DE474969C - Device for moving overburden conveyor bridges - Google Patents

Device for moving overburden conveyor bridges

Info

Publication number
DE474969C
DE474969C DEK99528D DEK0099528D DE474969C DE 474969 C DE474969 C DE 474969C DE K99528 D DEK99528 D DE K99528D DE K0099528 D DEK0099528 D DE K0099528D DE 474969 C DE474969 C DE 474969C
Authority
DE
Germany
Prior art keywords
bridge
overburden conveyor
masses
support
overburden
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DEK99528D
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LUDWIG KAEHLER DIPL ING
Original Assignee
LUDWIG KAEHLER DIPL ING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LUDWIG KAEHLER DIPL ING filed Critical LUDWIG KAEHLER DIPL ING
Priority to DEK99528D priority Critical patent/DE474969C/en
Application granted granted Critical
Publication of DE474969C publication Critical patent/DE474969C/en
Expired legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G65/00Loading or unloading
    • B65G65/28Piling or unpiling loose materials in bulk, e.g. coal, manure, timber, not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forklifts And Lifting Vehicles (AREA)

Description

Vorrichtung zum Bewegen von Abraumförderbrücken Einrichtungen zum Gewinnen., Fortschaffen und Abstürzen von Abraummassen, insbesondere im Braunkohlentagebau unter Benutzung einer Abraümförderbrücke, bedingen bei ungleichnnäßiger Mächtigkeit und unregelmäßigem Verlauf der .einzelnen Schichten die Verteilung der gewonnenen Abraummassen auf der Haldenseite. Dies wird nach den bisherigen Vorschlägen dadurch ermöglicht, daß die beiden Fahrwerke der Brücke mit verschiedenen Geschwindigkeiten laufen, wodurch ein Voreilen oder ein Verzögern -der beiden Enden ermöglicht wird. Im vorliegenden Falle wird auf eine derartige Verschiedenartigkeit der Geschwindigkeiten der beiden Enden durch die Fahrwerke durch gesonderte Antriebe verzichtet. Es ist nur auf einem Fahrwerk ein Antrieb vorgesehen, welcher der gesamten Brücke eine einheitliche Winkelgeschwindigkeit erteilt. Die von der Mächtigkeit bedingte Stellung der Brücke wird dadurch erzielt, daß ein Führungsgleis vorgesehen ist, durch welches die Brücke eine solche Stellung zum abzubauenden Deckgebirge oder zur Halde erhält, daß eine entsprechende Verteilung der gewonnenen Massen auf der Haldenseite durchgeführt werden kann. Das Neue besteht darin, «aß nur eine Stütze der Abraumförderbrücke einen Antrieb erhält und durch ein entsprechend dem abzubauenden Deckgebirge verlegtes Führungsgleis die planmäßige Verteilung der Massen auf der Haldenseite vorgesehen ist, :das der Gewinnung und Verteilung _entsprechend-Krümmungen oder Kurven erhält.Device for moving overburden conveyor bridges devices for Extraction, removal and falling of debris, especially in lignite mining using a clearing conveyor bridge, due to uneven thickness and irregular course of the .individual layers the distribution of the obtained Removal dimensions on the pile side. According to the previous proposals, this will be the result allows the two undercarriages of the bridge to operate at different speeds run, whereby a leading or a deceleration of the two ends is made possible. In the present case, such a diversity of speeds is pointed out the two ends are dispensed with by the trolleys by means of separate drives. It is A drive is only provided on one chassis, which drives the entire bridge uniform angular velocity granted. The position determined by the thickness the bridge is achieved in that a guide track is provided through which the bridge is in such a position to the overburden to be mined or to the dump, that a corresponding distribution of the masses obtained is carried out on the dump side can be. The novelty consists in “eating only one support of the overburden conveyor bridge receives a drive and is laid by a corresponding to the overburden to be mined The track provided the planned distribution of the masses on the dump side is: that receives curvatures or curves corresponding to the extraction and distribution.

Auf der Zeichnung ist in Abb. i, 2, 3, q. das Gelände dargestellt. Abb.5 und 6 zeig-en einen Plan des abzubauenden Deckgebirges mit Brücke und Gleisanlagen, Abb. 7, 8, 9 die Ausführungsform einer Brücke.On the drawing is in Fig. I, 2, 3, q. the terrain shown. Fig. 5 and 6 show a plan of the overburden to be dismantled with a bridge and track systems, Fig. 7, 8, 9 the embodiment of a bridge.

Durch die zeichnerische Ermittlung (Abb. i bis 3) des Flächen- und Massenprofils wird die Massenverteilung unter Berücksichtigung ;der Förderungsart- erleichtert. Die Seiten der Querschnitte (Abb. 2) werden als Längen auf den dem Längsschnitt (Abb.3) entsprechenden Ordinaten von der Gradienten x (Neigungslinie) nach .oben und nach unten (Ab- und Auftrag) aufgezeichnet, die Auftragsordinate im Verhältnis der Auflockerung verkleinert. Sodann sind die Flächenseiten des so entstandenen (Abb. q.) Flächenprofils die Massen; sie werden mit dem Planimeter ermittelt. Um nun die Verteilung z. B. durch den Ausleger einer Brücke vorzunehmen, wird das Flächenprofil (Flächeninhalt der Kurve mit der wagerechten Grundlinie) in Position A, B, C usw. (Abb. 5) so eingeteilt, daß beispielsweise Position C so viel Auftragmasse enthält, wie B bis zur Gradienten y benötigt. Die Positionen sind also so angelegt, daß der Ausgleich ihrer Massen in die Höhe der Gradlenten y fallen muß. Die Gradierte y (Abb. q.) wird dadurch bestimmt, daß möglichst die als Flächenprofil @da.rgestellten Massen über und unter ihr J,n der Flächensumme gleich sind. Das Verhältnis H C und H B gibt an, um wieviel die erstere gegenüber der anderen Stütze voreilen muß, um die Massen links (Abb.6) gleichmäßig zu verteilen. Während z. B. die Stütze rechts (Abb. 6) von a nach ß kommt, ist die Stütze links von y bis b in derselben Zeit zu bewegen im Verhältnis der zu verteilenden (von C nach B) Massen. Durch die Gerade a--f (bzw. ß-b) ist die Lage der auf einer starr verbundenen, stehenden Geradem f1, f2 und damit die jeweilige Richtung des Gleises vom. Führungsgleis zeichnerisch vor Beginn des Betriebes festgelegt. Nach solchem Gleisplan werden die Gleise im Betriebe gelegt. Sie geben der Brücke die- Führung, so daß die Massen am Ausleger auf gleichmäßige Höhe verteilt werden. Die Erklärung kann auch noch auf andere Weise gegeben werden, derart, daß die Verteilung der in der Position C vorhandenen Massen auf der Haldenseite nicht auf vier Felder erfolgt, sondern daß die Massen auf fünf Felder verstürzt werden, so daß die in der PositionB noch verbleibenden vier Felder der Deckgebirgsseite nur auf drei Felder der Haldenseite zur Verteilung gelangen..Through the graphical determination (Fig. I to 3) of the area and mass profile, the mass distribution is facilitated, taking into account the type of funding. The sides of the cross-sections (Fig. 2) are recorded as lengths on the ordinates corresponding to the longitudinal section (Fig. 3) from the gradient x (inclination line) to the top and bottom (removal and application), the application ordinate in relation to the loosening scaled down. Then the surface sides of the surface profile created in this way (Fig. Q.) Are the masses; they are determined with the planimeter. To now the distribution z. B. to be carried out by the boom of a bridge, the surface profile (area of the curve with the horizontal base line) is divided into positions A, B, C etc. (Fig. 5) so that, for example, position C contains as much coating material as B to required for gradient y. The positions are thus laid out in such a way that the compensation of their masses must fall at the level of the graduation y. The graded y (Fig. Q.) Is determined by the fact that the masses presented as the surface profile @ are equal above and below it J, n of the area sum. The ratio HC and HB indicates how much the former has to lead the other support in order to evenly distribute the masses on the left (Fig. 6). While z. B. If the support on the right (Fig. 6) comes from a to ß, the support on the left must be moved from y to b in the same time in relation to the masses to be distributed (from C to B). The straight line a - f (or ß-b) is the position of the rigidly connected, standing straight line f1, f2 and thus the respective direction of the track from. The guide track was drawn up before the start of operation. The tracks are laid in the company according to such a track plan. They give the bridge the lead so that the masses are distributed evenly on the boom. The explanation can also be given in another way, such that the distribution of the masses present in position C on the heap side does not take place over four fields, but that the masses are reduced to five fields, so that those still remaining in position B four fields on the overburden side can only be distributed on three fields on the dump side.

Die in Abb.7, 8, 9 dargestellte Brücke, welche die Verteilung der gewonnenen Massen vornehmen soll, ist in. drei Punkten a, b, c gelagert, wobei a und b die Endpunkte einer festen Geraden sind, d#e stets in festem Abstand zueinander liegen. Die Gerade a-b gibt der Brücke, die zu ihr im festen Winkel. und starr mit ihr in Verbindung steht, die Be- wegung, die Fahrtrichtung und in Ruhe und Bewegung die Lage im Raume an. Der Punkt c hat von der Geraden a-b keinen, festen Abstand; er stellt sich aber, da er zwangläufig durch das Brückengerüst mit -der Geraden a-b Verbindung hat und zugleich von allseitiger Gelenkigkeit in der Lagerung ist, auf jede beliebige, von der Geraden a-b in "Ruhe und Bewegung verlangte Lage im Raume so ein, :daß !er immer die Brückestützt. Die Antriebsstütze a, b ist links und die Manövrierstütze c ist rechts vorgesehen.The bridge shown in Fig. 7, 8, 9, which is supposed to distribute the masses obtained, is supported in three points a, b, c, where a and b are the end points of a fixed straight line, d # e always in fixed Distance to each other. The straight line from gives the bridge that to it at a fixed angle. and rigid movement, direction of travel and at rest and movement, the position in space is in touch with her to. The point c has no fixed distance from the straight line; But since it inevitably has a connection with the straight line through the bridge frame and at the same time is flexible in all directions, it adapts to any position in space required from the straight line in "rest and movement": that ! he always supports the bridge. The drive support a, b is provided on the left and the maneuvering support c is provided on the right.

Bei dem vorliegenden Beispiel ist die Wahl der Auslegerlänge derart bestimmt, -daß bei. nur auf dem Ausleger ruhender Last, z. B. bei größtem Drehmoment, in der Senkrechten für die Brücke kein Kippen erfolgt. Das durch die Gewichte der Lasten @erzeugte Reibungsgewicht wird dadurch größtenteils auf die Stütze a, b links gelenkt, so daß zweckmäßig der Antrieb der ganzen Brücke nur links an .der Stütze erfolgt, während Idie Stütze c links mitgezogen wird, also nur als Manövriierstütze dient. Sie paßt sich den Bewegungen der Brücke, die bestimmt sind durch die Lage der Geraden a, b der Stütze links im Raume, in Ruhe und Bewegung an, und zwar durch die allseitige Gelenkigkeit ihrer Lagerung. Die Stütze rechts ist in ihren Bewegungen nach links begrenzt durch einen Anschlag, damit sie nur bis zu dem Gewicht belastet wird, das sie verträgt, ohne in ihrer Konstruktion als Manövrierstütze schwerfällig zu werden oder die zum Antrieb der Brücke erforderliche Größe des Reibungsgewichtes zu vermindern.In the present example, the choice of the boom length is determined in such a way that at. only load resting on the boom, e.g. B. at maximum torque, no tilting occurs in the vertical for the bridge. The frictional weight generated by the weights of the loads @ is thereby largely directed to the support a, b on the left, so that the propulsion of the entire bridge is expediently only on the left of the support, while support c is pulled along on the left, i.e. only serves as a maneuvering support . It adapts to the movements of the bridge, which are determined by the position of the straight lines a, b of the column on the left in space, at rest and in motion, namely by the flexibility of its position on all sides. The right support is limited in its movements to the left by a stop so that it is only loaded up to the weight it can withstand without becoming cumbersome in its construction as a maneuvering support or reducing the amount of friction weight required to drive the bridge.

Claims (1)

PATEN TANSPRUCII Vorrichtung zum Bewegen von Abraumförderbrück en, dadurch gekennzeichnet, rlaß nur eiüe einzige Stütze der Abraumförderbrücke einen Bewegungsantrieb erhält und die verschiedenen Geschwindigkeiten der Enden der Abraumförderbrücke durch Kurven und Krümmungen der Fahrbahn erreicht werden, die planmäßig dem abzubauender und aufzuschüttenden Gelände angepaßt sind. PATEN TANSPRUCII Device for moving overburden conveyor bridges, characterized in that only a single support of the overburden conveyor bridge receives a movement drive and the different speeds of the ends of the overburden conveyor bridge are achieved through curves and curvatures of the roadway, which are systematically adapted to the terrain to be excavated and filled up.
DEK99528D 1926-06-19 1926-06-19 Device for moving overburden conveyor bridges Expired DE474969C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DEK99528D DE474969C (en) 1926-06-19 1926-06-19 Device for moving overburden conveyor bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEK99528D DE474969C (en) 1926-06-19 1926-06-19 Device for moving overburden conveyor bridges

Publications (1)

Publication Number Publication Date
DE474969C true DE474969C (en) 1929-04-20

Family

ID=7239176

Family Applications (1)

Application Number Title Priority Date Filing Date
DEK99528D Expired DE474969C (en) 1926-06-19 1926-06-19 Device for moving overburden conveyor bridges

Country Status (1)

Country Link
DE (1) DE474969C (en)

Similar Documents

Publication Publication Date Title
DE474969C (en) Device for moving overburden conveyor bridges
DE647402C (en) Hopper trolley to which the material to be conveyed is fed by a conveyor belt for distribution to three conveyors
EP3554912B1 (en) Transport system comprising a cable-drawn vehicle
DE1036743B (en) Device for the continuous production of prestressed concrete slabs with the help of automatic slab pavers
DE936979C (en) Mobile charger
DE617371C (en) Belt conveyor system fed by an excavator
DE1658532C3 (en) GuBasphalt installation device
DE456186C (en) Automatic control device for bucket chain excavators with caterpillar conveyor
DE452059C (en) Connection conveyor for overburden conveyor bridge systems
DE580360C (en) Open-cast mine with conveyor-connected open-cast mining equipment, which work on two slopes one behind the other in the mining direction
DE930198C (en) Movable conveyor belt element
DE217727C (en)
DE841280C (en) Crawler vehicle, especially excavator or similar heavy opencast mining equipment
DE850795C (en) Portal-like device for lifting, moving and depositing loads
DE622572C (en) Loading bridge
DE236370C (en)
DE437770C (en) Abraumfoerderbruecke
DE4222331C2 (en) Method and device for regulating the horizontal mass distribution of bulk material
DE472171C (en) Overburden conveyor bridge with raised lower chord on the excavator side and conveyor belt detached from the lower chord
DE1817603A1 (en) Conveyor device
DE928096C (en) Loading system for at least a three-track loading operation with only one loading cab
DE649586C (en) Device for securing and leveling heaps
DE1719336U (en) MOBILE CHARGER WITH TWO CONVEYOR CHANNELS.
DE424943C (en) Process for depositing the excavated material by means of an excavation conveyor bridge
DE513923C (en) Abraumfoerderbruecke