DE495731C - Procedure for switching instrument transformers on and off Like. In line networks, especially high-voltage lines, without power interruption - Google Patents
Procedure for switching instrument transformers on and off Like. In line networks, especially high-voltage lines, without power interruptionInfo
- Publication number
- DE495731C DE495731C DEST46039D DEST046039D DE495731C DE 495731 C DE495731 C DE 495731C DE ST46039 D DEST46039 D DE ST46039D DE ST046039 D DEST046039 D DE ST046039D DE 495731 C DE495731 C DE 495731C
- Authority
- DE
- Germany
- Prior art keywords
- terminals
- switch
- changeover
- switching
- voltage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01F—MAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
- H01F38/00—Adaptations of transformers or inductances for specific applications or functions
- H01F38/20—Instruments transformers
Description
Verfahren zum Ein- und Ausschalten von Meßwandlern u. dgl. in Leitungsnetzen, besonders Hochspannungsleitungen, ohne Stromunterbrechung Dic Betriebsführung von Elektrizitätswerken, die Messung verkaufter elektrischer :Xrbeit usw. verlangen die Anbringung von Kontroll- und Meßinstrumenten, die laufend auf Genauigkeit und Empfindlichkeit beobachtet «=erden müssen. Soweit es sich hierbei um direkt angeschaltete Instrumente handelt, hat die Technik längst Hilfsmittel und Schaltungen gefunden, um ohne Stromunterbrechung die Instrumente überprüfen, ausbauen und wieder einbauen zu können.Procedure for switching instrument transformers and the like in line networks on and off, especially high-voltage lines, without power interruption Dic operational management of Electric utilities that require metering of sold electrical work, etc. the installation of control and measuring instruments, which continuously check for accuracy and Sensitivity observed «= must be grounded. As far as this is directly connected Instruments, technology has long since found tools and circuits, to check, remove and reinstall the instruments without interrupting the power supply to be able to.
Bei höheren Spannungen und Stromstärken müssen die Instrumente jedoch mittels Strom-und Spannungswandler an das Leitungsnetz angeschlossen werden, und hier genügt nicht allein die Kontrolle der Niederspannung und Kleinstrom führenden Instrumente selbst, sondern es ist auch die dauernde Beobachtung und die Kontrolle der Meßwandler und der gesamten Aggregate erforderlich.At higher voltages and currents, however, the instruments must be connected to the line network by means of current and voltage converters, and Here it is not enough to just check the low voltage and low current carrying Instruments themselves, but it is also constant observation and control the transducer and the entire aggregate required.
Trotz der Wichtigkeit dieser Messungen sind bisher diese Meßaggregate so angeschaltet worden, daß für die Kontrolle der Aggregate einschließlich Meßwandler und für den Ausbau und Einbau solcher Wandler die Leitungen abgeschaltet «-erden müssen.In spite of the importance of these measurements, these measurement units have so far been used been switched on so that for the control of the aggregates including transducers and for the removal and installation of such converters, the lines switched off «- earthed have to.
Da die Stromabnehmer dies meist als eine Belästigung und Schädigung empfinden, müssen diese Arbeiten meistens an Sonn- und Feiertagen oder in der \ acht vorgenommen werden.Since the pantographs this mostly as a nuisance and damage feel, this work usually has to be done on Sundays and public holidays or in the \ eight can be made.
Für die Elektrizitätswerke bedeutet dies Verteuerung des Betriebes und Ungenauigkeit der Wartung wegen der meist gering zur Verfügung stehenden Zeit.For the electricity companies this means more expensive operations and inaccuracy of maintenance due to the usually short time available.
Zweck der Erfindung .ist die Möglichkeit der Überprüfung der an das Leitungsnetz mittels Meßwandler angeschalteten Meß-und Kontrollinstrumente und Apparate sowie an die Hochspannung direkt angeschlossener gleichartiger Gegenstände, die Ermöglichung ihres Einbaues und Ausbaues, ohne die Leitungsanlage strom- und spannungslos machen zu müssen, also ohne Störung des Betriebes.The purpose of the invention is the possibility of checking the data sent to the Network of measuring and control instruments and apparatus connected by means of transducers as well as similar objects directly connected to the high voltage that Facilitating their installation and expansion without the power and voltage of the line system to have to do, i.e. without disrupting operations.
Die Zeichnung (Fig. r) läßt beispielsweise die Anschaltung eines Hochspannungs-Elektrizitätszählers in der bekannten Zweiwattmeterschaltung an ein Drehstrotnnetz erkennen. Die Sekundärwicklungen der Wandler und die Zähler selbst sind der Übersichtlichkeit halber weggelassen.The drawing (Fig. R) shows, for example, the connection of a high-voltage electricity meter Recognize in the known two watt meter circuit to a three-phase network. The secondary windings the converter and the counters themselves have been omitted for the sake of clarity.
In die Leitung R wird ein zweipoliger Umschalter Ur ohne Unterbrechung eingeschaltet dessen zwei; linke Klemmen1i und L. durch den Bügel b1 stets miteinander verbunden sind.A two-pole changeover switch Ur is connected to line R without interruption turned on its two; left terminals1i and L. always with one another through bracket b1 are connected.
An die .beiden rechten Klemmen r, und r= bzw. die damit leitend verbundenen Kleininen r', und r'., wird der Stromwandler Si- angeschlossen in Hintereinanderschaltung mit einem Klenimensatz r111, r", und dessen Ver-'»ci!l,ingsbüjel b r. The current transformer Si is connected to the two right-hand terminals r, and r = or the small bits r ', and r'. l, ingsbüjel b r.
In die L ^itung T würde für Einschaltung Ies Stromwandlers St die gleiche Klemmenuin4c]i.iltekembination genügen.In the line T, the current transformer St would be switched on same clamps in4c] i.iltekembination suffice.
Da jedoch der für die Wattmetermessung erforderliche Spannungswandler auch an die dritte Drehstromleitung S angeschlossen weren muß, ist die Verwendung eines dreipoligen Umschalters Ut zweckmäßig, dessen dritte Rechtsklemme r, mit einer Klemmer', am Aufstellungsort des Spannungswandlers S p verbunden wird. Die beiden linken Kleminen l; und l,, sind stets durch den Bügel b. 1-e rbunden.However, since the voltage converter required for the wattmeter measurement must also be connected to the third three-phase line S, it is advisable to use a three-pole changeover switch Ut whose third right-hand terminal r is connected to a terminal r 'at the installation site of the voltage converter S p. The two left clamps l; and l ,, are always through the bracket b. 1-bound.
Sind die beiden Umschalter Ur und Ut nach rechts gelegt, also die Verbindung von R über r1 und r. nach r', r', 711l, b7-, r", bzw. von T über ra und r-, nach r'3, r', r'a, bt, r'4 und von S über r, nach r', hergestellt und die Verbindung von. R nach b1, T nach bz unterbrochen, so ist der Meßsatz in Wattmeterschaltung betriebsmäßig angeschlossen.If the two switches Ur and Ut are set to the right, i.e. the connection of R via r1 and r. to r ', r', 711l, b7-, r ", or from T via ra and r-, to r'3, r ', r'a, bt, r'4 and from S via r, to r ', established and the connection from R to b1, T to bz interrupted, the measuring set is operationally connected in wattmeter circuit.
Soll eine Biberprüfung des Meßsatzes erfolgen, so werden die UmschalterUr und Ut nach links gelegt. Dadurch werden sämtliche Klemmen i- spannungslos, und es können Flie Kontrollwandler P7 und Pt an Stelle der Bügel bi- und bt sowie der Spannungswandler Psp parallel zu Sp angeschaltet werden.If a beaver test of the measurement set is to take place, the switch Ur and Ut placed to the left. This will de-energize all terminals i-, and Flie control converters P7 and Pt can be used instead of the bi- and bt and the Voltage converter Psp can be connected in parallel to Sp.
Da bei alleiniger Umlegung des Umschalters Ur die Klemme r', unter Spannung bliebe, sind die beiden Umschalter Ur und LTt miteinander zu kuppeln.Since the sole assignment of the switch for the terminal r ', remain are under tension to couple the two switches and Ur LTt each other.
Für Messungen im Einphasennetz kommt ein Umschalter U t zur Verwendung, für Messungen im Vierleiterdrelistromnetz sind drei Umschalter Ut in Gebrauch zu nehmen, falls drei Einphasenspannungswandler eingebaut sind, oder zwei doppelpolige und ein dreipoliger Umschalter, miteinander gekuppelt, falls ein Drehstromspannungswandler verwendet ist. A changeover switch U t is used for measurements in a single-phase network; for measurements in a four-wire relay network, three changeover switches Ut must be used if three single-phase voltage converters are installed, or two double-pole and one three-pole changeover switch, coupled together, if a three-phase voltage converter is used.
In der Stellung der Umschalter Ur und Ut nach links können auch die Stromwandler Sr und St und der Spannungswandler Sp ausgebaut und durch andere ersetzt werden.With the changeover switches Ur and Ut to the left, the current transformers Sr and St and the voltage transformer Sp can also be removed and replaced by others.
Für die Klemmen r111 und r112 können Mes-:erschalter oder Klemmenkombinationen oder :ihnliche Apparate verwendet werden.Measuring switches or terminal combinations can be used for terminals r111 and r112 or: similar devices are used.
Die konstruktive Ausführung des Umschalters kann in verschiedener Weise erfolgen. Fig. i zeigt z. B. einen Messerumschalter, bei welchem für jeden Umschalterpol ein Umschaltemesser in Form eines Hebels mit zwei im stumpfen Winkel stehenden, starr miteinander verbundenen Hebelarmen hl und laz verv endet ist. Der Umschalter besitzt also nicht .Nfonientausschaltung. Will man eine Momentausschaltung verwenden, so sind z. B. an Stelle des starren Winkelhebels für jeden Pol zwei Trennmesser ml und in, (Fig. 2) anzubringen, von welchen z. B. ml durch Druck bei Drehung des Schaltorgans s eingeschaltet und nach vollzogener Einschaltung von ml das zweite Messer m,. durch die Kraft der Feder f2 momentan ausgelöst wird und umgekehrt.The design of the switch can be in different Way. Fig. I shows e.g. B. a knife switch, in which for each Changeover pole a changeover knife in the form of a lever with two at an obtuse angle standing, rigidly interconnected lever arms hl and laz verv ends. Of the Changeover switch does not have. Do you want a momentary switch-off use, so are z. B. instead of the rigid angle lever for each pole two cutting blades ml and in, (Fig. 2) to attach, of which z. B. ml by pressing when turning the Switching organ s switched on and after switching on ml the second Knife m ,. is triggered momentarily by the force of the spring f2 and vice versa.
An Stelle von Messerumschaltern können natürlich auch Kurbelumschalter Verwendung finden.Instead of knife switches, crank switches can of course also be used Find use.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEST46039D DE495731C (en) | 1929-06-29 | 1929-06-29 | Procedure for switching instrument transformers on and off Like. In line networks, especially high-voltage lines, without power interruption |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEST46039D DE495731C (en) | 1929-06-29 | 1929-06-29 | Procedure for switching instrument transformers on and off Like. In line networks, especially high-voltage lines, without power interruption |
Publications (1)
Publication Number | Publication Date |
---|---|
DE495731C true DE495731C (en) | 1930-04-14 |
Family
ID=7465057
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DEST46039D Expired DE495731C (en) | 1929-06-29 | 1929-06-29 | Procedure for switching instrument transformers on and off Like. In line networks, especially high-voltage lines, without power interruption |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE495731C (en) |
-
1929
- 1929-06-29 DE DEST46039D patent/DE495731C/en not_active Expired
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE495731C (en) | Procedure for switching instrument transformers on and off Like. In line networks, especially high-voltage lines, without power interruption | |
Schurig | A Miniature AC. Transmission System For the Practical Solution of Network and Transmission-System Problems | |
AT119431B (en) | Electric switch. | |
DE960911C (en) | Test terminal box with test terminals isolated from one another, especially for electricity meters | |
DE430050C (en) | Device for testing consumption lines for short-circuit current | |
DE2160568A1 (en) | ADAPTER FOR CHECKING ELECTRICITY COUNTERS AT THE INSTALLATION SITE | |
DE502145C (en) | Transmission device for electrical remote transmission of finely graduated angle settings | |
AT93625B (en) | Equipment for the operation of electrical power generation machines in large centers. | |
DE596057C (en) | Circuit for electrical energy transmission using double lines | |
DE877635C (en) | Device for operational determination of the earth fault compensation current to be set in a distribution network | |
DE756683C (en) | Test device for direct current meter | |
AT130114B (en) | Device for measuring alternating current. | |
DE554170C (en) | Procedure for measuring the leakage currents of multi-phase networks | |
DE515366C (en) | Switching arrangement for telemetry instruments for monitoring several electrical devices connected in parallel with at least one common measurement return line | |
DE633697C (en) | Clamp arrangement for testing electrical measuring devices such as counters and wattmeters without interrupting the power output | |
DE335120C (en) | Device for switching on measuring devices in power lines without power interruption | |
DE605589C (en) | Terminal arrangement for testing electrical measuring devices such as counters and wattmeters without interrupting the power output | |
DE302719C (en) | ||
DE972513C (en) | Counter checking device with means for checking in the start-up area | |
DE740487C (en) | Three-phase current meter that can be used for three- and four-wire connection with two drive systems connected in an Aron circuit | |
DE521809C (en) | Arrangement for measuring the current in branch lines of high-voltage systems using measuring transformers | |
DE898613C (en) | Arrangement for the optional measurement of voltage, current and power with three-phase alternating current | |
DE425754C (en) | Protection device for parallel electrical power lines | |
DE135720C (en) | ||
DE226318C (en) |