DE3048742A1 - Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling - Google Patents

Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling

Info

Publication number
DE3048742A1
DE3048742A1 DE19803048742 DE3048742A DE3048742A1 DE 3048742 A1 DE3048742 A1 DE 3048742A1 DE 19803048742 DE19803048742 DE 19803048742 DE 3048742 A DE3048742 A DE 3048742A DE 3048742 A1 DE3048742 A1 DE 3048742A1
Authority
DE
Germany
Prior art keywords
piling
welded
welding
sheet pile
connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
DE19803048742
Other languages
German (de)
Inventor
Volker von Dipl.-Ing. 8011 Vaterstetten Gottstein
Wolfgang Dipl.-Ing. 8000 München Roßner
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilit und Woerner Bau AG
Original Assignee
Heilit und Woerner Bau AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilit und Woerner Bau AG filed Critical Heilit und Woerner Bau AG
Priority to DE19803048742 priority Critical patent/DE3048742A1/en
Publication of DE3048742A1 publication Critical patent/DE3048742A1/en
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

Connecting media are welded on, in a process for providing temporary or permanent connection between sheet piling and concrete (5) under water. The connecting medium (2) or part of it, is joined to the sheet piling (1), by welding, above water, and lowered together with the sheet piling. The welded part may be supplemented by an additional part with screwing, plugging or clamping involved; or with contact involved. Such processes may partially or completely replace welding. Steel connection is provided without costly measures or elaborate controls involved in use of divers for welding.

Description

Bezeichnung: Verfahren zur Herstellung einer temporärenName: Method of making a temporary

oder dauernden Verbindung von Spundwänden mit Unterwasserbeton VERFAHREN ZUR HERSTELLUNG E@@R TEMPORA@@@ ODER DAUER@D@N VERBINDUNG VON SPUNDWÄNDEN MIT UNTRWASS@RBETON Die Erfindung betrifft die Herstellung einer temporären oder dauernden Verbindung von Spundwänden mit Unterwasserbeton, wobei das Verbindungsmittel oder ein Teil desselben ijber Wasser durch Schweißen mit der Spundwand verbunden und gemeinsam mit der Spundwand niedergebracht wird. Dabei kann die Schweißverbindung teilweise oder zur Gaze durch eine Steck-, Schraub-, Klemm-, Niet-, Press- oder Klebeverbindung ersetzt werden. or permanent connection of sheet pile walls with underwater concrete PROCEDURE FOR THE PRODUCTION OF E @@ R TEMPORA @@@ OR PERMANENT @ D @ N CONNECTION OF SHEET WALLS WITH UNDERWATER @ RBETON The invention relates to the establishment of a temporary or permanent connection of sheet piling with underwater concrete, the fastener or part The same is connected to the sheet pile wall by welding and shared by water is brought down with the sheet pile wall. The welded connection can be partially or to the gauze through a plug, screw, clamp, rivet, press or adhesive connection be replaced.

Bekanntlich müssen trogartige Bauwerke, die aus Spundwänden und einem unter Wasser eingebrachten, unmittelbar anschließenden Betonteil zusammengesetzt sind, so dimensioniert werden, daß sie den auf den Bauwerkstrog einwirkenden Auftriebskräften widerstehen.It is well known that trough-like structures made of sheet piling and a Immediately adjoining concrete part placed under water are, are dimensioned so that they the lifting forces acting on the building trough resist.

Reicht hierzu die Eigenlast des Betonteils sowie ggf. die Reibungskraft zwischen Betonteil und Spundwand nicht aus, so ist zwischen Spundwand und Betonteil eine Kraftschlüssige Verbindung herzustellen, wodurch erreicht wird, daß die zwischen Spundwand und Boden vorhandenen fleibungskräfte oder andere auf die Spundwand einwirkende vertikale Kräfte zur Auftriebssicherung des Gesamtbauwerks herangezogen werden können.The dead weight of the concrete part and, if applicable, the frictional force is sufficient for this between the concrete part and the sheet pile wall does not exist, so is between the sheet pile wall and the concrete part establish a force-fit connection, whereby it is achieved that the between Existing friction forces in the sheet pile wall and floor or other forces acting on the sheet pile wall vertical forces can be used to secure the entire structure against buoyancy.

Die Krafteinleitung vom Betonteil in die Spundwand erfolgt nach den bekannten Ausführungsformen über eine stählerne Verbindung, die unter Wasser durch Taucher anzuschweißen ist.The introduction of force from the concrete part into the sheet pile wall takes place according to the known embodiments via a steel connection that goes through under water Diver is to be welded.

Erfahrungsgemäß sind derartige Schweißarbeiten unter Wasser durch Taucher kostenaufwendig und zeitraubend und verursachen zur Sicherung der Tragfähigkeit und Dauerhaftigkeit der Schweißverbindung aufwendige Kontrollmaßnahmen.Experience has shown that such welding work is done under water Divers costly and time consuming and cause to secure the carrying capacity and durability of the welded joint, elaborate control measures.

Der Erfindung liegt nun die Aufgabe zugrunde, eine stählerne Verbindung von Spundwänden mit Unterwasserbeton herzustellen, welche ohne technische Schwierigkeiten, ohne wirtschaftliche Nachteile und ohne aufwendige Kontrollmaßnahmen, die das Unterwasserschweißen durch Taucher verursacht, bewerkstelligt wird.The invention is now based on the object of a steel connection of sheet piling with underwater concrete, which without technical difficulties, without economic disadvantages and without complex control measures that involve underwater welding caused by divers.

Diene Aufgabe wird durch die Erfindung dadurch gelöst, daß das Verbindungsmittel oder ein Teil desselben über Wasser an der Spundwand angebracht und gemeinsam mit der Spundwand niedergebracht wird.This object is achieved by the invention in that the connecting means or a part of it attached to the sheet pile wall above water and together with the sheet pile is being driven down.

Unterwasserarbeiten durch Taucher an der Verbindung selbst sind daher überflüssig oder beschränken sich auf einfache, ohne Schweißvorgang rasch und wirtschaftlich durchzuführende und einfach zu kontrollierende Arbeiten.Underwater work by divers on the connection itself is therefore necessary superfluous or limited to simple, without welding process quickly and economically work to be carried out and easy to control.

Nachstehend wird die Erfindung anhand einiger, in den Zeichnungen dargestellter, Ausführungsbeispiele näher erläutert: Es zeigen: Fig. 1 einen Vertikalsehnitt einer Spundwand mit angeschweißter stählerner Lamelle und darunter angeordnetem Auflagerriegel Fig. 2 einen Horizontalschnitt einer Spurdwand mit angeschweißten stählernen Stahllamellen und darunter angeordnetem Auflagerriegel Fig. 3 einen Vertikalschnitt einer Spundwand mit angeschweißter Gewindemuffe und eingedrehtem Ankerstab Fig. 4 einen Horizontalschnitt einer Spundwand mit angeschweißten Gewindemuffen und eingedrehten Ankerstäben An die in Figur 1 und 2 gezeigte Spundwand 1 werden vorzugsweise im Schloßbereich von Spundwandtülern Stahllamellen 2, 2' angeschweißt, die zur Aufnahme des Auflagerriegels 3 dienen, über welchen die Auftriebskräfte der Unterwasserbetonsohle in die Spundwand eingeleitet werden. Gezeigt ist eine temporäre Verbindung. Die Klammern 4, 4' dienen zur einfachen Führung, Zentrierung und Befestigung des Riegels 3 an den Stahllamellen 2, 2' vor und während des Einbringens des Unterwasserbetons 5.The invention is illustrated below with reference to some in the drawings The illustrated exemplary embodiments are explained in more detail: FIG. 1 shows a vertical section a sheet pile wall with welded-on steel lamella and an underneath Support bar Fig. 2 shows a horizontal section of a track wall with welded-on steel lamellas and support bar arranged underneath Fig. 3 is a vertical section a sheet pile wall with welded-on threaded sleeve and screwed-in tie rod Fig. 4 a horizontal section of a sheet pile wall with welded-on threaded sockets and screwed-in Tie rods to the sheet pile wall 1 shown in Figures 1 and 2 are preferably in Lock area of sheet pile wall sleeves, steel lamellae 2, 2 'welded on, which are used for receiving of the support bar 3 are used, via which the buoyancy forces of the underwater concrete floor be introduced into the sheet pile wall. A temporary connection is shown. the Brackets 4, 4 'are used for simple guidance, centering and fastening of the bolt 3 on the steel lamellas 2, 2 'before and during the introduction of the underwater concrete 5.

An die in Figur 3 und 4 gezeigte Spundwand 1 werden stählerne Muffen 6, 6' angeschweißt, die durch Ankerstäbe 7, 7' ergänzt werden. Gegen Verschmutzen durch Eindringen von Bodenteilen beim Vorgang des Niederbringens sind die Muffen 6, 6' durch Abdeckkappen 8, 8' geschützt. Gezeigt ist eine dauernde Verbindung.Steel sleeves are attached to the sheet pile wall 1 shown in FIGS. 3 and 4 6, 6 'welded on, which are supplemented by tie rods 7, 7'. Against soiling due to the penetration of soil parts during the process of lowering, the sleeves are 6, 6 'protected by cover caps 8, 8'. A permanent connection is shown.

Die Erfindung wird durch die gezeigten Ausführungsarten nur beispielhaft erläutert und nicht auf die Ausführungsbeispiele beschränkt. Beispielsweise kann die in Figur 3 und 4 gezeigte Schraubverbindung durch eine Steckverbindung ersetzt werden.The embodiments shown are only exemplary of the invention explained and not limited to the exemplary embodiments. For example, can the screw connection shown in Figure 3 and 4 is replaced by a plug connection will.

LeerseiteBlank page

Claims (4)

PATENTANSPRÜCHE 1. Verfahren zur Herstellung einer temporären oder dauernden Verbindung von Spundwänden mit Unterwasserbeton durch angeschweißte Verbindungsmittel, dadurch gekennzeichnet, daß das Verbindungsmittel oder ein Teil desselben iiber Wasser durch Schweißen mit der Spundwand verbunden und gemeinsam mit der Spundwand niedergebracllt wird.PATENT CLAIMS 1. Method for producing a temporary or permanent connection of sheet pile walls with underwater concrete using welded-on fasteners, characterized in that the connecting means or a part thereof over Water connected to the sheet pile wall by welding and shared with the sheet pile wall being beaten down. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß das angeschweißte Teil unter Wasser durch ein zusätzliches Teil mit einer Schraub-, Steck- oder Klenunvorrichtung ergänzt wird.2. The method according to claim 1, characterized in that the welded Part under water with an additional part with a screw, plug or Klenun device is supplemented. 3. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß das angeschweißte Teil unter Wasser durch ein zusätzliches Teil durch Kontakt ergänzt wird.3. The method according to claim 1, characterized in that the welded Part under water is supplemented by an additional part through contact. 4. Verfahren nach Anspruch 1 bis 3, dadurch gekennzeichnet, daß die Schweißverbindung teilweise oder zur Gänze durch eine Steck-, Schraub-, Klenm-, Niet-, Prcss- oder Klebeverbindung ersetzt wird.4. The method according to claim 1 to 3, characterized in that the Part or all of the welded connection by means of a plug-in, screw, clamp, Riveted, Prcss or glued connection is replaced.
DE19803048742 1980-12-23 1980-12-23 Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling Ceased DE3048742A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19803048742 DE3048742A1 (en) 1980-12-23 1980-12-23 Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19803048742 DE3048742A1 (en) 1980-12-23 1980-12-23 Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling

Publications (1)

Publication Number Publication Date
DE3048742A1 true DE3048742A1 (en) 1982-07-22

Family

ID=6120114

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19803048742 Ceased DE3048742A1 (en) 1980-12-23 1980-12-23 Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling

Country Status (1)

Country Link
DE (1) DE3048742A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866801A (en) * 2014-03-28 2014-06-18 上海绿地建设(集团)有限公司 Steel sheet pile 'pass muster' device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE6609772U (en) * 1968-05-24 1972-09-21 Heilmann & Littmann Bau Ag COMPONENT FOR THE PRODUCTION OF SLOTTED OR DRILLED PILE WALLS.
DE1634372B2 (en) * 1966-04-05 1974-02-28 Bernt Hjalmar Goeteborg Gerde (Schweden) Shallow foundations for buoyant structures

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1634372B2 (en) * 1966-04-05 1974-02-28 Bernt Hjalmar Goeteborg Gerde (Schweden) Shallow foundations for buoyant structures
DE6609772U (en) * 1968-05-24 1972-09-21 Heilmann & Littmann Bau Ag COMPONENT FOR THE PRODUCTION OF SLOTTED OR DRILLED PILE WALLS.

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866801A (en) * 2014-03-28 2014-06-18 上海绿地建设(集团)有限公司 Steel sheet pile 'pass muster' device

Similar Documents

Publication Publication Date Title
DE60309116T2 (en) Construction for buildings and methods of making same
DE1951223A1 (en) Insert
DE2838658A1 (en) CONTAINER WITH A TENSIONED WALL IN THE CIRCUMFERENCE, COMPOSED OF PANEL-SHAPED CONCRETE ELEMENTS
DE2656178A1 (en) DEVICE FOR CONNECTING PONTONS
DE2920165A1 (en) DEVICE FOR SEALING CYLINDRICAL PIPES AND THE like.
DE2261265C3 (en) Plate holder for membranes for fluid separators
DE1659343B1 (en) Device for attaching thermal insulation panels made of compressible material and used as roof covering
DE2622991C3 (en) Device for driving underwater piles and methods of their use
DE3048742A1 (en) Joining sheet piling to underwater concrete - involves first welding connectors above water and submerging with piling
DE1586449C3 (en) Process for producing tear lines on metal container lids
DE2354172A1 (en) Anchoring for preventing buoyancy lift of structures - uses temporary tensioning members operated above ground water level
DE3122032C2 (en) Process for the subsequent anchoring of sheet pile walls, as well as a mounting device for a drilling device and anchor pile for carrying out the process
DE2325371A1 (en) PROCEDURE FOR ALIGNING THE EDGES OF TWO PLATES
DE3443451C1 (en) Apparatus for installing a support
DE2922567A1 (en) FASTENING ELEMENT WITH ANCHOR BOLT AND SPREAD
DE2439905B2 (en) Device for attaching a precast concrete part to a hoist
DE3110920C2 (en) Method for anchoring the bottom of an underwater structure against buoyancy
DE2948879C2 (en) Process for the production of in-situ concrete driven piles
DE2847885A1 (en) MOUNTING PLATE WITH SUPPORTING HOLDING PARTS FOR THE HEATING PIPES OF A FLOOR HEATING
DE2811431C3 (en) Overhead line mast
DE4013806C1 (en) Open tunnel construction - comprises longitudinal corrugated profiled sections with sheet walling and roofing sections
DE1684439B2 (en) PROCESS FOR INSERTING FILLER INTO FINE CRACKS OF BUILDINGS AND INJECTOR FOR CARRYING OUT THE PROCESS
DE2618330A1 (en) CONTAINER OF PRE-FABRICATED PARTS WITH DEVICES FOR SEALING THE PARTS AND METHOD FOR PERFORMING THE SEALING
DE2140304C3 (en) Method and device for connecting a pipe string to an underwater station
DE188118C (en)

Legal Events

Date Code Title Description
8110 Request for examination paragraph 44
8120 Willingness to grant licences paragraph 23
8131 Rejection