DE1634652A1 - Foundation stake - Google Patents

Foundation stake

Info

Publication number
DE1634652A1
DE1634652A1 DE19661634652 DE1634652A DE1634652A1 DE 1634652 A1 DE1634652 A1 DE 1634652A1 DE 19661634652 DE19661634652 DE 19661634652 DE 1634652 A DE1634652 A DE 1634652A DE 1634652 A1 DE1634652 A1 DE 1634652A1
Authority
DE
Germany
Prior art keywords
shaft
pile
cement slurry
head
adjoining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DE19661634652
Other languages
German (de)
Inventor
Auf Nichtnennung Antrag
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WILHELM VOELKER GEGR FA
Original Assignee
WILHELM VOELKER GEGR FA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WILHELM VOELKER GEGR FA filed Critical WILHELM VOELKER GEGR FA
Publication of DE1634652A1 publication Critical patent/DE1634652A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

Wilhelm Völker r Hoch-, Tief- und Ingenieurbau, 3587 BorkenWilhelm Völker r civil engineering and civil engineering, 3587 Borken

Gründungs pfahlFoundation stake

Es ist bekannt, während des Bammens und unmittelbar nach dem Kämmen von Gründungspfählen durch das Pfahlinnere oder durch ein beigelegtes Hohr Zementhrei bzw. Mörtel einzupressen. Die Verpreßmasse tritt oberhalb der verdickten Pfahlspitze längs des Schaftes aus und dringt in den freien Hohlraum und in die Poren des Erdreiches ein, so daß nach der Verfestigung der Pfahlschaft mit dem Erdreich innig verbunden wird. (M?-Pfahl) Sa man Pfahlgründungen gewöhnlich bei schlechter Beschaffenheit der oberen Bodenschicht verwendet, ist die Mantelreibung in dem oberen Teil des Pfahles nicht groß. Die Tragfähigkeit des Pfahles ergibt sich hauptsächlich aus der Mantelreibung der unteren tragfähigen Bodenschichten und den Spitzenwiderstand.It is known during the banging and immediately after the combing of foundation piles through the inside of the pile or with an enclosed Hohr cement egg or mortar. The grout occurs above the thickened pole tip along the shaft and penetrates into the free cavity and into the pores of the soil a, so that after the stake shaft has solidified with the Earth is intimately connected. (M? -Pole) Pile foundations were usually said to be in poor condition When using the upper soil layer, the skin friction in the upper part of the pile is not great. The load-bearing capacity of the pile results mainly from the skin friction of the lower load-bearing soil layers and the tip resistance.

Beim fiammen mit gleichzeitiger Einpressung der Zementschlämme tritt bei den bisherigen Verfahren ein. Teil der Zementschlämme ringsum den Pfahl an der Oberfläche aus und läßt keine Drucksteigerung beim Verpreßvorgang zu. In dieser Hinsicht gibt es auch Lösungen mittels Verpreßglocken, die als verloren oder als mehrfach verwea&bares Werkzeug zum Abdämmen am Pfahlschaft oben angesetzt werden. Es handelt sich hierbei um Lösungen, die bei weniger gut tragfähigen Bodenschichten im oberen Pfahlbereich versagen. Schon bei geringen Drucksteigerungen tritt ein Aufbruch des Erdreiches im Bereich der Verpreßglocke ein. Die Erfindung stellt sich die Aufgabe, solche Verluste zu vermeiden, auch wenn der Druck so hoch gemacht wird, wie es zum Eindringen der Zeiaents chi amme in das Erdreich eKrttasoht ist. Bafeei wird vom der Erlceaatais Gebrauch gemacht, daß der ofeere Teil los Pfaklso treraig zur Smgfähigksit beiträgt, wie obea gesagt.In the previous process, when the cement slurry is fired and injected at the same time, this occurs. Part of the cement slurry all around the pile on the surface and does not allow any pressure increase during the grouting process. In this regard, there are also solutions by means of grouting bells, which can be used as lost tools or tools that can be used several times for damming on the pile shaft at the top. These are solutions that fail in the case of less stable soil layers in the upper pile area. Even with a slight increase in pressure, the earth breaks up in the area of the injection bell. The object of the invention is to avoid such losses, even if the pressure is made as high as it is necessary for the Zeiaents chi amme to penetrate into the ground. Bafeei is made use of the Erlceaatais that the open part los Pfaklso treraig contributes to smg ability, as obea said.

ßoaä® files Ssfiagnag uieä sum Biapsessea von ZeseatscliläiaH® währead dos Ibqboss vmi. iMmitt&Xhas aaeh dss HaEasaeia ©ia Staiilb©t©apfahl sen Eii£§ta©B &©£■ gsmoatseSiläEra© axt üiaer L&w.Qu'buksmig %ux Pfahlopitso 0® gestaltet, äaß ia sateres B©s?e±oh. ü.@v Sfahlsefeaft Isleiaarßoaä® files Ssfiagnag uieä sum Biapsessea by ZeseatscliläiaH® during dos Ibqboss vmi . iMmitt & Xhas aaeh dss HaEasaeia © ia Staiilb © t © apfahl sen Eii £ §ta © B & © £ ■ gsmoatseSiläEra © axt üiaer L &w.Qu'buksmig% ux Pfahlopitso 0® designed, äaß ia sateres B © s? e ± oh. ü. @ v Sfahlsefeaft Isleiaar

Bos' os£±B&miQosone.Bo &züm&MBßo®£e,fol tons in am siofe "bßlraaatQB. If©ioaBos' os £ ± B & miQosone.Bo & züm & MBßo® £ e, fol tons in am siofe "bßlraaatQB. If © ioa

Boten fesotoboa. . .Messengers fesotoboa. . .

Der Yorteil der Erfindung besteht darin, daß der obere Seil des Schaftes, der im allgemeinen im wenig oder nicht tragfähigem Boden zu stehen koamt, den Verpressraum oberhalb der Pfahlspitze zum Pfahlkopf hin fest verschließt und dadurch das Entweichen der eingepreßten Zementsehlämme verhindert, wesentliche Drucksteigerungen der Einpreßmasse zuläßt und somit einen besonders guten Verbund zwischen Pfahlschaft und Erdreich gewährleistet. Zusätzlich wirkt die Verpreßmasse für den oberen verdickten Schaft als Schmiermittel und damit wird geringere Rammenergie benötigt.The Yorteil of the invention is that the upper rope of the Shaft, which is generally in little or no load-bearing soil Koamt to stand, the grouting area above the pile tip to the pile head tightly closes and thereby the escape of the pressed in Prevents cement floss, allows significant pressure increases in the grout and thus a particularly good bond guaranteed between the stake shaft and the ground. In addition, the molding compound acts as a lubricant for the upper thickened shaft and thus less ramming energy is required.

Sie Quellwirkung der speziell für die Bodenverdichtung entwickelten Zugabeaittel bei den verschiedenen Zements orten kommt bei der erfindungsgemäßen Gestaltung erst voll zur Geltung, da nach Beendigung des Terpreßvorganges das Zuleitungsrohr am Pfahlkopf dicht verschlossen werden kann, so daß die Verpreßmasse unter Beibehaltung des Verpreßdruckes und eventueller Drucksteigerung infolge Quellwirkung erhärten kann. Dadurch wird eine zusätzliche Bodenverdichtung im Tragbereich des Pfahles erzielt.The swelling effect of the specially developed for soil compaction Admixture in the various cement locations is only fully effective in the design according to the invention, since after Completion of the Terpreßvorganges the supply pipe at the pile head can be tightly closed so that the grout while maintaining the grouting pressure and any increase in pressure due to the swelling effect can harden. This results in additional soil compaction in the bearing area of the pile.

Die Zeichnung zeigt ein Ausführungsbeispiel der Erfindung. Die wirklichen Maßverhältnisse sind in der Zeichnung nicht eingehalten, um die deutliche Übersicht nicht zu stören.The drawing shows an embodiment of the invention. The real proportions in the drawing are not adhered to, so as not to disturb the clear overview.

Figur 1 zeigt den Pfahl von der Seite. Figur 2 ist in größerem Maßstab ein Längsschnitt durch den obersten Seil des Schaftes. Figur 3 ist ein Querschnitt durch den unteren Teil des Schaftes längs der Linie III-III der Figur 1. Figur 4 ist ein Längsschnitt durch die Pfahlspitze.Figure 1 shows the pile from the side. FIG. 2 is, on a larger scale, a longitudinal section through the uppermost rope of the shaft. Figure 3 is a cross-section through the lower part of the shaft along the line III-III of Figure 1. Figure 4 is a longitudinal section through the pole tip.

Mit 1 ist die Spitze bezeichnet, mit 2 der obere Teil der Pfahlspitze, mit 5 der untere Teil des Schaftes und mit 4 der erfindungsgemäß gleich oder dicker als der Teil 2 der Pfahlspitze ausgeführte obere Teil des Schaftes, »er Teil 5 geht axt einer Stufe $" in den Teil 4 über.With 1 the tip is designated, with 2 the upper part of the pole tip, with 5 the lower part of the shaft and with 4 the upper part of the shaft designed according to the invention the same or thicker than the part 2 of the pole tip, »he part 5 goes ax of a step $ " in Part 4.

Durch fast die ganze Länge tee Pfahles erstreckt sich die Bohrung 6, die oberhalb der Pfahlepitxe seitlich vom Schaft 5 in Öffnungen 7 ausmündet und oben mit einer Eintrittsöffnung 8 veraehen ist.The bore extends through almost the entire length of the pile 6, which are above the pole epitxes on the side of the shaft 5 in openings 7 opens out and is provided with an inlet opening 8 at the top.

009838/0453009838/0453

Claims (2)

Patentanspruch.Claim. Gründungspf ahl zum Einspritzen von Zementschlämme während des Eammens und unmittelbar nach dem Rammen, mit einer Längs-"bohrung zum Zuführen der Zementschlämme und einem zugespitzten Kopf, dessen öfterer Teil einen größeren Querschnitt hat als der .daran anschließende Schaft und an seiner Oberseite neben dem Schaft Austrittsöffnungen für die Zementschlämme hat, dadurch gekennzeichnet, daß der an den Kopf (1,2) anschließende Schaftteil (3) oben mit einer Stufe (5) in einen dickeren Teil (4-) übergeht, dessen Querschnitt etwas größer ist als der des oberen Teils (2) des Kopfes„Foundation pile for injecting cement slurry during of the embedding and immediately after the ramming, with a longitudinal "bore for feeding the cement slurry and a pointed head, the more often part of which has a larger cross-section than the shaft adjoining it and on its upper side next to the shaft has outlet openings for the cement slurry, characterized in that the shaft part (3) adjoining the head (1, 2) at the top with a step (5) into a thicker one Part (4-) passes over, the cross-section of which is slightly larger than that of the upper part (2) of the head " 2) Gründungspfahl nach Anspruch 1, dadurch gekennzeichnet, daß er aus eisenarmiertem Beton besteht.2) foundation pile according to claim 1, characterized in that it consists of iron-reinforced concrete. 0098387045300983870453 LeerseiteBlank page
DE19661634652 1966-05-12 1966-05-12 Foundation stake Pending DE1634652A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEV0031039 1966-05-12

Publications (1)

Publication Number Publication Date
DE1634652A1 true DE1634652A1 (en) 1970-09-17

Family

ID=7586117

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19661634652 Pending DE1634652A1 (en) 1966-05-12 1966-05-12 Foundation stake

Country Status (1)

Country Link
DE (1) DE1634652A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0371538A1 (en) * 1988-11-28 1990-06-06 de Waal, Victor Jan, Dr.Ir. Foundation pile which is made up of a number of pile elements

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0371538A1 (en) * 1988-11-28 1990-06-06 de Waal, Victor Jan, Dr.Ir. Foundation pile which is made up of a number of pile elements

Similar Documents

Publication Publication Date Title
DE1759338C3 (en) Method for producing a grout anchor and device for carrying out the method
DE955678C (en) Method and device for mountain fastening by bolts and for fastening bolts in boreholes, especially in mining operations
DE1945188U (en) DEVICE FOR INSERTING ANCHORS IN LOOSE AND SOLID SOIL.
DE1946026U (en) MOUNTAIN ANCHORS.
DE2432708A1 (en) TUBULAR PILE AND PROCEDURE FOR ITS GROUND IN A DRILLED HOLE
DE2226169C2 (en) Device for the formation of a grouting anchor
DE2147051A1 (en) PROCEDURE FOR MAKING A PRESSURE POST IN THE SOIL
DE3204417C2 (en) Arrangement for setting a rock nail
DE618328C (en) Support walls, dam walls, weir systems or similar structures
DE1634652A1 (en) Foundation stake
DE2034662A1 (en) Method for attaching an anchor in the ground and the like and anchors for carrying out this method
DE2229383A1 (en) METHOD AND DEVICE FOR CONSOLIDATING THE SOIL, IN PARTICULAR FOR THE FOUNDATION OF PILES OR SIMILAR FOUNDATION STRUCTURES
DE1215603B (en) Procedure for increasing the load-bearing capacity of prefabricated piles and prefabricated piles for carrying out this procedure
DE1904371A1 (en) Method for producing a tie rod for anchoring components in the ground and injection anchors, in particular for carrying out the method
DE683407C (en) Procedure for the foundation of concrete piles
DE1129895B (en) Method and device for the production of a foundation pile with concrete casing
AT269002B (en) Injection tension anchoring in the ground and process for their production
DE902959C (en) Device and method for the production of foundation piles
DE2412667A1 (en) ANCHORS FOR STRENGTHENING THE MOUNTAIN OF STOLLEN, TUNNEL AND DGL
DE1634431A1 (en) Procedure for restoring the load-bearing capacity of foundation bodies that have become damaged
DE1928471A1 (en) Process and device for compacting and draining soil
DE1634554A1 (en) Injection tie rods
DE747192C (en) Founding procedure for piles in non-rammable rock
AT204986B (en) Double wedge anchors, especially for pit and tunnel construction
DE29715363U1 (en) Anchor element for a grout anchor