DE1484559A1 - Floatable drilling rig or the like. - Google Patents
Floatable drilling rig or the like.Info
- Publication number
- DE1484559A1 DE1484559A1 DE19641484559 DE1484559A DE1484559A1 DE 1484559 A1 DE1484559 A1 DE 1484559A1 DE 19641484559 DE19641484559 DE 19641484559 DE 1484559 A DE1484559 A DE 1484559A DE 1484559 A1 DE1484559 A1 DE 1484559A1
- Authority
- DE
- Germany
- Prior art keywords
- legs
- ballast
- platform
- water
- leg
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
- E02B17/027—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto steel structures
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Earth Drilling (AREA)
- Heat Treatment Of Water, Waste Water Or Sewage (AREA)
Description
Roger SELlGMAN ,17 Bayou Bonfuca R?ad/ Slidell, Louisiana, USARoger SELlGMAN, 17 Bayou Bonfuca R? Ad / Slidell, Louisiana, USA
Schv/i; unfähige Bohrinsel od. dgl.Schv / i; incompetent drilling rig or the like.
Die Erfindung bezieht sioh auf schwimmfähige Arbeitsplattformen bzw. schwimmfähige Bohrinseln für Arbeiten auf dem Wasser, die eine gegenüber dem Seegrund bzw· Meeresgrund feststehende Plattform bilden können. Insbesondere bezieht sich die Erfindung auf eine Arbeitsplattform, welche schwimmt, so lange sie noch nicht zum Durchführen eines Bohrvorganges an der gewünschten Stelle fest verankert" bzw. angeordnet ist.The invention relates sioh to floating work platforms or floating drilling rigs for work on the water, which are opposite to the lake bed or Can form a fixed platform at the bottom of the sea. In particular, the invention relates to a work platform which floats while it is not is firmly anchored or arranged to carry out a drilling process at the desired location.
Bisher wurde ein Großteil der Unterwasserbohrungen naoh Öl und Gas von Plattformen ausgeführt, die teleskopartig nach unten auf den Seegrund oder den Meeresgrund verschiebbare Beine aufweisen, oder von Plattformen, die auf in den Meeresgrund eingerammten Säulen errichtet sind. Diese bekannten Vorrichtungen haben senkrechtSo far, most of the underwater drilling has been carried out Oil and gas run from platforms that telescope down to the lake bed or the ocean floor have slidable legs, or of platforms erected on pillars rammed into the seabed are. These known devices have perpendicular
909821/0053909821/0053
_2_ . H84559 »_ 2 _. H84559 »
verlaufende Stützbeine. Die bekannten Vorrichtungen dieser Art weisen die Nachteile auf, daß sie entweder direkt am Bohrplatz errichtet werden müssen, oder, wenn es sich um schwimmfähige Plattformen handelt, daß sie äußerst sperrig und schwierig an den gewünschten Arbeitsort zu ziehen sind, wobei sie während der Beförderung zu dem gewünschten Ort kippen bzw. kentern können. Außerdem erfordern diese bekannten schwimmfähigen Bohrinseln bzw. Plattformen eine sehr aufwendige Vorrichtung zum Verankern der Plattform auf dem Meeresgrund. Deshalb besteht der Hauptzweck der Erfindung darin, eine schwimmfähige Plattform zu schaffen, welche sich selbst verankern kann und mit Stützbeinen versehen ist, die sich nach unten und nach den Seiten, deh. also schräg nach unten und außen zum Stabilisieren der Plattform erstrecken, wenn diese verankert ist.running support legs. The known devices of this type have the disadvantages that they either directly must be erected at the drilling site, or, if floating platforms are involved, that they are extremely bulky and difficult to move to the desired place of work while being transported to the desired one The place can tip over or capsize. In addition, these known buoyant drilling rigs or platforms require a very complex device for anchoring the platform on the seabed. Therefore the main purpose of Invention is to create a buoyant platform that can anchor itself and with support legs is provided that extends downwards and to the sides, deh. so diagonally downwards and outwards to stabilize the Extend the platform when it is anchored.
Weiterhin besteht die Aufgabe der Erfindung darin, eine schwimmfähige Plattform zu schaffen, deren Einzelteile größtenteils verhältnismäßig nahe an dem Wasserspiegel liegen, wenn sie sich in der Schleppstellung befindet. Weiterhin bezweckt die Erfindung eine schwimmfähige Bohrplattform bzw. Bohrinsel für Arbeiten auf dem Meer zu schaffen, welche gelenkig angeordnete Beine aufweist, die dadurch in ihre Arbeitsstellung gebracht werden, daß Ballast in Kammern dieser Beine eingebracht wird. Außerdem soll durch die vorliegende Erfindung eine schwimmfähige Bohrplattform geschaffen werden, die in die Hohrstellung gebracht werden kann, indem man Ballast innerhalb der Gesamtkonstruktion verschiebt. Ferner soll gemäßFurthermore, the object of the invention is to create a buoyant platform, its individual parts for the most part are relatively close to the water level when in the towing position. Furthermore, the invention aims to provide a floating drilling platform or drilling platform for work at sea create which has articulated legs which are thereby brought into their working position that Ballast is introduced into chambers of these legs. In addition, the present invention is intended to provide a buoyant Drilling platform can be created that can be raised by putting ballast inside of the overall construction. Furthermore, according to
909821/0053909821/0053
der vorliegenden Erfindung eine Bohrinsel geschaffen werden, welche nach unten und auswärts verlaufende Beine aufweist, die sich auf dem Seeboden bzw. Meeresboden an der Stelle abstützen können, an welcher ein Bohrvorgang geplant ist; außerdem sollen die an der schwimmfähigen Bohrplattform angelenkten Beine in einer Vielzahl von verschiedenen Winkeln zur Plattform eingestellt werden können, wobei sie sich nach unten und auswärts von der Plattform erstrecken. the present invention provides an oil rig, which has downwardly and outwardly extending legs that are located on the seabed and seabed on the Can support point at which a drilling process is planned; in addition, they should be on the floating drilling platform hinged legs can be adjusted at a variety of different angles to the platform, being they extend downward and outward from the platform.
Weiterhin besteht die Aufgabe der Erfindung darin, eine " Arbeitsplattform eu schaffen, die mit Ballast zu versehende Beine aufweist, wobei die Beine in einer bestimmten Neigungslage während des Anbringens des Ballastes an der Stützvorrichtung bzw. während des Entfernens desselben von der Stützvorrichtung hydrostatisch stabil sind, so daß die gesamte Vorrichtung stabil ist.Furthermore, the object of the invention is to provide a " Create work platform eu that has legs to be ballasted, the legs in a certain Inclination position during the attachment of the ballast to the support device or during the removal of the same of the support device are hydrostatically stable, so that the entire device is stable.
Y/eiterhin soll durch die vorliegende Erfindung eine schwimmfähige Plattform geschaffen werden, die eine Vielzahl von Beinen aufweist, von denen zwei aus einer horizontalen Schlepp- und Schwimmstellung in eine nach unten geneigte Stellung verschwenkt werden können, wobei diese Beine zu ihren freien Enden gegeneinander divergieren. Diese Schwenkbewegung wird durch ein gesteuertes Anbringen bzw. Entfernen des Ballastes in den Kammern der Beine bewirkt.The present invention also aims to provide a buoyant Platform can be created that has a plurality of legs, two of which are horizontal Towing and floating position can be pivoted into a downwardly inclined position, with these legs too their free ends diverge from one another. This pivoting movement is controlled by attaching or removing of the ballast in the chambers of the legs.
v:eiterhin ist es Aufgabe der Erfindung, eine schwimmfähige Arbeitsinsel für die Verwendung auf Seen oder die Meere v: eiterhin it is an object of the invention to provide a buoyant work island for use on lakes or oceans
909821 /0053909821/0053
-*- - H84559- * - - H84559
zu schaffen, welche als Auftriebskörper bzw. als Schwimmkörper dienende Beine aufweist, welche in eine nach unten und auswärts verlaufende Stellung zur Plattform durch Anbringen von Ballast bzw. Entfernen von Ballast geschwenkt werden können.to create, which has legs serving as a buoyancy body or as a floating body, which in a downward direction and pivoted outward position to the platform by adding ballast or removing ballast can be.
Diese und andere Merkmale der Erfindung sind ausführlich in Verbindung mit der Zeichnung beschrieben. In der Zeichnung ist ein Ausführungsbeispiel der schwimmfähigen Plattform gemäß der Erfindung dargestellt, und zwar zeigtThese and other features of the invention are described in detail in connection with the drawing. In the drawing an embodiment of the buoyant platform according to the invention is shown, namely FIG
Fig. 1 eine perspektivische Ansicht mit den Beinen in ihrer abgesenkten Stellung,Fig. 1 is a perspective view with the legs in their lowered position,
Fig. 2 eine Seitenansicht der Plattform in ihrer Schwimmstellung, wobei die Beine hochgeschwenkt sind und zu erkennen ist, wie sie zum Wasserspiegel liegen,Fig. 2 is a side view of the platform in its floating position with the legs pivoted up are and can be seen how they are to the water level,
Pig. 3 eine Seitenansicht der Plattform mit den Beinen in ihrer unteren Stellung, wobei die Schwimmlage der Plattform in dieser Lage gegenüber dem Wasserspiegel zu erkennen ist,Pig. Figure 3 is a side view of the platform with the legs in its lower position, the floating position of the platform in this position relative to the water level it can be seen
Fig. 4 eine andere Seitenansicht der Plattform, wobei sie sich auf dem Seegrund bzw. Meeresgrund abstützt und ihre Lage zum Wasserspiegel zu erkennen ist,Fig. 4 is another side view of the platform, wherein it is supported on the lake bed or sea bed and its position in relation to the water level can be recognized is,
Pig. 5 eine Seitenansicht der Plattform in Schwimmstellung mit hochgeklappten Beinen,Pig. 5 is a side view of the platform in the floating position with the legs folded up;
909821/0083909821/0083
- 5 - H84559- 5 - H84559
Pig. 6 eine Ansicht, teilweise nach linie VI - VI in Pig, 5 geschnitten,Pig. 6 a view, partially cut along line VI - VI in Pig, FIG.
Pig. 7 eine schematische Ansicht eines Beines, aus welcherPig. 7 is a schematic view of a leg from which
Kammern, die einzelnen in dem Bein angeordnetenvLeixungen,Chambers, the individual ligaments arranged in the leg,
Ventile und Pumpen zu erkennen sind, undValves and pumps can be seen, and
Pig.. 8 eine schematische Ansicht der schwimmfähigen Plattform mit geneigten Schwenkachsen für die hinteren Beine, wobei die Beine in ausgezogenen linien in ihrer oberen Stellung und in gestrichelten Linien * in ihrer unteren Stellung dargestellt sind.Pig .. 8 a schematic view of the buoyant platform with inclined pivot axes for the rear legs, the legs being shown in solid lines in their upper position and in dashed lines * in their lower position.
Wie in Pig. 1 dargestellt, wird die Plattform 1 von hinteren Beinen 2 und 3 und von vorderen Beinen 4 und 5 abgestützt. Ein Bohrturm 6 ist auf einer Bohrplattform 7 angeordnet, die an der Vorderseite der Plattform 1 befestigt ist. Die Plattform 1 kann in jeder geeigneten Weise hergestellt sein, jedoch sollte sie vorzugsweise in einzelne Kammern aufgeteilt und mit geeigneten Pumpen zum Einbringen und Entfernen von Ballast und mit entsprechenden Steu- . ( ergeräten für Zwecke versehen sein, die nachstehend ausführlich erklärt sind. Die hinteren Beine 2 und 3 sind in geeigneter V/eise durch waagerechte Streben 8 und 9 und durch Querstreben 10 und 11 miteinander verbunden. Jedes Bein 2,Like in Pig. 1, the platform 1 is supported by rear legs 2 and 3 and front legs 4 and 5. A derrick 6 is arranged on a drilling platform 7 which is attached to the front of the platform 1 is. The platform 1 can be manufactured in any suitable manner, but it should preferably be made into individual parts Divided chambers and with suitable pumps for introducing and removing ballast and with appropriate control. ( must be provided for purposes that are explained in detail below. The rear legs 2 and 3 are in suitably connected by horizontal struts 8 and 9 and cross struts 10 and 11. Each leg 2,
cd 3,4 und 5 besteht aus zwei rohrförmigen Teilen 12 und 13,cd 3, 4 and 5 consists of two tubular parts 12 and 13,
*° 14 und 15, 16 und 17 bzw. 18 und 19. Diese rohrförmigen ^, Teile sind an ihren äußeren Enden aneinander-geschweißt, ; ο an ihren inneren Enden durch Schwenkarme 20, 21, 22 bzw.* ° 14 and 15, 16 and 17 or 18 and 19. These tubular ^, parts are welded together at their outer ends,; ο at their inner ends by swivel arms 20, 21, 22 or
*** 23 untereinander verbunden und außerdem über Streben 24, 25, 26 bzw. 27 gegeneinander abgestützt. Wie am besten*** 23 connected to each other and also via struts 24, 25, 26 and 27 are supported against one another. How best
aus Pig. 6 zu erkennen, sind die rohrförmigen Teile 17 und 9 der vorderen Beine 4 und 5 an ihren oberen Enden miteinander verbunden und an der Plattform 1 mittels eines Lagers 28 gehalten. Wenn es erwünscht ist, daß sich die Beine 4 und 5 unabhängig voneinander aus nachstehend näher beschriebenen Gründen bewegen können, sind die rohrförmigen Teile 17 und 19 nicht in der in Pig. 6 dargestellten Weise miteinander verbunden, sondern vielmehr so ausgebildet, daß sie gegeneinander bewegt werden können. Die Beine 4 und 5 sind nicht wie die Beine 2 und 3 durch Streben miteinander verbunden. Geeignete Streben können Anwendung finden, wenn die rohrförmigen Teile 17 und 19 miteinander verbunden werden sollen und solche Streben'*nicht den besonderen Einsatzmöglichkeiten auf dem Wasser entgegenstehen, für welche die schwimmfähige Plattform bestimmt ist. Wenn die Plattform zum Bohren verv/endet wird, muß Sorgfalt auf das Abstützen der Beine 4 und 5 gegeneinander verwendet werden, insbesondere auf ein Verbinden der rohrförmigen Teile 17 und 19, da ein solches gegenseitiges Abstützen in der Stützstellung der Beine die Bohrarbeiten u.U. behindern kann. Das Lager 28 besitzt eine Achse 29, welche sich durch die miteinander verbundenen Teile 17 und 19 und durch Augen 30 erstreckt, die an der Unterseite der Plattform angebracht sind. Schließlich erstreckt sich die Achse 29 noch durch die Arme 22 und 23, wodurch die Beine 4 und 5 schwenkbar an der Plattform 1 gehalten werden.from Pig. 6, the tubular parts 17 and 9 of the front legs 4 and 5 are connected to one another at their upper ends and are held on the platform 1 by means of a bearing 28. If it is desired that the legs 4 and 5 can move independently of each other for reasons described in more detail below, the tubular parts 17 and 19 are not in that shown in Pig. 6 connected to each other, but rather designed so that they can be moved against each other. Legs 4 and 5 are not connected to one another by struts like legs 2 and 3. Suitable struts can be used when the tubular parts 17 and 19 are to be connected to one another and such struts' * do not conflict with the special uses on the water for which the buoyant platform is intended. If the platform is used for drilling, care must be taken to support the legs 4 and 5 against each other, in particular to connect the tubular parts 17 and 19, since such mutual support in the support position of the legs may interfere with the drilling work . The bearing 28 has an axis 29 which extends through the interconnected parts 17 and 19 and through eyes 30 attached to the underside of the platform. Finally, the axis 29 also extends through the arms 22 and 23, as a result of which the legs 4 and 5 are held pivotably on the platform 1.
- 7 -909821/0053- 7 -909821/0053
.-'7- U84559.- ' 7 - U84559
Die hinteren Beine 2 und 3 sind ebenfalls an der Unterseite der Plattform 1 mittels Lagern 31 bzw. 32 schwenkbar ge gehalten. Das Lager 31 besitzt eine Achse 33, die sich durch den rohrförmigen Teil 13 des Beines 2, durch von der Unterseite der Plattform ausgehende Augen 34 und durch den Arm 20 erstreckt. Das Lager 32 besitzt eine Achse 35, welche sich durch den rohrförmigen Teil 15 des Beines 3, durch von der Unterseite der Plattform 1 ausgehende Augen 36 und durch den Arm 21 erstreckt.The rear legs 2 and 3 are also pivotable ge on the underside of the platform 1 by means of bearings 31 and 32 respectively held. The bearing 31 has an axis 33 which extends through the tubular part 13 of the leg 2, through eyes 34 extending from the underside of the platform and through the arm 20 extends. The bearing 32 has an axis 35 which extends through the tubular part 15 of the leg 3 eyes 36 extending from the underside of the platform 1 and through the arm 21.
Eine zum Anbringen von Bolzen bestimmte Verriegelungsplat- f te 37 ist am inneren Ende des Teiles 12 des Beines 2 angeschweißt und kann durch einen Schlitz 38 in der Plattform 1 hindurchtreten, wenn das Bein 2 abgesenkt wird. In ähnlicher Weise ist der Teil 14 des Beines 3 mit einer Verriegelungsplatte 39 versehen, welche durch einen Schlitz 40 hindurchtreten kann, während der Teil 16 des Beines 4 mit einer Verriegelungsplatte 41 versehen ist, die durch einen Schlitz 42 hindurchtreten kann, und der Teil 18 des Beines > 5 ist mit einer ähnlichen nicht dargestellten Verriegelungsplatte versehen, die durch einen Schlitz 43 hindurchtreten kann. Die Verriegelungsplatte für den Teil 18 des Beines 5 ist deshalb nicht dargestellt, weil sie in sämtlichen Figuren von anderen Teilen verdeckt ist. Sie ist ähnlich wie die Verriegelungsplatte 41, jedoch spiegelbildlich ausgeführt. Die vier Verriegelungsplatten besitzen alle eine Mehrzahl von Bohrungen in der gezeichneten Weise zur Aufnahme geeigneter Bolzen in jeder gewünschten Stellung der Beine, um die Stellung der Beine festlegen zu können.A locking plate 37 intended for attaching bolts is welded to the inner end of the part 12 of the leg 2 and can pass through a slot 38 in the platform 1 when the leg 2 is lowered. Similarly, the part 14 of the leg 3 is provided with a locking plate 39 which can pass through a slot 40, while the part 16 of the leg 4 is provided with a locking plate 41 which can pass through a slot 42, and the part 18 of the leg > 5 is provided with a similar locking plate, not shown, which can pass through a slot 43. The locking plate for part 18 of leg 5 is not shown because it is covered by other parts in all of the figures. It is similar to the locking plate 41, but designed as a mirror image. The four locking plates all have a plurality of bores in the manner shown for receiving suitable bolts in any desired position of the legs in order to be able to determine the position of the legs.
909821/0053909821/0053
H84559H84559
Die Beine 2 und 4 sind außerdem mit zweiten Verriegelungsplatten 37a und 41a versehen, welche an den Teilen 13 bzw. 17 befestigt sind, wie am besten aus Figur 1 zu erkennen ist. Die Beine 3 und 5 sind mit ähnlichen nicht dargestellten zweiten Verriegelungsplatten versehen. Diese Verriegelungsplatten dienen dazu, um die Beine in ihrer Schleppstellung zu befestigen.The legs 2 and 4 are also provided with second locking plates 37a and 41a which are attached to the parts 13 and 13, respectively. 17 are attached, as can best be seen from FIG. The legs 3 and 5 are not shown with similar ones second locking plates provided. These locking plates are used to keep the legs in their towing position to fix.
Das in Fig. 7 dargestellte Bein ist typisch für die innere Konstruktion aller Beine gemäß der vorliegenden Erfindung. Zum Zwecke der nötigen Klarheit ist dieses Bein als Bein 2. bezeichnet. Die äußere Verbindung der Teile 12 und 13 bildet eine Kammer 44, indem eine Zwischenwand 45 in dem Teil 12 und eine Zwischenwand 46 in dem Teil 13 eingeschweißt ist. Ferner sind Zwischenwände 47, 48 und 49 in den TeilThe leg shown in Figure 7 is typical of the internal construction of all legs in accordance with the present invention. For the sake of clarity, this leg is referred to as leg 2. The external connection of the parts 12 and 13 forms a chamber 44 by welding an intermediate wall 45 in part 12 and an intermediate wall 46 in part 13 is. Furthermore, partitions 47, 48 and 49 are in the part
12 eingesohweißt, so daß Kammern 50, 51, 52 und 53 gebildet werden. Zwischenwände 54, 55 und 56 sind in den Teil12 welded in so that chambers 50, 51, 52 and 53 are formed will. Partitions 54, 55 and 56 are in the part
13 eingeschweißt, so daß in diesem Kammern 57, 58, 59 und 60 gebildet sind. Das äußere Ende des Beines 2 ist von einer Platte 61 verschlossen, welche an dieses Ende angeschweißt ist, um die Kammer 44 abzuschließen. Die Platte 61 ist so angeordnet, daß sie auf dem See- bzw. Meeresgrund aufliegen kann, auf dem die Plattform 1 verankert und abgestützt werden soll. Die Platte 61 liegt in einem13 welded, so that in this chambers 57, 58, 59 and 60 are formed. The outer end of the leg 2 is closed by a plate 61 which is welded to this end is to close the chamber 44. The plate 61 is arranged so that it is on the sea bed can rest on which the platform 1 is to be anchored and supported. The plate 61 lies in one
·* geeigneten Winkel zum Bein 2, so daß sie im wesentlichen J£ horizontal verläuft, wenn sich das Bein 2 in seiner Stütz- -» lage befindet. Außerdem sollen sämtliche Zwischenwände ° der Teile 12 und 13 vollständig dicht eingeschweißt wer-· * Appropriate angle to leg 2 so that it is essentially J £ runs horizontally when leg 2 is in its support - »is located. In addition, all partition walls should ° of parts 12 and 13 are welded in completely tight
Yl den, so daß sie wasserdichte Kammern bilden und ein Lekken von Ballast' zwischen den einzelnen Kammern verhindern. Yl den, so that they form watertight chambers and prevent leakage of ballast 'between the individual chambers.
In der Kammer 60 let eine Pumpe 62 angeordnet, Sie besitzt eine Einlaßleitung 63 mit einem Ventil 64, um den Wasserzufluß zur Pumpe 62 zu steuern. Die Pumpe 62 wird durch, einen Motor 65 angetrieben. Zweokmäßigerweise 1st der Motor 65 ein Elektromotor, um die Steuerung zu vereinfachen. Die Kabel und Sohalter zum Steuern des Motores 65 sind nicht dargestellt, aber wohl bekannt, und es ist jede geeignete Steuereinrichtung für den Motor denkbar. Die Einlaßleitung 63 ist an eine Wasserquelle angeschlossen, die als Ballast dient. Offensiohtlioh ist das Wasser, auf welchem die Plattform 1 aufgestellt werden soll, im allgemeinen die beste Wasserquelle für den Ballast, es sei denn» das Wasser enthält solche korrodierenden Bestandteile, die das nachstehend vollständig beschriebene Ballastsystem unbrauchbar maohen würden. In diesem Pail muß eine geeignete Wasserquelle oder eine andere Ballastflüssigkeit verwendet werden. Das Ballastsystem ist so ausgelegt, daß ob normales Meereswasser oder Seewasser verwenden kann· Dementsprechend sind die Werkstoffe für die Pumpen, Ventile und Leitungen so gewählt, daß normales Meereswasser keine Korrosioneersoheinungen hervorruft, welohe das Ballastsystem unbrauchbar maohen würden·In the chamber 60 let a pump 62 arranged, you owns an inlet line 63 with a valve 64 to control the flow of water to the pump 62. The pump 62 is a motor 65 is driven. Suitably, the motor 65 is an electric motor for ease of control. The cables and holders for controlling the motor 65 are not shown but well known, and any suitable control device for the engine is conceivable. The inlet line 63 is connected to a water source which serves as ballast. Offensiohtlioh, the water on which the platform 1 is to be set up is generally the best source of water for the ballast, unless » the water contains such corrosive components that would render the ballast system described in full below unusable. A suitable source of water or other ballast fluid must be used in this pail. The ballast system is designed so that whether Can use normal sea water or sea water · The materials for the pumps and valves are accordingly and pipes chosen so that normal sea water does not Causes corrosion, which would render the ballast system unusable
Die Auslaßleitung bzw. Druckleitung 66 der Pumpe 62 dient als Verteilungsleitung zu Ventilen 67» 68 und 69· BiBe leitung 70 verbindet da« Ventil 67 mit der Kammer 99· tin· Leitung 71 verbindet das Ventil 6Θ mit der Kammer 58 und eine Leitung 72 verbindet da· Ventil 69 Bit A tr ItMtV 57·The outlet conduit or pressure line 66, the pump 62 serves as a distribution line to valves 67 »68 and 69 · BIBE circuit 70 connects as" valve 67 to the chamber 99 · connects tin · conduit 71, the valve 6Θ with the chamber 58 and a line 72 connects da valve 69 bit A tr ItMtV 57
100821/0053100821/0053
- 10 -- 10 -
;G,,.·;: i^r-EO'; G ,,. · ;: i ^ r-EO '
An die Kammern 57, 58 und 59 sind Entlüftungen! tungtn 73, 74 bzw. 75 angeschlossen. Aus den Kammern 57, 58 und 3$ eretreoken sioh Auslaßleitungen 76, 77 bzw. 78 zu Ventilen 79, 80 bzw. 81. Eine Sammelleitung 81a führt von dien Ventilen 79, 80 und 81 zur Saugeeite einer Pumpe 82. In der Zeichnung ist eine Steuerstange 83 dargestellt, wtlohe sioh aus der Kammer 60 zum Ventil 79 erstreckt. Die-There are vents on chambers 57, 58 and 59! tungtn 73, 74 or 75 connected. From chambers 57, 58 and $ 3 Eretreoken sioh outlet lines 76, 77 and 78 to valves 79, 80 and 81, respectively. A collecting line 81a leads from the dien Valves 79, 80 and 81 on the suction side of a pump 82. In the drawing shows a control rod 83 which extends out of the chamber 60 to the valve 79. The-
se Stange dient als Beispiel für die Fernsteuerung der Ventile 79, 80 und 81. Jede geeignete Fernsteuerung zum Steuern der Ventile kann in dem Ballastsystem gemäß der vorliegenden Erfindung Verwendung finden, beispielsweise auoh eine elektrische Fernsteuerung.^ This rod serves as an example of the remote control of the valves 79, 80 and 81. Any suitable remote control for controlling the valves can be used in the ballast system according to the present invention, for example an electrical remote control. ^
Die Pumpe 82 wird von einem Motor 84 angetrieben, der für Ferneteuerung geeignet ist. Die Druckleitung 85 der Pumpe 82 erstreckt sioh naoh oben duroh den Teil 12 und aus der Kammer 53 heraus und ist mit einem Steuerventil 86 versehen. Das als Ballast verwendete Wasser wird beim Entleeren duroh die Leitung 85 in das Wasser zurückbefördert, auf dem die Plattform 1 angeordnet iet« Wenn die erfindungsgemäß vorgeschlagene Vorrichtung nicht einen genügenden überschüssigen Auftrieb besitzt, sollte aus den Beinen keine herauegepumpte Ballastflüssigkeit an der Vorrichtung aufbewahrt werden, es sei denn, sie wird, wenn das Wasser, in welchem die Vorrichtung angeordnet let, ungeeignet ist, getrennt von der Vorrichtung aufbewahrt.The pump 82 is driven by a motor 84 suitable for remote control. The pressure line 85 of the pump 82 extends close to the top through part 12 and out of chamber 53 and is provided with a control valve 86. The water used as ballast is returned to the water via line 85 during emptying, on which the platform 1 is arranged. If the device proposed according to the invention does not have sufficient excess buoyancy, the No ballast fluid pumped out can be retained on the device unless it will, when the water in which the device is placed is unsuitable, stored separately from the device.
- 11 109121/0013 - 11 109121/0013
Se let jedoch, wie nachstehend ausführlich beschrieben, zweckmäßig, Ballast in den Kammern der Plattform 1 unterzubringen und dann in die Beine 2 und aus diesen zu pumpen, um das Einstellen der Beine gegenüber der Fiattform 1 EU unterstützen.Let us, however, as described in detail below, expedient to accommodate ballast in the chambers of the platform 1 and then to pump into and out of the legs 2 in order to adjust the legs relative to the platform 1 EU support.
den Kammern 50, 51 und 52 verlaufen Auslaßleitungen 87, 88 bew, 89 zu Ventilen 90, 91 bzw. 92. Eine Sammelleitung 93 verbindet die Ventile 90, 91.und 92 mit der Saugeelte der Pumpe 82. Sine Steuerstange 94 od. dgl. erstreckt sich aus der Kammer 53 zu den Ventilen 90, 91 *The chambers 50, 51 and 52 run outlet lines 87, 88 bew, 89 to valves 90, 91 and 92, respectively. A collecting line 93 connects the valves 90, 91st and 92 to the suction element of the pump 82. Its control rod 94 or the like. extends from chamber 53 to valves 90, 91 *
und 92. Entlüftungsleitungen 95, 96 und 97 erstreckenand 92. Vent lines 95, 96 and 97 extend
sich von den Kammern 50, 51 bzw. 52 bis zur Außenseite der Kammer 53, um eine geeignete Entlüftung der Kammern 50, 51 und 52 während des Füllens oder Entleerens derselben zu bewirken.from the chambers 50, 51 and 52 to the outside of the chamber 53, for a suitable venting of the chambers 50, 51 and 52 to effect during the filling or emptying of the same.
In Figur 7 ist keine Füllvorrichtung für die Kammern 50, 51 und 52 dargestellt, jedoch ist sie vorgesehen. Zweckmäßigerweise wird die Pumpe 62 auch zum Einbringen von Ballast in die Kammern 50, 51 und 52 verwendet, und es sind entweder zusätzliche Ventile in der Pumpendruckleitung 66 vorgesehen, um das Ballastwasser in die Kammern 50, 51 und 52 je nach Wunsch zu leiten, oder es ist eine besondere Füllpumpe und eine Ventilanordnung zusätzlich zu der in der Kammer 60 gezeigten in der Kammer 53 vorgesehen. In Figure 7 there is no filling device for the chambers 50, 51 and 52, but it is provided. The pump 62 is expediently also used for introducing Ballast is used in chambers 50, 51 and 52 and there are either additional valves in the pump discharge line 66 is provided to direct the ballast water into chambers 50, 51 and 52 as desired, or it is one A special filling pump and valve arrangement in addition to that shown in chamber 60 is provided in chamber 53.
909821/0053909821/0053
Nach einem bevorzugten Ausführungsbeispiel der Erfindung ist jede der Kammern 50, 51, 52, 57, 58 und 59 mit der Fülleinrichtung und der Entleerungseinrichtung des BaI-lastsystemes verbunden, so daß sie unabhängig voneinander gefüllt und entleert werden können. Es ist auch möglich, das Ballastsystem derart abzuwandeln, daß der Füll- und Entleerungsvorgang der Kammern mit einem einzigen Satz von Steuervorrichtungen und Pumpen besorgt wird, indem man einfach die Kammern untereinander verbindet, d.h. indem man die Kammer 50 mit der Kammer 57, die Kammer 51 mit der Kammer 58 und die Kammer 52 mit der Kammer 59 verbindet. Hierbei muß man jedoch Sorgfalt darauf verwenden, daß die Lage der Beine mit Sicherheit genau durch das Eindringen bzw. Entfernen des Ballastes gesteuert werden kann. Eine unabhängige Beeinflussung des Ballastes jeder Kammer ist vorzuziehen. Gemäß der Erfindung kann ferner die Kammer 4% über geeignete Steuergeräte mit Ballast gefüllt, entleert und entlüftet werden, jedoch sind diese Geräte in der Zeichnung nicht dargestellt, damit das Steuersystem deutlich in Bezug auf die anderen Kammern dargestellt wird. Es ist hervorzuheben, daß wegen der sehr großen Abmessungen der rohrförmigen Teile der Beine das Anordnen der Ventile, der Pumpe und dee Motors in der Kammer 44 verhältnismäßig wenig Platz im Vergleich zu der wirkli-According to a preferred embodiment of the invention, each of the chambers 50, 51, 52, 57, 58 and 59 is connected to the filling device and the draining device of the ball load system so that they can be filled and drained independently of one another. It is also possible to modify the ballast system so that the filling and emptying of the chambers is carried out with a single set of control devices and pumps by simply connecting the chambers to one another, ie by connecting chamber 50 with chamber 57, the chamber 51 with the chamber 58 and the chamber 52 with the chamber 59 connects. However, care must be taken to ensure that the position of the legs can be precisely controlled by the penetration or removal of the ballast. It is preferable to influence the ballast of each chamber independently. According to the invention, the chamber 4% can be filled with ballast, emptied and vented via suitable control devices, but these devices are not shown in the drawing so that the control system is clearly shown in relation to the other chambers. It should be emphasized that because of the very large dimensions of the tubular parts of the legs, the arrangement of the valves, the pump and the motor in the chamber 44 is relatively little space compared to the real
Ä chen Größe der Kammer 44 beansprucht. Auch kann die Kam- Ä chen size of the chamber 44 claimed. The cam-
o .o.
«o Bier 44 mit Ballastwasser gefüllt werden, wenn die Ventile, *» die Pumpe und der Motor derart ausgebildet sind, daß sie ^ gut arbeiten, wenn sie in Ballastwasser, das sich in der«O Beer 44 should be filled with ballast water if the valves * »The pump and the motor are designed in such a way that they ^ work well when in ballast water which is in the
«· Kassier 44 befindet, eingetaucht sind.«· Cashier 44 is located, are immersed.
• '■'■'■· ■■- 13·--• '■' ■ '■ · ■■ - 13 · -
Der Hauptzweck des Anbringens von Ballast und Entfernens des Ballastes ist, die Stabilität der s chwimmf äiiigen Bohrinsel zu gewährleisten. Ein direktes Fluten der in den Beinen befindlichen Kammern durch Flutventile oder Umführungspumpen sollte nicht vorgenommen werden. Bei einem derartigen direkten Fluten bleibt Luft in den Kammern, welphe einem zusätzlichen Druck wegen der Tiefe unter dem Wasserspiegel ausgesetzt sind, wodurch Volumenänderungen der Kammerfüllung eintreten können, die außerhalb menschlicher Beeinflussungsmöglichkeiten liegen. Daraus können wiederum Fehler in der Steuerung des Einbringens von Ballast bzw. Entfernen von Ballast entstehen, welche ein Kippen bzw. Kentern oder ein ernstes Schrägstellen der schwimmfähigen Plattform hervorrufen können.The main purpose of adding ballast and removing the ballast is to ensure the stability of the floating oil rig. A direct flood of the in the Leg chambers by flood valves or bypass pumps shouldn't be done. With such a direct flooding, air remains in the chambers, Puppies are exposed to additional pressure because of the depth below the water level, causing volume changes the chamber filling can occur that are beyond human control. From this you can in turn, errors in the control of the introduction of ballast or removal of ballast arise, which lead to tipping or capsizing or serious tilting of the buoyant platform.
Ein anderes Verfahren zum Anbringen von Ballast und Entfernen von Ballast besteht darin, in der Plattform 1 befindliches Ballastwasser zu steuern. Wie weiter oben bereits angedeutet, ist die Plattform 1 so ausgebildet, daß sie Ballastwasser enthält. Entsprechend Fig. 2 kann die ( Plattform 1 schwer mit Ballastwasser beladen sein. Am Arbeitsplatz wird die Plattform 1 entlastet, indem der Ballast in ähnlicher Weise wie vorstehend in Verbindung mit den Beinen beschrieben aus der Plattform entfernt wird. Dann taucht die Plattform 1 aus dem Wasser heraus, währendAnother method of adding ballast and removing ballast is by being in platform 1 To control ballast water. As already indicated above, the platform 1 is designed so that it contains ballast water. According to FIG. 2, the (platform 1 can be heavily loaded with ballast water. At the workplace the platform 1 is relieved of load by removing the ballast in a manner similar to that described above in connection with the legs described is removed from the platform. Then the platform 1 emerges from the water while
o die Beine in das Wasser abgesenkt werden. Der Vorgang wird o the legs are lowered into the water. The process will
** so lange fongesetzt, bis die Beine die gewünschte Tiefe** Continue to sit down until the legs are the desired depth
C erhalten haben. Zum Entfernen der Plattform von der Aro ■ ■■*.·>C received. To remove the platform from the Aro ■ ■■ *. ·>
ο beitssteile wird die Plattform wieder mit Ballaet verse- ; •n . . . .ο the platform is re-equipped with ballet ; • n . . . .
ω hen, nachdem die Beine vom Seeboden bzw. Meeresboden ge- ω hen after the legs off the seabed or ocean floor overall
- 14 -- 14 -
- Mi- - - Mi- -
U84559U84559
löst und die Bolzen aus den Bolzenplatten 37, 39, 41 usw. herausgezogen worden sind.loosens and the bolts have been pulled out of the bolt plates 37, 39, 41, etc.
und Entlasten Dieses Verfahren zum BelastenVder Plattform gewährleistet eine bessere Kontrolle. Wenn jedoch ein derartiges Verfahren angewendet wird, ist die gesamte Vorrichtung normalerweise größer als sonst erforderlich. Es ist vorzuziehen, daß ein Kompromiß zwischen beiden Verfahren gewählt wird, der in der Praxis von anderen Bedingungen abhängt, wie beispielsweise der Tiefe des Wassers und der zu überdeckenden Y/as serf lache, dem zu befördernden Gewicht und der Begrenzung des Wasserkanales.and unloading This method of loading the platform ensures better control. However, when such a method is used, the entire apparatus is normally larger than otherwise required. It is preferable that a compromise be chosen between the two methods which in practice depends on other conditions, such as the depth of the water and the Y / as serf pool to be covered, the weight to be carried and the limitation of the water channel.
Es ist eine schwierige Aufgabe, in Wasser eingetauchte röhrenförmige Teile zu stabilisieren, wie leicht zu erkennen ist, wenn man eine geringe Menge Wasser in eine normale durch einen Stopfen verschlossene Hasche einbringt. Die Flasche wird nicht in einer geneigten Lage schwimmen, sondern sofort eine praktisch horizontale Stellung im Yfasser einnehmen.It is a difficult task to stabilize tubular parts immersed in water, as can easily be seen is when you add a small amount of water to a normal stoppered hash. The bottle will not float in an inclined position, but immediately in a practically horizontal position take in the Yfasser.
Für eine wirksame Steuerung sind die Beine aus zwei rohrförmigen Teilen hergestellt, die V-förmig zueinander angeordnet sind. Derartige Beine ermöglichen eine einfache, zwangsläufige und sichere Steuerung und außerdem als Nebenvorteil die erforderliche Stärke bzw. Steifigkeit. Jedes Bein muß in sich selber in seiner Schwenkebene stabil sein, und zwar auch dann, wenn alle Zapfen und Bolzen ge-For effective control, the legs are made from two tubular parts which are arranged in a V-shape to one another. Such legs allow a simple, compulsory and safe control and also, as a secondary advantage, the required strength or rigidity. Each leg must be stable in itself in its pivoting plane, even if all the pins and bolts bought and
809821/0063-809821 / 0063-
löst sind. Wie aus der Schiffbautechnik bekannt, ist der Aufbau und die Wirkungsweise so, daß der GM-Wert jedes Beines stets positiv ist, d.h. der Schwerpunkt der Vorrichtung liegt stets unter dem. Wasserspiegel. Die oben genannte V-Form, welche eine große Wasserfläche zwischen der mit Ballast versehenen Kammer und der mit Luft gefüllten Kammer gewährleistet, ist die bevorzugte Aueführungeform, um dies zu erreichen.solves are. As known from shipbuilding technology, the Structure and mode of operation in such a way that the GM value of each leg is always positive, i.e. the center of gravity of the device is always below that. Water level. The above-mentioned V-shape, which has a large body of water between the ballasted chamber and the air-filled chamber is the preferred design, to achieve this.
Die hier vorgesehenen positiven G-M-Werte zeigen an, daß der vorgeschlagene Schwimmkörper stabil ist, d.h. daß der Schwerpunkt mit oder ohne Ballast unter dem Metazentrum bei entsprechenden Lasten liegt, die sich aus der angehängten Stützvorrichtung für die Plattform 1 ergeben.The positive G-M values provided here indicate that the proposed float is stable, i.e. that the center of gravity with or without ballast is below the metacenter is at corresponding loads, which result from the attached support device for the platform 1.
Wie in lig. 8 dargestellt, können die Beine 2 und 3 besser an schräggestellte Lager angehängt sein, als an die in-anderen Figuren dargestellten Lager 31 und 32. Biee ermöglicht es, die Beine 2 und 3 parallel zueinander ssu legen, wenn sie in der Schleppetellung der Plattform sind, ( während sie einen gewissen ¥inkel zueinander einnehmen und schräg nach außen verlaufen, wenn sie nach unten verschwenkt in das Wasser eingetaucht sind oder sich in ihrer Stützstellung befinden. Diese beiden Stellungen bestimmen eine Ebene, in der die Beine verschwenkt werden können; die Achse des Schwenklagere verläuft lotrecht mn dieser Schwenkebene. Dieses Schwenklager kann leicht dadurch angebracht werden, daß die Beine in die richtigeAs in lig. 8, legs 2 and 3 can be better attached to inclined bearings than to bearings 31 and 32 shown in other figures. Biee enables legs 2 and 3 to be parallel to each other when they are in the towing position of the platform are, (while they assume a certain angle to each other and run obliquely outwards when they are immersed in the water pivoted downwards or are in their support position. These two positions define a plane in which the legs can be pivoted; the axis of the pivot Lagere is perpendicular mn this pivoting plane. this pivot bearing can be easily attached in that the legs in the correct
Lage unter der Plattform 1 gebracht werden und dann mit den die Schwenkachse abstützenden Augen gebohrt werden, so daß die mittlere Achse der Lagerachse mit der gewünsch-.ten Schwenkachse zusammenfällt.Position under the platform 1 and then drilled with the eyes supporting the pivot axis, so that the middle axis of the bearing axis with the desired Pivot axis coincides.
Das Befördern der Vorrichtung gemäß der vorliegenden Erfindung in ihre Arbeitsstellung ist deutlich in Verbindung mit den Figuren 2, 3 und 4 beschrieben. Pig. 2 zeigt die Plattform 1 mit den Beinen 2, 3, 4 und 5 in der Schleppstellung, wobei sie auf der Wasseroberfläche 98 schwimmen. In dieser Lage kann die Vorrichtung an den Einsatzort geschleppt werden. Wenn beachtliche Entfernungen beim Schleppen der schwimmfähigen Vorrichtung zu dem gewünschten Einsatzort zu überwinden sind, sind die Schwenkachsen bzw. Schwenklager 31 und 32 geneigt angeordnet, so daß die Beine 2 in der gewünschten Weise gespreizt sind, wenn sie eich in ihrer abgesenkten Stellung befinden, und praktisch parallel zueinander liegen, wenn sie sich in ihrer Schleppstellung befinden, was schematisch in Figur 8 dargestellt und anschließend beschrieben ist·Moving the device according to the present invention into its working position is clearly related with the figures 2, 3 and 4 described. Pig. 2 shows the platform 1 with the legs 2, 3, 4 and 5 in the towing position, floating on the water surface 98. In this position, the device can be towed to the place of use will. If considerable distances are required when towing the buoyant device to the desired location are to be overcome, the pivot axes or pivot bearings 31 and 32 are inclined so that the legs 2 are spread in the desired manner when they are calibrated in their lowered position, and practical lie parallel to each other when they are in their towing position are located, which is shown schematically in FIG and is then described
Bei einer derartigen Ausführung müssen die Streben 8, 9» 10 und 11 weggelassen werden, und die Verriegelungsplat*- ten 37 und 39 müssen schräg etehen, um durch die Schlitze 38 und 40 beim Bewegen der Seine 2 und 3 hindurcfctreten zu können.With such a design, the struts 8, 9 » 10 and 11 can be omitted, and the locking plate * - th 37 and 39 have to be at an angle to get through the slots 38 and 40 to be able to step back when moving the Seine 2 and 3.
Wenn sich die Beine in der in Fig. 2 dargestellten Lage befinden, wird Wasserballast aus den Kammern der Platt-When the legs are in the position shown in FIG water ballast from the chambers of the
909821/0053909821/0053
■'■'- ■■■ - 17 - ■ '■' - ■■■ - 17 -
• - π - U84559• - π - U84559
form gleichzeitig in die äußeren Kammern der Beine 2,3, 4 und 5 eingebracht, nachdem aus den entsprechenden zweiten Verriegelungsplatten die Bolzen herausgezogen wurden. Das Einbringen von Ballastwasser in die Kammern der Beine, aus den Kammern der Plattform verändert den Schwerpunkt der Beine nach außen, während das durch die Auftriebskräfte bestimmte Massenzentrum bzw. Gewicht nicht verändert wird. Dieses Verändern des Schwerpunktes der Beine nach außen bewirkt, daß die Beine mit ihren äußeren Enden in das Wasser eintauchen und die Plattform 1 vom Wasserspie- ä gel 98 abgehoben wird. Wenn der Ballast aus einer anderen Quelle als von der Plattform 1 stammt, verdrängt die ge_ samte Vorrichtung noch genügend Wasser, um im Wasser schwimmen, jedoch es ist ein größerer Teil der Vorrichtung im Wasser eingetaucht als vor dem Einbringen des Ballastes. Die Bewegung der Beine aufgrund des Ballastes wird solange fortgesetzt, bis sie die in Fig. 3 dargestellte Stellung erreicht haben.form is introduced into the outer chambers of the legs 2, 3, 4 and 5 at the same time after the bolts have been pulled out of the corresponding second locking plates. The introduction of ballast water into the chambers of the legs from the chambers of the platform changes the center of gravity of the legs outwards, while the center of mass or weight determined by the buoyancy forces is not changed. This causes change the center of gravity of the legs to the outside, that the legs plunge with their outer ends in the water and the platform 1 by the constant depth ä gel 98 is lifted. If the ballast comes from a source other than the platform 1, the entire device still displaces enough water to swim in the water, but a larger part of the device is submerged in the water than before the ballast was introduced. The movement of the legs due to the ballast is continued until they have reached the position shown in FIG.
Es ist darauf zu achten, und es können, falls erforder- I Care must be taken and, if necessary, I
lieh, nicht dargestellte mechanische Endanschläge vorgesehen sein, daß die Beine nicht so weit belastet werden, daß ihre Aufrichtbewegung umgekehrt wird. Wenn irgendeines der Beine einen solchen Punkt erreichen kann, könnte das Entlasten des Beines und Belasten der !Plattform 1 nicht das Zurückschwenken des Beines in seine obere Stellung bewirken. Indem man die Winkelstellung der Beine ausserhalb der kritischen Stellung unter ihren entsprechenden Schwenklagern hält, 1st ein richtiges Zurückkehren der borrowed, mechanical end stops, not shown, be provided that the legs are not stressed so much that their righting movement is reversed. If any of the legs can reach such a point, unloading the leg and loading the platform 1 could not cause the leg to pivot back into its upper position. By keeping the angular position of the legs outside of the critical position under their respective pivot bearings, there is a proper return of the
909821/0053909821/0053
- 18 -- 18 -
■ 18 " U84559■ 18 "U84559
Beine ausscliließlicli aufgrund des Entlastens derselben, des Belastens der Plattform 1 oder aufgrund beider Tatsachen möglich.Legs exclusively due to the relief of the same, the loading of the platform 1 or due to both facts possible.
Es sei darauf hingewiesen, daß das Bewegen der Beine in die kritische Stellung unter ihre Schwenklager an der Plattform 1 eine Instabilität der Vorrichtung bewirken und grössere Unfälle während des Entlastens der Beine hervorrufen kann, da ihre Bewegung nach oben beschränkt werden könnte, bis sie sich aus ihrer senkrechten Lage entfernen. Wenn eine solche Bewegung verhindert wird, bis das Entlasten im wesentlichen abgeschlossen ist, wäre die Auftriebskraft der Beine enorm hoch, sobald sich'Hie Beine aus ihrer senkrechten Stellung entfernen. In diesem Augenblick befinden sich alle Beine in der abgesenkten Lage. Sie werden in dieser Lage durch die in die Verriegelungs-* platten gesteckten Bolzen an der Plattform 1 gehalten. Dabei befindet sich die Plattform 1 über dem Wasserspiegel 98, und die unteren Enden der Beine befinden sich noch über dem Boden bzw. Meeresgrund 99· In. diesem Augenblick hat die Vorrichtung einen ein Schwimmen bewirkenden Auftrieb, d.h. es ist zusätzliches Ballastwasser einzubringen, um die Beine der Vorrichtung auf dem Meeresgrund 99 in der in Pig. 4 gezeigten Weise abzustellen. Die Anbringung dieses Zusatzballastes wird mit dem Ballastsystem in einfacher Weise erreicht..It should be noted that the movement of the legs to the critical position under their pivot bearing on the platform 1 cause instability of the device and cause major accidents during the unloading of the legs as their upward movement could be restricted until they move away from their perpendicular position. if preventing such movement until the unloading is substantially complete would be the buoyancy force The legs are enormously high as soon as there are legs out their vertical position. At this point all legs are in the lowered position. They are held in this position on the platform 1 by the bolts inserted in the locking plates. The platform 1 is above the water level 98 and the lower ends of the legs are still in place above the ground or seabed 99 · In. at this moment the device has a buoyancy causing swimming, i.e. additional ballast water has to be brought in to keep the legs of the device on the seabed 99 in the in Pig. 4 to turn off. This additional ballast is attached using the ballast system in easily achieved ..
Es ist größte Sorgfalt beim Füllen der Beine mit Wasser-Great care is taken in filling the legs with water
909821/0053 - 19 - .909821/0053 - 19 -.
ballast erforderlich, um zu erreichen, daß die Plattform 1 in ihrer waagerechten Lage bleibt und die Beine gleichmäßig mit Ballast versehen werden. Das Einbringen des Ballastes soll von einer nicht gezeigten zentralen Steuereinrichtung überwacht werden, die sich auf der Plattform 1 befindet. Die Überwachung kann entweder von Hand durch Steuerung derPumpen und Ventile oder selbsttätig durch bekannte Steuereinrichtungen erfolgen, um die Plattform 1 während des Einbringens des Ballastes in die Beine in ihrer horizontalen Lage zu halten.ballast required to ensure that the platform 1 remains in its horizontal position and the legs evenly be ballasted. The introduction of the ballast should be carried out by a central control device (not shown) which is located on platform 1. Monitoring can either be done manually Control of the pumps and valves or take place automatically by known control devices to the platform 1 to hold them in their horizontal position while the ballast is being introduced into the legs.
Normalerweise ist die Vorrichtung gemäß der vorliegenden Erfindung so ausgebildet, daß die Beine die erforderliche Länge und Größe haben, damit die Stützvorrichtung den erwünschten Auftrieb entsprechend der Wassertiefe hat, für welche die Bohrinsel bestimmt ist. Wenn das Wasser im Vergleich zu der Länge der Beine verhältnismäßig flach ist, werden die Beine nur so weit mit Ballast versehen, bis sie in eine weniger tiefe Lage als die in den Figuren 1,3 und 4 dargestellte Lage gelangt sind. Dann werden die Beine in dieser Stellung festgelegt, während die Vorrichtung immer noch einen gewiesen Auftrieb besitzt, d.h. ihre Beine den Meeresgrund 99 noch nicht berühren· Das Festlegen der Beine erfolgt, indem man Bolzen durch die entsprechenden Verriegelungsplatten la die Plattform 1 steckt. Wenn die Bei- · ne in dieser Stellung festgelegt sind, wird zusätelicher Ballast eingebracht, so daß die gesamte Stützvorrichtung im Wasser abgesenkt ist und di,e Beine fest auf dem Boden 99 aufsitzen. Gemäß der vorliegenden Erfindung iet außer- Typically, the apparatus of the present invention is designed so that the legs are of the required length and size to provide the support structure with the desired buoyancy corresponding to the depth of water for which the rig is intended. If the water is relatively shallow in comparison to the length of the legs, the legs are only provided with ballast until they have reached a position that is less deep than the position shown in FIGS. 1, 3 and 4. Then, the legs are set in this position, while the device still has a pointed lift her legs do not yet touch · ie the seabed 99 The setting of the legs is carried out by bolts inserted through the respective locking plates la the platform. 1 When the legs are fixed in this position, additional ballast is introduced so that the entire support device is lowered into the water and the legs sit firmly on the floor 99. According to the present invention outside iet
- 20 -- 20 -
dem die Möglichkeit vorgesehen, daß die Plattform auch auf einem Boden abgesetzt werden kann, der nicht vollständig eben ist. Deshalb können eines oder mehrere der Beine verschieden weit nach unten verschwenkt werden, um Unebenheiten des Bodens angepaßt zu werden. Die Beine 4 und 5 befinden sich in derselben lage, solange die Teile 17 und 19 miteinander verbunden sind, während sich die Beine 2 und 3 stets in derselben Stellung befinden, wenn nicht die Streben 8, 9, 10 und 11 weggelassen sind. Wenn es erwünscht ist, daß die Beine 4 und 5 verschieden tief absinken, dann dürfen sie nicht in der in der Zeichnung dargestellten Weise miteinander verbunden sein,which provided the possibility that the platform too can be set down on a floor that is not completely flat. Therefore, one or more of the Legs can be pivoted downwards to different degrees to accommodate unevenness in the floor. The legs 4 and 5 are in the same position as long as parts 17 and 19 are connected to one another while the legs 2 and 3 are always in the same position unless the struts 8, 9, 10 and 11 are omitted. If it is desired that the legs 4 and 5 sink to different depths, then they must not be in the one in the drawing be connected to each other in the manner shown,
Ea ist außerdem gemäß der vorliegenden Erfindung vorgesehen, daß die Vorrichtung in Wasser verankert wird, das so tief ist, daß die Beine sich nicht auf dem Boden absetzen können. Deshalb wird vorgeschlagen, daß Anker mit Schwimmkörpern vorgesehen sind, um die Vorrichtung in der gewünschten Lage schwimmend festzuhalten. Diese Anker und Schwimmkörper zum Pestlegen der Schwimmvorrichtung am gewünschten Ort sind bekannt und deshalb in der Zeichnung nicht dargestellt.Ea is also provided according to the present invention, that the device is anchored in water so deep that the legs do not settle on the ground can. Therefore, it is proposed that anchors are provided with floating bodies to the device in the to hold the desired position floating. These anchors and Floats for plaguing the swimming device at the desired location are known and are therefore shown in the drawing not shown.
Wenn es erwünscht ist, die Vorrichtung gemäß der vorliegenden Erfindung wieder vom Einsatzort fortzubringen, wird das Entfernen und Verschieben des Ballastes in der nachstehend ausführlich beschriebenen Weise besorgt. Durch das Entfernen des Wasserballastes soll die Vorrichtung zunächstWhen it is desired to remove the device according to the present invention from the site, will takes care of removing and moving the ballast in the manner detailed below. By the The device should first remove the water ballast
909821/0053909821/0053
- 21 -- 21 -
U84559U84559
durch den erhöhten Auftrieb wieder schwimmfähigegemacht werden, wie in Pig. 3 dargestellt. Dann werden die Bolzen aus den entsprechenden Verriegelungsplatten und der Plattform 1 herausgezogen, woraufhin das Entfernen oder Verschieben des Wasserballastes fortgesetzt wird, bis die' Vorrichtung sich in ihrer in Fig. 2 dargestellten Schleppstellung befindet. Wenn sich die Beine nun in ihrer obersten Schleppsteilung befinden, werden sie in dieser Stellung mittels durch ihre entsprechenden zweiten Verriegelungsplatten gesteckten Bolzen an der Plattform 1 festgelegt. Die Belegung der Beine aus einer Stellung in die andere fmade buoyant again by the increased buoyancy be like in Pig. 3 shown. Then the bolts from the corresponding locking plates and the Platform 1 is pulled out, whereupon the removal or movement of the water ballast continues until the ' The device is in its towing position shown in FIG. When the legs are now in their topmost They are in this position fixed to the platform 1 by means of bolts inserted through their respective second locking plates. The assignment of the legs from one position to the other f
kann in einfacher Weise ausschließlich durch das Hinzufügen bzw. Entfernen von Wasserballast in den einzelnen Kammern der rohrförmigen Teile der Beine bewirkt 'werden. Bs ist jedoch auch möglich, daß in Fällen, in denen wegen der geringen Wassertiefe kein genügender Auftrieb erzielt werden kann, mechanische Einrichtungen zum Verschwenken der Beine in ihre gewünschte abgesenkte Stellung vorgesehen werden können, wobei der gewünschte Auftrieb beibehalten wird. Es kann außerdem wünschenswert sein, solche mechanischen Einrichtungen zum Bewegen der Beine vorzusehen, um sie in ihrer Stellung während des Einsteekens oder Herausziehens der Verriegelungsbolzen in die bzw. aus den Verriegelungsplatten und der Plattform zu halten. Geeignete Winden, Flaschenzüge, Drahtseile oder pneumatische oder hydraulische Vorrichtungfcn sind Beispiele für die mechanischen Einrichtungen, um die Beine gemäß der vorliegenden Erfindung in ihre gewünschten Stellungen bringen zucan be done in a simple manner exclusively by adding or removing water ballast in the individual Chambers of the tubular parts of the legs are effected '. However, it is also possible that in cases where, due to the shallow water depth, sufficient buoyancy is not achieved mechanical means can be provided for pivoting the legs into their desired lowered position while maintaining the desired buoyancy. It may also be desirable to have such to provide mechanical means for moving the legs to keep them in position during embarkation or pulling the locking bolts into and out of the locking plates and the platform. Suitable Winches, pulley blocks, wire ropes or pneumatic or hydraulic devices are examples of the mechanical ones Means for bringing the legs into their desired positions according to the present invention
909821/0053909821/0053
- 22 -- 22 -
H84559H84559
können. Diese mechanischen Einrichtungen sollten in der Lage sein, die Beine bewegen-zu können,, ohne daß eine Unterstützung diese Bewegung durch Anbringen des Ballastes oder Entfernen des Ballastes erforderlich wäre, so daß die Beine unabhängig von evtl. Störungen des Ballastsystemes verschwenkt werden können.can. These mechanical devices should be in the Be able to move your legs, without any support this movement would be required by adding the ballast or removing the ballast, so that the legs can be swiveled independently of any disturbances in the ballast system.
Die Vorrichtung gemäß der vorliegenden Erfindung kann in verschiedenen Größen ausgeführt werden, aber mit Rücksicht auf die flexible Anwendbarkeit der Konstruktion und die veränderbare Anordnung der Beine ist es zweckmäßig, daß beispielsweise eine einzige Vorrichtung für Wassertiefen von etwa 50 m bis etwa 85 m gebaut wird'.' Diese weitgehende Anpaßbarkeit bzw. Flexiblität der Vorrichtung gestattet einen maximalen Anwendungsbereich für Y/assertiefen für jede Größe der Stützvorrichtung»The device according to the present invention can be made in various sizes, but with consideration on the flexible applicability of the construction and the changeable arrangement of the legs, it is expedient that for example a single device is built for water depths of about 50 m to about 85 m '. This extensive Adaptability or flexibility of the device allowed a maximum area of application for Y / water depths for each size of the support device »
Bei der Konstruktion einer schwimmfähigen Plattform gemäß der Erfindung muß außerdem die maximale Wellenhöhe berücksichtigt werden, welcher die Vorrichtung ausgesetzt wird, wenn sie auf dem Meeresgrund abgesetzt ist. Maximale Wellenhöhen betragen gewöhnlich etwa 10 - 17 m bei Arbeiten vor der Küste. Deshalb muß für jede vorbestimmte Wassertiefe, wenn die Vorrichtung auf dem Meeresgrund abgestützt sein soll, die minimale Länge der Beine wenigstens gleich der maximalen Wassertiefe am Arbeitsort plus der erwünschten Höhe der Gelenke über dem Wasserspiegel plus einer weiteren Länge sein, die ausreicht, um es den Beinen zu ermöglichen, auf dem Meeresgrund zu bleiben, ohne genauWhen constructing a buoyant platform according to the invention, the maximum wave height must also be taken into account to which the device is exposed when it is deposited on the seabed. Maximum wave heights are usually around 10-17 m when working offshore. Therefore, for any predetermined depth of water when the device is supported on the seabed the minimum length of the legs should be at least equal to the maximum water depth at the work site plus the desired The height of the joints must be above the water level plus another length sufficient to accommodate the legs allow to stay on the ocean floor without being accurate
909821/0053909821/0053
- 23 -- 23 -
- - 23 - U84559- - 23 - U84559
senkrecht stehen zu müssen, wobei zusätzlich noch eine Länge von wenigstens 10 bis 17 m hinzukommt, um die zu erwartende maximale Wellenhöhe ausgleichen zu können·To have to stand vertically, with a length of at least 10 to 17 m added to the to be able to compensate for the expected maximum wave height
Die Beine sind vorzugsweise, wie in der Zeichnung dargestellt, rohrförmig ausgebildet, jedoch können sie auch aus Stahlprofilen hergestellt und mit an diesen vorgesehenen Behältern versehen sein, wobei die Behälter eine genügende Auftriebskraft entwickeln müssen, um die Beine, die Plattform und die ladung tragen und die gesamte Vorrichtung anheben zu können, so daß sich die Plattform wenigstens 10 m über dem Wasserspiegel befindet. Diese Behälter sollten ebenfalls mit einer Pumpe und Steuereinrichtungen zum Einbringen des Ballastes und Entfernen desselben, wie weiter oben beschrieben, versehen sein, wobei ähnliche Pumpen und Steuereinrichtungen vorgesehen sein sollen, wie in den in der Zeichnung dargestellten Beinen.The legs are preferably, as shown in the drawing, tubular, but they can also made of steel profiles and provided with these provided containers, the container a Develop sufficient buoyancy to support the legs, platform and cargo, and the entire device to be able to lift so that the platform is at least 10 m above the water level. These containers should also be equipped with a pump and control devices for introducing and removing the ballast, as described above, similar pumps and controls being provided should, as in the legs shown in the drawing.
Die Wirkungsweise des Ballastsystems ist am besten in Verbindung mit Fig. 7 zu verstehen. Wenn alle Kammern leer sind, befinden sich die Beine in der in Fig. 2 und 5 dargestellten Lage. Das Anbringen von Ballast beginnt, indem das Ventil 64 geöffnet und Wasser in die Einlaßleitungen 63 eingebracht wird. Dann wird der Motor 65 bei geöffnetem. Ventil 69 angefahren, und die Pumpe 62 pumpt Wasserballast durch die Leitung 66, das Ventil 69 und die Leitung 72 in die Kammer 57Λ, Wenn der rohrförmige Teil 12 mit einem getrennten Füllsystem versehen ist, beginnt seine Pumpe zur selben £«3-$ (wi« üj,e· PAunpe 62 zu arbeiten,The operation of the ballast system is best understood in conjunction with FIG. When all chambers are empty, the legs are in the position shown in Figs. Ballasting begins by opening valve 64 and introducing water into inlet lines 63. Then the motor 65 is opened with. Valve approached 69, and the pump 62 pumps water ballast through line 66, valve 69 and line 72 into the chamber 57 Λ, when the tubular part is provided with a separate filling system 12, its pump starts at the same £ «3- $ (wi «üj, e · PAunpe 62 to work,
909821/0053909821/0053
- 24 -- 24 -
und die Kammer 50 wird zur selben Zeit wie die Kammer 57 gefüllt. Wenn die Kammer 44 zur Aufnahme von Ballast be-^ stimmt ist, wird sie zuerst gefüllt, um ein maximales Schwenkmoment auf das betreffende Bein auszuüben und das Bein schneller in seine nach unten gerichtete lage zu schwenken. Wie weiter oben bereits erwähnt, findet das Anbringen des Ballastes bei allen Beinen gleichzeitig statt, und die Plattform 1 wird dabei praktisch in horizontaler Lage gehalten. Wenn die zuerst zu füllenden Kammern vollständig mit Wasserballast gefüllt sind, wird als nächstes die Kammer gefüllt, welche sich am weitesten entfernt von der Plattform 1 befindet und ein weiteres maximales Moment zum Verschwenken des Beines erzeugt« Wenn das Bein teilweise durch Füllung der Kammer 44 mit Ballast versehen ist, wird die Kammer 50 vor der Kammer 57 gefüllt, weil sie einen größeren Einfluß auf die Bewegung des Beines in seine abgesenkte lage ausübt. Die Reihenfolge zum Füllen der Kammern, falls diese unabhängig voneinander gefüllt und entleert werden können, setzt sich folgendermaßen zusammen: zuerst wird·die Kammer 44 gefüllt, dann die Kammer 50, dann die Kammer 57, dann die Kammer 51, und wenn das Bein sich seiner abgesenkten lage nähert, wird die Kammer 52 gefüllt, um den letzten Teil der Bewegung des Beines in seine abgesenkte Lage zu bewirken. Die Kammern 58 und 59 können gefüllt werden, um die Schwimmfähigkeit der Vorrichtung aufzuheben, nachdem die Beine in ihrer gewünschten Stellung festgelegt wurden. Wenn" die Vorrichtung auf dem Meeresboden in ihrer gewünschten Stellung festgesetzt ist, sind alle Kammern vollständig ge-and chamber 50 is filled at the same time as chamber 57. When the chamber 44 is used to hold ballast is correct, it is first filled in order to exert a maximum pivoting moment on the leg in question and that Swivel leg faster to its downward position. As mentioned above, that finds Attaching the ballast to all legs takes place at the same time, and the platform 1 is practically in a horizontal position Location held. When the chambers to be filled first are completely filled with water ballast, a next filled the chamber which is furthest away from platform 1 and another maximum Moment to pivot the leg generated «If the leg is partially filled by filling the chamber 44 with ballast is provided, the chamber 50 is filled before the chamber 57 because it has a greater influence on the movement of the leg in its lowered position. The order in which the chambers are filled, if they are independent of each other can be filled and emptied, is composed as follows: first the chamber 44 is filled, then chamber 50, then chamber 57, then chamber 51, and when the leg approaches its lowered position, the chamber 52 is filled to effect the final part of the movement of the leg to its lowered position. the Chambers 58 and 59 can be filled to disable the buoyancy of the device after the legs were set in their desired position. When "the device on the seabed in its desired position is fixed, all chambers are completely
909821/0053909821/0053
- 25 -- 25 -
U84559U84559
füllt, um jeden Auftrieb auszugleichen und dadurch einen stabilen Stand der Vorrichtung zu schaffen, welcher nicht durch Wasserbewegungen beeinträchtigt wird, und zwar weder duroh Wellen auf der Oberfläche noch duroh Wasserströmungen·fills to compensate for any buoyancy and thereby one to create a stable position of the device, which is not affected by water movements, neither duroh waves on the surface nor duroh water currents
Während des Einbringens des Ballastes, wenn die Kammer 57 gefüllt ist und es erwünsoht ist, mit dem Tüllen der Kammer 58 zu beginnen, wird das Ventil 69 geschlossen und das Ventil 68 geöffnet. Die Beendigung des Füllvorganges der Kammer 57 kann durch Beobachtungen des duroh die Bntlüftungsleitung 73 austretenden Wassers bestimmt werden oder es kann die gewünschte Ballastwassermenge gemessen werden. Wenn genügend Ballast in die Kammer 57 eingebracht wurde, kann mit dem Einbringen von Ballast in die näohste Kammer begonnen werden, indem die Ventile 67, 68 und 69 entsprechend umgestellt werden.During the introduction of the ballast, when the chamber 57 is filled and it is desired to begin spouting the chamber 58, the valve 69 is closed and the valve 68 opened. The completion of the filling process of the chamber 57 can be determined by observing the water exiting through the ventilation line 73 or the desired amount of ballast water can be measured. When enough ballast is introduced into the chamber 57 can with the introduction of ballast in the nearest Chamber can be started by opening valves 67, 68 and 69 be converted accordingly.
Die Bntlüftungsieitungen 73, 74, 75, 95, 96 und 97 siad an allen Kammern vorgesehen, welche Wasserballast aufnehmen sollen, um einen Druokaufbau in den Kammern während des Füllvorganges und die Bildung eines Vakuums während d·« Entleerens des Wasserballastea zu verhindern. Se ist vorzuziehen, jede Kammer nioht ganz zu füllen, um daa Tüllen der Entlüftungsleitungen zu verhindern. Wenn die Bntltiftungsleitungen voll sind, befindet sioh im Inneren jeder Kammer wegen der geringen Höhe des Bntlüftungsleitunge- j auslasses über dem Wasserspiegel stets ein etwas höhtr·? Druck als auf der Außenseite. Das *Üllen der Bn-kltiftung·- leitungen bewirkt einen Druckunterschied awiaohen tin·» ιThe ventilation lines 73, 74, 75, 95, 96 and 97 are connected all chambers are provided, which are supposed to accommodate water ballast, in order to build up pressure in the chambers during the To prevent the filling process and the formation of a vacuum during the emptying of the water ballast. It is preferable not to completely fill each chamber in order to make the spouts to prevent the vent lines. When the discharge lines are full, everyone is inside Chamber because of the low height of the ventilation duct j the outlet above the water level is always a little higher ·? Print than on the outside. The * oiling of the Bn-kltiftung - lines causes a pressure difference awiaohen tin · »ι
909821/0053 ! 909821/0053 !
- 26 -- 26 -
U84559U84559
vollständig gefüllten Kammer und der anschließenden Kammer, wenn diese nicht vollständig gefüllt ist. Um derartige Druckunterschiede zu verhindern und stets sicherzustellen, daß der Druck in den Kammern geringer als der Wasserdruck um die Kammern herum ist, ist es vorzuziehen, daß die Entlüftungsleitungen nicht gefüllt sind, und daß die unteren Teile der Beine so ausgelegt sind, daß sie dem unteren Wasserdruck in der Tiefe, in der eie sioh befinden können, standhalten.completely filled chamber and the subsequent chamber if it is not completely filled. To such To prevent pressure differences and always ensure that the pressure in the chambers is less than that Water pressure around the chambers, it is preferable that the vent lines are not filled and that the lower parts of the legs are designed so that they can withstand the lower water pressure in the depth at which eie sioh can withstand.
Das Entfernen des Wasserballastes aus den Beinen beginnt zweckmäßigerweise durch öffnen des Yentiles 86 und des Ventiles 81 mittels der Betätigungsstange 83. Wenn die Ventile 81 und 86 offen sind, wird der Motor 84 angefahren, und es wird Wasser aus der Kammer 60 durch die leitung 78, das Ventil 81, das Sammelrohr 81a, die Pumpe 82, die leitung 85 und das Ventil 86 normalerweise in die Kammern der Plattform 1 oder in das umliegende Wasser gepumpt.The removal of the water ballast from the legs begins expediently by opening the Y-valve 86 and the Valve 81 by means of the actuating rod 83. When the valves 81 and 86 are open, the motor 84 is started, and there is water from the chamber 60 through the line 78, the valve 81, the collecting pipe 81a, the pump 82, line 85 and valve 86 are normally pumped into the chambers of platform 1 or into the surrounding water.
8t8t
Wenn die Kammer 60 leer ist, wird das VentilygeschlOBsen und das Ventil 80 geöffnet, um mit dem Entleeren der Kammer 59 beginnen zu können. Die Kammern im rohrförmigen Teil 12 können vom Wasserballast zur selben Zeit wie die Kammern im rohrförmigen Teil 13 entleert werden, indem die Ventile 90, 91 oder 92 geöffnet werden, weil die Sammelleitung 81a und die Sammelleitung 93 direkt mit der Saugseite der Pumpe 82 verbunden sind. Es wird zunächst genügend Ballast entfernt, bis die Vorrichtung wieder schwimmfähig geworden ist, wie Pig. 3 zeigt. Dann werden die HaI-When the chamber 60 is empty, the valve is closed and valve 80 opened to begin emptying chamber 59. The chambers in the tubular Part 12 can be emptied of the water ballast at the same time as the chambers in the tubular part 13 by the Valves 90, 91 or 92 are opened because the manifold 81a and the manifold 93 are directly connected to the suction side the pump 82 are connected. Sufficient ballast is first removed until the device is buoyant again has become like Pig. 3 shows. Then the shark
909821/0053909821/0053
--27 ---27 -
■: "- 27 - H84559■: "- 27 - H84559
teboleen für die Beine aus der Plattform 1 herausgezogen, woraufhin das Entfernen des Ballastes aus den Beinen fortgesetzt wird, bis die Beine in die Schleppstellung der Vorrichtung hochgeschwenkt sind. Das Entfernen des Ballastes ist mit Sorgfalt durchzuführen, damit die Plattform 1 praktisch stets waagerecht bleibt. Dies kann durch eine Steuerung von Hand oder durch selbsttätige Steuereinrichtungen bewirkt werden, wie weiter oben in Verbindung mit dem Einbringen des Ballastes in die Beine beschrieben wurde.teboleen pulled out of platform 1 for the legs, whereupon the removal of the ballast from the legs continues until the legs are in the towing position of the Device are pivoted up. The removal of the ballast must be carried out with care so that the platform 1 practically always remains horizontal. This can be done by manual control or by automatic control devices be effected as described above in connection with the introduction of the ballast into the legs became.
Aus dem Vorstehenden ist zu ersehen, daß durch die vorliegende Erfindung eine Arbeitsplattform geschaffen wird, die vor der Küste bzw. in einem See aufgestellt werden kann, wobei sie zum Schleppen zum Arbeitsort schwimmfähig ist und sich selbsttätig in die Bohrstellung bzw. Arbeitsstellung bringen kann, indem Kammern in ihren Beinen mit Ballast versehen werden. Das Belasten der Beine und Entlasten der Plattform bewirkt, daß die Beine der Vorrichtung aus einer praktisch waagerechten Schwimmstellung in eine nach unten und auswärts gerichtete Stellung geschwenkt werden. Ein weiteres Anbringen von Ballast nach dem Festlegen bzw. Verriegeln der Beine in dieser Stellung setzt die Vorrichtung auf dem Meeresboden oder Seeboden in der gewünschten Stellung ab. Durch die vorliegende Erfindung wird eine schwimmfähige Plattform für Arbeiten auf See, beispielsweise zum Unterwasserbohren, geschaffen, welche nach unten und auswärts verlaufende Beine aufweist, dieFrom the above it can be seen that the present invention creates a work platform, which can be set up off the coast or in a lake, whereby they can float to be towed to the place of work is and can automatically bring itself into the drilling position or working position by adding chambers in their legs Ballast can be provided. Loading the legs and unloading the platform causes the legs of the device pivoted from a practically horizontal floating position to a downward and outward position will. Another attachment of ballast after fixing or locking the legs in this position sets in the device on the seabed or seabed in the desired position. Through the present invention a floating platform is created for work at sea, for example for underwater drilling, which has downwardly and outwardly extending legs that
909821/0053909821/0053
— 28 —- 28 -
148Λ559148-559
sich auf dem Meeresboden oder Seeboden am Einsatzort abstützen können, wobei die verschiedenen Einstellmöglichkeiten der Beine eine große Flexibilität bzw. Anpaßbarkeit an verschiedene Bodenstrukturen und Wassertiefen und eine große Stabilität der Plattform auf ihren Stützen bewirken. can be supported on the seabed or seabed at the place of use, with the various adjustment options of the legs causing great flexibility or adaptability to different bottom structures and water depths and great stability of the platform on its supports.
Durch die vorliegende Erfindung wird eine schwimmfähige Arbeitsplattform bzw. Bohrinsel geschaffen, an welche Auftriebskörper darstellende Beine angelenkt sind, die nach unten bewegt werden, während die Plattform über den Wasserspiegel angehoben wird. Wenn die Beine nach unten in die gewünschte Stellung bewegt worden sind, werden sie in dieser Stellung festgelegt, um ein weiteres Verschwenken derselben um ihre Gelenke zu verhindern, woraufhin die gesamte Vorrichtung durch Anbringen weiteren Ballastes auf dem Meeresboden abgesetzt wirde The present invention creates a buoyant working platform or drilling rig to which legs constituting floats are articulated and which are moved downward while the platform is raised above the water level. When the legs have been moved down to the desired position, they are fixed in this position in order to prevent further pivoting of the same about their joints , whereupon the entire device is set down on the seabed by adding further ballast
Durch die Erfindung wird weiterhin eine Stütz- und Tragvorrichtung für eine schwimmfähige Plattform geschaffen, welche durch Anbringen bzw. Einbringen von Ballast in jede gewünschte Stellung gebracht werden kann und welche nach dem Entfernen des Ballastes in ihre Ausgangsstellung zurückkehrt. Deshalb wird die Stellung der Stützvorrichtung durch die Menge des Ballastes gesteuert, und durch das Steuern des Ballastes erhält man einen festen Stand der Vorrichtung in der gewünschten Stellung. Ferner wirdThe invention also provides a support and carrying device for a buoyant platform which can be brought into any desired position by attaching or introducing ballast and which returns to its starting position after the ballast has been removed. Therefore, the position of the support device is controlled by the amount of ballast, and by controlling the ballast one obtains a firm stand of the device in the desired position. Furthermore,
- 29 909821 /0053- 29 909821/0053
. -29- K84559. -29- K84559
durch die vorliegende Erfindung eine schwimmfähige Arbeitsplattform bzw. Bohrinsel geeohaffen, welche eine Mehrzahl von Beinen hat, von denen wenigstens zwei aus einer im wesentlichen waagerechten Schleppstellung in eine im Wasser eingetauchte Stellung verschwenkt werden können, in welcher sie gegeneinander divergierend schräg nach unten verlaufen.by the present invention a buoyant work platform or drilling platform geeohaffen which has a plurality of legs, at least two of which can be pivoted from a substantially horizontal towing position into a submerged position in which they diverge diagonally downwards from one another.
909821/0053909821/0053
Claims (1)
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US304590A US3306052A (en) | 1963-08-26 | 1963-08-26 | Floatable structure and method of operating same |
Publications (1)
Publication Number | Publication Date |
---|---|
DE1484559A1 true DE1484559A1 (en) | 1969-05-22 |
Family
ID=23177142
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19641484559 Pending DE1484559A1 (en) | 1963-08-26 | 1964-08-26 | Floatable drilling rig or the like. |
Country Status (6)
Country | Link |
---|---|
US (1) | US3306052A (en) |
BE (1) | BE652206A (en) |
DE (1) | DE1484559A1 (en) |
ES (1) | ES303480A1 (en) |
GB (1) | GB1077738A (en) |
NL (1) | NL6409902A (en) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3352269A (en) * | 1964-10-23 | 1967-11-14 | Otis Eng Co | Floating work platform |
US3388556A (en) * | 1966-10-10 | 1968-06-18 | Mobil Oil Corp | Marine storage structure |
US3716993A (en) * | 1971-01-18 | 1973-02-20 | M Sumner | Modular offshore structures system |
US3922868A (en) * | 1974-08-27 | 1975-12-02 | Reagan W Mcdonald | Deep water platform construction |
US4106302A (en) * | 1976-05-17 | 1978-08-15 | Maschinenfabrik Augsburg-Nurnberg Aktiengesellschaft | Off-shore drilling and production platform and method of building same |
US4474509A (en) * | 1978-02-03 | 1984-10-02 | Antes Ronald E | Method of erecting a marine structure utilizing a removable watertight plug assembly |
JPS6070213A (en) * | 1983-09-27 | 1985-04-22 | Kaiyo Toshi Kaihatsu Kk | Regulating mechanism for landing of marine structure on bottom |
US4818145A (en) * | 1986-09-16 | 1989-04-04 | Cbs Engineering, Inc. | Offshore support structure methods and apparatus |
US4842446A (en) * | 1986-09-16 | 1989-06-27 | Cbs Engineering, Inc. | Offshore support structure methods and apparatus |
US5181799A (en) * | 1990-04-03 | 1993-01-26 | Cbs Engineering, Inc. | Offshore support structure apparatus |
US5308194A (en) * | 1990-04-03 | 1994-05-03 | Cbs Engineering, Inc. | Offshore support structure apparatus |
US5122010A (en) * | 1990-09-13 | 1992-06-16 | Burguieres Jr Sam T | Offshore platform structure |
NL1009128C2 (en) * | 1998-05-11 | 1999-11-12 | Zwagerman International B V J | Lifting Island. |
US7293939B2 (en) * | 2004-02-10 | 2007-11-13 | Phillip Andrew Abbott | Inclined leg floating production platform with a damper plate |
GB0704897D0 (en) * | 2007-03-14 | 2007-04-18 | Rotech Holdings Ltd | Power generator and turbine unit |
US9637257B2 (en) * | 2013-05-24 | 2017-05-02 | L'Air Liquide Société Anonyme Pour L'Étude Et L'Exploitation Des Procedes Georges Claude | Weather shelter for use in a remote manufacturing yard |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2608829A (en) * | 1948-03-30 | 1952-09-02 | Standard Oil Dev Co | Portable marine foundation |
US2598329A (en) * | 1948-06-23 | 1952-05-27 | Harvey A Wilson | Offshore drilling platform and method of constructing same |
US2600761A (en) * | 1948-12-06 | 1952-06-17 | Erle P Halliburton | Offshore drilling means |
US2622404A (en) * | 1949-03-24 | 1952-12-23 | George P Rice | Offshore drilling apparatus and method of installing the same |
US2968930A (en) * | 1955-10-12 | 1961-01-24 | Offshore Structures & Service | Mobile self-erecting marine platforms |
-
1963
- 1963-08-26 US US304590A patent/US3306052A/en not_active Expired - Lifetime
-
1964
- 1964-08-24 BE BE652206D patent/BE652206A/xx unknown
- 1964-08-26 NL NL6409902A patent/NL6409902A/xx unknown
- 1964-08-26 ES ES0303480A patent/ES303480A1/en not_active Expired
- 1964-08-26 DE DE19641484559 patent/DE1484559A1/en active Pending
- 1964-08-26 GB GB35020/64A patent/GB1077738A/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
GB1077738A (en) | 1967-08-02 |
BE652206A (en) | 1965-02-24 |
US3306052A (en) | 1967-02-28 |
ES303480A1 (en) | 1965-03-16 |
NL6409902A (en) | 1965-03-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2913570C2 (en) | Offshore platform and procedure for setting up an offshore platform | |
DE1484559A1 (en) | Floatable drilling rig or the like. | |
DE1456235A1 (en) | Floating storage container | |
EP2539219B1 (en) | Device for transporting and installing an arrangement of an offshore wind turbine comprising a raft foundation and method for transporting and installing such an arrangement having a raft foundation | |
DE2359540A1 (en) | UNDERWATER FUNDABLE EQUIPMENT AND PROCEDURE FOR ESTABLISHING IT ON THE SEA FLOOR | |
DE1506207A1 (en) | Floatable storage device and method for its operation | |
DE2416357A1 (en) | METHOD AND DEVICE FOR CONVERTING A FLOATING MONKEY INTO A SEMI-SUBMERSIBLE FLOATING VEHICLE, IN PARTICULAR A FLOATING WORK ISLAND | |
DE102008046359A1 (en) | Device for transporting and installing at least one flat foundation comprehensive arrangement of an offshore wind turbine and method for transport and installation of such a flat foundation with mast | |
DE1431323A1 (en) | Swimming structure | |
DE1956328A1 (en) | At some distance from the coast, retractable device for the extraction and storage of oil | |
DE3219968A1 (en) | DEVICE FOR LIFTING AND REMOVING THE SCAFFOLD USED OFFSHORE CONSTRUCTIONS | |
DE2728994C2 (en) | Underwater tank with an articulated column supporting an overwater platform, as well as a method for sea transport and lowering of such an underwater tank | |
DE2121020A1 (en) | Anchoring device for offshore drilling rigs and the like and methods for their laying | |
DE1294840B (en) | Manned offshore station | |
EP2623674A1 (en) | Substructure for an offshore platform and method for installing same | |
DE2512565A1 (en) | PIPE LAYING SHIP | |
DE1812174C3 (en) | Device for stabilizing work ships, such as drilling ships or similar floating structures | |
DE1781292A1 (en) | SEMI-SUBMERSIBLE DOUBLE HULL SHIP WITH ONE OR MORE LOADING ARMS | |
DE2458694A1 (en) | SINGLE POINT ANCHORING DEVICE AND METHOD FOR MAKING IT OPERATIONAL | |
DE1925142A1 (en) | Device for transporting a floating offshore platform | |
DE1953753C3 (en) | Device for assembling hulls from ring sections | |
DE2713756B2 (en) | Container to be placed on the seabed for storing liquids | |
DE2159378C3 (en) | Method for erecting a hydraulic engineering structure and device for carrying out the method | |
DE2758339A1 (en) | IMPROVEMENTS TO THE PLATFORMS FOR EXPLOITING THE SEA FLOOR | |
EP2623675A1 (en) | Platform topside for an offshore platform and method for installing such a platform topside |