DE19744499C1 - Emptying machine for bulk material sacks - Google Patents
Emptying machine for bulk material sacksInfo
- Publication number
- DE19744499C1 DE19744499C1 DE1997144499 DE19744499A DE19744499C1 DE 19744499 C1 DE19744499 C1 DE 19744499C1 DE 1997144499 DE1997144499 DE 1997144499 DE 19744499 A DE19744499 A DE 19744499A DE 19744499 C1 DE19744499 C1 DE 19744499C1
- Authority
- DE
- Germany
- Prior art keywords
- load cross
- springs
- emptying
- load
- cross
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65B—MACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
- B65B69/00—Unpacking of articles or materials, not otherwise provided for
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Supplying Of Containers To The Packaging Station (AREA)
Abstract
Description
Die vorliegende Erfindung betrifft eine Vorrichtung zum Entleeren von Schüttgut enthaltenden Säcken, bei welcher die Säcke, insbesondere sogenannte Big Bags oder FIBC's, über Schlaufen in ein Lastkreuz eingehängt und über die Entleer station gefahren werden. Zum Entleeren wird der Bodenrüssel des Sacks, d. h. seine untere Öffnung an einem Stutzen festgelegt.The present invention relates to a device for emptying bulk goods containing bags, in which the bags, in particular so-called big bags or FIBC's, hung in loops in a load cross and over the emptier station are driven. For emptying the bottom trunk of the sack, i.e. H. its lower opening fixed to a nozzle.
Um das Entleeren zu verbessern, d. h. für einen kontinuierlichen Fluß des Schütt gutes ohne Brückenbildung zu sorgen, wurde vom Stand der Technik vorgeschla gen, das Lastkreuz auf Druckfedern zu lagern, so daß diese den Sack beim Ent leeren hochziehen, d. h. spannen, s. DE 44 19 599 C1.To improve emptying, i.e. H. for a continuous flow of the bulk Providing good without bridging has been suggested by the prior art gene to store the load cross on compression springs, so that the bag at Ent pull up empty, d. H. tension, s. DE 44 19 599 C1.
Die bekannte Lösung hat jedoch den Nachteil, daß sie nur für eine einzige Sack größe aufnahmebereit ist, für kürzere oder längere Säcke mußten die das Last kreuz tragenden Stempel in ihrer Länge verändert werden, was bei jedem Wech sel der Sackgröße eine Neujustierung bedeutet.However, the known solution has the disadvantage that it is only for a single sack size is ready to take, for shorter or longer sacks they had to carry the load cross-bearing stamp can be changed in length, which with each change sel the bag size means a realignment.
Man geht daher meist so vor, daß man die Lastkreuze am Hebezeug (Kran, Lauf katze) beläßt und dieses gelegentlich mit Hilfe des Hebezeuges leicht anhebt. Dies sorgt natürlich nicht für eine kontinuierliche Straffung des Sackes.It is therefore usually done in such a way that the load crosses on the hoist (crane, barrel cat) and occasionally lifts it slightly with the aid of the hoist. Of course, this does not ensure a continuous tightening of the sack.
Der vorliegenden Erfindung liegt daher die Aufgabe zugrunde, ein Lastkreuz zu schaffen, das am Hebezeug verbleiben kann, somit unterschiedliche Sackgrößen zum Entleeren zuläßt, das jedoch den Sack dabei kontinuierlich spannt.The present invention is therefore based on the object of a load cross create that can remain on the hoist, thus different sack sizes allows for emptying, but this continuously tightens the sack.
Die Lösung dieser Aufgabe gelingt bei einer Vorrichtung zum Entleeren von mit Schüttgut gefüllten Säcken, wobei die Säcke an ihrem Oberteil im Träger eines ersten Lastkreuzes einhängbare Schlaufen aufweisen und die Säcke mit Hilfe von Federn beim Entleeren nach oben hin gestrafft werden, dadurch, daß dem ersten Lastkreuz ein darüberliegendes zweites Lastkreuz zugeordnet ist, zwischen dem oberen Lastkreuz und dem unteren Lastkreuz vier erste Zugfedern vorgesehen sind und sich zwischen oberem und unterem Lastkreuz den Zugfedern zugeord nete Schwingsicherungen in Form von Gelenkstangen befinden und zwischen die Gelenke der Gelenkstangen zweite Zugfedern eingespannt sind.This object is achieved with a device for emptying Bags filled with bulk goods, the bags on their upper part in the carrier of a have hooks that can be attached to the first load cross and the sacks with the aid of Feathers are tightened upwards when emptying, in that the first Lastkreuz an overlying second load cross is assigned between the four first tension springs are provided for the upper load cross and the lower load cross and are assigned to the tension springs between the upper and lower load cross Vibration locks are in the form of articulated rods and between the Joints of the joint rods second tension springs are clamped.
Die Funktion der Vorrichtung ist folgende. Zunächst werden die Schlaufen des Sacks an den Trägern des ersten Lastkreuzes festgelegt. Danach hebt das Hebe zeug den Sack an und verfährt ihn zur Entleerungsstation, wobei infolge des Sackgewichts die Federn gedehnt und die zunächst eingeknickten Gelenkstangen gestreckt sind.The function of the device is as follows. First, the loops of the Sacks set on the carriers of the first load cross. Then the lift lifts testifies to the sack and moves it to the emptying station, whereby as a result of the Bag weight, the springs stretched and the articulated rods that were initially buckled are stretched.
Nach dem Festlegen des Bodenrüssels des Sacks am Stutzen (Trichter) der Abfüllstation wird ggf. das Hebezeug unter Straffen des Sacks leicht zurückgefah ren und der Entleerungsvorgang durch Öffnen des Stutzens begonnen.After the bottom proboscis of the sack has been fixed on the nozzle (funnel) Filling station, if necessary, the hoist is slightly retracted while tightening the sack and the emptying process is started by opening the nozzle.
Infolge des dabei auftretenden Gewichtsverlustes heben die ersten Federn das Sackoberteil an und straffen den Sackmantel kontinuierlich bis zum Beenden des Entleerungsvorganges, wobei die Gelenkstangen infolge der Wirkung der zweiten Zugfedern einknicken.As a result of the weight loss that occurs, the first springs lift that Upper part of the bag and tighten the bag jacket continuously until the end of the Emptying process, the joint rods due to the action of the second Fold in tension springs.
Die Gelenkstangen sind mit den Lastkreuzen ebenfalls gelenkig verbunden, die Gelenke sind jedoch relativ steif, so daß für die Bewegung der Gelenkstangen nur ein Freiheitsgrad zugelassen ist. Auf diese Weise kann daher der Sack zwar um das Seil des Hebezeugs um seine Hochachse gedreht werden, ein Verdrehen innerhalb der Lastkreuze ist jedoch ausgeschlossen, und ein Schwingen an den ersten Federn wird gedämpft, so daß der Sack von der Bedienperson ohne weite res schnell positioniert werden kann.The joint rods are also articulated to the load crosses, which Joints, however, are relatively stiff, so that only for the movement of the joint rods a degree of freedom is permitted. In this way, the sack can therefore the rope of the hoist is rotated about its vertical axis, a twisting within the load crosses, however, and swinging on the The first springs are damped so that the sack can be easily stretched by the operator res can be positioned quickly.
Eine solche Vorrichtung erlaubt das Entleeren jeder Sackgröße, da das diesen tragende Lastkreuz in seiner Höhenlage oberhalb des Entleerungsstutzens nicht festgelegt ist.Such a device allows the emptying of any sack size, as this is this not carrying load cross in its height above the emptying nozzle is set.
Um die Bauhöhe des Lastkreuzpaares niedrig zu halten, wird vorgeschlagen, die Schlaufenträger vom unteren Lastkreuz nach oben hin zu versetzen, wozu auf dieses Distanzstücke aufgeschweißt werden. In order to keep the height of the pair of load crosses low, it is proposed that To move the loop carrier from the lower load cross upwards, for what purpose this spacers are welded on.
Um ferner das Volumen der Vorrichtung bei Nichtgebrauch klein zu halten, sind die Gelenkstangen vorzugsweise vollständig zusammenlegbar und das untere Lastkreuz um das Maß der Distanzstücke vergrößert, so daß das obere zwischen diese auf das untere Lastkreuz auflegbar ist.In addition, to keep the volume of the device small when not in use the joint rods are preferably completely collapsible and the lower one Load cross enlarged by the size of the spacers, so that the upper between it can be placed on the lower load cross.
In einer weiteren Ausführungsform ist mindestens einer Feder eine Skala zuge ordnet, so daß an dieser das Sackgewicht bzw. der Entleerungsgrad abgelesen werden kann. Die Federn sind dabei für den praktischen Anwendungsfall so aus gelegt, daß 4 cm Federweg 100 kg Gewicht entsprechen.In a further embodiment, at least one spring is assigned a scale arranges so that the sack weight or the degree of emptying can be read from this can be. The springs are made for practical use placed that 4 cm of travel correspond to 100 kg of weight.
Letztlich wird noch vorgeschlagen, zwischen den Lastkreuzen bzw. auf dem unte ren Lastkreuz Auflagerstempel anzuordnen, auf die das obere Lastkreuz aufleg bar ist, um die darunter befindliche Mechanik zu schützen, wobei die Auflager stempel geringfügig länger als die entspannten ersten, die Last aufnehmenden Federn sind.Ultimately, it is still suggested between the load crosses or on the bottom to arrange the load cross on which the upper load cross rests bar to protect the underlying mechanics, the support stamp slightly longer than the relaxed first, the load-bearing Feathers are.
Anhand der beiliegenden Figuren wird die Erfindung durch ein Ausführungsbei spiel näher erläutert. Dabei zeigenBased on the accompanying figures, the invention is by an example game explained in more detail. Show
Fig. 1 die entlastete Vorrichtung Fig. 1 the relieved device
Fig. 2 die Vorrichtung unter Last Fig. 2 shows the device under load
Fig. 3 eine solche gemäß Fig. 1 um 90° gedreht und Fig. 3 rotated such as shown in FIG. 1 by 90 ° and
Fig. 4 eine solche über der Entleerungsstation. Fig. 4 such over the emptying station.
Fig. 1 zeigt einen großen Sack (Big Bag) 1 mit seinem unteren Boden 10 sowie seinen oberen Schlaufen 3, die diesen an allen vier Ecken tragen. Die Schlaufen 3 sind im Schlaufenträger 6 des unteren Lastkreuzes 2 eingehängt. Dieses kann ein Stahlrohrrahmen sein. An den Ecken des unteren Lastkreuzes 2 befinden sich Distanzstücke 11, die auf das Lastkreuz 2 aufgesetzt sind, so daß sich dieses nach dem Einhängen der Schlaufen 3 in den Schlaufenträger 6 nahe dem Sack kopf 12 befindet. Fig. 1 shows a large sack (big bag) 1 with its lower bottom 10 and its upper loops 3 , which carry this at all four corners. The loops 3 are suspended in the loop carrier 6 of the lower load cross 2 . This can be a tubular steel frame. At the corners of the lower load cross 2 there are spacers 11 , which are placed on the load cross 2 , so that this is after hanging the loops 3 in the loop holder 6 near the bag head 12 .
Oberhalb des unteren Lastkreuzes 2 befindet sich ein oberes Lastkreuz 5 mit einer Öse 13 zur Anbringung des Hakens eines Hebezeuges. Above the lower load cross 2 is an upper load cross 5 with an eyelet 13 for attaching the hook of a hoist.
Oberes 5 und unteres Lastkreuz 2 weisen Laschen 14 auf, an denen die Gelenk stangen 7 schwenkbar befestigt sind, wobei die Gelenkstangen 7 über ein mittiges Gelenk 8 fest miteinander verbunden sind. Zwischen den Gelenken 8 befindet sich die zweite Zugfeder 9, die die Gelenke 8 bei Entlastung zueinander zieht. Grundsätzlich können dabei die zweiten Zugfedern so stark ausgebildet sein, daß sie mit den ersten Federn 4 zusammenwirken, diese sind am oberen Lastkreuz 5 angedeutet.Upper 5 and lower load cross-2 have tabs 14, on which the hinge bars are pivotally 7, wherein the connecting rods 7 are connected by a central joint 8 to each other. Between the joints 8 there is the second tension spring 9 , which pulls the joints 8 towards one another when relieved. Basically, the second tension springs can be so strong that they interact with the first springs 4 , these are indicated on the upper cross 5 .
Die Wirkung der zweiten Zugfedern 9 ist dabei am stärksten, wenn die Gelenk stangen 7 gestreckt sind, d. h. die ersten Federn unter Vollast stehen.The effect of the second tension springs 9 is strongest when the joint rods 7 are stretched, ie the first springs are under full load.
Fig. 2 zeigt die Vorrichtung unter der Last des Sacks 1. Die vier Gelenkstangen 7 sind gestreckt, die zweiten Zugfedern 9 befinden sich unter maximaler Ausdeh nung. Fig. 2 shows the device under the weight of the bag 1. The four link rods 7 are stretched, the second tension springs 9 are under maximum expansion.
Fig. 3 zeigt den Zustand aus Fig. 1, dabei jedoch um 90° gedreht, so daß die dort hinter den Gelenkstangen 7 verdeckten (vier) ersten Spiralfedern 4 zwischen unterem 2 und oberem Lastkreuz 5 sichtbar werden. Es ist ohne weiteres möglich, die Aufhängungen 15 der Spiralfeder 4 vertikal veränderbar auszubilden, so daß die Federspannung veränderbar wird. Fig. 3 shows the state of Fig. 1, but rotated by 90 °, so that there hidden behind the articulated rods 7 (four) first coil springs 4 between the lower 2 and upper load cross 5 are visible. It is easily possible to design the suspensions 15 of the spiral spring 4 so that they can be changed vertically, so that the spring tension can be changed.
Fig. 4 zeigt die gesamte Anlage mit einer Laufkatze 16 samt Hebezeug. Diese trägt die erfindungsgemäße Vorrichtung, so daß wie in Fig. 2 die Gelenkstangen 7 gestreckt sind. Unterhalb des Sackes 1 ist die Entleerungsvorrichtung 17 darge stellt. Diese weist einen Förderer 18 auf, sowie einen Stutzen 19, an dem der Bodenrüssel 21 des Sacks 1 festgespannt wird, sowie einen darunterliegenden Trichter 20, über den das Schüttgut in den Förderer 18 gelangt. Fig. 4 shows the entire system with a trolley 16 including a hoist. This carries the device according to the invention, so that the articulated rods 7 are stretched as in FIG. 2. Below the bag 1 , the emptying device 17 is Darge. This has a conveyor 18 , as well as a nozzle 19 , on which the bottom trunk 21 of the bag 1 is clamped, and an underlying funnel 20 , through which the bulk material reaches the conveyor 18 .
11
Sack
bag
22nd
Lastkreuz (unteres)
Load cross (lower)
33rd
Schlaufen
Loops
44th
erste Federn
first feathers
55
oberes Lastkreuz
upper load cross
66
Schlaufenträger
Loop holder
77
Gelenkstangen
Articulated rods
88th
Gelenke
Joints
99
zweite Zugfedern
second tension springs
1010th
Boden
ground
1111
Distanzstücke
Spacers
1212th
Sackkopf
Sack head
1313
Öse
eyelet
1414
Laschen
Tabs
1515
Aufhängungen
Suspensions
1616
Laufkatze
Trolley
1717th
Entleerungsvorrichtung
Emptying device
1818th
Förderer
Sponsor
1919th
Stutzen
Support
2020th
Trichter
funnel
2121
Bodenrüssel
Soil proboscis
Claims (5)
- a) dem ersten Lastkreuz (2) ist ein darüberliegendes zweites Lastkreuz (5) zugeordnet;
- b) zwischen dem oberen Lastkreuz (5) und dem unteren Lastkreuz (2) sind vier erste Zugfedern (4) angeordnet;
- c) zwischen oberem (5) und unterem Lastkreuz (2) befinden sich den ersten Federn (4) zugeordnete Schwingsicherungen in Form von Gelenkstangen (7)
- d) zwischen die Gelenke (8) der Gelenkstangen (7) sind zweite Zugfedern (9) eingespannt.
- a) the first load cross ( 2 ) is assigned an overlying second load cross ( 5 );
- b) four first tension springs ( 4 ) are arranged between the upper load cross ( 5 ) and the lower load cross ( 2 );
- c) between the upper ( 5 ) and lower load cross ( 2 ) there are vibration locks assigned to the first springs ( 4 ) in the form of articulated rods ( 7 )
- d) second tension springs ( 9 ) are clamped between the joints ( 8 ) of the joint rods ( 7 ).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1997144499 DE19744499C1 (en) | 1997-10-09 | 1997-10-09 | Emptying machine for bulk material sacks |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1997144499 DE19744499C1 (en) | 1997-10-09 | 1997-10-09 | Emptying machine for bulk material sacks |
Publications (1)
Publication Number | Publication Date |
---|---|
DE19744499C1 true DE19744499C1 (en) | 1999-02-18 |
Family
ID=7844978
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1997144499 Expired - Fee Related DE19744499C1 (en) | 1997-10-09 | 1997-10-09 | Emptying machine for bulk material sacks |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE19744499C1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10110025A1 (en) * | 2001-03-01 | 2002-09-05 | Stockhausen Chem Fab Gmbh | Last Traverse |
EP2128052A2 (en) | 2008-05-28 | 2009-12-02 | Günther GmbH | Method and device for handling BigBags |
DE102009013392A1 (en) * | 2008-05-28 | 2009-12-24 | Günther GmbH | Heavy loadable bag i.e. big bag, handling device for use in e.g. pharmaceutical industry, has lifting device spaced in longitudinal direction of rail and having cutting bars arranged transverse to longitudinal direction of conductor rail |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4419599C1 (en) * | 1994-06-03 | 1996-01-25 | Schreier Maschinen Und Apparat | Device for emptying sacks containing earth |
-
1997
- 1997-10-09 DE DE1997144499 patent/DE19744499C1/en not_active Expired - Fee Related
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4419599C1 (en) * | 1994-06-03 | 1996-01-25 | Schreier Maschinen Und Apparat | Device for emptying sacks containing earth |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10110025A1 (en) * | 2001-03-01 | 2002-09-05 | Stockhausen Chem Fab Gmbh | Last Traverse |
EP2128052A2 (en) | 2008-05-28 | 2009-12-02 | Günther GmbH | Method and device for handling BigBags |
DE102009013392A1 (en) * | 2008-05-28 | 2009-12-24 | Günther GmbH | Heavy loadable bag i.e. big bag, handling device for use in e.g. pharmaceutical industry, has lifting device spaced in longitudinal direction of rail and having cutting bars arranged transverse to longitudinal direction of conductor rail |
EP2128052A3 (en) * | 2008-05-28 | 2009-12-30 | Günther GmbH | Method and device for handling BigBags |
DE102009013392B4 (en) * | 2008-05-28 | 2010-11-11 | Günther GmbH | Apparatus and method for handling bigbags |
DE102009013392C5 (en) * | 2008-05-28 | 2013-06-06 | Günther GmbH | Apparatus and method for handling bigbags |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1349788B1 (en) | Device for large-volume containers | |
EP0612301B1 (en) | Transport and/or storage device for general cargo items | |
DE3424613A1 (en) | DEVICE FOR FILLING FLEXIBLE BULK CONTAINER | |
AT394540B (en) | HOLDING DEVICE FOR BAGS | |
WO1993025464A1 (en) | Hoisting device for loads | |
DE1816627A1 (en) | Large-capacity transport container for liquid or flowable goods | |
DE1586738A1 (en) | Container for loose goods | |
DE19744499C1 (en) | Emptying machine for bulk material sacks | |
DE3206829A1 (en) | Device for transporting a laundry bag by means of a suspended roller conveyor | |
DE2148048A1 (en) | CONTAINER FOR SHOULDER OR FLOWABLE GOODS, IN PARTICULAR BUILDING MATERIALS, WITH A BASE | |
DE3912409C2 (en) | ||
DE4419599C1 (en) | Device for emptying sacks containing earth | |
EP0338492B1 (en) | Split-container for the segregated collection of different materials | |
DE69819530T2 (en) | METHOD AND DEVICE FOR PRESS-PACKING TREES AND STRUSHING PLANTS ON PALLETS WITH SIDE EDGES | |
DE2646493A1 (en) | LIFTING HARNESS FOR FILLED BAGS | |
EP0216950B1 (en) | Carrier for an overhead conveyor | |
DE10041832B4 (en) | Silo or container using limp wall material | |
WO2007082871A2 (en) | Suspended flexible compartment structure | |
EP0422521B1 (en) | Filter press | |
DE2506358C3 (en) | Air freight container | |
DE19858177A1 (en) | Holding device for sack, e.g. for refuse, with holding device formed from adjustable rack | |
DE2825643C3 (en) | Device for simultaneous lifting and moving of loads | |
DE2929318A1 (en) | Ceiling formwork element hinged support assembly - has angular bars with top loop shackles, welded on bottom of tubular struts | |
DE19741108A1 (en) | Folding frame for flexible intermediate bulk container holding products | |
DE2408427C3 (en) | Device for fixing two wall parts of a lattice box pallet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8100 | Publication of the examined application without publication of unexamined application | ||
D1 | Grant (no unexamined application published) patent law 81 | ||
8364 | No opposition during term of opposition | ||
8339 | Ceased/non-payment of the annual fee |