DE1939551A1 - Track wagons for hammers - Google Patents

Track wagons for hammers

Info

Publication number
DE1939551A1
DE1939551A1 DE19691939551 DE1939551A DE1939551A1 DE 1939551 A1 DE1939551 A1 DE 1939551A1 DE 19691939551 DE19691939551 DE 19691939551 DE 1939551 A DE1939551 A DE 1939551A DE 1939551 A1 DE1939551 A1 DE 1939551A1
Authority
DE
Germany
Prior art keywords
track
hammers
demolition hammers
wagon according
track wagon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DE19691939551
Other languages
German (de)
Inventor
Alfred Wassmer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to BE754301D priority Critical patent/BE754301A/en
Application filed by Individual filed Critical Individual
Priority to DE19691939551 priority patent/DE1939551A1/en
Priority to AT702370A priority patent/AT306082B/en
Priority to FR7029150A priority patent/FR2056700A5/fr
Priority to CH1174570A priority patent/CH519063A/en
Publication of DE1939551A1 publication Critical patent/DE1939551A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/06Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
    • E01C23/09Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges
    • E01C23/0906Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges for forming, opening-out, cleaning, drying or heating cuts, grooves, recesses or, excluding forming, cracks, e.g. cleaning by sand-blasting or air-jet ; for trimming paving edges
    • E01C23/0926Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges for forming, opening-out, cleaning, drying or heating cuts, grooves, recesses or, excluding forming, cracks, e.g. cleaning by sand-blasting or air-jet ; for trimming paving edges with power-driven tools, e.g. vibrated, percussive cutters

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

Alfred Wassmer 3 BlattAlfred Wassmer 3 sheets

Btthl/BadenBtthl / Baden

Industriestrasse 24
Spurwagen für Schlaghämmer
Industriestrasse 24
Track car for demolition hammers

Die Erfindung betrifft einen Spurwagen, der mehrere Schlaghämmer stationär aufnehmen kann, sie mit einem Verteilersystem verbindet und fahrbar voll Binsatzfähig, die Spureinstiche ausführt.The invention relates to a track wagon that has several hammers Can pick up stationary, connect them to a distribution system and fully deployable, the track punctures executes.

Bekannt sind bisher der manuelle Einsatz von Schlaghämmern im Tiefbau.The manual use of hammer hammers are known so far in civil engineering.

Im Zuge der Rationalisierung unter Verwendung von Baumaschinen verschiedenster Art, bleibt der manuelle Einsatz von Schlaghämmern hinter der maschinellen Ausfühtung bemerkenswert zurück. In the course of rationalization using construction machinery of various kinds, the manual use of impact hammers lags behind the mechanical execution remarkably.

Die körperlichen Aufwendungen nehmen viel Zeit in Anspruch, dadurch entstehen mitunter erhebliche Wartezeiten für Baumaschinen, die im Arbeitseinsatz folgen. Diese Wartezeiten sollen verhindert werden.The physical effort takes a lot of time, which sometimes results in considerable waiting times for construction machinery, which follow in work. These waiting times should be avoided.

.Der Erfindung liegt die Aufgabe zugrunde, die Schlaghammer in Verbindung mit den Spurwagen mechanisch und fahrbar einzusetzen.The invention is based on the object of the hammer in To be used mechanically and movably in connection with the track wagons.

Dies wird erfindungsgemäss dadurch erzielt, dass Vorzugsweise ζ«ei Schlaghammer zu beiden Seiten des Spurwagens an eine Führungsvorrichtung hängen, die Verstellbar ist.This is achieved according to the invention in that preferably ζ «ei hammer on both sides of the track carriage to one Hang guide device that is adjustable.

An der Pührungsvorrichtung können die Schlaghämmer je nach erforderlichen Abständen voneinander eingestellt werden.The hammer can be attached to the guiding device as required Distances from each other can be set.

Die Versorgungsanschlüsse der Schlaghämmer werden mit dem Verteilersystem des Spurwagens verbunden.The supply connections of the demolition hammers are connected to the distribution system of the track car connected.

Der steuerbare Spurwagen ist einsatzbereit und kann seine Binstichspur abfahren. 109808/0157The steerable track wagon is ready for use and can use its binstitch track depart. 109808/0157

Auf diese Weise werden zwei parallel laufende Einstichepuren mit einem Arbeitsgang ausgeführt, die bisher mehrere Arbeitsgänge erforderten.In this way, two puncture tracks running in parallel are carried out in one operation, which was previously several operations required.

Haben die Spaten der Schlaghämmer ihre Tiefe in der Straßendecke erreicht, werden sie mechanisch angehoben. Der Spurwagen rollt um eine Spatenbreite weiter und setzt zum nächsten Einstich wieder an.When the spades of the demolition hammers have reached their depth in the road surface, they are lifted mechanically. The track car rolls by a spade width and starts again for the next cut.

Somit kann durch eine Aufsichtsperson mindestens zwei Schlagh'ämmer zur gleichen Zeit,ohne körperliche Anstrengungen betätigt werden.A supervisor can therefore use at least two demolition hammers be operated at the same time without physical exertion.

Sin Zentralschmiersystem versorgt alle Verschleissteile wartungsfrei. Sin central lubrication system supplies all wear parts maintenance-free.

Die einmal ermittelte Spureinstellung,- die doppelseitige Arbeit swirkung, und die Fahreigenschaft,- macht -dieses Gerät rationell und führt zu einer exakten Spurarbeit.The track setting once determined, - the double-sided work effect, and the driving characteristics, - is what makes this device rational and leads to precise tracking.

Die variable Einsatzmöglichkeiten, erlauben alle gewünschten Bauformen, die den Erfindungsgegenstand betreffen. Daher wird im Rahmen dieser Erfindung, Patentschutz begehrt.The variable application options allow all desired designs that relate to the subject matter of the invention. Therefore, patent protection is sought in the context of this invention.

Zur weiteren Erläuterung, wird eine Ausführungsart auf die Zeichnung hingewiesen.For further explanation, an embodiment is referred to the drawing.

Die Erfindung wird dargestellt durch,-Abb. I in Vorderansicht,
Abb. 2 in Seitenansicht.
The invention is illustrated by -Fig. I in front view,
Fig. 2 in side view.

Während die Schlaghämmer I,in Tätigkeit sind, senkt eich die Führungsvorrichtung 2,mit den kurzen Hebelarm 4,in ihr· Führungsäulen 6,nach jedem Hammerschlag.While the demolition hammers are in action, they are lowered Guide device 2, with the short lever arm 4, in it Guide pillars 6, after each hammer blow.

Haben die Spaten 5iihre Tiefe in der Strassendacke erreicht, steht der lange Hebelarm 4,in waagerechte Stellung.When the spades have reached their depth in the street roof, the long lever arm 4 is in a horizontal position.

109808/0157109808/0157

Durch Gegendruck auf den langen Hebelarm 4, werden die Schlaghanraier mit der Führungsvorrichtung über den Drehpunkt des Hebelarmes 7t wieder angehoben und zum nächsten Einstich freigegeben, wenn der Spurwagen um eine Spatenbreite weiter gerollt ist.By counter-pressure on the long lever arm 4, the striker with the guide device are raised again over the pivot point of the lever arm 7t and released for the next puncture when the track carriage has rolled a spade width further.

Die Führungsplatten 3iHiit den daran befestigten SchlaghSmmem I, sind voneinander verstellbar.The guide plates 3iHi with the attached hammer I, are adjustable from each other.

Claims (5)

Patentanspruch Spurwagen, zur stationären Aufnahme mehrere Schlaghämmer, die alle gleichzeitig betätigt werden,,Patent claim track wagon, several demolition hammers for stationary recording, all of which are operated at the same time, 1. ist nach Patentanspruch dadurch gekennzeichnet, dass durch eine Aufsichtsperson mehrere Schlaghämmer in einem Arbeitsgang fahrbar betätigt werden.1. is characterized according to claim characterized in that by a supervisor can operate several demolition hammers in one operation. 2. Spurwagen nach Anspruch I dadurch gekennzeichnet, dass die Spurweite der Schlaghämmer voneinander verstellbar sind. 2. Track wagon according to claim I, characterized in that the track width of the demolition hammers are adjustable from one another. 3· Spurwagen nach Anspruch I und 2 dadurch gekennzeichnet, dass er von Hand gesteuert werden kann.3 · track wagon according to claim 1 and 2, characterized in that it can be controlled by hand. 4. Spurwagen nach Anspruch I bis 3 dadurch gekennzeichnet, dass er automatisch gesteuert=werden kann.4. track wagon according to claim I to 3, characterized in that it can be controlled automatically. 5. Spurwagen nach Anspruch I bis 4 dadurch gekennzeichnet, dass er in allen gewünschten Bauformen hergestellt werden kann. Änderungen vorbehalten.5. track wagon according to claim I to 4, characterized in that it can be produced in all desired designs. Subject to changes. 109808/0157109808/0157 LeerseiteBlank page
DE19691939551 1969-08-04 1969-08-04 Track wagons for hammers Pending DE1939551A1 (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
BE754301D BE754301A (en) 1969-08-04 GUIDE TROLLEY FOR PUNCH HAMMERS
DE19691939551 DE1939551A1 (en) 1969-08-04 1969-08-04 Track wagons for hammers
AT702370A AT306082B (en) 1969-08-04 1970-08-03 Device for holding simultaneously operated hammers with spades to tear open the road surface
FR7029150A FR2056700A5 (en) 1969-08-04 1970-08-03
CH1174570A CH519063A (en) 1969-08-04 1970-08-04 Track carriage for picking up simultaneously operated hammers with spades for tearing open the road surface

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19691939551 DE1939551A1 (en) 1969-08-04 1969-08-04 Track wagons for hammers

Publications (1)

Publication Number Publication Date
DE1939551A1 true DE1939551A1 (en) 1971-02-18

Family

ID=5741836

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19691939551 Pending DE1939551A1 (en) 1969-08-04 1969-08-04 Track wagons for hammers

Country Status (5)

Country Link
AT (1) AT306082B (en)
BE (1) BE754301A (en)
CH (1) CH519063A (en)
DE (1) DE1939551A1 (en)
FR (1) FR2056700A5 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1980002704A1 (en) * 1979-06-07 1980-12-11 Joad Eng Ltd Scabblers

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988315B (en) * 2017-05-18 2023-01-31 中国水利水电第五工程局有限公司 Dam bedding material spreading machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1980002704A1 (en) * 1979-06-07 1980-12-11 Joad Eng Ltd Scabblers

Also Published As

Publication number Publication date
FR2056700A5 (en) 1971-05-14
BE754301A (en) 1971-01-18
AT306082B (en) 1973-03-26
CH519063A (en) 1972-02-15

Similar Documents

Publication Publication Date Title
DE9017638U1 (en) Rail breaker
DE2716741A1 (en) IMPROVED EARTHMOVING MACHINE
DE1939551A1 (en) Track wagons for hammers
DE3437401C2 (en)
DE1583806B2 (en) Pneumatic percussion hammer
DE2830802A1 (en) TRACK DRIVING MACHINE
DE2340346C3 (en) Tool fastening device for a stone working machine, in particular for a mining machine in underground mining
DE2316019A1 (en) LAYING VEHICLE FOR FLOORING SLABS AND METHOD OF LAYING FLOORING SLABS USING THIS INSTALLATION VEHICLE
DE519943C (en) Punching and punching machine with punch holder that can be moved by hand independently of the power drive
DE10354265B4 (en) Double wood splitter
DE668624C (en) Conveyor slide with an extendable trough, the feed of which is driven independently by the slide drive
DE102016010913A1 (en) System for handling lattice pieces
DE568529C (en) Wedge head rigidly connected with mining hammers
DE638177C (en) Device for feeding the dredged material in a portal swing excavator working in front of the head
DE875793C (en) Shovel with foldable and lockable shovel blade for digging groin holes in underground mining
DE2455078A1 (en) SELF-PROPELLED VEHICLE FOR MINING
DE644560C (en) Hand-held power rams, especially for compacting soil
DE1910484C3 (en) Paver finisher
DE2639148C3 (en) Activated coal plow for underground longwall mining
DE69317011T2 (en) Excavator bucket with a hydraulic breaker
DE2114150C (en) Vehicle with a boom that accepts a drilling or shaft tool
DD216496A1 (en) DEVICE FOR BREAKING ROAD CEILINGS
DE2412996C3 (en) Process for fully mechanical coal extraction from seams stored between 50 and 100 «
DE2552103A1 (en) HANDHELD TRUCK, IN PARTICULAR FOR THE TRANSPORTATION AND LOADING AND UNLOADING OF STACKABLE GOODS
DE435067C (en) Hand lever press for the production of bricks, roof tiles, panels, etc. like