Bauleistungssteigerung bringen, verglichen mit der üblichen Deckenherstellung aus einem Straßenbeton steifer Konsistenz. Durch die gemeinsame Anwendung von an sich bekannten und neuartigen Maßnahmen sollen mit dem wasserreichen Beton sämtliche Güteanforderungen, wie sie an den Straßenbeton gestellt werden, erreicht und darüber hinaus noch eine beträchtliche Bauleistungssteigerung erzielt werden.The invention relates to the production of concrete roads and concrete surfaces with a soft concrete with 6% to 8% molar content and a cement of medium fineness and a clay module between 0.5 and 2.5. The chewing bodies produced with soft concrete of this type have so far generally not reached the grit and strength of structures made of earth-moist concrete. The purpose of the invention is to obtain structures, in particular concrete road ceilings, even with soft concrete, which meet all of the quality requirements placed on them. According to the invention, the soft concrete should not only produce technically equivalent concrete ceilings, taking into account certain processing rules and taking into account the cement properties and aggregate composition, in addition to the use of suitable compacting equipment, but also bring about a significant increase in construction performance compared to the usual ceiling production from a street concrete of a stiff consistency. Through the joint application of known and novel measures, the water-rich concrete is intended to meet all the quality requirements that are placed on road concrete and, in addition, to achieve a considerable increase in construction output.

Eine gebräuchliche Einbauart . für Betonstraßendecken setzt sich zusammen aus der Verwendung eines sehr «-eichen Betons mit meist sehr fein gemahlenen Zementen und aus der Verwendung leichter, häufig von Hand be- dienter Geräte zur Verdichtung 1121d Ebnung eines Betonstreifens. Andererseits werden die IktotstraliC'11CIEClien mit Stanlpfbetoll. ;7( lIlell- ten mittlerer oder grober Mahlung und schwe- ren Verdichtung-sinaschinen eiergestellt. 11e-il@= Bauweisen zeigen _Mänel, die zu einer ii'iiii- zeitigen Zerstörung der I)ccl:en Veranlassung geben können. So wird insbesondere durch tlle nasse Verarbeitung des Betwls 111d durch die häufig einfachen Geräte für die Bettnv Learbeitung eine nicht befriedigende Decken ebenlieit erzielt. Ferner ist ini a111-eine,ll@rl die Rissehä ußäkeit bei den mit sehr weichem Beton hergestellten Decken grö ßer als bei den Stampfhetondecken. 1-e1 letzteren d<lge5en kann besonders bei zweilagigern Ihnliau de: Statnpfbetons der Verbund zwischen Ober- lind. Unterbeton leiden. Dazu kommt clre Lift il-enig gelte Cleiclimäßigkeit ini Butonguüigc. Die wirtschaftlichen Vorteile, die die hin arbeltung von weichem Betoll Z@@"aIlgslar1115 durch den Wegiall der intensiven `erdicll- tungsarbeitbeim Stumpfbeton bringt, wurden bei der Erfindung kombiniert finit d(-i- Erfül- lung der Giltivorschrlften f111' Stra1acubeton durch die L# estlegung der richtigen holisistciiz, Zusammeilsetzung, Verarbeitung, Verdich- tung, Ebnung und \achbelmridlung des Wich- betons. Das Verfahren setzt sich ertin dun5s<@@n,:@l.I ans folgenden einzc-lnen an sich 5rl@l.itenteils bekanntere Merkmalen -zusammen: I. der- l` asserbehalt des 1'riscllbetwls hegt Zwischen 1i "/p und 81,f, des Gesa111tgewIClits. Dadurch wird ein Setzmali zwischen o2 cln 11n(1 3,o cnl und ein Ausbreitmaß zwischen 35 an und -13 lnl erhelt. Die Konslsmllz des Weichbewns ist demnach trockener als beün Eisenbeton und nasser als Ahn erdfeuchten beton. , Zemente mit Mahlfeinheiten unter 3 und über 1,2 % Rückstand auf dein Siel> finit 4900 Maschen je cm! ferner solche finit einem kleineren Tonerdenlodul als o,5 und einem größeren Tonerdeniodul als @,5 scheiden aus. Aus den handelsüblichen Straßenzementen werden demnach nur die üben bestimmten mit mittlerer Mahlfeinheit ausgewidilt, die dein Zuschlagstoff-Wasser-Gerniscli in den Weben Mengen beigegeben werdeq. 3. Das Zuschlagstoifgeinisch ist in bekamt- ter Welse zusammengesetzt, jedoch mit delle Unterschied, dall zur Erhöhung der Selbstver- dichtung b; ini Schüttvorgang des Weichbetons 2 °/o bis 6 % Durchfall feinstriiineralischer Be- s s tandteile (Feinstsand oder traß; ähnliche Be- standteile) durch das o,2-nlill-Siel) vorhanden sind. d. Der in Mischniaschinert finit möglichst niedriger Auswurfhöhe gleichmäßig gemischte Weichbeton wird durch die @'erteilererite g@tl@l@lllal:@lg l11 Lagen bis Zu 2(-# CIII Hölle Ver- teilt. Sofort nach dein Schütten des Weich- re trns wird dieser in einem Arbeitsgang mit ;iilrlt: Iertiäirgerät, dessen Arbeitselemente eiii c>,ler zwei leichte, breite Schleifbalken finit htlieniörtnigem Anlauf oder in beiden Rich- taugen drehbare Hohlwalzen sind, abgeglichen tun! verdichtet. Schwere, schlagende, li:bn- in onide oder vibrierende Arbeitselein ente wie i;ci den i;iilichen behailitteil Fertibergeräten iür ihn @tampfhetünstral:@enbau scheiden dem- nach für die Verdichtung und Ebnmig des =chh,#tons aus. Lediglich leichte, parallel der @berllächc hin und her gehende Balken oder in beiden Richtungen drehbare `@@ @ilzeil .find als Arbcitseleinente für die in der Arbcits- gLschwindigkeit \erstelibaren 1#crtigererätc zur l»ariieiulng des iVeichbewnverweiWar. a Nach dcnl erstell Arbeitsbang tritt eitle l@rllli-li@llse 1>1s Z11 '1;1 stunden e111. ;. Nach der Ruhepause wird finit uineiii gleichartigen 1.,'ertigergei':it wie unter 5. die Liti1CC r17 eint171 ü-eitcre77 Ai'1Jelt@S@ili@ geebllct. i1. ninlttulbar nach teer Ebnung wird die Lecke finit einer wenig filier ihrer (-)berfLiche liegenden Schutzbedeckung versehen, 111111'r der die 1-)e@l;e noch dein 1,'i-li:ii"teli des Be- tons mit fein verteiltem `Nasser besprüht wird, worauf die übliche Nachbeliandhing durch feuchte Abdeckung lind Bew:isserunä ei-folgt. Fugen, Dübel Ankereisen und Bewehrungs- maLLn werden nach bukannte77 1'erfahrell elll- geLatlt. 171e Decke kann In eileer oder Zwei Ingen hergestellt werden. Die praktische Er- prlAltIW &s neuen Verfahrens hat ergeben, das dic Deckel, finit Weichbeton sich gut be- \:allreil t111(1 bed;alt@tld hllllger llel-Zlistvlllll sind als Deckel] finit St£ililpflJU-t@iii. A common type of installation. for concrete road pavements consists of the use of a very «oak concrete with mostly very finely ground cements and the use of lighter, often hand-loaded used devices for compaction 1121d leveling of a concrete strip. On the other hand, the IktotstraliC'11CIEClien with Stanlpfbetoll. ; 7 ( lIlell- medium or coarse grind and heavy ren compaction machines. 11e-il @ = Construction methods show _M änel that lead to a ii'iiii- early destruction of the I) ccl: en cause can give. So in particular is through tlle wet processing of the bed 111d the often simple devices for bed nv Workmanship of an unsatisfactory ceiling also achieved. Furthermore, ini is a111-ein, ll @ rl the appearance of cracks in those with very soft Concrete made ceilings larger than the Tamped hetone blankets. 1-e1 the latter d <lge5en can especially with two-layer Ihnliau de: Statnpfbetons the bond between upper lind. Suffering from the sub-concrete. There is also the elevator This is also true of cleverness ini Butonguüigc. The economic benefits that go arbeltung of soft Betoll Z @@ "aIlgslar1115 through the path of the intense `` earthly work on die-cut concrete in the invention combined finite d (-i- fulfillment- tion of the rules of application for 111 'Stra1acubeton by laying down the right holisistciiz, Composition, processing, compression direction, leveling and suppression of the weight concrete. The procedure continues ertin dun5s <@@ n,: @ lI to the following single c-lnen to 5rl@l.itteils better known features - together: I. The water content of the 1'riscllbetwls cherishes Between 1i "/ p and 81, f, of the total weight. This creates a setting penalty between o2 cln 11n (1 3, o cnl and a slump between 35 on and -1 3 lnl received. The consular office of Weichbewns is therefore drier than beün Reinforced concrete and wetter than Ahn concrete. , Cements with a fineness of less than 3 and over 1.2 % residue on your sewer> finite 4900 meshes per cm! furthermore such finite one smaller alumina modulus than o, 5 and one larger alumina iodine than @, 5 are ruled out. From the commercially available street cements therefore only those who practice will participate medium fineness of grind that your Aggregate-Water-Gerniscli in the weave Quantities are added q. 3. The aggregate table is known in The catfish assembled, but with a dent Difference, because to increase self-loss seal b; ini pouring process of the soft concrete 2 ° / o to 6% loading diarrhea feinstriiineralischer s s tandteile (very fine sand or trass; similar loading components) through the o, 2-nlill-Siel) available are. d. The one in Mischnimachert finite as possible low ejection height, evenly mixed Soft concrete is distributed through the @ ' g @ tl @ l @ lllal: @lg l11 layers up to 2 (- # CIII hell ver Splits. Immediately after you pour the soft re trns will do this in one go ; iilrlt: Iertiary device, its working elements eiii c>, ler two light, wide sanding bars finite international approach or in both directions suitable rotatable hollow rollers are calibrated to do! condensed. Heavy, beating, li: bn- in onide or vibrating working line duck like i; ci the i; i; i; i; i; i; i; i; i; i; i; i; i; i; i; i; i; i; i; the behavior of the finished equipment iür him @ tampfhetünstral: @enbau divorce dem- after for the compression and evenness of the = chh, # tons off. Only light, parallel the @ berllächc bar going back and forth or in both directions rotatable `@@ @ilzeil .find as work elements for those in the work speed \ createable 1 # crtigererätc for the termination of the deposit. a After dcnl created work anxiety comes to vain l @ rllli-li @ llse 1> 1s Z11 '1; 1 hours e111. ;. After the pause it becomes finite uineiii similar 1., 'ertigergei': it as under 5. die Liti1CC r17 at171 ü-eitcre77 Ai'1Jelt @ S @ ili @ geebllct. i1. ninlttulbar after tar leveling is the Lick finite a little filier of your (-) surface lying protective cover provided, 111111'r who the 1-) e @ l; e nor your 1, 'i-li: ii "teli des be tons is sprayed with finely divided water, whereupon the usual Nachbeliandhing through Moist cover and evidence of damage. Joints, dowels, anchor iron and reinforcement Sometimes, according to buannte77 1'erfahrell elll- gelatlt. 171e ceiling can be in one or two Ingen be produced. The practical prlAltIW & s new procedure has shown the dic lid, finite soft concrete is easy to \: allreil t111 (1 bed; alt @ tld hllllger llel-Zlistvlllll are as a cover] finite St £ ililpflJU-t @ iii.

Claims (1)

PATEN-raNSrr,ucn: @-erfaln-en zur Herstellung von lictü11- stral.iendeeken unter Ver«eiidung eines @i C@Cllbetöfl; 1111t bis Wassel-- gehalt und einem Zement mittlerer Malll- f#-illlleit t111,1 nlit eitlem @ünenlem<ldul zwi- sCheli a5 111g1 3.5. daduCCli geknnweidniet, da!.@ der Beton, der mit AM]] 2 ";`77 Iris 0 "/,l bis zu 0,2 tunt Korngrölle eiltlialteil(len Zu- hergestellt ist! 111111)1ttt'l- l:ar nach dein Schüttele auf die @ nterlage mitttb eines 1.'#fl'tigergerät@s, dessen Ar- bri@sc@emen@e Icichte, breite Schleifbalken finit ktifeilförinige.in Anlauf oder in bei- den 1.ticlltungen drehbare Walzeit sind, i11 ehirm Arbeitsgang abgeglichen u11(1 ver- riichtet itnd nach einer Ruhepaus. bis zti :l, r Stunden mit demselben Geriet in eitlem weiteren Arbeitsgang geebnet wird. I'n- init@c-lbar anschliellend wird die I@et@711-
decke mit einer wenig über ihrer Oberfläche liegenden Schutzbedeckung versehen und noch vor dein Erhärten des Betons mit fein verteiltem Wasser besprüht, worauf die übliche Nachbehandlung durch feuchte Abdeckung oder Bewässerung erfolgt. Zur Abgrenzung des Anrneldungsgegen- i Standes vom Stand der Technik sind im Erteilungsverfahren folgende Druckschriften in 13etraclit gezogen worden: Reiner, Landbuch der neuen Straßenhauweisen, Berlin 1929, Verlag von Julius Springer, S. 24-., 246 und 3oo bis 3o-[; c_ri-iiii, Der Beton (1926), S. 21 bis ::8; Riepert, Betonstraßenbau in Deutschland (r928), Zementverlag GmbH., Charlottenburg, S. 1d2; Hentrich, Der neuzeitliche Straßenbau, 1928, Teil IV, Verlag von Wilhelm Knapp, Halle (Saale), S. 85, 86, 89 und io6; Zeitschrift: Zement, Heft 3 vom 2o. 1. 1938, S. 41 und .t2; Zeitschrift: Teer und Bitumen, Heft -a2 vom 1. 8. 1935, S. 285 und 286; Richtlinien für I ahrbalindecken der Direktion der Reichsautobahnen, Ausgabe April 193f, S. -1.l ; Merkblatt für Betonstraßen; Zeitschrift: Construction methodes, Juni 1931 S. 53.
PATEN-raNSrr, ucn: @ -erfaln-en for the production of lictü11- stral.iendeeken in avoidance of one @i C @ Cllbetöfl; 1111t to Wassel-- content and a medium-sized cement f # -illlleit t111,1 nlit eitlem @ ünenlem <ldul bet- sCheli a5 111g1 3.5. daduCCli knnnnweidniet, da!. @ the concrete that starts with AM]] 2 ";` 77 Iris 0 "/, l up to 0.2 tunt Korngrölle rapid part (len supply is made! 111111) 1ttt'l- l: ar after your shaking on the mat in the midst of a 1.'#fl'tigergerät@s whose work bri @ sc @ emen @ e Icichte, wide sanding bars finitely ctifeilförinige.in approach or in both the 1st events are rotatable whale time, i11 ehirm operation matched u11 (1 ver directs itnd after a rest. until zti : l, r hours with the same device in vain further work step is leveled. In- init @ c-lbar then the I @ et @ 711-
cover with a protective cover slightly above its surface and spray it with finely divided water before the concrete has hardened, after which the usual after-treatment takes place by moist cover or watering. In order to distinguish the subject of the registration from the state of the art, the following documents were drawn up in the grant procedure: Reiner, Landbuch der neue Straßenhauweise, Berlin 1929, Verlag von Julius Springer, pp. 24-., 246 and 3oo to 3o- [; c_ri-iiii, Der Beton (1926), pp. 21 to :: 8; Riepert, Concrete Road Construction in Germany (r928), Zementverlag GmbH., Charlottenburg, p. 1d2; Hentrich, Der neuzeitliche Straßenbau, 1928, part IV, published by Wilhelm Knapp, Halle (Saale), pp. 85, 86, 89 and io6; Magazine: Zement, Issue 3 from 2o. 1. 1938, p. 41 and .t2; Magazine: tar and bitumen, Issue -a2 from 1 8th 1935, pp. 285 and 286; Guidelines for annual ceilings of the Directorate of the Reichsautobahn, April 193f edition, pp. -1.l; Leaflet for concrete roads; Journal: Construction methodes, June 1931 p. 53.
DEE53094D 1939-10-29 1939-10-29 Process for the production of concrete pavements Expired DE747634C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DEE53094D DE747634C (en) 1939-10-29 1939-10-29 Process for the production of concrete pavements

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEE53094D DE747634C (en) 1939-10-29 1939-10-29 Process for the production of concrete pavements

Publications (1)

Publication Number Publication Date
DE747634C true DE747634C (en) 1944-10-06

Family

ID=7081700

Family Applications (1)

Application Number Title Priority Date Filing Date
DEE53094D Expired DE747634C (en) 1939-10-29 1939-10-29 Process for the production of concrete pavements

Country Status (1)

Country Link
DE (1) DE747634C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0086188A1 (en) * 1982-02-08 1983-08-17 Romain Jean-Baptiste Buys Process for baring a concrete slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
None *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0086188A1 (en) * 1982-02-08 1983-08-17 Romain Jean-Baptiste Buys Process for baring a concrete slab

Similar Documents

Publication Publication Date Title
CN110656753A (en) Concrete grindstone terrace
DE3215777A1 (en) Fluid cement mortar
DE747634C (en) Process for the production of concrete pavements
CN106186942A (en) A kind of self-compacting mortar and grout construction method thereof
US5709824A (en) Method for forming a roller compacted concrete industrial floor slab
DE19848927B4 (en) Process for producing a cast asphalt screed with terrazzo elements
DE3531772A1 (en) Basalt concrete stone
DE19714438C1 (en) Method for renovating concrete
DE4429115C1 (en) Method of producing terraced flooring
DE3811417A1 (en) Method for applying coating concretes of high adhesion to old-concrete surfaces
DE511883C (en) Process for the production of a covering for floors, walls u. like
DE806348C (en) Process for the production of fibrous boards provided with a hard covering to increase the stability
DE102005007537A1 (en) Method to produce quasi-monolithic fixed road coating with paved surface around rails for stability for heavy loads; road coating consists of concrete underlay on which adhesive is applied and paved layer laid on top
DE2557594A1 (en) BUILDING MATERIAL BASED ON CALCIUM SULFATE-ALPHA-HALBHYDRATE
DE689057C (en) Process for the production of mortar-bound road surfaces
DE3403071A1 (en) Floor-levelling compound
EP0282014A2 (en) Method for constructing heavy duty concrete floors
CH711468B1 (en) Floor covering system, in particular for mineral floor slabs, for preventing moisture stains and discoloration and method for constructing a floor covering system.
DE1471135A1 (en) Process for the production of concrete and concrete produced by this process
DE2456712A1 (en) Fibrous constructional materials including concrete - where fibres are spread on concrete before setting to prevent escape of water
AT278325B (en) Floor or wall covering for sound insulation
JPS5829970A (en) Conditioning and repairing of non-land part of concrete or mortar floor
DD143936B1 (en) METHOD FOR PRODUCING FILTER WASTE SURFACE
DE2421170A1 (en) FLOORING AS A DRY SCREED
EP2336095A1 (en) Thin-bed mortar