DE2904236A1 - Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles - Google Patents

Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles

Info

Publication number
DE2904236A1
DE2904236A1 DE19792904236 DE2904236A DE2904236A1 DE 2904236 A1 DE2904236 A1 DE 2904236A1 DE 19792904236 DE19792904236 DE 19792904236 DE 2904236 A DE2904236 A DE 2904236A DE 2904236 A1 DE2904236 A1 DE 2904236A1
Authority
DE
Germany
Prior art keywords
joints
edges
tiles
tool
plastic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19792904236
Other languages
German (de)
Inventor
Host Eiskirch
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SECUPLAN BELAGTECHNIK GmbH
Original Assignee
SECUPLAN BELAGTECHNIK GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SECUPLAN BELAGTECHNIK GmbH filed Critical SECUPLAN BELAGTECHNIK GmbH
Priority to DE19792904236 priority Critical patent/DE2904236A1/en
Publication of DE2904236A1 publication Critical patent/DE2904236A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • E04F15/14Construction of joints, e.g. dividing strips
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/165Implements for finishing work on buildings for finishing joints, e.g. implements for raking or filling joints, jointers

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Road Paving Structures (AREA)

Abstract

Edges of expansion gaps an industrial floors are protected by a reinforced plastic cement. Floor is laid on a concrete base with expansion gaps at intervals. Over this is laid a covering e.g. in plastic. To allow for expansion but at the same time to protect the edges, the gap is filled with a plastic or synthetic resin with a steel filler for reinforcement. A polythene insert is fitted into the gap, and the joint is then made using a special tool which projects down into the slot. For use on industrial floors. Gives improved life to the floor by reducing wear and damage due to passage of trucks etc with metal wheels.

Description

1. wortgetreue Abschrift der Beschreibung und Patenan-1. Verbatim copy of the description and sponsorship

sprüche Verfahren zur Herstellung von standfesten- und geradlinigverlaufenden Fugenkanten Böden für Industriebauten bestehen in der Regel aus einem Betonunterbau und einem darübergelegten Estrich. Zur Vermeidung von Hissbildung werden diese Böden in bestimmten Abständen mit Trennfugen versehen, die sowohl den Estrich, wie auch den Unterbau durchziehen.Proverbs Process for the production of stable and straight joint edges Floors for industrial buildings usually consist of a concrete substructure and a screed placed on top. To avoid the formation of cracks, these floors are provided with separating joints at certain intervals, which run through both the screed and the substructure.

Die Kanten im Estrich bröckeln aber unter der Verkehrsbeanspruchung - z.B. darüberrollende Eisenräder von Transportkarren - rasch ab.However, the edges in the screed crumble under traffic - E.g. iron wheels from trolleys rolling over them - quickly.

Diessieht zunächst einmal unschön aus. Durch die dann immer breiter werdenden Trennfugen entsteht zudem eine erhebliche Verkehrsgefahr z.B. können Lasten vom Stapler fallen.At first glance, this looks ugly. Because of that, it becomes wider and wider The resulting separating joints also create a significant traffic hazard, e.g. loads fall off the truck.

Um dies zu vermeiden wurden die Kanten schon mit Metallschienen armiert, die mit Schrauben oder Bolzen im Betonunterbau befestigt sind, Im Laufe der Zeit lockern sich jedoch die Metailschienen.To avoid this, the edges have already been reinforced with metal rails, which are fastened with screws or bolts in the concrete substructure, Over time however, the metal rails loosen.

Dies führt wieder zu neuen Unzuträglichkeiten.This again leads to new inconveniences.

Die Erfindung will diesen Nachteil bei Fugenkanten von Böden für Industriebauten mit einem Unterbau aus Beton und darübergelegter Estrichauflage und in gewissen Abständen angeordneten Fugen zum Dehungsausgleich, dadurch vermeiden, daß im Estrich und im Betonunterbau angeordnete Fugen mit einem Kunststoff oder Kunstharzmörtel oder einem anderen, geeigneten Werkstoff von hoher Kantenfestigkeit innig und untrennbar verbunden bzw. armiert sind. Der gegenüberdem normalen Estrich außerordentlich feste Kunststoff hält an den Kanten die Verkehrsbelastung aus, kann sich gleichzeitig, im Gegensatz zu Metallschienen, infolge seines innigen Verbundes mit dem Beton, nicht losrütteln.The invention aims to address this disadvantage in joint edges of floors for industrial buildings with a substructure made of concrete and overlaid with a screed layer and in certain Spaced joints to compensate for expansion, thereby avoiding that in the screed and joints arranged in the concrete substructure with a plastic or synthetic resin mortar or another suitable material with high edge strength intimately and inseparably are connected or reinforced. The extremely solid compared to the normal screed Plastic can withstand the traffic load at the edges, but can at the same time, in contrast to metal rails, due to its close bond with the concrete, do not shake loose.

Nach einem weiteren Vorschlag der Erfindung sind in dem zur Armierung dienenden Kunststoffmörtel in demselben verteilte Einlagen aus Sahlfasern und Elektrocorundkörnung eingearbeitet.According to a further proposal of the invention are in the for reinforcement serving plastic mortar in the same distributed deposits of steel fibers and electrocorundum grain incorporated.

Dies trägt zu einer weiteren Erhöhung der Kantenfestigkeit bei. Dadurch werden horizontal und vertikal auftreffende Lasten elastisch abgefangen.This contributes to a further increase in edge strength. Through this horizontally and vertically impacting loads are elastically absorbed.

uie Herstellung der Fugenkanten erfolgt dadurch, daß zu ihrer Herstellung ein hobel- oder schlittenartigen Werkzeug vorgesehen ist, das in Längsrichtung mit einem auswechselbaren Steg zur Fixierung der Fugenbreite und beiderseitig desselben mit auswechselbaren und festklemmbaren Höhenfixi-ersteren versehen ist Der schwertartige Steg erzeugt beim Durchziehen des Werkzeuges die Fugen im Kunststoffmörtel, während die seitenverschiebbaren Höhenfixierstege die Breite des Kunststoff-Mörtelbereiches bestimmen.uie production of the joint edges takes place in that for their production a plane or slide-like tool is provided, which in the longitudinal direction with an exchangeable bar to fix the joint width and on both sides of the same The sword-like is provided with exchangeable and clampable height fixtures-the former Steg creates the joints in the plastic mortar when the tool is pulled through, while the laterally adjustable height fixing bars the width of the plastic mortar area determine.

Weiterhin ist vorgesehen, daß zur Längsführung des schlittenartigen Werkzeuges in Längsrichtung ein- oder beiderseitig Führungsbalken angeordnet sind, die nach Fertigstellung wieder entfernt werden.It is also provided that for the longitudinal guidance of the slide-like Tool are arranged in the longitudinal direction on one or both sides guide bars, which will be removed after completion.

Auf diese Weise ist die geradli nige Führung des Werkzeuges gewährleistet. Zur Ersparnis teuren Kunststoffmörtels sind in der kuge des Betonunterbaues PE-Vorfüllprofile eingelegt.In this way, the rectilinear guidance of the tool is guaranteed. To save on expensive plastic mortar, there are PE pre-fill profiles in the corner of the concrete substructure inserted.

Andernfalls würde der Kunststoffmörtel bis auf denGrund des Bekannterbaues durchlaufen.Otherwise the plastic mortar would down to the reason of the familiar building run through.

Die Zeichnungen zeigen ein Ausführungsbeispiel der Erfindung.The drawings show an embodiment of the invention.

Es bedeuten: Figur 1: ein Querschnitt durch einen fertigen Fußboden mit en armierten Fugenkanten Figur 2: einen Querschnitt durch den Fußboden im Augenblick der Herstellung mit dem erfindungsgemäßen Werkzeug.It denotes: FIG. 1: a cross section through a finished floor with reinforced joint edges Figure 2: a cross-section through the floor at the moment the production with the tool according to the invention.

Figur 3: eine Seitenansicht des Werkzeuges.Figure 3: a side view of the tool.

Figur 4: eine Draufsicht auf das Werkzeug in Richtung des Pfeiles A von Figur 3.FIG. 4: a plan view of the tool in the direction of the arrow A of Figure 3.

Figur 5: eine Draufsicht auf das Werkzeug in Richtung des Pfeiles B von Figur 3.FIG. 5: a plan view of the tool in the direction of the arrow B of Figure 3.

Figur 6: einen Schnitt durch das Werkzeug nach der gestrichelten Linie D-D und Blickrichtung in Richtung des Pfeiles C von Figur 3.FIG. 6: a section through the tool along the dashed line D-D and viewing direction in the direction of arrow C in FIG. 3.

In Figur 1 ist 1 der Betonunterbau mit der Fuge 2 und dem Estrich 3 mit der Fuge 4, in der sich der zur Armierung diene Kunststoffmörtel 5 befindet.In Figure 1, 1 is the concrete substructure with the joint 2 and the screed 3 with the joint 4, in which the plastic mortar 5 is used for reinforcement.

In dem Kunststoffmörtel 5 befindet sich noch das PE-Vorfüllprofil 8. Mit 9 sind in dem Kunststoffmörtel verteilte ioage aus Stahlfasern und Korundkörnung bezeichnet.The PE pre-fill profile is still located in the plastic mortar 5 8. With 9 ioage of steel fibers and corundum grains are distributed in the plastic mortar designated.

10 ist ein zur Herstellung der Fugen 6 dienendes hobel- oder schlittenartiges Werkzeug, das aus Metall oder Kunststoff gefertigten sein kann, mit dem seitenverschiebbaren Höhenfixiersteg 1 und dem schwertartigen Steg 12.10 is a plane or sled-like one used to produce the joints 6 Tool, which can be made of metal or plastic, with the side-shiftable Height fixing web 1 and the sword-like web 12.

13 sind Führungsbalken zur geradlinigen Führung des Werkzeuges 10.13 are guide bars for guiding the tool 10 in a straight line.

14 steilen Flügelschrauben dar zum festklemmen der seitlich Verschiebbaren Höhenfixierstege 11, während der schwertartige Steg 12 mit der Flügelschraube 15 befestigt wird.14 steep wing screws are used to clamp the laterally movable ones Height fixing webs 11, while the sword-like web 12 with the wing screw 15 is attached.

Der Schlitten 10 trägt den Handgriff 16.The carriage 10 carries the handle 16.

Die Höhenfixierstege 11 sind in Schlitzen 17, die sich im Werkzeug @@ befinden, seitlich verschiebbar angeordnet.The height fixing webs 11 are in slots 17 in the tool @@ are located, arranged to be laterally displaceable.

18 ist die Schubrichtung des Werkzeuges 10.18 is the thrust direction of the tool 10.

Wirkungsweise: Zunächst wird der Betonunterbau 1 mit der Fuge 2 in bekannter weise gefertigt, in die dann das PE-Vorfüllprofil 8 eingelegt wird, Sodann werden auf dem Betonunterbau 1 die Führungsbalken 13 fixiert.How it works: First, the concrete substructure 1 with the joint 2 in manufactured in a known manner, in which the PE pre-fill profile 8 is then inserted, then the guide bars 13 are fixed on the concrete substructure 1.

Dann wird Lir Saum zwischen den Höhenfixierstegen 11 und dem Vorfüllprofil 8 mit Kunststoffmörtel 5 ausgefüllt. Sodann wird das Werkzeug 10 an den Führungsbalken 13 geführt und das Werkzeug 10 in Schubrichtung 18 längs verschoben.Then the Lir hem between the height fixing webs 11 and the pre-fill profile 8 filled with plastic mortar 5. The tool 10 is then attached to the guide bar 13 and the tool 10 is moved longitudinally in the thrust direction 18.

Der schwertartige Steg 12 drückt sich dabei in das weiche PE-Vorfüllprofil 8 hinein. Durch diese Längsverschiebung verdrängt ;n - gerundete1 schwertartige Steg 12 den Kunst-Stoffmörtel 5 und erzeugt so die Fuge 6.The sword-like web 12 is pressed into the soft PE pre-fill profile 8 in. Displaced by this longitudinal shift; n - rounded1 sword-like Web 12 the synthetic fabric mortar 5 and thus creates the joint 6.

Nach Herstellung der Fuge 6 wird das Werkzeug 10 aus dem Kunststoffmörtel 5 herausgehoben und die Führungsbalken 12 entfernt.After the joint 6 has been produced, the tool 10 is made from the plastic mortar 5 lifted out and the guide bar 12 removed.

Nach der Erhärtung des Kunststoffmörtels 5 wird der Estrich 3 angearbeitet.After the plastic mortar 5 has hardened, the screed 3 is applied.

Die Erfindung bezieht sich nicht nur auf das beschriebene Ausführungsbeisiel' sondern umfaßt auch alle anderen nach dem gleichen Prinzip arbeitenden Herstellungsweisen von armierten Bugensranten.The invention relates not only to the exemplary embodiment described but also includes all other manufacturing methods that work according to the same principle of reinforced bow rims.

L e e r s e i t eL e r s e i t e

Claims (5)

Patentansprüche 1.)Fugenkanten von Böden für Industriebauten mit einem Unterbau aus Beton mit darübergelegter Estrichauflage und in gewissen Abständen angeordneten Fugen zum Dehnungsausgleich, dadurch gekennzeichnet, daR die in Estrich und im Beton-Unterbau angeordneten Fugen (2) mit einem Kunststoff- oder Kunstharzmörtel oder einem anderen geeigneten Werkstoff (5) von hoher Kantenfestigkeit innig und untrennbar verbunden bzw. armiert sind. Claims 1.) Joint edges of floors for industrial buildings with a concrete substructure with a screed layer on top and at certain intervals arranged joints for expansion compensation, characterized in that the in screed and joints (2) arranged in the concrete substructure with a plastic or synthetic resin mortar or another suitable material (5) with high edge strength and intimately are inseparably connected or reinforced. 2. Fugenkanten nach Anspruch 1, dadurch gekennzeichnet, daß der zur Armierung dienende Kunststoffmörtel (5) mit in demselben verteilten Einlagen (9) aus Stahlfasern und eine elastische Elektrokorund-Körnung eingearbeitet sind.2. joint edges according to claim 1, characterized in that the for Reinforcement plastic mortar (5) with inserts (9) distributed in the same made of steel fibers and an elastic corundum grain are incorporated. 3. Fugenkanten nach uem ansprüchen 1 und 2, dadurch gekenn zeichnet, daß zu ihrer Herstellung ein hobel- oder schlittenartiges Werkzeug (10) vorgesehen ist das in Längsrichtung mit einem auswechselbaren, schwertartigen Steg (12) und beiderseitig desselben mit auswechselbaren und festklemmbaren Höhenfixierstegen (11) versehen ist.3. Joint edges according to uem claims 1 and 2, characterized in that that a plane or slide-like tool (10) is provided for their production is that in the longitudinal direction with an exchangeable, sword-like web (12) and Both sides of the same with exchangeable and clampable height fixing bars (11) is provided. 4. Fugenkanten nach den Ansprüchen 1-3, dadurch gekennzeichnet, daß zur Längsführung des schlittenartigen Werkzeuges (10) in Längsrichtung ein oder,beiderseitig Führungsbalken (13) angeordnet sind, die nach Fertigstellung wieder entfernt werden. 4. joint edges according to claims 1-3, characterized in that for longitudinal guidance of the slide-like tool (10) in the longitudinal direction one or both sides Guide bars (13) are arranged, which are removed again after completion. 5. Fugenkanten nach den Ansprüchen 1-4, dadurch gekennzeichnet, daß das Werkzeug (10) mit einem Handgriff (16) versehen ist.5. joint edges according to claims 1-4, characterized in that the tool (10) is provided with a handle (16).
DE19792904236 1979-02-05 1979-02-05 Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles Withdrawn DE2904236A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19792904236 DE2904236A1 (en) 1979-02-05 1979-02-05 Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19792904236 DE2904236A1 (en) 1979-02-05 1979-02-05 Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles

Publications (1)

Publication Number Publication Date
DE2904236A1 true DE2904236A1 (en) 1980-08-07

Family

ID=6062164

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19792904236 Withdrawn DE2904236A1 (en) 1979-02-05 1979-02-05 Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles

Country Status (1)

Country Link
DE (1) DE2904236A1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4875802A (en) * 1988-09-07 1989-10-24 The Edward W. Face Co., Inc. Installational concrete joint insert and method of preventing edge spalling
EP0833020A1 (en) * 1996-09-30 1998-04-01 Jürgen Schmidt Device for the establishment of a defined joint as predetermined breaking point between two plates of floor cement and use of the device
DE10002866A1 (en) * 2000-01-24 2001-08-16 Reiner Ulbrich Joint gap filling profile for floors serving for air cushion transport has a vertical section extending into the joint gap, and a horizontal section filling the top broadened zone of the joint gap
EP1489247A1 (en) * 2003-06-09 2004-12-22 Lutz Keidel Flexible sealants repellant tool
EP2098651A2 (en) 2008-03-03 2009-09-09 SK Wiegrink Beteiligungs GmbH Joint sealing profile and method for its production
US20170321432A1 (en) * 2016-05-06 2017-11-09 Sk Wiegrink Beteiligungs Gmbh Joint Filling Profile

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4875802A (en) * 1988-09-07 1989-10-24 The Edward W. Face Co., Inc. Installational concrete joint insert and method of preventing edge spalling
EP0833020A1 (en) * 1996-09-30 1998-04-01 Jürgen Schmidt Device for the establishment of a defined joint as predetermined breaking point between two plates of floor cement and use of the device
DE10002866A1 (en) * 2000-01-24 2001-08-16 Reiner Ulbrich Joint gap filling profile for floors serving for air cushion transport has a vertical section extending into the joint gap, and a horizontal section filling the top broadened zone of the joint gap
DE10002866B4 (en) * 2000-01-24 2008-02-07 Sk Wiegrink Beteiligungs Gmbh Method for producing a joint filling profile
EP1489247A1 (en) * 2003-06-09 2004-12-22 Lutz Keidel Flexible sealants repellant tool
EP2098651A2 (en) 2008-03-03 2009-09-09 SK Wiegrink Beteiligungs GmbH Joint sealing profile and method for its production
DE102008012302A1 (en) 2008-03-03 2009-09-10 Sk Wiegrink Beteiligungs Gmbh Joint filling profile and method for its production
US20170321432A1 (en) * 2016-05-06 2017-11-09 Sk Wiegrink Beteiligungs Gmbh Joint Filling Profile
US10577806B2 (en) * 2016-05-06 2020-03-03 Sk Wiegrink Beteiligungs Gmbh Joint filling profile

Similar Documents

Publication Publication Date Title
DE2733011C3 (en) Fastening device for rails for arrangement on a rail pad
DE2362732A1 (en) DEWATERING DEVICE FOR THE SCREEN OR FELT PART OF A FABRIC DRAINING MACHINE AND PROCESS FOR ITS MANUFACTURING
DE2347636A1 (en) Road tarmac, or permanent way construction - has ribs in longitudinal direction with reinforcement forming trapeze and shock absorbing layer
DE1759903A1 (en) Process and machine for the production of elongated concrete objects
EP0428762A1 (en) Slab-shaped paving element
DE2904236A1 (en) Fixing industrial plastic tiles onto concrete base - using reinforced plastic cement in joints to allow for expansion and to protect the edges of the tiles
DE4400807C2 (en) Machine arrangement and method for stuffing a track
DE2614036A1 (en) EQUIPMENT FOR MANUFACTURING PRE-FABRICATED ELEMENTS FROM STRENGTHENED CONCRETE WITH IMMEDIATE BONDING
DE2257768A1 (en) PLANT FOR PRODUCING PRE-FABRICATED CONCRETE PARTS
DE3587713T2 (en) Pull-off track.
EP1022386A2 (en) Method for fixing a railway track on supporting slabs of a substructure, as well as an apparatus and shuttering for applying this method
DE10133607B4 (en) Method and pallet for producing a precise precast concrete part
DE10311894B4 (en) Covering consisting of individual plates made of mineral material
DE19848655B4 (en) Renovation of slab tracks
EP1371781A1 (en) Modular station platform system
DE9114733U1 (en) Kit for a drainage channel
DE10246898A1 (en) Adjustment assembly for the rails of a railroad permanent way, laid on divided sleeper blocks, has a lateral bar structure between the rails with adjustment screw bolts for rail alignment and height setting
DE3047650A1 (en) METHOD AND DEVICE FOR PRODUCING A CONCRETE PANEL
DE1683943C3 (en)
DE10064748B4 (en) Method and device for correcting the position of a slab construction made of precast concrete slabs
EP1378618A2 (en) Apparatus for forming an accurate screeding profile
DE1658445C (en) Joint formation for road pavement and process for their manufacture
DE29712510U1 (en) Device for generating a predetermined breaking point
DE1658445B1 (en) Joint training for road surfaces and processes for their production
DE679649C (en) Permanent joint insert, especially for concrete pavements

Legal Events

Date Code Title Description
8139 Disposal/non-payment of the annual fee