DE10349041A1 - Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod - Google Patents

Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod Download PDF

Info

Publication number
DE10349041A1
DE10349041A1 DE2003149041 DE10349041A DE10349041A1 DE 10349041 A1 DE10349041 A1 DE 10349041A1 DE 2003149041 DE2003149041 DE 2003149041 DE 10349041 A DE10349041 A DE 10349041A DE 10349041 A1 DE10349041 A1 DE 10349041A1
Authority
DE
Germany
Prior art keywords
length
concrete
accuracy
measuring
distance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE2003149041
Other languages
German (de)
Inventor
Jouri Selski
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Selski Jouri Dr-Ing
Original Assignee
Selski Jouri Dr-Ing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Selski Jouri Dr-Ing filed Critical Selski Jouri Dr-Ing
Priority to DE2003149041 priority Critical patent/DE10349041A1/en
Publication of DE10349041A1 publication Critical patent/DE10349041A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • E04B1/043Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Length-Measuring Instruments Using Mechanical Means (AREA)

Abstract

Direct measuring of path lengths, height and right angles without the use of a geodetic instrument using an inventive device that comprises a cylindrical measurement scale (1) that is used with a marking rod (6) that slides along the rod.

Description

STAND DER TECHNIKSTATE OF THE ART

Die Bemessung bei Ausbau basiert auf Verwendung von Geodäsiegeräten einerseits und Handhabung von verschiedenen Manuellmitteln andererseits. Zur Zeit existieren verschiedene Vermessungsgeräte von einfachen Bandmaßen, Schnurloten bis Nivellieren und Theodoliten einschließlich modernen Elektronischen Tachymetern mit Feldrechner und zulässiger Genauigkeit (ca. 3 mm und 1 mgon für Winkel) und Digitalnivelliere.The dimensioning is based on expansion on the use of geodesy devices on the one hand and handling of various manual means on the other hand. to Various measuring devices exist from simple tape measures, cord plummets to leveling and theodolites including modern electronics Tachymeters with field calculator and permissible accuracy (approx. 3 mm and 1 mgon for Angles) and digital levels.

Man verwendet vielfältige Verbindungen zwischen Ränder von benachbarten Fertigteilen, hauptsächlich durch Vorsprünge für Bewehrung, die auf Baustelle mit Vergussbeton vereinigt werden.Various connections are used between edges of neighboring prefabricated parts, mainly through projections for reinforcement, which are combined with grouting concrete on site.

KRITIK DES STANDES DER TECHNIKCRITICISM OF THE STATE OF THE TECHNOLOGY

Man bewahrt erhebfichen Unterschied zwischen zulässigen Toleranzen und minimalen verwendeten Blechendicken in Maschinenbau und BauwesenYou keep a significant difference between permissible Tolerances and minimum sheet thicknesses used in mechanical engineering and construction

Das biegsame Bandmaß taugt nicht für Halterung, Genauigkeit von Libellen in Geodäsiegeräten sehr abhängig vom Radius und Gleichformigkeit der Schliffkurve, der Große der Libellenblase, Art der Flüssigkeit, Temperatureinflüssen.The flexible tape measure is good not for Bracket, accuracy of dragonflies in geodesic devices very dependent on Radius and uniformity of the cut curve, the size of the bubble, Type of liquid, Temperature influences.

Nur unmittelbare Streckenmessung, z.B. mit Stahlbandmass, kann die Streckengenauigkeit 1/10000 sein, weil moderne Geodäsiegeräte (Angaben 2002) nur Genauigkeit ca. 25 mm auf 20 m Zielweite gewährleisten.Only direct route measurement, e.g. with steel tape measure, the track accuracy can be 1/10000, because modern geodesy equipment (data 2002) only guarantee accuracy of approx. 25 mm at 20 m target range.

AUFGABETASK

Die Gegenstand der Erfindung ist Vervollkommnung von Bemessungen für Fertigteilen und bei Montage, um Kluft zwischen obengenannten Toleranzen zu vermindern Andererseits ist wichtig die Fuge zwischen einzelnen Bauteilen soweit möglich zu Eigenschaften von monolithischen Aufbau zu annähern und mit Automatisierung zu fertigenThe object of the invention is Perfection of dimensions for finished parts and during assembly, to narrow the gap between the above tolerances it is important to close the joint between individual components as far as possible Approximate properties of monolithic structure and with automation to manufacture

LÖSUNG DER AUFGABESOLUTION TO THE TASK

Das moderne Technikniveau und zeit- oder temperaturabhängige Veränderung von Ausmaßen für Stahl und auf bestimmte Weise befeuchteten Beton zeigen deutlich dafür, dass die Toleranzen für Fertigbauteilen und bei Montage können und sollen die Große ± (3 – 5mm) nicht überschreiten..The modern level of technology and or temperature dependent change of dimensions for steel and concrete moistened in certain ways clearly show that the tolerances for finished parts and when assembling and should not exceed the size ± (3 - 5mm) ..

Dadurch schafft man folgende Voraussetzungen: 1) die Ausmaße von Bauelementen kann man so anordnen, dass Zwischenschlitzen die Möglichkeit von Ausgleich bei Montage und gleichzeitig gute Qualität bei Trockenbauweise gewährleisten, 2) die Unübereinstimmung geplanten Positionen bei Schraubenverbindungen kann man durch leichte Hammerschläge beseitigen.This creates the following requirements: 1) the dimensions of components can be arranged so that intermediate slots possibility of compensation during assembly and at the same time good quality with dry construction guarantee, 2) the mismatch planned positions for screw connections can be eliminated by light hammer blows.

Eines Paar von Markierungsstiften auf einen FertigteilA pair of marker pens on a finished part

Markierungsstift oder einfach Marker 6 (1b) ist kurz hervorragender aus einen seitlichen Flache (Dickenflache) von Fertigteil metallischer Stift, der zu Vermessung seiner Position bezüglich anderen gleichen Markern dient. Die Markern eines Paares werden auf bestimmten Abstand voneinander angeordnet. Dafür braucht man runde Aussparungen oder kurze Rohrchen am Ränder von Fertigteilen, innerhalb denen vor der Vermessung diese Markern eingesetzt werden. Diese Markern, die für bequeme Benutzung innerhalb Höhe ca. 1.5m positioniert werden, müssen mindestens für eckige Elemente von einer Gebäude vorausgesehen werden.Marker pen or simply marker 6 ( 1b ) is briefly more outstanding from a lateral surface (thickness surface) of the finished part metallic pin, which is used to measure its position with respect to other identical markers. The markers of a pair are arranged at a certain distance from each other. For this you need round recesses or short tubes on the edges of finished parts, within which these markers are used before the measurement. These markers, which are positioned for easy use within a height of approx. 1.5m, must be foreseen at least for square elements of a building.

Langennormal.Long Normal.

Dafür benutzt man einen Profil 1 aus rostfreien Stahl oder Aluminiumlegierungen mit Eingravierungen von metrischer Skale, die bei Warm- oder Kaltwalzen durch entsprechend geriffelte Walzenoberfläche aufgetragt wird (1a). Jeder Langennormal hat zwei Haltern mit Öffnungen für Anhängen auf Mackern - einen unbeweglichen O-Halter und zweiter transparenter Schieber (analogisch diejenigen für Rechenstab), aber mit Befestigung- bzw. Reibungsschrauben (1b).For this you use a profile 1 Made of stainless steel or aluminum alloys with engravings of a metric scale, which is applied to hot or cold rolls by means of a corrugated roll surface ( 1a ). Each length standard has two holders with openings for attachments to mackers - an immovable O-holder and a second transparent slide (similar to those for rake rods), but with fastening or friction screws ( 1b ).

Diese Langennormale können in 2 Kategorien aufteilen: 1) erste Kategorie bedeutet, dass bei bestimmter Temperatur Abweichung von genauen Wert auf voller Lange kann bestimmten Wert (1mm oder seine Bruchteil) nicht überschreiten, 2) zweite Kategorie bedeutet, dass vorhandene Skala dieser Bedienung nicht genügt, deshalb sollen unmittelbar auf diesen Normal auch Umrechnungskoeffizient gezeigt wird.These long standards can be in Split 2 categories: 1) first category means that certain Temperature deviation from exact value over full length can be determined Do not exceed value (1mm or its fraction), 2) second category means that the existing scale does not suffice for this operation, therefore should also directly convert to this standard will be shown.

Dieser Profil dient nach Auftragen von numerischen Anzeigen als Langennormal, die nicht nur für Bemessung auf Baustelle, aber auch für Fertigung präzisen geschweißten Schalungen für Baugewerbe oder Baustelle benutzt wird.This profile is used after application of numerical displays as length standards that are not just for dimensioning on construction sites, but also for Manufacturing precise welded Formwork for Construction or construction site is used.

Zusammen mit befestigten durch Öffnungen in dem Profil 1 Wasserwaage wird eines Langennormal auch für Korrigierung von projektangeordneter gleicher Höhe beiden Stützpunkten benutzt.Along with fastened through openings in the profile 1 Spirit level of a length standard is also used for correcting project-equal height of both bases.

Winkelvermessung durch drei Langennormalen.Angle measurement by three length standards.

Was betrifft genaue Vermessung von rechten Winkeln in horizontalen und vertikalen Ebenen und folgend mit Projekt bezeichnete Auflage von Wand- und Geschossdeckenelementen, so einfachster und gleichzeitig genauerster Weg zu dieser Ziel ist Benutzung von diesem Langennormalen, drehenden bezüglich bestimmten Achse. Dann eine Verbindung diesen beiden Normalen mit Lange A und B mit drittem Normal (Diagonale) mit Lange √A² + B² gibt genaue Lage. Diese Diagonale funktioniert als Halter für wirklich vertikale Tragwand bei Montage (1b).As far as accurate measurement of right angles in horizontal and vertical planes and subsequent project-related support of wall and floor ceiling elements, the simplest and most precise way to achieve this goal is to use this length normal, rotating with respect to a specific axis. Then connect these two norms with length A and B with third tem normal (diagonal) with length √ A² + B² gives exact location. This diagonal works as a holder for a really vertical supporting wall during assembly ( 1b ).

Besonders leicht ist die Verwertung dieser Weise bei stationären Bedingungen in Baugewerbe, wo diese Vermessungen und Fixierungen werden in horizontaler Flache bezüglich deutlich erkannten Markierungen auf bequemen Tischhöhe erffüllt. Nach der Schweißen damit präziser angeordneter Schalung mit Langennormalen werden auch Montagelasche oder Aussparung mit entsprechenden Markierungen ebensoviel präzis angeordnet.Recycling is particularly easy this way with stationary Conditions in construction where these surveying and fixing are in a horizontal area with respect to clearly recognized markings at a comfortable table height erffüllt. After welding thus more precise arranged formwork with length standards also become mounting brackets or recess with corresponding markings arranged just as much precisely.

Natürlich braucht diese Vermessung und Montageweise einen Schieber entlang Langennormal mit einem Begrenzer und optischer Vergrößerung, um möglichst genau verordneten Ausmaß gewährleisten.Of course, this measurement needs and mounting a slide along length normal with a limiter and optical magnification, in order as possible ensure precisely prescribed extent.

Für typische für mittlere Wohn- und Bürogebäude Ausmaßen in 10-100 m in Plan ist also obengeschilderte Weise mehr vorhersagende vom Standpunkt der Genauigkeit und jedenfalls konkurenzfähige.For typical for medium residential and office building dimensions in 10-100 m in plan is therefore more predictive of the above Viewpoint of accuracy and at any rate competitive.

Höhenbestimmung in Zwischenpunkten bei Schnurabsteckung durch Kraftmessgerät.Height determination in intermediate points if the cord is unplugged using a force measuring device.

Die wichtigste Vermessung auf Baustelle beginnt von Fundamenten. Nämlich ist die Genauigkeit Ihrer Lage zusammen mit dieser für Fertigteile maßgebende für weiteren Toleranzen bei damit schon abhängigen Bauprozess. Dafür sind zwei Bemerkungen entscheidend: 1) auf dieser Etappe kann man negative Windwirkung am meistens ausschließen, 2) für Korrigierung von obengenannter Lage ist immer benötige Mengen von Boden, Schotter usw. vorhanden und werden leicht betätigt. Im Gegenteil bringt die Benutzung von kleinen Mengen von Beton oder Mörtel für Unterlagen viele Problemen.The most important survey on site starts from foundations. Namely is the accuracy of your location along with that for finished parts authoritative for more Tolerances with already dependent Building process. Therefore two comments are crucial: 1) on this stage you can Mostly exclude negative wind effects, 2) for correction of the above Location is always needed Amounts of soil, gravel, etc. are present and are easily operated. in the On the contrary, the use of small amounts of concrete or mortar for documents many problems.

Ausgestreckter durch auf gleichen Niveau befindete Enden von Bauabschnitt Schnur gilt als zuverlässiger Anzeiger nicht nur in Plan, aber auch für Höhe von inzwischen ausgebauten Objekten.Outstretched by on same Level ends of the cord construction section are considered a reliable indicator not only on schedule, but also for the amount of now developed objects.

Bei einer unbeweglichen und anderen, benutzten für Spannung beweglicher Rolle, fixierenden auf gleicher Höhe (1c), einer Schnur biegt sich unter Eigengewicht in Form einer Parabel mit wer Durchbiegung f = γL2/8[σ], wobei γ-Volumengewicht von Schnurstoff, L-Schnurlange, [σ]-Spannung in Schnur. Bei mäßigen Langen und zulässigen Spannungen beträgt f die Großen in einige mm oder sogar ihre Bruchteile.In the case of an immovable and other roller used for tensioning, fixing at the same height ( 1c ), A cord bends under its own weight in the form of a parabola with who deflection f = γL 2/8 [σ], where γ volume weight of cord fabric, L-string Lange, [σ] -voltage in cord. With moderate lengths and permissible stresses, the size is a few mm or even a fraction of it.

Tragwandfügen(4)Supporting wall joining ( 4 )

Die Kreuzungen von Tragwänden sind die Plätze für fast monolithische Ihre Verbindung, die durch Verwendung am Randen Stahlblechen 2 einerseits und Schleifensvorsprrüngen 3 mit vertikalen Bewehrungsstäben 4 andererseits erreicht wird. Letzte sind so angeordnet, dass sich in zentraler Zone von zukunftiger Säule freier Raum für Beton- und Vibratortransfer befindet. Offen gebliebene Seite wird durch wiederverwendbare Schalung 5 oder 7 zu Montagelasche in Fertigteil angeschraubt 6.The intersections of supporting walls are the places for almost monolithic your connection, which is achieved by using sheet steel edges 2 on the one hand and loop projections 3 with vertical reinforcement bars 4 on the other hand is achieved. The latter are arranged so that there is free space for concrete and vibrator transfer in the central zone of the future pillar. The open side is made possible by reusable formwork 5 or 7 screwed to the mounting bracket in the finished part 6 ,

Durch Vorhandensein von Verdichtungen 8, 10 wird dieser Raum hermetisch geschlossen. Bei gesteuerter Fixierung für Betoncontainer mit Hosen und Verriegeln ist Bedienung für Betonieren von unten möglich. Man verwendet ähnlich die elastische Hose zu Vibrator durch einfache Anlage mit einer Rolle in bestimmten Platz.By the presence of densifications 8th . 10 this room is hermetically sealed. With controlled fixation for concrete containers with pants and locks, operation for concreting is possible from below. One uses similarly the elastic pants to vibrator by simple arrangement with a role in certain place.

ERZIELBARE VORTEILEACHIEVABLE BENEFITS

  • 1. Höhere Genauigkeit bei wirtschaftlicher Verwendung von Langennormalen und Schnuren führt zu Vereinfachung von Montage- und Fügensverbindungen.1. Higher Accuracy with economical use of length standards and Leads to simplify assembly and joining connections.
  • 2. Wesentliche Ökonomie von Baukosten für mehrschichtige Baukonstruktionen bei erforderlichen Schallschutz2. Essential economy of construction costs for multilayer Building constructions with necessary sound insulation
  • 3. Wirtschaftliche kraftschlüssige Konstruktionsfügen.3. Economic non-positive Add construction.

BESCHREIBUNG VON AUSFÜHRUNGSBEISPIELENDESCRIPTION OF EXAMPLES

Präzise VermessungPrecise measurement

Beim Warmwalzen von Langennormalen sollen die Teilungsintervalle berechenbar vergrößern, um nach Schrumpfung richtige Anzeige für normale Temperatur zu geben. Die numerische Angaben werden durch wasserfeste Farbe aufgetragen Nach am meistens verwendeten Ausmaßen für Bauzelle ist Ihre Lange (Abstand zwischen benachbarten Tragwänden) bis ca. 6 m und für Diagonal für eckige Elemente mit Markerabstand ca. 4 m auch ca. 6 m.When hot rolling long standards should increase the division intervals in a calculable way in order to correct them after shrinking Ad for to give normal temperature. The numerical information is indicated by waterproof paint applied according to the most commonly used dimensions for building cells is your length (distance between adjacent bulkheads) to about 6 m and for Diagonal for square elements with marker spacing approx. 4 m also approx. 6 m.

Berechnungen zeigen, dass bei mäßigen für Handhabung Eigengewicht haben solche biegsame Langennormale aber ausreichende Steifigkeiten, um möglich erschienende bei Montage Druckkräfte bis 1 Tonne ohne Knick zu aushalten.Calculations show that moderate for handling Such flexible long standards have sufficient dead weight Stiffness to possible pressure forces appearing during assembly up to 1 ton without a kink.

Für eine Gebäude mit 5 Eingängen und Lange ca. 60 m (2) beträgt die maximale Durchbiegung von Schnur aus Stahldraht bei Spannung bis Streckengrenze, berechnete durch obengenannte Formel, nur mehrere mm.For a building with 5 entrances and a length of approx. 60 m ( 2 ) the maximum deflection of steel wire cord at tension up to the line limit, calculated by the above formula, is only several mm.

Drei Langennormalen für Winkelmessung 1, 2, 3 (1b) mit bestimmten Anzeigen für Schiebern S und entsprechender Positionen für live Öffnungen werden nacheinander auf unbeweglichen O-Halter 5 von einer Seite und durch Öffnungen in Schiebern 4 von anderer Seite auf Markern 6 in Konstruktionsvertiefungen gesetzt.Three length standards for angle measurement 1 . 2 . 3 ( 1b ) with certain displays for sliders S and corresponding positions for live openings are successively on immobile O-holders 5 from one side and through openings in slides 4 from another side on markers 6 set in construction recesses.

Prinzip von Verwertung diesen Vermessungen sehr einfach: 1) eckiger echt vertikaler Bauelement muss horizontale Oberflache haben, 2) Quer angeordneter gleicher Bauelement kann auf genau rechten Winkel bei Montage ausrichten, 3) mit zwei parallelen Langennormalen kann man weitere Elemente justieren, 4) Seltener Ausgleich in Höhe nach Anzeigen von Wasserwaage erfüllt man durch Einsatz von fester Unterlagen benötigter Kleindicke, um Montagekran nicht lange zu aushalten, 5) Nach Abnehmen von wiederverwendbaren Langennormalen und Markern sind die Kontaktflächen für Montage von benachbarten Elementen wieder glatt. Analogisch gilt diese Weise für horizontale Elemente.The principle of recycling these measurements is very simple: 1) angular, real vertical component must have a horizontal surface, 2) the same component arranged transversely can align at exactly the right angle during assembly, 3) with two Parallel length standards can be adjusted, 4) Rarely compensation in height after the spirit level is displayed can be achieved by using the fixed base of the required small thickness, in order not to endure the assembly crane. 5) After removing reusable length standards and markers, the contact surfaces for mounting are neighboring elements smooth again. This applies analogously to horizontal elements.

Diese wirtschaftliche Vermessungen sind nur für Basisbauelemente benötigt. Weitere Trassierungen für andere, mit schon abhängiger Lage Bauelemente erfüllt man durch Verwendung von Schnurren und Loten, für dessen auch die Markern benutzt werden.These economic surveys are only for Basic components needed. Further alignment for other, with already dependent Location components met one by using purrs and plumb bobs, for which the markers are also used become.

a) Vorgefertigter Geschossdeckenelement A und seine Fügena) Prefabricated floor element A and its joints

Verwendung dieser Konstruktion ist besonders günstig für Gebäuden mit vielen Eingängen und herausfolgenden querliegenden Tragwänden 6 (2)Use of this construction is particularly favorable for buildings with many entrances and subsequent transverse bulkheads 6 ( 2 )

Ähnliche Reihe von Bauelementen A unterbricht sich nur bei Treppenhäusern 9. Der Element A besteht aus oberer bewehrter Leichtbetonplatte 1, Zuschlag 2 aus einem Schaumstoff mit Aussparungen mit kaschierendem Tragnetz 3 und feuerbeständigen Putz 5 von unten.A similar row of components A only interrupts stairwells 9 , Element A consists of an upper reinforced lightweight concrete slab 1 , Surcharge 2 made of a foam with recesses with a concealing net 3 and fire-resistant plaster 5 from underneath.

Die quere Aussparungen werden so angeordnet, dass beliebige Normal zu Deckenflache eine Luftschicht durchkreuzt und damit bei bestimmtem flachenbezogenen Massen für 1 und 5 normierende Schalldämmung gewährleistet wird.The cross recesses are like this arranged that any normal to ceiling surface is an air layer crossed and thus with certain flat-related masses for 1 and 5 standard sound insulation guaranteed becomes.

Die Konstruktion enthielt kaschierte in Schaumkern 2 eines Stahltragnetz aus krummen Blechen 3 zwischen einen Putz 5 aus feuerbeständigen Stoff und Deckenschicht 1 aus bewehrter Superleichtbeton. Die Abstände 30-50 cm zwischen schwach gekrümmten auf Radius Blechen 3 genügen für Durchlassen eines Schachtes, wenn es nötig ist.The construction contained a foam core 2 a steel support net made of crooked sheets 3 between a plaster 5 made of fire-resistant fabric and top layer 1 made of reinforced super light concrete. The distances 30-50 cm between slightly curved on radius sheets 3 suffice for passage of a shaft if necessary.

Am Rande enthielt der Element A Stahlprofil 4, der gleichzeitig als Schalung bei Ausschäumen und Ortbetonieren, Stützung auf Tragwand 6 und Befestigung von Streifen 3 benutzt wird. Man verwendet die Schraubenmuffe 7 für kraftschlüssige Verbindung zwischen benachbarten Elementen bei erforderlicher Toleranz.At the edge, element A contained steel profiles 4 , which is also used as formwork for foaming and in-situ concreting, support on the supporting wall 6 and fastening strips 3 is used. The screw sleeve is used 7 for positive connection between adjacent elements with required tolerance.

b) Gefertigte auf Baustelle Geschossdecke mit Netztragwerkb) Manufactured on site Floor ceiling with network structure

Prinzipielle Idee für Tragwerk mit krummen schalenartigen Deckschichten beruht sich auf Fähigkeiten sehr dünnen nicht biegenden Schalen, gleichmäßig verteilte Belastung, vielmehr übertreffende ihre Eigengewicht, zu aushalten.Basic idea for the structure with crooked shell-like top layers is based on skills very thin non-bending shells, evenly distributed Burden, rather exceeding theirs Endurance, endurance.

Die Realisierung dieser Idee für Stahlkonstruktion wird auf ca. gleicher Beanspruchung positioniertes in Schalensflache von positiver Gaußkrümmung Netzes aus krummen Blechen bei bestimmten Verhältnissen zwischen Blech- und Schalendicken basiert. Wegen großen (untransportablen) Ausmaßen des Netzes wird Ihre Fertigung nur durch Zusammenbau auf Baustelle erfüllt.Realizing this idea for steel structure is positioned on the same surface in the shell surface of positive Gaussian curvature of the network from crooked sheet metal under certain conditions between sheet metal and Shell thickness based. Because of the large (untransportable) dimensions of the Your production will only be fulfilled by assembly on the construction site.

Wirtschaftliche Schaumfüllung 2 kann bei diesen Umständen nur mittels kaltes Prozesses für Ausschäumen, ähnlichen Schaumbeton, geführt werden. Für geforderte Schallschutz wird dabei offenzelliger Schaum z. B. durch hydraulischen Stoß gefertigt. Flachengewicht dieses Stoffes beträgt wegen Zementgehalt eine Große zwischen reines Schaums und Schaumbeton.Economical foam filling 2 can only be carried out in these circumstances using a cold process for foaming, similar foam concrete. For the required sound insulation, open-cell foam is used for. B. manufactured by hydraulic shock. The weight per unit area of this material is between pure foam and foam concrete due to the cement content.

Die Konstruktion enthielt kaschierte in Schaumkern 2 eines Stahltragnetz aus krummen Blechen 3 zwischen einen Putz 5 aus feuerbeständigen Stoff und Deckenschicht 1 aus bewehrter Superleichtbeton. Die Abstände 30-50 cm zwischen schwach gekrümmten auf Radius Blechen 3 genügen für Durchlassen eines Schachtes, wenn es nötig ist.The construction contained a foam core 2 a steel support net made of crooked sheets 3 between a plaster 5 made of fire-resistant fabric and top layer 1 made of reinforced super light concrete. The distances 30-50 cm between slightly curved on radius sheets 3 suffice for passage of a shaft if necessary.

Die Tragnetzelemente 3 (3) mit Endgewinden 9 werden zu Randprofil 4 durch Unterlage 7 (beide mit Öffnungen) befestigt.The support net elements 3 ( 3 ) with end threads 9 become edge profile 4 by document 7 (both with openings) attached.

Randprofile 4 werden auf schon gefertigte bis ihren unteren Niveau Tragwand gelegt, Netzelemente 3 ähnlich gezeigten auf 1 miteinander befestigt und mit Vergussbeton zwischen beiden Profilen 4 gefüllt. Eine kraftschlüssige Verbindung zwischen Enden 9 von benachbarten Elementen ist bei niedrigen Toleranzen auch möglich.edge profiles 4 are placed on supporting walls that have already been manufactured to their lower level, network elements 3 similarly shown on 1 fastened together and with grouting concrete between the two profiles 4 filled. A positive connection between ends 9 neighboring elements are also possible with low tolerances.

c) Höhe Genauigkeit bei Fertigung und Montage von einzelne Tragwänden 1 führen zu einwandfreien Schraubenverbindungen 6 und Betonierensvorgang für Fügen.c) High level of accuracy in the manufacture and assembly of individual supporting walls 1 lead to perfect screw connections 6 and concreting process for joining.

Die ungewöhnliche für Bauwesen Randbleche 2 mit einer Dicke ca. 1 mm, die für Trennung von Bewehrungsvorsprüngen bei Fertigung dienen, gewährleisten durch Haftung mit Vergussbeton Eigenschaften von monolithischen Konstruktionen.The unusual for construction edge plates 2 With a thickness of approx. 1 mm, which are used to separate reinforcement protrusions during production, they guarantee the properties of monolithic structures through adhesion with grouting concrete.

Claims (8)

Unmittelbare Vermessung von Streckenlange, gleichen Zwischenhöhen und rechten Winkel ohne Geodäsiegeräten dadurch gekennzeichnet, dass Ihre leicht geprüfte Genauigkeit enthielt nur die Fehler, die mit Auftragung von metrischer Skala und Berechnungen verursacht werden und damit können 1/10000 und weniger von absoluten Wert von gemessener Große erreichen. Damit schafft man Voraussetzungen Tür kraftschlüssige Verbindungen (Fügen) zwischen benachbarten Geschossdecken und TragwändenImmediate measurement of route length, equal intermediate heights and right angles without geodetic devices characterized in that your easily checked accuracy only contained the errors that are caused by plotting the metric scale and calculations and thus can reach 1/10000 or less of absolute value of measured size , This creates the conditions for door non-positive connections (joining) between adjacent floor ceilings and supporting walls Eine ziemlich fester Langennormal 1 (bei großen Ausmaßen zusammenklappbar) für Messung von Streckenlange nach Anspruch 1 dadurch gekennzeichnet, dass er durch entsprechend geriffelte Walzenoberflache als Metallwgieerzeugnis bei schlüpfungsfreien Walzenziehung (Profil mit höchster Genauigkeit für mm-Skala) aus rostfreien Stahl oder Aluminiumlegierungen gefertigt wird und einen O-Halter 4 und einen transparenten Schieber 5 hat. Letzter kann Fixierungsschrauben und Vergrößerung für Ablesensgenauigkeit haben.A pretty solid length standard 1 (collapsible for large dimensions) for measurement of track length according to claim 1, characterized in that it is made of stainless steel or aluminum alloys by a corrugated roller surface as a metal weighing product with slip-free roll drawing (profile with the highest accuracy for mm scale) and an O-holder 4 and a transparent slider 5 Has. The latter can have fixation screws and magnification for reading accuracy. Einer Markierungsstift bzw. Marker 6 für Vermessung nach Anspruch 1 dadurch gekennzeichnet, dass er in vorausgesehene Vertiefung oder kurzes Röhrchen in einem Fertigteil eingesetzt und für Anhängen von Langennormalen betätigt wird (1b). Eine Röhrchen mit Gewinde 11 kann man sowohl für Hebeschleife 12 als auch für Marker 6 benutzen (1d).A marker pen or marker 6 for surveying according to claim 1, characterized in that it is inserted in the intended recess or short tube in a prefabricated part and is actuated for attaching length standards ( 1b ). A threaded tube 11 can be used for both lifting loops 12 for markers as well 6 to use ( 1d ). Ein Schnur 8 (1c) für Bestimmung der Position gleichen Zwischenhöhen nach Anspruch 1 dadurch gekennzeichnet, dass mit Berücksichtigung von zulässigen Anzeigen für Kraftmesser 10 und Eigenschaften von Schnurstoff kann man die richtige Höhe berechenbar korrigieren.A cord 8th ( 1c ) for determining the position of the same intermediate heights according to claim 1, characterized in that taking into account permissible displays for dynamometers 10 and properties of cord material, the correct height can be calculatedably corrected. Prozess von Bestimmung von rechten Winkel nach Anspruch 1 dadurch gekennzeichnet, dass er bei entsprechenden Auflegung von Ränder für drei Langennormalen 1, 2, 3 bei bestimmt berechenbaren Positionen von Ihren Schiebern 5 erreicht wird (1b)Process of determination of the right angle according to claim 1, characterized in that, with the corresponding laying of edges for three length normals 1 . 2 . 3 at certain predictable positions from your sliders 5 is reached ( 1b ) Vorgefertigter Geschossdeckenelement (2) nach Anspruch 1 mit kaschierendem zwischen Deckenschichten 1, 5 innerhalb der Zuschlag 2 Tragnetz dadurch gekennzeichnet, dass Längsstreifen 3 von benachbarten Tragnetzen durch Schrauben 7 verbunden und danach mit Vergussbeton zwischen Randprofilen 4 für Tragwand 6 umgegeben werden.Prefabricated floor element ( 2 ) according to claim 1 with lamination between ceiling layers 1 . 5 within the surcharge 2 Carrying net characterized in that longitudinal stripes 3 from neighboring support nets by screws 7 connected and then with grouting concrete between edge profiles 4 for bulkhead 6 be surrounded. Gefertigte auf Baustelle Geschossdecke (3) nach Anspruch 1 dadurch gekennzeichnet, dass nach Verlegung von unteren Betonschicht 5 Ihre Tragwerk aus Blechenstreifen 3 in Längs- und Querrichtungen, fixierenden in Randprofilen 4, zusammengebaut wird. Dann werden Schaumstoffperlen durch Treibmittel und Zugabe von Zement ausgeschäumt. Dieser neuer Stoff für Zuschlag unterscheidet von Schaumbeton durch offenzellige Struktur und weniger Zementgehalt.Manufactured floor slab on construction site ( 3 ) according to claim 1, characterized in that after laying the lower concrete layer 5 Your structure made of sheet metal strips 3 in longitudinal and transverse directions, fixing in edge profiles 4 , is assembled. Then foam beads are foamed by blowing agent and adding cement. This new aggregate material differs from foam concrete in that it has an open-cell structure and less cement content. Die vorgefertigte Tragwand nach Anspruch 1 dadurch gekennzeichnet, dass Ihre Fügen (4) zwischen wiederverwendbaren Schalungen 5, 7, verschraubten zu Laschen 6 in Fertigteilen, und Verdichtungen 8, 10 produziert werden. Die Stahlelemente für diese Füge bestehen aus Bewehrungsvorsprüngen 3, Stäben 4 und dünnen Randblechen 2.The prefabricated supporting wall according to claim 1, characterized in that your joints ( 4 ) between reusable formwork 5 . 7 , screwed to tabs 6 in finished parts, and compaction 8th . 10 to be produced. The steel elements for this joint consist of reinforcement projections 3 , Rods 4 and thin edge plates 2 ,
DE2003149041 2003-10-22 2003-10-22 Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod Withdrawn DE10349041A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE2003149041 DE10349041A1 (en) 2003-10-22 2003-10-22 Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE2003149041 DE10349041A1 (en) 2003-10-22 2003-10-22 Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod

Publications (1)

Publication Number Publication Date
DE10349041A1 true DE10349041A1 (en) 2004-09-30

Family

ID=32921200

Family Applications (1)

Application Number Title Priority Date Filing Date
DE2003149041 Withdrawn DE10349041A1 (en) 2003-10-22 2003-10-22 Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod

Country Status (1)

Country Link
DE (1) DE10349041A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116447951A (en) * 2023-06-15 2023-07-18 山东天元绿色建筑科技有限公司 Measuring device for construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2736097A (en) * 1956-02-28 coleman
FR2349124A1 (en) * 1976-04-22 1977-11-18 Hauville Jean Optical magnifying cursor for graduated rule - has mobile index used for tracing applications accurate to 0.2 mm
DE3840645A1 (en) * 1988-12-02 1989-07-13 Lothar Winkler Rule (ruler) for measuring and drawing - a device which incorporates all conventional rules
DE9114391U1 (en) * 1991-11-19 1992-05-21 Ing. G. Dekorsy GmbH, 7760 Radolfzell Ruler with at least one drawing or reference edge
DE9213205U1 (en) * 1992-10-01 1992-12-03 Kluckow, Ernst, 5600 Wuppertal Cord device for aligning wall or ceiling structures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2736097A (en) * 1956-02-28 coleman
FR2349124A1 (en) * 1976-04-22 1977-11-18 Hauville Jean Optical magnifying cursor for graduated rule - has mobile index used for tracing applications accurate to 0.2 mm
DE3840645A1 (en) * 1988-12-02 1989-07-13 Lothar Winkler Rule (ruler) for measuring and drawing - a device which incorporates all conventional rules
DE9114391U1 (en) * 1991-11-19 1992-05-21 Ing. G. Dekorsy GmbH, 7760 Radolfzell Ruler with at least one drawing or reference edge
DE9213205U1 (en) * 1992-10-01 1992-12-03 Kluckow, Ernst, 5600 Wuppertal Cord device for aligning wall or ceiling structures

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116447951A (en) * 2023-06-15 2023-07-18 山东天元绿色建筑科技有限公司 Measuring device for construction
CN116447951B (en) * 2023-06-15 2023-08-29 山东天元绿色建筑科技有限公司 Measuring device for construction

Similar Documents

Publication Publication Date Title
CN102733545A (en) Section steel column for high-rise building section steel concrete combination structure, and construction method thereof
CN111519909A (en) Construction process flow of assembled shear wall structure
CN105986676B (en) Large-span concrete floor flatness control system and use method
DE10349041A1 (en) Path measurement device, especially for measuring the distance between interlocking joints of a multi-layer construction for use in the building industry, has a cylindrical measurement scale that is used with a marking rod
CN210562902U (en) T-shaped steel floor plate of integrated house
CN208792138U (en) A kind of steel suspension bridge
CN101354844A (en) Integrative training method of building occupation skill
CN107419833A (en) A kind of annular two-way double helix prestressing without bondn cored slab track construction method
CN114232983A (en) Construction method and system of pool wall template
Vujović The mala Rijeka bridge-specificity of maintenance
US3736712A (en) Composite building structure and walls therefor
CN206174235U (en) Steel bar truss's building carrier plate
DE10328050B4 (en) Method for producing and assembling a floor ceiling or load-bearing wall on a construction site
DE7027429U (en) PREFABRICATED ROOM ELEMENT FOR ERECTING BUILDINGS.
CN218714370U (en) Control cushion block for thickness of concrete member protective layer
DE10190253B4 (en) Template device to facilitate brickworking comprises vertically installed support upon which is fitted horizontally extending cantilever arm movable in vertical direction and with horizontally extending pivotable templates installed on it
CN209482597U (en) Thick controller of three-layer water-stop ring plate
Heathcote et al. MOVEMENT OF ARTICULATED BUILDINGS ON SUBSIDENCE SITES.
Talbot et al. Tests of reinforced concrete buildings under load
DE802653C (en) Reinforced concrete ceiling
BR202020022398U2 (en) Constructive arrangement applied in metallic modular template for civil works
EP4202137A1 (en) Method for erecting a building and building created using the method
WO2023159286A1 (en) Building construction system with prefabricated blocks and guides and a cast-in-situ structure
DE859220C (en) Prefabricated reinforced concrete ceiling beams
Myers Distribution of Reinforcing Steel in Concrete Beams and Slabs

Legal Events

Date Code Title Description
OAV Applicant agreed to the publication of the unexamined application as to paragraph 31 lit. 2 z1
OM8 Search report available as to paragraph 43 lit. 1 sentence 1 patent law
OP8 Request for examination as to paragraph 44 patent law
8139 Disposal/non-payment of the annual fee