DE2721050B2 DE19772721050 DE2721050A DE2721050B2 DE 2721050 B2 DE2721050 B2 DE 2721050B2 DE 19772721050 DE19772721050 DE 19772721050 DE 2721050 A DE2721050 A DE 2721050A DE 2721050 B2 DE2721050 B2 DE 2721050B2
Authority
DE
Germany
Prior art keywords
strands
compensator
length
arrangement according
changes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
DE19772721050
Other languages
German (de)
Other versions
DE2721050C3 (en
DE2721050A1 (en
Inventor
Franz 7530 Pforzheim Buchauer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Witzenmann GmbH
Original Assignee
Witzenmann GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Witzenmann GmbH filed Critical Witzenmann GmbH
Priority to DE19772721050 priority Critical patent/DE2721050C3/en
Publication of DE2721050A1 publication Critical patent/DE2721050A1/en
Publication of DE2721050B2 publication Critical patent/DE2721050B2/en
Application granted granted Critical
Publication of DE2721050C3 publication Critical patent/DE2721050C3/en
Expired legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L51/00Expansion-compensation arrangements for pipe-lines

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Electric Cable Arrangement Between Relatively Moving Parts (AREA)
  • Manipulator (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Description

realisiert.realized.

Im einfachsten Fall können die Leitungsstränge an den Umlenkpunkten ein Drehgelenk aufweisen, beispielsweise derart, daß der dem Drehgelenk zulaufende Leitungsstrang gegenüber dem ablaufenden Leitungsstrang senkrecht zur Schwenkebene versetzt und die beiden Stränge durch eine Schwenkverbindung miteinander verbunden sind. Dabei wechselt der Leitungsstrang bei jedem Drehgelenk die Fließebene. In the simplest case, the cable strands can have a swivel joint at the deflection points, for example in such a way that the line loom running towards the swivel joint is opposite to the running line loom offset perpendicular to the swivel plane and the two strands with each other by a swivel connection are connected. The cable harness changes the flow level at each swivel joint.

Für höhere Beanspruchungen, insbesondere hinsieht- w lieh der Betriebsdrücke, ist es zweckmäßig, wenn die Leitungsstränge an den Umlenkpunkten einen Balg aufweisen. Ein Versatz des zulaufenden gegenüber dem ablaufenden Leitungsstrang erübrigt sich hierbei, so daß jeder Leitungssirang innerhalb einer Ebene verläuft und ι "> die Umlenkverluste geringer werden. Besonders günstig ist hierbei die Verwendung von Angularkompensatoren. Denn bei ihnen werden die aus dem Innendruck resultierenden Zugkräfte direkt vom Gelenk aufgenommen. Er ist dadurch für besonders hohe innendruckbe- -?<> anspruchung geeignet. Außerdem hat die erfindungsgemäßc Aufteilung in zwei oder mehr Leitungsstränge bei Verwendung von Balgkompensatoren den Vorteil, daß die "erkleinerung auf querschnittsgleiche Kompensatordurchmesscr deren Winkelbeweglichkeit übcrpro- .'"> portional erhöht.For higher loads, especially looking w borrowed the operating pressures, it is useful if the line strands at the deflection points a bellows exhibit. An offset of the incoming compared to the outgoing cable harness is unnecessary here, so that each line sirang runs within a level and ι "> the deflection losses are lower. The use of angular expansion joints is particularly favorable here. Because with them, the tensile forces resulting from the internal pressure are absorbed directly by the joint. This makes it suitable for particularly high internal pressure loads. In addition, the invention c Division into two or more strands when using bellows expansion joints the advantage that the "reduction to compensator diameters of the same cross-section their angular mobility is increased proportionally.

Zur Herstellung der Schwenkverbindung an den Kreuzungspunkten von zueinander spicgc bildlichen Leitungssträngen empfiehlt es sich, die beiden Stränge senkrecht zur Schwenkebene um zumindest den «> Durchmesser eines Leilungsstranges gegeneinander zu versetzen, d. h, den Strang als Ganzes zu versetzen, so daß sich keine Erhöhung der Umlenkstellen ergibt. Zur Schwcnklagerung bedarf es lediglich eines in der Schwenkebene angeordneten Bolzens, der an beiden r> Leitungssträngen geführt ist.To produce the pivotal connection at the crossing points of mutually spicgc pictorial strands of wire it is recommended that the two strands perpendicular to the pivoting plane by at least a «> diameter to enable a Leilungsstranges against each other, d. That is, to move the strand as a whole, so that there is no increase in the deflection points. All that is required for pivoting is a bolt arranged in the pivot plane, which is guided on both cable strands.

Um ein Durchhängen der Leitungssträngc /u vermeiden, ist es günstig, sie an den Umlcnkpunktcn und/oder Knuzungspunkten abzustützen. Dies kann insbesondere durch horizontal verschiebbare Stützen, ■"' beispielsweise in Form von Gleitlagern erfolgen.To prevent sagging of the strand c / u avoid it, it is beneficial to keep them at the turning points and / or support points of connection. This can be achieved in particular by horizontally displaceable supports, ■ "' take place, for example, in the form of plain bearings.

Als Festpunkt der Kompensatoranordnung fungiert zweckmäßigerweise ein endständiger Kreuzungspunkt mit einer sich anschließenden Weiche, durch welche die Rohrleitung in die beiden spiegelbildlich verlaufenden ir> Stränge aufgeteilt wird. Damit auch die an die Weiche angeschlossenen Leitungsstränge an der Kompensationsbewegung teilnehmen können, sind sie jeweils über eine elastische Verbindung an die Weiche angeschlossen. As a fixed point of the compensator advantageously acts a terminal point of intersection with a subsequent switch through which the pipe is divided into two mirror image extending i r> strands. So that the cable strands connected to the switch can also participate in the compensation movement, they are each connected to the switch via an elastic connection.

Sind besonders lange Transportleitungen zu kompensieren, empfiehlt es sich, zwei Scherenanordnungen hintereinander zu schalten und den Festpunkt dazwischen zu legen.If particularly long transport lines are to be compensated, it is advisable to use two scissor arrangements to switch one after the other and place the fixed point in between.

Zur Verringerung der Umlenkverlusle in den Γ·Γ> Angularkompensatoren empfiehlt es sich, daß diese im Inneren des Balgteiles ein Schutzrohr aufweisen.To reduce the deflection losses in the Γ · Γ > angular expansion joints, it is recommended that these have a protective tube inside the bellows part.

Schließlich besteht auch die Möglichkeit, die spiegelbildlich zueinander verlaufenden Leitungsstränge unter Verzicht auf einzelne Kompensatoren auf ihrer w> gesamten Länge elastisch auszubilden, indem beispielsweise Wellschläuche verwendet werden.Finally, there is also the possibility of underneath the line strands running in mirror image to one another Eliminating the need to design individual compensators to be elastic over their entire length, for example by Corrugated hoses are used.

Ein Ausführungsbeispiel der Erfindung ergibt sich aus der nachfolgenden Beschreibung anhand der Zeichnung; dabei zeigt hr>An embodiment of the invention results from the following description with reference to the drawing; while h r >

Fig. 1 die Kompensatoranordnung in schematischer Darstellung und1 shows the compensator arrangement in schematic form Representation and

F i g. 2 ein Beispiel für die Schwenkverbindung an den Kreuzungspunkten.F i g. 2 an example of the swivel connection to the Crossing points.

Zunächst sei mit Hilfe der strichpunktierten Linien in Fig. 1 das Schema der sog. Nürnberger Schere erläutert. An einem Festpunkt A sind zwei Schenkel a und b gelenkig gelagert und laufen von dort spiegelbildlich nach außen bis zu zwei äußeren Umlenkpunkten B und C. Vom Punkt B läuft ein weiterer Schenkel c parallel zum Schenkel'/» nach innen. Spiegelbildlich hierzu läuft vom Punkt Cein Schenkel d parallel zum Schenkel α nach innen. Im Kreuzungspunkt D der beiden Schenkel c und d sind sie schwenkbar miteinander verbunden. Vom Punkt D können die Schenkel weiterlaufen, um ein neues Scherenparallelogramm zu bilden. Die Schenkellängen bleiben dabei stets gleich, so daß die äußeren Umlenkpunkte und die Kreuzungspunkte jeweils auf parallelen Geraden liegen.First, the diagram of the so-called Nuremberg scissors will be explained with the aid of the dash-dotted lines in FIG. 1. At a fixed point A , two legs a and b are articulated and run from there in a mirror-inverted manner outwards to two outer deflection points B and C. From point B another leg c runs parallel to the leg '/ »inwards. In a mirror image of this, a leg d runs inwards from point C parallel to leg α . At the intersection point D of the two legs c and d , they are pivotably connected to one another. From point D the legs can continue to form a new scissor parallelogram. The leg lengths always remain the same, so that the outer deflection points and the intersection points each lie on parallel straight lines.

Durch die gelenkige Verbindung der Schenkel untereinander kann der Punkt D bei festgehaltenem Punkt A nach rechts verschoben werden, wodurch die Punkte B und C schräg nach innen wandern. Durch Hintereinanderschaltung mehrerer Scherengitier können große Längenänderungen bei relativ geringen Breitenänderungen des Systems aufgenommen werden. Selbstverständlich kann die Bewegung auch im Punkt A eingeleitet werden. Um dieses Prinzip für den Dehnungsausgleich von Rohrleitungen verwenden zu können, wird die Rohrleitung I in einer Abzweigung 2 in einen oberen und einen unteren Leitungsstrang 3 bzw. 4 aufgeteilt. Beide Rohrstränge laufen in jeweils verschiedener Höhe zunächst noch jeweils durch einen Angularkonipensator (in F i g. I ist lediglich der obere Kompensator 5 für den Leitungsstrang 3 sichtbar) und werden dann spiegelbildlich zueinander nach außen umgelenkt. An den äußeren Umlenkpunkien B und C sitzt jeweils ein Angularkompensator 6 bzw. 7. Der Anschluß an die Kompensatoren erfolgt über Rohrkrümmer, deren Umlenkwinkel so gewählt ist, daß der Biegewinkel der Kompensatoren etwa bei null liegt, wenn die Schere 50% der Maximaldehnung aufgenommen hat. Dadurch wird die Winkelbewegl'.chkeit der Kompensatoren optimal ausgenützt. Statt dessen kann die Schwenkverbindung beispielsweise als Rohrgelenk oder als dichter Torsionskompensator ausgebildet sein.Due to the articulated connection of the legs with one another, point D can be shifted to the right while point A is held, whereby points B and C move diagonally inwards. By connecting several scissor gites one behind the other, large changes in length can be accommodated with relatively small changes in width of the system. The movement can of course also be initiated at point A. In order to be able to use this principle for the expansion compensation of pipelines, the pipeline I is divided in a branch 2 into an upper and a lower line strand 3 and 4, respectively. Both pipe strings initially run at different heights through an angular connector (in FIG. 1, only the upper compensator 5 for the pipeline 3 is visible) and are then deflected outward in mirror image to one another. An angular compensator 6 or 7 is located at the outer deflection points B and C respectively. The connection to the compensators is made via pipe bends, the deflection angle of which is selected so that the bending angle of the compensators is approximately zero when the scissors have absorbed 50% of the maximum expansion . As a result, the angular mobility of the expansion joints is optimally used. Instead, the pivot connection can be designed, for example, as a tubular joint or as a tight torsion compensator.

Von den Kompensatoren 6 und 7 ausgehend, werden die Leitungsstränge 3 bzw. 4 wieder nach innen umgelenkt zum Kreuzungspunkt D. Dort sind beide Leitungsstränge durch ein Schwenklagcr, das in F i g. 2 dargestellt ist, miteinander verbunden. Die Leitungsstränge laufen dann zur Bildung weiterer Scherenelemente, die genauso aufgebaut sind wie das zuvor beschriebene, weiter.Starting from the compensators 6 and 7, the line strands 3 and 4 are deflected inwards again to the intersection point D. There both line strands are through a pivot bearing, which is shown in FIG. 2 is shown connected to one another. The cable strands then continue to form further scissor elements, which are constructed in the same way as the one previously described.

Der Winkel, unter dem die Schenkel a, b, rund dder einzelnen Scherenglieder aus der Scherenlängserstrekkung herausgeschwenkt werden, ist maßgebend für die Wirksamkeit der Schere. Die größte Dehnungsaufnahme bezogen auf das Breitenwachstum ergibt sich bei Winkeln von 90°; dann erreichen allerdings auch die Umlenkverluste ihr Maximum.The angle at which the legs a, b, round d of the individual scissor links are pivoted out of the longitudinal extension of the scissors is decisive for the effectiveness of the scissors. The greatest expansion absorption related to the growth in width occurs at angles of 90 °; then, however, the deflection losses also reach their maximum.

Um den Umlenkungen der beiden Leitungsstränge einen harmonischen Verlauf zu geben, können sich die Rohrkrümmer über den ganzen Bereich zwischen den äußeren Extrempunkten und den inneren Kreuzungspunkten erstrecken. Es entsteht dann ein sinuskurvenähiilicher Verlauf.The Extend the pipe elbow over the entire area between the outer extreme points and the inner crossing points. A sinusoidal curve then arises Course.

Es können auch die spiegelbildlich zueinander laufenden Leitungsstränge in sich elastisch ausgebildet werden, also beispielsweise in Form von Wellschläuchen. Bei ausreichender Winkelbeweglichkeit derselbenThe line strands running in mirror image to one another can also be designed to be elastic in themselves be, for example in the form of corrugated hoses. With sufficient angular mobility of the same

können die äußeren Angularkompensatoren 6 und 7 entfallen.the outer angular expansion joints 6 and 7 can be omitted.

Fi g. 2 zeigt die Schwenklagerung an den Kreuzungspunkten. Hierzu weisen die sich überkreuzenden Rohre 8 und 9 jeweils an ihren einander zugewandten Seiten eine Armierung 10 bzw. 11 auf. In beiden Armierungen befindet sich eine in der Schwenkachse liegende Bohrung, in der ein gemeinsamer Lagerstift 12 sitzt. Die Rohre können dadurch eine definierte Schwenkbewegung ausführen.Fi g. 2 shows the swivel mounting at the crossing points. The crossing pipes point to this 8 and 9 each have a reinforcement 10 and 11 on their mutually facing sides. In both reinforcements there is a hole in the pivot axis in which a common bearing pin 12 is seated. the As a result, pipes can execute a defined pivoting movement.

Selbstverständlich kommen auch andere Drehlagerungen in Frage. Soll auch ein seitliches Auswandern aus der vorgegebenen Schwenkebene zugelassen werden, werden Gelenkverbindungen eingesetzt.Of course, other rotary bearings are also possible. Should also emigrate to the side the specified swivel plane are permitted, articulated connections are used.

Zur Kompensation großer Transportleitungen wie Fernwärmeleitungen empfiehlt es sich, jeweils zwei Kompensationselemente an einer Stelle zusammenzufassen, d. h.. man verwendet ein Kompcnsationselement. das sowohl für die Dehnungsaufnahme des ankommenden als auch für die Dehnungsaufnahme des weglaufenden Leitungsstranges ausgelegt ist. Sind die von beiden Leitungssträngen aufzunehmenden Maximaldehnungen gleich groß, so wird der Festpunkt dieses Dehnungselementes in die Mitte seiner Längserstreckung gelegt. Sind die aufzunehmenden Dehnungen ungleich auf die , beiden Rohrstränge verteilt, so wird das Kompensalionselement entsprechend diesem Verhältnis geteilt und der Festpunkt dort angeordnet.To compensate for large transport lines such as district heating lines, it is advisable to use two at a time To summarize compensation elements in one place, d. h .. one uses a compensation element. both for the expansion of the incoming as well as for the expansion of the departing Cable harness is designed. Are the maximum expansions to be absorbed by both cable strands the same size, the fixed point of this expansion element is placed in the middle of its longitudinal extension. If the expansion to be absorbed is unevenly distributed between the two pipe strings, the compensation element becomes divided according to this ratio and the fixed point is arranged there.

Die Schwenkebene ist an sich beliebig, vorzugsweise aber horizontal. Ihre Abstützung zur VermeidungThe pivot plane is arbitrary per se, but preferably horizontal. Your support to avoid it

κι unzulässiger Durchbiegung der Leilungsstränge kann mittels an sich bekannter Loslager erfolgen.κι impermissible deflection of the Leilungsstrangen can take place by means of known floating bearings.

Um die Umlenkverluste in den Angularkompensatoren zu reduzieren, können diese eine glatte Innenverkleidung oder beispielsweise ein am einen FlanschIn order to reduce the deflection losses in the angular expansion joints, they can have a smooth inner lining or for example one on a flange

ι. fixiertes Schutzrohr aufweisen. Bei größeren Winkclbcwegungen des Anguiators empfiehlt es sich, von beiden Flanschseiten des Kompensator Schutzrohre nach innen laufen zu lassen, wobei das eine Schutzrohr mit einem gewissen Spiel in das andere hineinläuft, so daßι. Have fixed protective tube. For larger angular movements des Anguiators, it is recommended to use both Flange sides of the expansion joint to allow protective tubes to run inwards, with the one protective tube a certain game runs into the other, so that

jo beide Schutzrohre relativ zueinander winkelbewcglich sind.jo both protective tubes angularly movable relative to one another are.

Hierzu 1 Blatt Zeichnungen1 sheet of drawings

Claims (13)

Patentansprüche:Patent claims: 1. Kompensatoranordnung zum Ausgleich von Längenänderungen in einer Rohrleitung unter Aufteilung der Rohrleitung in wenigstens zwei Stränge, die spiegelbildlich zueinander etwa bogenförmig verlaufen, wobei die Schenkel jedes Rohrbogens zueinander winkelbeweglich sind, dadurch gekennzeichnet, daß jeder Leitungsstrang (3, 4) mehrere aufeinanderfolgende Bögen aufweist, die sich mit den Bögen des Nachbarstranges kreuzen und daß die Leitungsstränge (3, 4) an den Kreuzungspunkten (D) schwenkbar miteinander verbunden sind.1. Compensator arrangement to compensate for changes in length in a pipeline, dividing the pipeline into at least two strands which are approximately arcuate in mirror image to one another, the legs of each pipe bend being angularly movable to one another, characterized in that each line strand (3, 4) has several successive bends that intersect with the arches of the neighboring strand and that the strands of cables (3, 4) are pivotably connected to one another at the crossing points (D). 2. Kompensatoranordnung nach Anspruch 1, dadurch gekennzeichnet, daß die Leitungsstränge (3, 4) an den Umlenkpunkten (B, C) e:n Drehgelenk aufweisen.2. Compensator arrangement according to claim 1, characterized in that the cable strands (3, 4) at the deflection points (B, C) e: n have a swivel joint. 3. Kompensatoranordnung nach Anspruch 2, dadurch gekennzeichnet, daß der dem Drehgelenk zulaufende Leitungsstrang gegenüber dem ablaufenden Leitungsstrang senkrecht zur Schwenkebene versetzt und an diesen durch eine Schwenkverbindung angekoppelt ist.3. Compensator arrangement according to claim 2, characterized in that the swivel joint incoming cable loom opposite the outgoing cable loom perpendicular to the swivel plane offset and is coupled to this by a pivot connection. 4. Kompensatoranordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Leitungsstränge (3, 4) an den Umlenkpunkten (B, C) eine elastische Verbindung aufweisen und jeder Leitungsslrang in einer Ebene verläuft.4. Compensator arrangement according to one of the preceding claims, characterized in that the line strands (3, 4 ) have an elastic connection at the deflection points (B, C) and each line length runs in one plane. 5. Kompensatoranordnung nach Anspruch 4, dadurch gekennzeichnet, daß die elastische Verbindung ein Balg ist.5. Compensator arrangement according to claim 4, characterized in that the elastic connection is a bellows. 6. Kompensatoranordnung nach Anspruch 4, dadurch gekennzeichnet, daß die elastische Verbindung ein Angularkompensaior (6,7) ist.6. Compensator arrangement according to claim 4, characterized in that the elastic connection is an angular compensator (6,7). 7. Kompensatoranordnung nach Anspruch 1,2,4,5 und 6, dadurch gekennzeichnet, daß die zueinander spiegelbildlichen Leitungsstränge (3, 4) senkrecht zur Schwenkeber.e um zumindest den Durchmesser eines Leitungsstranges gegeneinander versetzt sind.7. Compensator arrangement according to claim 1,2,4,5 and 6, characterized in that the line strands (3, 4), which are mirror images of one another, are perpendicular zur Schwenkeber.e are offset from one another by at least the diameter of a line strand. 8. Kompensatoranordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Leitungsstränge (3, 4) an den Umlenkpunkten (B, C) und/oder den Kreuzungspunkien (D) gegen Durchhängen abgestützt sind.8. Compensator arrangement according to one of the preceding claims, characterized in that the cable strands (3, 4) are supported against sagging at the deflection points (B, C) and / or the intersection points (D). 9. Kompensatoranordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß ein endständiger Kreuzungspunkt (A) mi: einer sich anschließenden Weiche (2) als Festpunkt fungiert.9. Compensator arrangement according to one of the preceding claims, characterized in that a terminal crossing point (A) mi: an adjoining switch (2) acts as a fixed point. 10. Kompensatoranordnung nach Anspruch 9, dadurch gekennzeichnet, daß die Leitungsstränge (3, 4) über jeweils eine elastische Verbindung mit der Weiche (2) verbunden sind.10. Compensator arrangement according to claim 9, characterized in that the cable strands (3, 4) are each connected to the switch (2) via an elastic connection. U. Kompensatoranordnung nach einem der Ansprüche 1 bis 8, dadurch gekennzeichnet, daß der Festpunkt zwischen zwei hintereinandergeschalteten Scherenanordnungen angeordnet ist.U. Compensator arrangement according to one of claims 1 to 8, characterized in that the Fixed point is arranged between two series-connected scissor assemblies. 12. Kompensatoranordnung nach Anspruch 6, dadurch gekennzeichnet, daß der Angularkompensator (6,7) im Inneren des Balgteiles ein Schutzrohr aufweist.12. Compensator arrangement according to claim 6, characterized in that the angular compensator (6,7) in the interior of the bellows part is a protective tube having. 13. Kompensatoranordnung nach Anspruch 6, dadurch gekennzeichnet, daß die Leitungsstränge (3, 4) unter Verzicht auf einzelne Kompensatoren auf ihrer ganzen Länge elastisch aurgebildet sind.13. Compensator arrangement according to claim 6, characterized in that the cable strands (3, 4) are designed to be elastic over their entire length, dispensing with individual expansion joints. Die Erfindung betrifft eine Kompensatoranordnung zum Ausgleich von Längenänderungen in einer Rohrleitung unter Aufteilung der Rohrleitung in wenigstens zwei Stränge, die spiegelbildlich zueinander etwa bogenförmig verlaufen, wobei die Schenkel jedes Rohrbogens zueinander winkelbeweglich sind.The invention relates to a compensator arrangement for compensating for changes in length in a Pipeline dividing the pipeline into at least two strands that are mirror images of each other approximately arcuate, the legs of each pipe bend are angularly movable to one another. Eine derartige Kompensatoranordnung ist durch die DE-PS 1 30 270 bekannt geworden. Dabei sind zwei gegenüberliegende U-förmige Leitungsstränge vorgesehen, in denen die biegsamen Rohrstücke quer zur direkten Verbindung der Anschlußflansche verlaufen, so daß sie bei Relativbewegungen der Flansche eine Lateralverschiebung durchmachen. Für die Aufnahme sehr großer Längenänderungen, wie sie beispielsweise bei Fernheizleitungen auftreten, ist diese Anordnung nicht geeignet. Bei Fernheizleitungen strebt man aus Wirtschaftlichkeitsgründen möglichst lange, durchgehende Rohrstücke mil nur wenigen Kompensationsstellen an. Denn-wegen der unterirdischen Verlegung der Fernheizleitungen muß man für die Kornpensationsstellen umfangreiche Schachtbauwerke erstellen. Für das Beispiel einer Rohrstrecke von 2000 m Länge und einer Heizwassertemperatur von 160°C ergibt sicu eine notwendige Dehnungsaufnahme von etwa 4000 mm. Die Beherrschung solcher Längenänderungen wird bei Rohrdurchmessern in der Größenordnung von 1000 mm und Betriebsdrücken in der Größenordnung von 30 bar sehr kostenintensiv.Such a compensator arrangement has become known from DE-PS 1 30 270. There are two Opposite U-shaped strands are provided in which the flexible pipe sections transversely to direct connection of the connecting flanges so that they have a relative movement of the flanges Go through a lateral shift. For the inclusion of very large changes in length, such as those for example occur in district heating lines, this arrangement is not suitable. One strives for district heating lines For reasons of economy, the longest possible, continuous pipe sections with only a few compensation points. Because-because of the underground laying of the District heating lines have to be built for the compensation points. For the An example of a pipe section of 2000 m in length and a heating water temperature of 160 ° C results in one necessary expansion absorption of about 4000 mm. The control of such changes in length is at Pipe diameters in the order of 1000 mm and operating pressures in the order of magnitude from 30 bar very costly. Auch der Rohrbündelkompensator gemäß der DE-PS 4 38 653, bei dem die Rohrleitung in fünf einzelne Lyrabögen aufgeteilt ist, ist für große Längenänderungen ungeeignet. Denn die erwähnte Aufteilung dieni vor allem der vereinfachten Herstellung und der Erzielung gleicher Beanspruchung sämtlicher Einzelrohre. Vor allem soll durch die Kronenform erreicht werden, daß bei Durchbiegung des Kompensator die Kraftrcsulticrende im Zentrum verläuft und die Anschlußflansche ihre zueinander parallele Lage beibehalten.Also the tube bundle compensator according to DE-PS 4 38 653, in which the pipeline is divided into five individual Lyra arcs is not suitable for large changes in length. Because the mentioned division serves before especially the simplified production and the achievement of the same stress on all individual tubes. before Above all, the shape of the crown is intended to ensure that when the compensator bends, the end of the force and the connecting flanges run in the center maintain their mutually parallel position. Schließlich ist durch die FR-PS 22 18 528 ein Dehnungsausgleich^ bekannt, der aus einem zickzackförmig abgebogenen Rohrstück besteht, dessen Schenkel durch ihre Winkelbeweglichkeit zur Kompensation von Lärtgenänderungen in der Rohrleitung zur Verfügung stehen.Finally, from FR-PS 22 18 528 an expansion compensation ^ is known, which consists of a zigzag bent piece of pipe, the legs of which by their angular mobility for compensation of changes in length in the pipeline are available. Hiervon ausgehend, liegt die Aufgabe der Erfindung darin, ein Kompensationssystem für extrem große Längenänderungen einer Rohrleitung zu entwickeln, wie sie beispielsweise bei Fernhcizleitangen auftreten.Proceeding from this, the object of the invention is to provide a compensation system for extremely large To develop changes in length of a pipeline, as they occur, for example, with Fernhcizleitangen. Diese Aufgabe wird erfindungsgemäß dadurch gelöst, daß jeder Leitungsstrang mehrere aufeinanderfolgende Bögen aufweist, die sich mit den Bögen des Nachbarstranges kreuzen und daß die Leitungsstränge an den Kreuzungspunkten schwenkbar miteinander verbunden sind.According to the invention, this object is achieved in that each cable run has several successive ones Has arcs that intersect with the arcs of the neighboring strand and that the strands of wire to the Crossing points are pivotally connected to each other. Durch die sich kreuzende Anordnung der Leitungsstränge und durch ihre schwenkbare Verbindung an den Kreuzungspunkten erfolgt die Kompensation praktisch nach dem Prinzip der Nürnberger Schere. Das bedeutet, daß eine sehr große Längenänderung in eine Vielzahl kleiner Breitenänderungen verwandelt wird, wobei die Summe der Breitenänderungen kleiner als die Gesamtlängenänderung ist, wenn man mit großen Öffnungswinkeln der einzelnen Scherenglieder arbeitet.Due to the crossing arrangement of the strands of cables and their pivotable connection to the At intersection points, the compensation is practically based on the principle of the Nuremberg scissors. That means, that a very large change in length is converted into a multitude of small changes in width, the The sum of the changes in width is smaller than the total change in length when working with large opening angles of the individual scissor links. Demgegenüber handelt es sich bei keiner der drei genannten Vorveröffeiitlichungen um ein echtes Überkreuzen benachbarter Leitungsstränge und in keinem Fall ist die für das Erfindungsprinzip entscheidende schwenkbare Verbindung an den KreuzungspunktenIn contrast, none of the three are involved named Vorveröffeiitlichungen about a real crossing of neighboring cable strands and in none The case is the pivotal connection at the intersection points, which is decisive for the principle of the invention
DE19772721050 1977-05-11 1977-05-11 Compensator arrangement to compensate for changes in length in the pipeline Expired DE2721050C3 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19772721050 DE2721050C3 (en) 1977-05-11 1977-05-11 Compensator arrangement to compensate for changes in length in the pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19772721050 DE2721050C3 (en) 1977-05-11 1977-05-11 Compensator arrangement to compensate for changes in length in the pipeline

Publications (3)

Publication Number Publication Date
DE2721050A1 DE2721050A1 (en) 1978-11-16
DE2721050B2 true DE2721050B2 (en) 1980-10-16
DE2721050C3 DE2721050C3 (en) 1981-09-17

Family

ID=6008544

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19772721050 Expired DE2721050C3 (en) 1977-05-11 1977-05-11 Compensator arrangement to compensate for changes in length in the pipeline

Country Status (1)

Country Link
DE (1) DE2721050C3 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE130270C (en) *
DE438653C (en) * 1925-02-05 1926-12-20 Saechsische Maschinenfabrik Vo Pipe bundle compensator for pipes
FR2218528B1 (en) * 1973-02-19 1977-12-30 Stein Industrie

Also Published As

Publication number Publication date
DE2721050C3 (en) 1981-09-17
DE2721050A1 (en) 1978-11-16

Similar Documents

Publication Publication Date Title
EP0210271B1 (en) Flexible corrugated hose with ring-shaped parallel waves with axial support
DE29913063U1 (en) Energy supply chain
EP3074572B1 (en) Bridging apparatus
EP0377140B1 (en) Connecting arrangement for the heat carriers of solar plants
DE102006019133B3 (en) Line e.g. cable, combination, has fastening unit formed between adjacent lines and exhibiting slide rail, where lines are held slide-movably in line longitudinal direction at slide rail that is formed as plastic-profile strip
DE3725957C1 (en) Shaft coupling element
DE2721050C3 (en) Compensator arrangement to compensate for changes in length in the pipeline
DE3900463C2 (en)
EP0601262B1 (en) Pipe subjected to differential dilatations
DE2557713A1 (en) MOVABLE PIPE ELEMENT
DE2824395A1 (en) Polyvinylidene fluoride hot water piping for district heating system - has corrugated sections alternating with plain sections with mounting points for other members
DE3643038C2 (en)
DE7714895U1 (en) COMPENSATOR ARRANGEMENT TO COMPENSATE FOR LENGTH CHANGES IN PIPING
DE1218821B (en) Articulated corrugated pipe compensator
EP0708287A1 (en) Pipe assembly
DE2653192A1 (en) THERMAL EXPANSION COMPENSATOR WITH AN ELASTIC ROD
EP3592922B1 (en) Boom system having a retracted position which reduces installation space
WO2012007218A1 (en) Pipeline arrangement
DE8906210U1 (en) Carrier connection
DE2856275B1 (en) Compensation device for hot pipes
DE130270C (en)
DE4205924C2 (en) Cabel Canal
DE2737022A1 (en) Hinged pipe resistant to high internal or external pressure - has reinforced pressure tubing coupling pipe arms on hinged pipes
AT389928B (en) CHAIN WITH CHAIN LINKS WELDED FROM ROUND MATERIAL
DE102005040093B4 (en) spacer

Legal Events

Date Code Title Description
OAP Request for examination filed
OD Request for examination
C3 Grant after two publication steps (3rd publication)
8339 Ceased/non-payment of the annual fee