DE102017208681A1 - Screwed down guide rail with threaded insert - Google Patents

Screwed down guide rail with threaded insert Download PDF

Info

Publication number
DE102017208681A1
DE102017208681A1 DE102017208681.5A DE102017208681A DE102017208681A1 DE 102017208681 A1 DE102017208681 A1 DE 102017208681A1 DE 102017208681 A DE102017208681 A DE 102017208681A DE 102017208681 A1 DE102017208681 A1 DE 102017208681A1
Authority
DE
Germany
Prior art keywords
guide rail
insert
bore
stepped bore
teeth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE102017208681.5A
Other languages
German (de)
Inventor
Markus Rumpel
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Robert Bosch GmbH
Original Assignee
Robert Bosch GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Robert Bosch GmbH filed Critical Robert Bosch GmbH
Priority to DE102017208681.5A priority Critical patent/DE102017208681A1/en
Publication of DE102017208681A1 publication Critical patent/DE102017208681A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B33/00Features common to bolt and nut
    • F16B33/002Means for preventing rotation of screw-threaded elements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C29/00Bearings for parts moving only linearly
    • F16C29/004Fixing of a carriage or rail, e.g. rigid mounting to a support structure or a movable part
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C2226/00Joining parts; Fastening; Assembling or mounting parts
    • F16C2226/50Positive connections
    • F16C2226/60Positive connections with threaded parts, e.g. bolt and nut connections
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C2226/00Joining parts; Fastening; Assembling or mounting parts
    • F16C2226/50Positive connections
    • F16C2226/80Positive connections with splines, serrations or similar profiles to prevent movement between joined parts

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bearings For Parts Moving Linearly (AREA)

Abstract

Die Erfindung betrifft eine Führungsschienenanordnung (10) mit einer Führungsschiene (20) und einer Basis (60), welche über mehrere Schraubbolzen (50) miteinander verschraubt sind.
Erfindungsgemäß ist in die Stufenbohrungen (24) der Führungsschiene (20) jeweils ein gesonderter Einsatz (70) mit einem Innengewinde (75) aufgenommen, wobei in den Einsatz (70) jeweils ein Schraubbolzen (50) von unten her eingeschraubt ist.

Figure DE102017208681A1_0000
The invention relates to a guide rail arrangement (10) with a guide rail (20) and a base (60), which are screwed together via a plurality of bolts (50).
According to the invention, a separate insert (70) with an internal thread (75) is received in each of the stepped bores (24) of the guide rail (20), wherein a threaded bolt (50) is screwed into the insert (70) from below.
Figure DE102017208681A1_0000

Description

Die Erfindung betrifft eine Führungsschienenanordnung für ein Linearwälzlager gemäß dem Oberbegriff von Anspruch 1.The invention relates to a guide rail arrangement for a linear rolling bearing according to the preamble of claim 1.

Aus dem Katalog, der am 21.04.2017 unter der Internetadresse http://www.boschrexroth.com/various/utilities/mediadirectory/download/ index.jsp?object_nr=R999000485 abrufbar war, sind verschiedene Linearwälzlager bekannt, die sich u. a. hinsichtlich der Befestigung der Führungsschiene unterscheiden (siehe beispielsweise Seite 109 des genannten Katalogs). Bei einem ersten Führungsschienentyp werden die Befestigungsschrauben von oben her durch eine Stufenbohrung der Führungsschiene gesteckt und in ein Maschinenbett eingeschraubt. Bei einem zweiten Führungsschienentyp werden die Befestigungsschrauben von unten her unmittelbar in die Führungsschiene eingeschraubt. Der erste Führungsschienentyp wird erheblich häufiger angewendet als der zweite Führungsschienentyp.From the catalog, which was available on 21.04.2017 under the Internet address http://www.boschrexroth.com/various/utilities/mediadirectory/download/ index.jsp? Object_nr = R999000485, various linear roller bearings are known which u. a. differ with regard to the attachment of the guide rail (see, for example, page 109 of said catalog). In a first guide rail type, the fastening screws are inserted from above through a stepped bore of the guide rail and screwed into a machine bed. In a second guide rail type, the fastening screws are screwed from below directly into the guide rail. The first guide rail type is used much more frequently than the second guide rail type.

Ein Vorteil der vorliegenden Erfindung besteht darin, dass der in großen Stückzahlen hergestellte und damit kostengünstige erste Führungsschienentyp auch für Einbaufälle verwendbar ist, in denen bisher der vergleichsweise teure zweite Führungsschienentyp verwendet wurde.One advantage of the present invention is that the first guide rail type manufactured in large quantities and thus cost-effective can also be used for installation cases in which the comparatively expensive second guide rail type has hitherto been used.

Gemäß dem selbständigen Anspruch wird vorgeschlagen, dass jedem Schraubbolzen eine Stufenbohrung zugeordnet ist, welche die Führungsschiene in Richtung einer Bohrungsachse durchsetzt, wobei die Bohrungsachse senkrecht zur Längsachse ausgerichtet ist, wobei die Stufenbohrung einen ersten und einen zweiten Abschnitt aufweist, die entlang der Bohrungsachse nebeneinander angeordnet sind, wobei der zweite Abschnitt einen größeren Durchmesser aufweist als der erste Abschnitt, wobei der zweite Abschnitt an der von der Basis abgewandten Seite der Führungsschiene angeordnet ist, wobei der erste Abschnitt der Basis zugewandt ist, wobei in dem zweiten Abschnitt ein gesonderter Einsatz aufgenommen ist, welcher mit einem Innengewinde versehen ist, wobei jeder Schraubbolzen den jeweils zugeordneten ersten Abschnitt der Stufenbohrung durchsetzt, wobei er mit seinem Außengewinde in das jeweils zugeordnete Innengewinde des Einsatzes eingeschraubt ist. Das unmittelbar in der Führungsschiene vorgesehene Innengewinde des zweiten Typs der Führungsschiene wird also durch ein Innengewinde in einem gesonderten Einsatz ersetzt, welcher in die Stufenbohrung eingebaut wird, die vom ersten Typ der Führungsschiene an sich bekannt ist. Die vorzugsweise identischen Einsätze können kostengünstig in großen Stückzahlen hergestellt werden.According to the independent claim it is proposed that each screw is associated with a stepped bore, which passes through the guide rail in the direction of a bore axis, wherein the bore axis is aligned perpendicular to the longitudinal axis, wherein the stepped bore has a first and a second portion arranged along the bore axis side by side are, wherein the second portion has a larger diameter than the first portion, wherein the second portion is disposed on the side facing away from the base of the guide rail, wherein the first portion facing the base, wherein in the second portion a separate insert is received , which is provided with an internal thread, wherein each bolt penetrates the respectively associated first portion of the stepped bore, wherein it is screwed with its external thread in the respective associated internal thread of the insert. The internal thread of the second type of guide rail provided directly in the guide rail is therefore replaced by an internal thread in a separate insert which is installed in the stepped bore known per se from the first type of guide rail. The preferably identical inserts can be produced inexpensively in large quantities.

In den abhängigen Ansprüchen sind vorteilhafte Weiterbildungen und Verbesserungen der Erfindung angegeben.In the dependent claims advantageous refinements and improvements of the invention are given.

Es kann vorgesehen sein, dass der Einsatz bezüglich der betreffenden Bohrungsachse unverdrehbar im zweiten Abschnitt der Stufenbohrung gehalten ist. Damit ist sichergestellt, dass sich der Einsatz beim Festdrehen des entsprechenden Schraubbolzens nicht mitdreht.It can be provided that the insert with respect to the respective bore axis is held non-rotatably in the second portion of the stepped bore. This ensures that the insert does not rotate when tightening the corresponding bolt.

Es kann vorgesehen sein, dass der Einsatz form- und/oder reibschlüssig im zweiten Abschnitt der Stufenbohrung gehalten ist. Hierdurch ergibt sich ein zuverlässiger Halt, der einfach herstellbar ist.It can be provided that the insert is held positively and / or frictionally engaged in the second section of the stepped bore. This results in a reliable hold, which is easy to produce.

Es kann vorgesehen sein, dass der Einsatz mit einer ersten Verzahnung mit einer Mehrzahl von ersten Zähnen versehen ist, wobei die ersten Zähne verteilt um die betreffende Bohrungsachse herum angeordnet sind, wobei sie nach radial außen weisen, wobei sie einen Halteabschnitt aufweisen, welcher im nicht montierten Zustand des Einsatzes einen ersten Durchmesser definiert, der größer als der Durchmesser des zweiten Abschnitts der Stufenbohrung im nicht montierten Zustand des Einsatzes ist. Der erste Durchmesser ist vorzugsweise in Richtung der Bohrungsachse konstant ausgebildet. Beim Einbau des Einsatzes in die Stufenbohrung werden die ersten Zähne elastisch und/oder plastisch verformt. Dies hat zur Folge, dass der Einsatz reibschlüssig an der Stufenbohrung anliegt. Darüber hinaus wird angestrebt, dass sich die ersten Zähne in die Stufenbohrung eingraben, so dass auch ein formschlüssiger Eingriff gegeben ist.It can be provided that the insert is provided with a first toothing with a plurality of first teeth, wherein the first teeth are distributed around the respective bore axis around, pointing radially outward, wherein they have a holding portion, which in not assembled state of the insert defines a first diameter which is greater than the diameter of the second portion of the stepped bore in the unassembled state of the insert. The first diameter is preferably constant in the direction of the bore axis. When installing the insert in the stepped bore, the first teeth are elastically and / or plastically deformed. This has the consequence that the insert frictionally applied to the stepped bore. In addition, it is desirable that the first teeth dig into the stepped bore, so that there is also a positive engagement.

Es kann vorgesehen sein, dass die ersten Zähne in einem Zentrierabschnitt einen zweiten Durchmesser definieren, welcher gegenüber dem ersten Durchmesser vermindert ist, wobei der Zentrierabschnitt in Richtung der Bohrungsachse auf der dem ersten Abschnitt der Stufenbohrung zugewandten Seite neben dem Halteabschnitt angeordnet ist. Hierdurch wird der Einbau der Einsätze in die betreffende Stufenbohrung erleichtert, wobei insbesondere ein Verkanten des Einsatzes verhindert wird. Der zweite Durchmesser ist vorzugsweise kleiner oder gleich dem Durchmesser des zweiten Abschnitts der Stufenbohrung ausgebildet.It can be provided that the first teeth define a second diameter in a centering section which is reduced in relation to the first diameter, wherein the centering section is arranged in the direction of the bore axis on the side facing the first section of the stepped bore next to the holding section. As a result, the installation of the inserts is facilitated in the respective stepped bore, in particular a tilting of the insert is prevented. The second diameter is preferably less than or equal to the diameter of the second portion of the stepped bore.

Es kann vorgesehen sein, dass der zweite Durchmesser in Richtung der Bohrungsachse zumindest abschnittsweise konstant ausgebildet ist. Der Durchmesser des zweiten Abschnitts der Stufenbohrung ist in Richtung der Bohrungsachse vorzugsweise konstant ausgebildet. Damit ergibt sich eine optimale Ausrichtwirkung des Zentrierabschnitts.It can be provided that the second diameter is designed to be constant at least in sections in the direction of the bore axis. The diameter of the second portion of the stepped bore is preferably constant in the direction of the bore axis. This results in an optimal alignment of the centering.

Es kann vorgesehen sein, dass der Einsatz mit einer zweiten Verzahnung mit einer Mehrzahl von zweiten Zähnen versehen ist, wobei die zweiten Zähne verteilt um die betreffenden Bohrungsachse herum angeordnet sind, wobei sie in Richtung der Bohrungsachse weisen, wobei sie an einem Grund des zweiten Abschnitts der Stufenbohrung anliegen. Hierdurch wird die Sicherung gegen Verdrehen weiter verbessert. Der Grund des zweiten Abschnitts der Stufenbohrung ist vorzugsweise als ebene Fläche ausgebildet, welche senkrecht zur Bohrungsachse ausgerichtet ist.It can be provided that the insert with a second toothing with a plurality of second teeth, the second teeth being distributed around the respective bore axis, pointing in the direction of the bore axis abutting a bottom of the second portion of the stepped bore. As a result, the backup against twisting is further improved. The base of the second portion of the stepped bore is preferably formed as a flat surface, which is aligned perpendicular to the bore axis.

Es kann vorgesehen sein, dass die ersten und/oder die zweiten Zähne derart asymmetrisch ausgebildet sind, dass sie in Anzugsdrehrichtung des betreffenden Schraubbolzen einen höheren Verdrehwiderstand bewirken als in Gegenrichtung. Insbesondere die zweiten Zähne sind vorzugsweise sägezahnartig ausgebildet. Hierdurch wird die Sicherung gegen Verdrehen weiter verbessert.It can be provided that the first and / or the second teeth are formed asymmetrically such that they cause a higher torsional resistance in the direction of tightening of the respective bolt than in the opposite direction. In particular, the second teeth are preferably formed like a sawtooth. As a result, the backup against twisting is further improved.

Es kann vorgesehen sein, dass die Einsätze aus einem hochfesten Stahl bestehen. Die Einsätze sind vorzugsweise wärmebehandelt, höchst vorzugsweise vergütet. Die Schraubbolzen haben vorzugsweise die Festigkeitsklasse 12.9 oder höher.It can be provided that the inserts are made of a high-strength steel. The inserts are preferably heat treated, most preferably tempered. The bolts preferably have the strength class 12.9 or higher.

Es kann vorgesehen sein, dass im zweiten Abschnitt der Stufenbohrung eine gesonderte Abdeckkappe aufgenommen ist, welchen den jeweils zugeordneten Einsatz und den jeweils zugeordneten Schraubbolzen überdeckt. Die Abdeckkappe bildet vorzugsweise zusammen mit einer Kopffläche der Führungsschiene eine ebene Fläche, wobei höchst vorzugsweise der Übergang zwischen der Abdeckkappe und der Kopffläche absatzfrei ausgebildet ist. Hierdurch werden Beschädigungen an den Enddichtungen des Führungswagens vermieden, wenn diese mit ihrer Dichtlippe über die Stufenbohrung gleiten.It can be provided that a separate cover cap is accommodated in the second section of the stepped bore, which covers the respective associated insert and the respective associated bolt. The cover preferably forms together with a top surface of the guide rail a flat surface, most preferably the transition between the cap and the top surface is formed without heels. As a result, damage to the end seals of the carriage are avoided when they slide with their sealing lip over the stepped bore.

Es versteht sich, dass die vorstehend genannten und die nachfolgend noch zu erläuternden Merkmale nicht nur in der jeweils angegebenen Kombination, sondern auch in anderen Kombinationen oder in Alleinstellung verwendbar sind, ohne den Rahmen der vorliegenden Erfindung zu verlassen.It is understood that the features mentioned above and those yet to be explained below can be used not only in the particular combination indicated, but also in other combinations or in isolation, without departing from the scope of the present invention.

Die Erfindung wird im Folgenden anhand der beigefügten Zeichnungen näher erläutert. Es zeigt:

  • 1 einen Querschnitt einer erfindungsgemäßen Führungsschienenanordnung;
  • 2 eine perspektivische Ansicht des Einsatzes von oben;
  • 3 eine perspektivische Ansicht des Einsatzes von unten; und
  • 4 eine Seitenansicht des Einsatzes.
The invention will be explained in more detail below with reference to the accompanying drawings. It shows:
  • 1 a cross section of a guide rail assembly according to the invention;
  • 2 a perspective view of the insert from above;
  • 3 a perspective view of the insert from below; and
  • 4 a side view of the insert.

1 zeigt einen Querschnitt einer erfindungsgemäßen Führungsschienenanordnung 10. Die Führungsschienenanordnung 10 umfasst eine Führungsschiene 20 und eine Basis 60, wobei die Führungsschiene 20 mit ihrer Bodenfläche 22 an einer Anlagefläche 61 der Basis 60 anliegt. Die Boden- und die Anlagefläche 22, 61 sind vorzugsweise eben ausgebildet. Bei der Basis 60 kann es sich beispielsweise um das Maschinenbett einer Werkzeugmaschine, insbesondere einer Drehmaschine handeln. Die Führungsschiene 20 erstreckt sich mit der in 1 dargestellten, konstanten Außenquerschnittsform parallel zu einer Längsachse 11, die senkrecht zur Zeichenebene der 1 ausgerichtet ist. Die entsprechende gerade Form der Führungsschiene 20 wird sichergestellt, indem diese seitlich an einer Ausrichtfläche 62 angelegt wird, welche genau parallel zur Längsachse 11 verläuft. Die Ausrichtfläche 62 ist vorzugsweise eben ausgebildet und senkrecht zur Anlagefläche 61 angeordnet. 1 shows a cross section of a guide rail assembly according to the invention 10 , The guide rail arrangement 10 includes a guide rail 20 and a base 60 , where the guide rail 20 with its bottom surface 22 on a contact surface 61 the base 60 is applied. The ground and the contact surface 22 . 61 are preferably flat. At the base 60 it may, for example, be the machine bed of a machine tool, in particular a lathe. The guide rail 20 extends with the in 1 illustrated, constant outer cross-sectional shape parallel to a longitudinal axis 11 perpendicular to the plane of the drawing 1 is aligned. The corresponding straight shape of the guide rail 20 is ensured by placing these laterally on an alignment surface 62 is created, which exactly parallel to the longitudinal axis 11 runs. The alignment surface 62 is preferably flat and perpendicular to the contact surface 61 arranged.

Die vorliegende Führungsschiene 20 ist zur Verwendung mit einem (nicht dargestellten) Führungswagen vorgesehen, der vier Reihen von endlos umlaufenden Wälzkörpern aufweist. Ein derartiger Führungswagen ist beispielsweise aus der DE 10 2014 210 171 A1 bekannt. Die Führungsschiene 30 hat dementsprechend vier Laufbahnen 23, deren Querschnittsform an kugelförmige Wälzkörper angepasst sind. Die Führungsschiene 20 besteht vorzugsweise aus Stahl und ist zumindest im Bereich der Laufbahnen 23 gehärtet. Es können auch Führungswägen mit rollenförmigen Wälzkörpern und/oder mit einer anderen Anzahl an Wälzkörperumläufen Verwendung finden.The present guide rail 20 is intended for use with a (not shown) carriage, which has four rows of endless rotating rolling elements. Such a carriage is for example from the DE 10 2014 210 171 A1 known. The guide rail 30 has accordingly four careers 23 , whose cross-sectional shape are adapted to spherical rolling elements. The guide rail 20 is preferably made of steel and is at least in the field of raceways 23 hardened. It is also possible to use guide carriages with roller-shaped rolling elements and / or with a different number of rolling element circuits.

Die Führungsschiene 20 hat eine ebene Kopffläche 21, welche parallel zur Bodenfläche 22 angeordnet ist. Die Laufbahnen 23 sind abseits der Boden- und der Kopffläche 22; 21 an den beiden gegenüberliegenden Seitenflächen der Führungsschiene 20 angeordnet. Die Führungsschiene 20 wird von einer Stufenbohrung 24 durchsetzt, deren gegenüberliegende Mündungsöffnungen in der Boden- bzw. der Kopffläche 22; 21 angeordnet sind. Die entsprechende Bohrungsachse 12 verläuft senkrecht zur Längsachse 11 und senkrecht zur Kopffläche 21. Die Stufenbohrung 24 hat einen ersten und einen unmittelbar angrenzenden zweiten Abschnitt 25; 26, wobei der Durchmesser des zweiten Abschnitts 26 größer als derjenigen des ersten Abschnitts 25 ausgebildet ist. Die Mündungsöffnung des ersten Abschnitts 26 ist in der Bodenfläche 22 angeordnet, so dass diese benachbart zur Basis 20 angeordnet ist. Die Mündungsöffnung des zweiten Abschnitts 26 ist in der Kopffläche 21 angeordnet, wobei diese mit einer gesonderten Abdeckkappe 90 verschlossen ist. Die Abdeckkappe 90 ist unter Vorspannung in den zweiten Abschnitt 26 eingebaut, wobei ihre ebene Oberfläche in einer Flucht mit der Kopffläche 21 angeordnet ist. Die Abdeckkappe 90 ist vorliegend als ebene Platte mit konstanter Dicke ausgebildet, wobei sie vorzugsweise aus Metall, insbesondere Messing besteht. Der Übergang zwischen der Abdeckkappe 90 und der Kopffläche 21 ist absatzfrei ausgebildet, so dass die Enddichtungen des Führungswagens nicht beschädigt werden, wenn deren Dichtlippen über die Stufenbohrung 24 gleiten.The guide rail 20 has a flat head surface 21 , which are parallel to the floor surface 22 is arranged. The raceways 23 are off the ground and the head area 22 ; 21 on the two opposite side surfaces of the guide rail 20 arranged. The guide rail 20 is from a stepped bore 24 interspersed, the opposite mouth openings in the bottom and the top surface 22 ; 21 are arranged. The corresponding bore axis 12 runs perpendicular to the longitudinal axis 11 and perpendicular to the head surface 21 , The stepped bore 24 has a first and an immediately adjacent second section 25 ; 26 where the diameter of the second section 26 greater than that of the first section 25 is trained. The mouth of the first section 26 is in the bottom area 22 arranged so that these are adjacent to the base 20 is arranged. The mouth of the second section 26 is in the head area 21 arranged, these with a separate cap 90 is closed. The cap 90 is under bias in the second section 26 installed, with their flat surface in alignment with the head surface 21 is arranged. The cap 90 is presently designed as a flat plate with a constant thickness, wherein it preferably consists of metal, in particular brass. The transition between the cap 90 and the head area 21 is designed paragraph free, so that the end seals of the carriage are not damaged if the sealing lips on the stepped bore 24 slide.

Zwischen der Abdeckkappe 90 und dem Grund 27 des zweiten Abschnitts 26 ist ein gesonderter Einsatz 70 derart unter Vorspannung eingebaut, dass dieser bezüglich der Bohrungsachse 12 unverdrehbar gegenüber der Führungsschiene 20 ist. Der Einsatz 70 liegt mit seiner Außenumfangsfläche an einer Innenumfangsfläche des zweiten Abschnitts 26 an. Weiter liegt er mit einer Stirnfläche am Grund 27 des zweiten Abschnitts 26 an. Zwischen dem Einsatz 70 und der Abdeckkappe 90 ist vorzugsweise ein schmaler Spalt vorgesehen, so dass die oben erläuterte fluchtende Ausrichtung der Abdeckkappe 90 und der Kopffläche 21 sicher hergestellt werden kann.Between the cap 90 and the reason 27 of the second section 26 is a separate use 70 installed in such a bias that this with respect to the bore axis 12 non-rotatable relative to the guide rail 20 is. The use 70 lies with its outer peripheral surface on an inner peripheral surface of the second section 26 at. Next he lies with a face at the bottom 27 of the second section 26 at. Between the insert 70 and the cap 90 Preferably, a narrow gap is provided, so that the above-explained alignment of the cap 90 and the head area 21 can be made safely.

Der Einsatz 70 ist mit einem Innengewinde 75 versehen, in welches ein Außengewinde 53 eines zugeordneten Schraubbolzens 50 eingeschraubt ist. Der Schraubbolzen 50 ist vorliegend als Zylinderkopfschraube ausgebildet. Er hat dementsprechend ein erstes und ein gegenüberliegendes zweites Ende 51; 52. Das erste Ende 51, welches im Bereich der Führungsschiene 20 angeordnet ist, ist mit einem Außengewinde 53 versehen. Das zweite Ende 52, welches im Bereich der Basis 60 angeordnet ist, ist mit einem bezüglich der Bohrungsachse 12 kreiszylindrischen Kopf 54 versehen, dessen Durchmesser größer als derjenige des Außengewindes 53 ist. Der Schraubbolzen 60 durchsetzt den ersten Abschnitt 25 der Stufenbohrung 24, wobei sein Kopf 54 in einer Senkbohrung 63 der Basis 60 formschlüssig abgestützt ist. Dementsprechend wird die Führungsschiene 20 gegen die Anlagefläche 61 der Basis 60 verspannt, wenn der Schraubbolzen 50 festgedreht wird.The use 70 is with an internal thread 75 provided, in which an external thread 53 an associated bolt 50 is screwed. The bolt 50 is presently designed as a cylinder head screw. He has accordingly a first and an opposite second end 51 ; 52 , The first end 51 , which is in the area of the guide rail 20 is arranged, is with an external thread 53 Mistake. The second end 52 which is in the area of the base 60 is disposed with respect to the bore axis 12 circular cylindrical head 54 provided whose diameter is larger than that of the external thread 53 is. The bolt 60 intervenes the first section 25 the stepped bore 24 , being his head 54 in a counterbore 63 the base 60 is positively supported. Accordingly, the guide rail 20 against the contact surface 61 the base 60 clamped when the bolt 50 is tightened.

2 zeigt eine perspektivische Ansicht des Einsatzes 70 von oben. 3 zeigt eine perspektivische Ansicht des Einsatzes 70 von unten. 4 zeigt eine Seitenansicht des Einsatzes 70. Der Einsatz 70 besteht vorzugsweise aus hochfestem Stahl. Er hat eine ebene Stirnfläche 80, welche senkrecht zur Bohrungsachse 12 angeordnet ist. Gegenüberliegend zur Stirnfläche 80 ist eine zweite Verzahnung 72 angeordnet. Am Außenumfang bezüglich der Bohrungsachse 12 ist eine erste Verzahnung 71 angeordnet. Das Innengewinde 75, welches vorzugsweise als Spitzgewinde ausgebildet ist, durchsetzt den Einsatz 70 konzentrisch zur Bohrungsachse 12. 2 shows a perspective view of the insert 70 from above. 3 shows a perspective view of the insert 70 from underneath. 4 shows a side view of the insert 70 , The use 70 is preferably made of high strength steel. He has a flat face 80 , which are perpendicular to the bore axis 12 is arranged. Opposite to the face 80 is a second gearing 72 arranged. On the outer circumference with respect to the bore axis 12 is a first gearing 71 arranged. The internal thread 75 , which is preferably designed as a pointed thread, passes through the insert 70 concentric to the bore axis 12 ,

Die erste Verzahnung 71 hat eine Vielzahl von identischen ersten Zähnen 73, welche gleichförmig verteilt um die Bohrungsachse 12 herum angeordnet sind. Im in 2 bis 4 dargestellten nicht montierten Zustand hat jeder erste Zahn in Richtung der Bohrungsachse 12 betrachtet eine spitzdachförmige Querschnittsform. In einem Halteabschnitt 78 definieren die entsprechenden Dachspitzen einen ersten Durchmesser 76, welcher größer als der Durchmesser des ersten zweiten Abschnitts (Nr. 26 in 1) der Stufenbohrung ist. Beim Einbau des Einsatzes 70 in die Stufenbohrung werden die Dachspitzen elastisch und/oder plastisch verformt, so dass die ersten Zähne 71 im Bereich des Halteabschnitts 78 unter Vorspannung an der Innenumfangsfläche des zweiten Abschnitts der Stufenbohrung anliegen.The first gearing 71 has a lot of identical first teeth 73 which are uniformly distributed around the bore axis 12 are arranged around. Im in 2 to 4 illustrated unassembled state, each first tooth in the direction of the bore axis 12 considered a pointed roof-shaped cross-sectional shape. In a holding section 78 define the corresponding rooftops a first diameter 76 which is larger than the diameter of the first second section (No. 26 in 1 ) is the stepped bore. When installing the insert 70 in the stepped bore, the roof tips are elastically and / or plastically deformed, so that the first teeth 71 in the area of the holding section 78 biased against the inner peripheral surface of the second portion of the stepped bore.

Bezüglich der Bohrungsachse 12 ist neben dem Halteabschnitt 78 ein Zentrierabschnitt 79 angeordnet, in welchem die Dachspitzen mittels einer Drehbearbeitung abgetragen wurden, so dass sich dort ein zweiter Durchmesser 77 ergibt, welcher minimal kleiner als der Durchmesser des zweiten Abschnitts der Stufenbohrung ist. Der Zentrierabschnitt 79 kann dementsprechend mit geringem Kraftaufwand in die Stufenbohrung eingeführt werden. Durch seine mit geringem Spiel an die Stufenbohrung angepasste Form wird der Einsatz gegenüber der Stufenbohrung ausgerichtet, so dass der Einsatz 70 exakt parallel zur Bohrungsachse 12 angeordnet ist. Beim anschließenden Einpressen des Einsatzes 70 in die Stufenbohrung wird hierdurch ein Verkanten des Einsatzes 70 vermieden. Der Zentrierabschnitt 79 ist an der Seite des Einsatzes 70 angeordnet, an der sich auch die zweite Verzahnung 72 befindet.Regarding the bore axis 12 is next to the holding section 78 a centering section 79 arranged in which the rooftops were removed by means of a turning, so that there is a second diameter 77 which is minimally smaller than the diameter of the second portion of the stepped bore. The centering section 79 can be introduced accordingly with little effort in the stepped bore. Due to its shape adapted to the stepped bore with little play, the insert is aligned with the stepped bore, so that the insert 70 exactly parallel to the bore axis 12 is arranged. During the subsequent pressing of the insert 70 in the stepped bore thereby tilting of the insert 70 avoided. The centering section 79 is at the side of the insert 70 arranged, at which also the second gearing 72 located.

Die zweite Verzahnung 72 hat ein Vielzahl von identischen zweiten Zähnen 74, welche gleichförmig verteilt um die Bohrungsachse 12 herum angeordnet sind, wobei sie in Richtung der Bohrungsachse 12 weisen. Die Breite der einzelnen zweiten Zähne 74 nimmt jeweils nach radial hin außen zu. Im Querschnitt betrachtet sind die zweiten Zähne 74 sägezahnartig ausgebildet. Sie sind also nicht symmetrisch, wie die ersten Zähne 72, sondern asymmetrisch. Diese Sägezahnanordnung liegt am Grund (Nr. 27 in 1) des zweiten Abschnitts der Stufenbohrung an. Die zweiten Zähne 74 sind so ausgerichtet, dass ein Mitdrehen der Einsätze 70 beim Festdrehen der Schraubbolzen vermieden wird.The second gearing 72 has a lot of identical second teeth 74 which are uniformly distributed around the bore axis 12 are arranged around, being in the direction of the bore axis 12 point. The width of each second tooth 74 increases radially outward. Viewed in cross section are the second teeth 74 formed like a sawtooth. So they are not symmetrical, like the first teeth 72 but asymmetrical. This sawtooth arrangement is located at the bottom (No. 27 in 1 ) of the second section of the stepped bore. The second teeth 74 are aligned so that turning the inserts 70 when tightening the bolts is avoided.

BezugszeichenlisteLIST OF REFERENCE NUMBERS

1010
Führungs schienenanordnungGuide rail arrangement
1111
Längsachselongitudinal axis
1212
Bohrungsachse bore axis
2020
Führungsschieneguide rail
2121
Kopfflächehead face
2222
Bodenflächefloor area
2323
Laufbahncareer
2424
Stufenbohrungstepped bore
25 25
erster Abschnitt der Stufenbohrungfirst section of the stepped bore
2626
zweiter Abschnitt der Stufenbohrungsecond section of the stepped bore
2727
Grund des zweiten Abschnitts Reason of the second section
5050
Schraubbolzenbolts
5151
erstes Endefirst end
5252
zweites Endesecond end
5353
Außengewindeexternal thread
5454
Kopf head
6060
BasisBase
6161
Anlageflächecontact surface
6262
Ausrichtflächealignment
6363
Senkbohrung countersink
7070
Einsatzcommitment
7171
erste Verzahnungfirst gearing
7272
zweite Verzahnungsecond gearing
7373
erster Zahnfirst tooth
7474
zweiter Zahnsecond tooth
7575
Innengewindeinner thread
7676
erster Durchmesserfirst diameter
7777
zweiter Durchmessersecond diameter
7878
Halteabschnittholding section
7979
Zentrierabschnittcentering
8080
Stirnfläche face
9090
Abdeckkappecap

ZITATE ENTHALTEN IN DER BESCHREIBUNG QUOTES INCLUDE IN THE DESCRIPTION

Diese Liste der vom Anmelder aufgeführten Dokumente wurde automatisiert erzeugt und ist ausschließlich zur besseren Information des Lesers aufgenommen. Die Liste ist nicht Bestandteil der deutschen Patent- bzw. Gebrauchsmusteranmeldung. Das DPMA übernimmt keinerlei Haftung für etwaige Fehler oder Auslassungen.This list of the documents listed by the applicant has been generated automatically and is included solely for the better information of the reader. The list is not part of the German patent or utility model application. The DPMA assumes no liability for any errors or omissions.

Zitierte PatentliteraturCited patent literature

  • DE 102014210171 A1 [0018]DE 102014210171 A1 [0018]

Claims (10)

Führungsschienenanordnung (10) mit einer sich entlang einer Längsachse (11) erstreckenden Führungsschiene (20), welche zur Verwendung mit einem Führungswagen vorgesehen ist, welcher mehrere Reihen von Wälzkörpern aufweist, wobei die Führungsschiene (20) für jede Reihe von Wälzkörpern eine Laufbahn (23) aufweist, die sich parallel zur Längsachse (11) erstreckt, wobei die Führungsschiene (20) mit einer Bodenfläche (22) an einer Anlagefläche (61) einer gesonderten Basis (60) anliegt, wobei sie über mehrere Schraubbolzen (50) fest mit der Basis (60) verbunden ist, wobei die Schraubbolzen (50) verteilt entlang der Längsachse (11) angeordnet sind, wobei die Schraubbolzen (50) jeweils ein erstes und ein gegenüberliegendes zweites Ende (51; 52) aufweisen, wobei das erste Ende (51) mit einem Außengewinde (53) versehen ist, wobei es im Bereich der Führungsschiene (20) angeordnet ist, wobei das zweite Ende (52) im Bereich der Basis (60) angeordnet und fest mit dieser verbunden ist, dadurch gekennzeichnet, dass jedem Schraubbolzen (50) eine Stufenbohrung (24) zugeordnet ist, welche die Führungsschiene (20) in Richtung einer Bohrungsachse (12) durchsetzt, wobei die Bohrungsachse (12) senkrecht zur Längsachse (11) ausgerichtet ist, wobei die Stufenbohrung (24) einen ersten und einen zweiten Abschnitt (25; 26) aufweist, die entlang der Bohrungsachse (12) nebeneinander angeordnet sind, wobei der zweite Abschnitt (26) einen größeren Durchmesser aufweist als der erste Abschnitt (25), wobei der zweite Abschnitt (26) an der von der Basis (60) abgewandten Seite der Führungsschiene (20) angeordnet ist, wobei der erste Abschnitt (25) der Basis (60) zugewandt ist, wobei in dem zweiten Abschnitt (26) ein gesonderter Einsatz (70) aufgenommen ist, welcher mit einem Innengewinde (75) versehen ist, wobei jeder Schraubbolzen (50) den jeweils zugeordneten ersten Abschnitt (25) der Stufenbohrung (24) durchsetzt, wobei er mit seinem Außengewinde (53) in das jeweils zugeordnete Innengewinde (75) des Einsatzes (70) eingeschraubt ist. A guide rail assembly (10) having a guide rail (20) extending along a longitudinal axis (11) and intended for use with a carriage having a plurality of rows of rollers, the guide rail (20) comprising a track (23) for each row of rollers ), which extends parallel to the longitudinal axis (11), wherein the guide rail (20) with a bottom surface (22) on a contact surface (61) of a separate base (60) is applied, wherein it via a plurality of bolts (50) fixed to the Base (60) is connected, wherein the threaded bolts (50) distributed along the longitudinal axis (11) are arranged, wherein the threaded bolts (50) each have a first and an opposite second end (51, 52), wherein the first end (51 ) is provided with an external thread (53), wherein it is arranged in the region of the guide rail (20), wherein the second end (52) arranged in the region of the base (60) and fixedly connected thereto is, characterized in that each screw (50) is associated with a stepped bore (24) which passes through the guide rail (20) in the direction of a bore axis (12), wherein the bore axis (12) is aligned perpendicular to the longitudinal axis (11) the stepped bore (24) has first and second portions (25; 26) juxtaposed along the bore axis (12), the second portion (26) having a larger diameter than the first portion (25), the second portion (26) facing away from the base (60) Side of the guide rail (20) is arranged, wherein the first portion (25) of the base (60) faces, wherein in the second portion (26) a separate insert (70) is received, which is provided with an internal thread (75) , wherein each screw bolt (50) passes through the respectively assigned first section (25) of the stepped bore (24), being screwed with its external thread (53) into the respectively assigned internal thread (75) of the insert (70). Führungsschienenanordnung nach Anspruch 1, wobei der Einsatz (70) bezüglich der betreffenden Bohrungsachse (12) unverdrehbar im zweiten Abschnitt (26) der Stufenbohrung (24) gehalten ist.Guide rail arrangement after Claim 1 wherein the insert (70) with respect to the respective bore axis (12) is held non-rotatably in the second portion (26) of the stepped bore (24). Führungsschienenanordnung nach einem der vorstehenden Ansprüche, wobei der Einsatz (70) form- und/oder reibschlüssig im zweiten Abschnitt (26) der Stufenbohrung (24) gehalten ist.Guide rail arrangement according to one of the preceding claims, wherein the insert (70) is positively and / or frictionally held in the second portion (26) of the stepped bore (24). Führungsschienenanordnung nach Anspruch 2 oder 3, wobei der Einsatz (70) mit einer ersten Verzahnung (71) mit einer Mehrzahl von ersten Zähnen (73) versehen ist, wobei die ersten Zähne (73) verteilt um die betreffende Bohrungsachse (12) herum angeordnet sind, wobei sie nach radial außen weisen, wobei sie einen Halteabschnitt (78) aufweisen, welcher im nicht montierten Zustand des Einsatzes (70) einen ersten Durchmesser (76) definiert, der größer als der Durchmesser des zweiten Abschnitts (26) der Stufenbohrung (24) im nicht montierten Zustand des Einsatzes (70) ist.Guide rail arrangement after Claim 2 or 3 wherein the insert (70) is provided with first teeth (71) having a plurality of first teeth (73), the first teeth (73) being distributed around the respective bore axis (12), being radially outward have a holding portion (78) which, in the unassembled state of the insert (70) defines a first diameter (76) greater than the diameter of the second portion (26) of the stepped bore (24) in the unassembled state of Insert (70) is. Führungsschienenanordnung nach Anspruch 4, wobei die ersten Zähne (73) in einem Zentrierabschnitt (79) einen zweiten Durchmesser (77) definieren, welcher gegenüber dem ersten Durchmesser (76) vermindert ist, wobei der Zentrierabschnitt (79) in Richtung der Bohrungsachse (12) auf der dem ersten Abschnitt der Stufenbohrung zugewandten Seite neben dem Halteabschnitt (78) angeordnet ist.Guide rail arrangement after Claim 4 wherein the first teeth (73) in a centering portion (79) define a second diameter (77) which is reduced from the first diameter (76), the centering portion (79) being in the direction of the bore axis (12) on the first one Section of the stepped bore facing side adjacent to the holding portion (78) is arranged. Führungsschienenanordnung nach Anspruch 5, wobei der zweite Durchmesser (77) in Richtung der Bohrungsachse (12) zumindest abschnittsweise konstant ausgebildet ist.Guide rail arrangement after Claim 5 , Wherein the second diameter (77) in the direction of the bore axis (12) is formed constant at least in sections. Führungsschienenanordnung nach einem der Ansprüche 2 bis 6, wobei der Einsatz (70) mit einer zweiten Verzahnung (72) mit einer Mehrzahl von zweiten Zähnen (74) versehen ist, wobei die zweiten Zähne (74) verteilt um die betreffende Bohrungsachse (12) herum angeordnet sind, wobei sie in Richtung der Bohrungsachse (12) weisen, wobei sie an einem Grund (27) des zweiten Abschnitts (26) der Stufenbohrung (24) anliegen.Guide rail assembly according to one of Claims 2 to 6 wherein the insert (70) is provided with a second toothing (72) having a plurality of second teeth (74), the second teeth (74) being distributed around the respective bore axis (12), facing in the direction of Bore axis (12), wherein they rest against a base (27) of the second portion (26) of the stepped bore (24). Führungsschienenanordnung nach einem der Ansprüche 4 bis 7, wobei die ersten und/oder die zweiten Zähne (73; 74) derart asymmetrisch ausgebildet sind, dass sie in Anzugsdrehrichtung des betreffenden Schraubbolzen (50) einen höheren Verdrehwiderstand bewirken als in Gegenrichtung.Guide rail assembly according to one of Claims 4 to 7 , wherein the first and / or the second teeth (73; 74) are formed asymmetrically such that they cause a higher torsional resistance in the direction of tightening of the relevant bolt (50) than in the opposite direction. Führungsschienenanordnung nach einem der vorstehenden Ansprüche, wobei die Einsätze (70) aus einem hochfesten Stahl bestehen.A guide rail assembly according to any one of the preceding claims, wherein the inserts (70) are made of a high strength steel. Führungsschienenanordnung nach einem der vorstehenden Ansprüche, wobei im zweiten Abschnitt (26) der Stufenbohrung eine gesonderte Abdeckkappe (90) aufgenommen ist, welche den jeweils zugeordneten Einsatz (70) und den jeweils zugeordneten Schraubbolzen (50) überdeckt.Guide rail arrangement according to one of the preceding claims, wherein in the second section (26) of the stepped bore a separate cover cap (90) is accommodated, which covers the respective associated insert (70) and the respective associated bolt (50).
DE102017208681.5A 2017-05-23 2017-05-23 Screwed down guide rail with threaded insert Withdrawn DE102017208681A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE102017208681.5A DE102017208681A1 (en) 2017-05-23 2017-05-23 Screwed down guide rail with threaded insert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102017208681.5A DE102017208681A1 (en) 2017-05-23 2017-05-23 Screwed down guide rail with threaded insert

Publications (1)

Publication Number Publication Date
DE102017208681A1 true DE102017208681A1 (en) 2018-11-29

Family

ID=64109485

Family Applications (1)

Application Number Title Priority Date Filing Date
DE102017208681.5A Withdrawn DE102017208681A1 (en) 2017-05-23 2017-05-23 Screwed down guide rail with threaded insert

Country Status (1)

Country Link
DE (1) DE102017208681A1 (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2544304A (en) 1946-12-09 1951-03-06 Dana C Eckenbeck Plug nut
US2685320A (en) 1949-08-15 1954-08-03 Rosan Joseph Clinch bolt and nut
US3198231A (en) 1962-01-09 1965-08-03 South Chester Corp High strength threaded insert
DE1400934A1 (en) 1962-03-02 1969-03-20 John Walsh & Co Inserts Ltd Fastening device for non-expandable sheet metal material and the like.
GB1497693A (en) 1976-10-11 1978-01-12 Shur Lok International Sa Assembly of panel and fastener
DE19733025A1 (en) 1997-07-31 1999-02-04 Schaeffler Waelzlager Ohg Arrangement of a guide rail on a machine frame
DE202006008714U1 (en) 2005-06-24 2006-10-05 Maximun Technology Inc., Shenkeng Linear guide comprises profile with wide upper groove connected by narrow groove to lower groove, guide rail being mounted in upper groove and held in position by bolts passing though bores along it and nuts fitted into lower groove
DE102009052023A1 (en) 2009-11-05 2011-05-12 Aktiebolaget Skf Linear guide, has fastening elements implemented as pins, which penetrate drilling bit in supporting element by part of its axial extension and penetrate drilling bit in guiding element, where pins are provided with coating
DE102014210171A1 (en) 2014-05-28 2015-12-17 Robert Bosch Gmbh Carriage with mounting hole, which is part of a lubricant flow path

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2544304A (en) 1946-12-09 1951-03-06 Dana C Eckenbeck Plug nut
US2685320A (en) 1949-08-15 1954-08-03 Rosan Joseph Clinch bolt and nut
US3198231A (en) 1962-01-09 1965-08-03 South Chester Corp High strength threaded insert
DE1400934A1 (en) 1962-03-02 1969-03-20 John Walsh & Co Inserts Ltd Fastening device for non-expandable sheet metal material and the like.
GB1497693A (en) 1976-10-11 1978-01-12 Shur Lok International Sa Assembly of panel and fastener
DE19733025A1 (en) 1997-07-31 1999-02-04 Schaeffler Waelzlager Ohg Arrangement of a guide rail on a machine frame
DE202006008714U1 (en) 2005-06-24 2006-10-05 Maximun Technology Inc., Shenkeng Linear guide comprises profile with wide upper groove connected by narrow groove to lower groove, guide rail being mounted in upper groove and held in position by bolts passing though bores along it and nuts fitted into lower groove
DE102009052023A1 (en) 2009-11-05 2011-05-12 Aktiebolaget Skf Linear guide, has fastening elements implemented as pins, which penetrate drilling bit in supporting element by part of its axial extension and penetrate drilling bit in guiding element, where pins are provided with coating
DE102014210171A1 (en) 2014-05-28 2015-12-17 Robert Bosch Gmbh Carriage with mounting hole, which is part of a lubricant flow path

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
BOSCH REXROTH AG: Ball rail systems - Ball runner blocks, ball rails, accessories. Schweinfurt, Germany, 2014 (Druckvermerk R999000485). S. 1-232. URL: http://www.boschrexroth.com/various/utilities/mediadirectory/download/index.jsp?object_nr=R999000485 [abgerufen am 2017-10-23]. - Firmenschrift

Similar Documents

Publication Publication Date Title
DE69111025T2 (en) Crank device for bottom bracket of a bicycle.
DE102012100976A1 (en) Screwing tool and tool holder for such a screw-in
EP1039173A2 (en) Bearing arrangement for a screw drive
DE102011005049A1 (en) Roller freewheel
EP3125382A1 (en) Cable clamping device for widening of braided shields of cables
DE3036323A1 (en) LINEAR BALL BEARING UNIT
DE102022200327A1 (en) bearing cage
DE3730128C2 (en) Ball bearing for linear movements
DE102013110429A1 (en) Plastic fastener and mounting arrangement hereby
DE102019112815A1 (en) Rolling bearing cage
DE2207875A1 (en) Clutch release bearing
CH636936A5 (en) BALL BUSH FOR THE LENGTH BALL GUIDE OF A SHAFT IN A HOUSING HOLE.
DE102017105100B4 (en) Ball screw and method for producing a ball screw
DE102016206013B4 (en) Sealing arrangement of a wheel bearing
EP2957782B1 (en) Guide carriage with roller body guide section which engages the path insert
DE102015223971A1 (en) Tapered roller bearings
DE102017208681A1 (en) Screwed down guide rail with threaded insert
DE102015114437A1 (en) Disc brake for a commercial vehicle
DE102004059518A1 (en) Slanted roller bearing, especially for a vehicle wheel bearing, has a separate outer bearing ring and flange of selected materials bonded together as a unit before installation
DE4136105A1 (en) SEALING DISC FOR LUBRICABLE BEARINGS, IN PARTICULAR BALL BEARINGS
DE1425013C3 (en) Component for ball guides
DE102009028509A1 (en) Mounting arrangement of a planetary gear bolt
DE102008056202A1 (en) bearings
DE19741626B4 (en) Ball bearing for longitudinal movements
WO2004009276A1 (en) Connection between two machine parts

Legal Events

Date Code Title Description
R163 Identified publications notified