DE2705744C3 - Method and device for stacking bricks on pallets - Google Patents
Method and device for stacking bricks on palletsInfo
- Publication number
- DE2705744C3 DE2705744C3 DE19772705744 DE2705744A DE2705744C3 DE 2705744 C3 DE2705744 C3 DE 2705744C3 DE 19772705744 DE19772705744 DE 19772705744 DE 2705744 A DE2705744 A DE 2705744A DE 2705744 C3 DE2705744 C3 DE 2705744C3
- Authority
- DE
- Germany
- Prior art keywords
- layers
- bricks
- brick
- pallet
- brick layers
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G57/00—Stacking of articles
- B65G57/02—Stacking of articles by adding to the top of the stack
- B65G57/16—Stacking of articles of particular shape
- B65G57/20—Stacking of articles of particular shape three-dimensional, e.g. cubiform, cylindrical
- B65G57/22—Stacking of articles of particular shape three-dimensional, e.g. cubiform, cylindrical in layers each of predetermined arrangement
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Stacking Of Articles And Auxiliary Devices (AREA)
- Specific Conveyance Elements (AREA)
- Carbon Steel Or Casting Steel Manufacturing (AREA)
Description
Die Erfindung bezieht sich auf ein Verfahren bzw. auf eine Vorrichtung zum Stapeln von Ziegeln zu einem Paket mit teilweise ineinandergreifende und gegeneinander schräg zur Mitte des Paketes nach unten verlaufenden Ziegellagen auf mit Stützkanten versehenen Paletten.The invention relates to a method and a device for stacking bricks to form a Package with partially interlocking and against each other obliquely to the middle of the package down running brick layers on pallets provided with supporting edges.
Für den Transport von Ziegeln aller Art und andere Produkte vom Erzeugerwerk zur Baustelle gibt es verschiedene Stapel- und Transportsysteme und auch unterschiedliche Pakete. Alle dienen dazu, einen möglichst sicheren Transport zu gewährleisten und die Ziegel vor Bruch und anderen Beschädigungen zu schützen. Für solche Verpackungssicherungen werden außer Paletten insbesondere Stahlband zur Umreifung, oder Schrumpffolie für eine Umhüllung verwendet. Damit werden die Pakete und die Paletten zu einer Einheit verbunden. An den Baustellen muß aber das Verpackungsmaterial, also das Stahlband bzw. die Schrumpffolie geöffnet werden. Danach muß dieses Material als Abfall entfernt werden. Die Paletten werden jedoch oft wieder in das Erzeugerwerl·: zurückgeführt und wieder verwende 1.For the transport of bricks of all kinds and other products from the manufacturing plant to the construction site there are different stacking and transport systems and also different packages. All serve to make one To ensure the safest possible transport and to protect the bricks from breakage and other damage protection. In addition to pallets, steel strapping in particular is used for such packaging securing, or shrink film used for wrapping. This means that the packages and the pallets become one Unity connected. At the construction site, however, the packaging material, i.e. the steel strip or the Shrink film can be opened. Thereafter, this material must be removed as waste. The pallets However, they are often returned to the producer: returned and reuse 1.
Bei einem bekannten Paket (Brick & Clay Record, De'ember 197 i, Seite 36 Bild unten) werden die Ziegel auf einer mit .Stützkanten versehenen Palette in Ziegellagen übereinander aufgestapelt, wobei die Stützkanten die ersten Ziegellagen, die schräg an die Stützkanten gesetzt werden, abstützen. Die folgenden Ziegellagen werden ebenfalls in schräg nach unten verlaufender Weise auf die ersten Ziegellagen aufgestapelt, so daß sich ein Paket bildet, deren Lagen gegeneinander geneigt in der Mitte des Paketes zusammentreffen, wobei die unteren Ziegel der auf der einen Seite des Paketes befindlichen Ziegellagen die unteren Ziegel der gegenüberliegenden Ziegellagen überlappen. Da die Ziege! schräg zur Mitte des Paketes geneigt auf der Palette aufgestapelt sind und sich dadurch das Paket während des Transportes verfestigt, wird kein Stahlband und keine Schrumpffolie zur Sicherung des Paketes mehr benötigt.In a known package (Brick & Clay Record, December 197 i, page 36 picture below) the bricks Stacked on a pallet with support edges in brick layers, the Support edges support the first brick layers that are placed at an angle on the support edges. The following Layers of bricks are also stacked on top of the first layers of bricks in a downward sloping manner, so that a package is formed, the layers of which are inclined towards one another in the middle of the package meet, the lower bricks of the brick layers located on one side of the package Overlap the lower bricks of the opposite brick layers. There the goat! at an angle to the middle of the package are stacked at an incline on the pallet and thereby solidify the package during transport, no steel band or shrink film is needed to secure the package.
Bei der Erstellung dieses Paketes werden jedoch die Ziegel üblicherweise von Hand auf die Palette gestapelt, wobei es erforderlich ist, daß für die Erstellung eines Paketes jeweils mindestens eine Arbeitskraft eingesetzt werden muß. Abgesehen von den hohen Lohnkosten, die sich hierdurch ergeben und die Wirtschaftlichkeit des Stapelvorganges herabsetzen, besteht ein weiterer Nachteil darin, daß die Leistung entsprechend niedrig ist. Da zudsm bei dieser Stapelweise die Ziegel nicht benutsam behandelt werden, treten an den Ziegeln Beschädigungen, und zwar namentlich an den Kanten, auf.When creating this package, however, the bricks are usually stacked on the pallet by hand, it is necessary that at least one worker is used to create a package must become. Apart from the high wage costs that result from this and the profitability Reduce the stacking process, there is another disadvantage that the performance is correspondingly low is. Because the bricks are not used in this way of stacking are treated carefully, damage occurs to the bricks, namely to the edges, on.
Der Erfindung liegt die Aufgabe zugrunde, ein Verfahren und eine zu dessen Durchführung geeignete Vorrichtung zum Stapeln von Ziegeln auf Paletten zu schaffen, die ohne Handarbeit ein einwandfreies sowie schnelles und wirtschaftliches Stapeln von Ziegeln zu Paketen ermöglicht, welche mit ineinandergreifenden und gegeneinander schräg zur Mitte der Pakete nach unten verlaufenden Ziegellagen versehen sind.The invention is based on the object of a method and a method suitable for carrying it out Device for stacking bricks on pallets to create a flawless as well as without manual labor enables bricks to be stacked quickly and economically to form packages with interlocking and facing each other obliquely to the center of the packages downwardly extending brick layers are provided.
Diese Aufgabe wird bei dem Verfahren erfindungsgemäß dadurch gelöst, daß jeweils zwei Ziegellagen gruppiert zugeführt und diese rechtwinklig aus der bisherigen Zuführrichtung abgeschoben werden, daß danach d'e beiden Ziegellagen aus der horizontalen Stellung in gegeneinander schräg nach unten verlaufende Stellungen überführt und in den Bereich oberhalb der Palette transportiert werden, und daß die Ziegellagen in diesen schrägen Stellungen der Palette übergeben werden.This object is achieved in the method according to the invention in that two brick layers in each case grouped fed and these are pushed off at right angles from the previous feed direction that then d'e two brick layers from the horizontal position in mutually sloping downward direction Positions transferred and transported in the area above the pallet, and that the brick layers in be transferred to these inclined positions of the pallet.
Zur Durchführung des Verfahrens wird erfindungsgemäß eine Vorrichtung verwendet, die darin besteht, daß an einem Zuführförderer im Abstand voneinander zwei quer zum Zuführförderer wirkende Abschubvorrichtungen vorgesehen sind, daß im Abschubbereich der Abschubvorrichtungen zwei Übergabebleche angeordnet sind, welche gegeneinander nach unten schwenkbar ausgebildet sind, daß jedes Übergabeblech jeweils auf einen verfahrbaren Wagen befestigt ist, der in den Bereich einer auf einen Heb- und Senktisch befindlichen Palette bewegbar ist, und daß den Übergabeblechen eine heb- und senkbare Sperre zum Abstreifen der Ziegellagen zugeordnet ist.To carry out the method, a device is used according to the invention, which consists in that on a feed conveyor at a distance from one another two pushing devices acting transversely to the feed conveyor it is provided that two transfer plates are arranged in the push-off area of the push-off devices are, which are designed to pivot downwards against each other, that each transfer plate each on a movable carriage is attached, which is located in the area of a lifting and lowering table Pallet is movable, and that the transfer plates have a liftable and lowerable lock for stripping Brick layers is assigned.
Zweckmäßigerweise ist die Schwenkachse des einen Übergabebleches an einem Exzenter gelagert.The pivot axis of the one transfer plate is expediently mounted on an eccentric.
Nach einer Weiterbildung der Erfindung besteht die Sperre aus zwei auf einem Träger bewegbaren Halteblechcn.According to a further development of the invention, the lock consists of two movable on a carrier Retaining plates.
Das Verfahren und die Vorrichtung nach der Erfindung vermeiden die Unzulänglichkeiten des Stapeins der Ziegel von I land, so daß /. B. das Erstellen der Ziegelpakete in einer geringeren Zeit vorgenommen werden kann. Eine Leistungssteigerung in Verbin-The method and apparatus according to the invention avoid the shortcomings of the Stapeins of bricks from I land so that /. B. made the creation of the brick stacks in less time can be. An increase in performance in connection
dung mit einer Personaleinsparung ist die unmittelbare Folge. Außerdem werden die Ziegel schonender behandelt, so daß Beschädigungen der Ziegel so gut wie ausgeschlossen sind.The immediate consequence is a reduction in personnel. In addition, the bricks are gentler treated so that damage to the brick is as good as impossible.
In der Zeichnung ist eine Vorrichtung zur Durchführung des Verfahrens nach der Erfindung schematisch dargestellt Es zeigtIn the drawing is a device for implementation of the method according to the invention shown schematically It shows
F i g. 1 die Draufsicht auf eine Vorrichtung gemäß der Erfindung,F i g. 1 the top view of a device according to the invention,
F i g. 2 eine Seitenansicht der Vorrichtung gemäß Fig.l,F i g. 2 shows a side view of the device according to FIG.
F i g. 3 eine Seitenansicht der Vorrichtung nach der Linie I1I-III in Fig.l,F i g. 3 is a side view of the device along the line I1I-III in Fig.l,
Fig.4 + 5 weitere Seitenansichten, ähnlich wie F i g. 3, jedoch in verschiedenen Verfahrensabschnitten und4 + 5 further side views, similar to FIG. 3, but in different procedural stages and
F i g. 6 ein mit der Vorrichtung erstelltes Paket.F i g. 6 a package created with the device.
Ein Zuführförderer 1 transportiert bereits gruppierte Ziegellagen 2 und 3, die aus einer oder mehreren Ziegelreihen bestehen können, in den Bereich von Abschubvorrichtungen 4 und 5, die die Ziegellagen 2 und 3 quer zur Laufrichtung des Zuführförderers 1 von diesem abschieben. Die Ziegellage 2 gelangt dadurch auf ein Übergabeblech 6, während die Ziegellage 3 auf ein Übergabeblech 7 geschoben wird, und zwar so, daß die Ziegellagen 2 und 3 auf den dem Zuführförderer 1 abgewandten Teilenden der Übergabebleche 6 und 7 in einer Bereitstellung Platz finden (Fig. 1 und 2). Anstatt der Abschubvorrichtungen 4 und 5 können auch Greifervorrichtungen angeordnet sein, die die Ziegellagen 2 und 3 vom Zuführförderer 1 abheben und auf die Übergabebleche 6 und 7 absetzen.A feed conveyor 1 transports already grouped layers of bricks 2 and 3, which can consist of one or more rows of bricks, into the area of pushing devices 4 and 5, which push the layers of bricks 2 and 3 off the feed conveyor 1 transversely to the direction of travel. As a result, the brick layer 2 reaches a transfer plate 6, while the brick layer 3 is pushed onto a transfer plate 7 in such a way that the brick layers 2 and 3 find space on the partial ends of the transfer plates 6 and 7 facing away from the feed conveyor 1 (Fig . 1 and 2). Instead of the push-off devices 4 and 5, gripper devices can also be arranged which lift the brick layers 2 and 3 from the feed conveyor 1 and place them on the transfer plates 6 and 7.
Die Übergabebleche 6 und 7 sind an Wagen 8 und 9 angeordnet und um die Drehachsen 10 und 11 gegeneinander schwenkbar ausgebildet, wobei die Drehachse 10 an einem Exzenter 12 gelagert ist. Nachdem die Ziegeilagen 2 und 3 in Bereitstellung auf die Übergabebleche 6· und 7 gebracht worden sind, schwenken die Übergabebleche 6 und 7 um ca. 45° gegeneinander, wobei die Ziegellagen 2 und 3 gegen Anschläge 13 und 14 rutschen.The transfer plates 6 and 7 are arranged on carriages 8 and 9 and around the axes of rotation 10 and 11 designed to be pivotable with respect to one another, the axis of rotation 10 being mounted on an eccentric 12. After the goat layers 2 and 3 have been placed in readiness on the transfer plates 6 and 7, swivel the transfer plates 6 and 7 against each other by approx. 45 °, with the brick layers 2 and 3 against each other Stops 13 and 14 slide.
Die Wagen 8 und 9 fahren nun mit den geschwenkten Übergabeblechen 6 und 7 in Richtung einer auf einen Heb- und Senktisch 115 befindlichen Palette 16. Die Übergabebleche 6 und 7 sind an den Wagen 8 und 9 so gelagert, daß sie mit den in Bereitsstellung befindlichen Ziegellagen 2 und 3 freitragend und kurz oberhalb der Palette 16 diese überragen (gestrichelt gezeichnete Stellung des Wagens 9 in F i g. 2 und F i g. 4).The carriages 8 and 9 now move with the pivoted transfer plates 6 and 7 in the direction of one on one Lifting and lowering table 115 located pallet 16. The transfer plates 6 and 7 are on the car 8 and 9 so stored that they are cantilevered with the brick layers 2 and 3 in readiness and just above the Pallet 16 project beyond this (position of the carriage 9 shown in dashed lines in FIG. 2 and FIG. 4).
Sobald die Übergabebleche 6 und 7 in der Übergabeposition oberhalb der Palette 16 angelangt sind, senkt sich eine Sperre 17 in Richtung auf die Übergabebleche 6 und 7 hinter den über der Palette 16 befindlichen Ziegellagen 2 und 3 ab. Die Sperre 17 besteht dabei aus einem heb- und senkbaren Träger 18 und auf dem Träger 18 hin- und herbewegbar ausgebildeten Halteblechen 19 und 20, die die Ziegellagen 2 und 3 hinterfassen.As soon as the transfer plates 6 and 7 have reached the transfer position above the pallet 16 are, a lock 17 lowers in the direction of the transfer plates 6 and 7 behind the above the pallet 16 brick layers 2 and 3 located. The lock 17 consists of a carrier 18 that can be raised and lowered and retaining plates 19 and 20 formed to be movable to and fro on the carrier 18, which hold the Put behind brick layers 2 and 3.
Nachdem nun die Sperre 17 abgesenkt ist, fahren die Wagen 8 und 9 und damit auch die Übergabebleche 6 und 7 in die Ausgangsstellung nahe dem Zuführförderer 1 wieder zurück, wobei die Haltebleche 19 und 20 die Ziege'lagen 2 und 3 festhallen und von den Übergabeblechen 6 und 7 abstreifen. Die Übergabebleche 6 und 7 werden somit unter den von den Halteblechen 19 und 20 festgehaltenen Ziegellagen 2 und 3 weggfzogen, wobeiAfter the lock 17 has now been lowered, the carriages 8 and 9 travel and thus also the transfer plates 6 and 7 back to the starting position near the feed conveyor 1, the retaining plates 19 and 20 the Hang on goat layers 2 and 3 and from the transfer plates Strip 6 and 7 off. The transfer plates 6 and 7 are thus under the support plates 19 and 20 held brick layers 2 and 3 away, with
ιυ sich die Ziegellagen 2 und 3 auf die Falette 16 ablegen. Damit die Ziegellagen auf der Palette 16 auch in der zugeführten schrägen Stellung liegen bleiben, weraen die ersten zugeführten Ziegellagen, die meist jeweils aus einer Ziegelreihe bestehen, gegen auf der Palette 16ιυ lay the brick layers 2 and 3 on the folds 16. So that the brick layers remain on the pallet 16 in the inclined position fed in, it is necessary the first brick layers supplied, each of which usually consists of a row of bricks, against on the pallet 16
π befindliche Stützkanten 16a gelegt (Fig.4). Die Stützkanten 16a können aus dreieckigen Holzklötzen oder aus auf der Palette 16 aufgelegten Ziegeln bestehen. Diese schrägliegenden ersten Ziegellagen bilden nun die schrägen Auflageflächen für die weiteren zuzuführenden Ziegellagen, die je nach Größe gruppiert zugeführt werden.π located support edges 16a placed (Figure 4). the Supporting edges 16a can consist of triangular wooden blocks or of bricks placed on the pallet 16 exist. These inclined first brick layers now form the inclined bearing surfaces for the others Brick layers to be fed in, which are fed in groups according to size.
In Ausgangsstellung nahe dem Zuführförderer 1 (Fig. 1—3) werden die Übergabebleche 6 und 7 wieder in eine waagerechte Stellung gebracht und sind somit bereit zur Aufnahme der nächsten Ziegellagen. Das Übergeben der Ziegellagen auf die Palette 16 erfolgt nach dem bereits beschriebenen Schema, wobei jedoch zu beachten ist, daß die Wagen 8 und 9 und damit auch die Übergabebleche 6 und 7 nach dem Übergeben einerIn the starting position near the feed conveyor 1 (Fig. 1-3), the transfer plates 6 and 7 are again brought into a horizontal position and are thus ready to take up the next brick layers. That The brick layers are transferred to the pallet 16 according to the scheme already described, although It should be noted that the carriages 8 and 9 and thus also the transfer plates 6 and 7 after the transfer of a
ίο Ziegellage jeweils um Ziegellagenstärke gegeneinander in Richtung der Pfeile A und B verfahren werden müssen, und zwar so lange, bis die Ziegellagen 2a und 3a in der Mitte der Palette 16 zusammenstoße;. (F i g. 5).ίο brick layer must be moved against each other by brick layer thickness in the direction of arrows A and B , until the brick layers 2a and 3a collide in the middle of the pallet 16 ;. (Fig. 5).
Ist das Stapeln so weit fortgeschritten, wird der Heb-When the stacking is so advanced, the lifting
)5 und Senktisch 15 um die Stärke einer Ziegellage abgesenkt und neue Ziegellagen 2b und 3b vor. den Übergabeblechen 6 und 7 zugeführt. Da sich die Ziegellagen 2b und 3b und auch die folgenden auf die Ziegellagen 2b und 3b abzusetzenden Ziegellagen an den unteren Enden überlappen bzw. versetzt zueinander liegen, wird die Ziegellage 2b zu der Ziegellage 3b in eine nach unten versetzte Stellung gebracht (F i g. 5). Dies geschieht dadurch, indem der Exzenter 12 die Drehachse 10 von der in Fig.4 in die in Fig. 5) 5 and lowering table 15 lowered by the thickness of a brick layer and new brick layers 2b and 3b in front. the transfer plates 6 and 7 fed. Since the brick layers 2b and 3b and also the following brick layers to be deposited on the brick layers 2b and 3b overlap at the lower ends or are offset from one another, the brick layer 2b is brought into a position offset downwards in relation to the brick layer 3b (Fig. 5). This is done by the eccentric 12 moving the axis of rotation 10 from that in FIG. 4 to that in FIG
t") dargestellte Stellung bewegt. Da die nachfolgend zugeführten Ziegellagen ebenfalls versetzt zueinander auf die bereits auf der Palette 16 befindlichen Ziegellagen abgesetzt werden, wird in der geschilderten Weise verfahren, wobei nach jede abgesetzte Ziegellaget ") moves. Since the following The brick layers supplied are also offset from one another on the brick layers already on the pallet 16 Brick layers are deposited, is described in the Proceed in a manner whereby after each stepped brick layer
ίο der Heb- und Senktisch 15 um die Stärke einer Ziegellage nach unten gefahren wird.ίο the lifting and lowering table 15 to the strength of one Brick layer is moved down.
Nachdem das Paket in der in F i g. 6 dargestellten Art fertiggestellt ist, wird es von einer Transportkette wegbefördert. Gleichzeitig wird eine neue ieere Palette 5 auf den Heb- und Senktisch 15 abgelegt, der dann in die Ausgangsposition zur Bildung eines neuen Paketes hochgefahren wird (F i g. 3).After the package is in the form shown in FIG. 6 is completed, it is carried out by a transport chain transported away. At the same time a new ieere pallet 5 is placed on the lifting and lowering table 15, which is then placed in the Starting position for the formation of a new package is raised (Fig. 3).
Hierzu 3 Blatt ZeichnungenFor this purpose 3 sheets of drawings
Claims (4)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19772705744 DE2705744C3 (en) | 1977-02-11 | 1977-02-11 | Method and device for stacking bricks on pallets |
SU772499154A SU890966A3 (en) | 1977-02-11 | 1977-06-20 | Device for making herryngbone brick piles |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19772705744 DE2705744C3 (en) | 1977-02-11 | 1977-02-11 | Method and device for stacking bricks on pallets |
Publications (3)
Publication Number | Publication Date |
---|---|
DE2705744A1 DE2705744A1 (en) | 1978-08-24 |
DE2705744B2 DE2705744B2 (en) | 1978-12-14 |
DE2705744C3 true DE2705744C3 (en) | 1979-08-16 |
Family
ID=6000913
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19772705744 Expired DE2705744C3 (en) | 1977-02-11 | 1977-02-11 | Method and device for stacking bricks on pallets |
Country Status (2)
Country | Link |
---|---|
DE (1) | DE2705744C3 (en) |
SU (1) | SU890966A3 (en) |
-
1977
- 1977-02-11 DE DE19772705744 patent/DE2705744C3/en not_active Expired
- 1977-06-20 SU SU772499154A patent/SU890966A3/en active
Also Published As
Publication number | Publication date |
---|---|
DE2705744B2 (en) | 1978-12-14 |
DE2705744A1 (en) | 1978-08-24 |
SU890966A3 (en) | 1981-12-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2702725C2 (en) | Panel dividing, sorting and stacking system with at least one stacking device | |
DE2929780A1 (en) | PALLETIZING MACHINE | |
DE2911457A1 (en) | STACKING DEVICE | |
DE2303127A1 (en) | COLLIS CONSTRUCTION OF MULTIPLE LAYERS OF PACKAGING ITEMS, AS WELL AS THE METHOD AND MACHINE FOR ASSEMBLING THESE | |
EP0156127A1 (en) | Palletising device | |
DE1584641B1 (en) | Plant for the production of extruded bricks | |
DE2614558A1 (en) | Palletless package assembly process - with standard size layers stacked and formed with lift fork access slots before covering | |
DE3232180C2 (en) | Stacking device for elongated goods | |
DE2106091C3 (en) | Device for nested, layer-by-layer stacking of profiled rolling stock | |
DE4436075C2 (en) | Device for palletizing piece goods into a piece goods stack | |
DE2705744C3 (en) | Method and device for stacking bricks on pallets | |
DE2501012A1 (en) | Timber cutting and stacking - transports partial stacks of timber transverse to their long direction and pushes separate stacks onto platform(s) | |
DE2353752A1 (en) | DEVICE FOR LAYERING STACKING OF BRICKS INTO A STACK | |
DE2524919C2 (en) | ||
DE69811817T2 (en) | Device and method for conveying cut tobacco containers | |
DE19621845C2 (en) | Method and device for feeding fresh bricks to a gripping station for loading the bricks | |
DE2431015A1 (en) | METHOD OF MANUFACTURING A STACK OF ITEMS AND DEVICE FOR CARRYING OUT THIS METHOD | |
DE2213072C3 (en) | Method and device for producing panels for building purposes | |
AT405508B (en) | Sorting and stacking apparatus for panel-cutting installations | |
DE3622477A1 (en) | Palletising apparatus for stackable articles | |
DE10006482C2 (en) | stacker | |
DE2160555B2 (en) | Package stack forming machine - has feed table clear of sinking one, by amount of stack width | |
DE2220846A1 (en) | METHOD AND DEVICE FOR DISASSEMBLING STACKS OF BRICKS | |
DE2312048A1 (en) | DEVICE FOR LOADING PALLETS WITH ACCESSORIES | |
DE3215743A1 (en) | DEVICE FOR WASHING THE VISIBLE SURFACE OF FRESH-PRESSED WASHED CONCRETE PLATES |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OAP | Request for examination filed | ||
OD | Request for examination | ||
C3 | Grant after two publication steps (3rd publication) | ||
8339 | Ceased/non-payment of the annual fee |