DE102009005238A1 - Belt conveyor for conveying scrap to form vehicle body part, has steep conveying unit forming ramp as body of drag chain conveyor section, where section is formed between trough and upper strand and mat operates pushing body along section - Google Patents

Belt conveyor for conveying scrap to form vehicle body part, has steep conveying unit forming ramp as body of drag chain conveyor section, where section is formed between trough and upper strand and mat operates pushing body along section Download PDF

Info

Publication number
DE102009005238A1
DE102009005238A1 DE200910005238 DE102009005238A DE102009005238A1 DE 102009005238 A1 DE102009005238 A1 DE 102009005238A1 DE 200910005238 DE200910005238 DE 200910005238 DE 102009005238 A DE102009005238 A DE 102009005238A DE 102009005238 A1 DE102009005238 A1 DE 102009005238A1
Authority
DE
Germany
Prior art keywords
ramp
belt conveyor
tub
mat
conveyor according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
DE200910005238
Other languages
German (de)
Other versions
DE102009005238B4 (en
Inventor
Heiner Steinbrecher
Klaus Bielefeld
Ralph Rehberg
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Buerener Maschinenfabrik GmbH
Original Assignee
Buerener Maschinenfabrik GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Buerener Maschinenfabrik GmbH filed Critical Buerener Maschinenfabrik GmbH
Priority to DE200910005238 priority Critical patent/DE102009005238B4/en
Publication of DE102009005238A1 publication Critical patent/DE102009005238A1/en
Application granted granted Critical
Publication of DE102009005238B4 publication Critical patent/DE102009005238B4/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G45/00Lubricating, cleaning, or clearing devices
    • B65G45/10Cleaning devices
    • B65G45/26Cleaning devices for gathering residue after cleaning

Abstract

The conveyor (1) has a continuous belt mat (3) running on a support frame (2) with upper and lower strands. Drives extend transverse towards the belt mat, project opposite to a belt mat plane and are spaced from each other. A trough is arranged below the belt mat. A steep conveying unit (11) is arranged at a distance towards a deflection unit (5) of the belt mat. The steep conveying unit forms a curved ramp (12) as a supporting body of a drag chain conveyor section. The section is formed between the trough and the upper strand, where the mat operates a pushing body along the section.

Description

Die Erfindung betrifft einen Bandförderer für Schrott mit einer endlosen, an einem Traggerüst umlaufenden Bandmatte nach dem Oberbegriff des Anspruchs 1.The The invention relates to a belt conveyor for scrap with an endless, on a support frame revolving band mat according to the preamble of claim 1.

Derartige Schrottförderbänder, wie sie bekannt sind aus DE 103 04 983 B4 und DE 103 04 984 B4 , werden insbesondere zur Förderung von Blechabfällen im Bereich des Zuschnitts und Umformens von Karosserieblechen eingesetzt, um die Blechabfälle vom Anfallsort weg hin zu einer Entsorgungs- oder Verladestation zu transportieren. Die anfallenden Blechabfälle umfassen Blechteile oder Blechbutzen unterschiedlichster Größen, Formen und Materialien. Es kann deshalb vorkommen, dass sich Teile des Blechabfalls an der Bandmatte, die vorzugsweise von einem Scharnierband gebildet wird, verklemmen und dadurch und/oder durch Adhäsionskräfte in den Bereich des Untertrums verschleppt werden und hier in eine unterhalb der Bandmatte angeordnete Wanne fallen. Dadurch kommt es zu einer verstärkten Verunreinigung der Wanne, so dass diese wiederholt zu säubern ist. Bekannt sind hierfür mit der Bandmatte verfahrbare Mitnehmer, die im Untertrum zur Ölwanne angestellt sind, wodurch die Ölwanne von Verunreinigungen frei geschoben wird.Such scrap conveyor belts, as they are known from DE 103 04 983 B4 and DE 103 04 984 B4 , are used in particular for the promotion of sheet metal waste in the field of cutting and forming of body panels to transport the waste metal from the place of seizure away to a disposal or loading station. The resulting sheet metal waste includes sheet metal parts or sheet metal pieces of various sizes, shapes and materials. It may therefore happen that parts of the sheet metal waste on the band mat, which is preferably formed by a hinge, jam and thereby and / or be dragged by adhesion forces in the area of the lower strand and fall here in a arranged below the belt mat pan. As a result, there is an increased contamination of the tub, so this is to be cleaned repeatedly. Are known for this purpose with the band mat movable carrier, which are employed in the lower strand to the oil pan, whereby the oil pan is pushed free of impurities.

Dieses kontinuierliche Reinigen der Wanne beim Laufen der Bandmatte führt zu einem Förderstrom an Verunreinigungen in der Wanne, der über eine Abgabe entladen wird. Das Entladen von Verunreinigungen aus der Wanne hat sich als nachteilig erwiesen.This Continuous cleaning of the tub while running the band mat leads to a flow of impurities in the tub, which is discharged via a tax. The unloading of impurities from the tub has proved to be disadvantageous.

Aufgabe der Erfindung ist es daher, einen Bandförderer für Schrott nach dem Oberbegriff des Anspruchs 1 zu schaffen, der das Säubern der Wanne von Verunreinigungen verbessert.task The invention is therefore a belt conveyor for To provide scrap according to the preamble of claim 1, which is the Cleaning the tub of contaminants improves.

Hierdurch wird ein Bandförderer für Schrott geschaffen, der das Säubern der Wanne von Verunreinigungen durch ein Überbrücken von Förderströmen mittels einer Steilförderung mechanisiert. Zur Steilförderung ist eine bogenförmige Rampe als Tragorgan vorgesehen, in der die Bandmatte als Schuborgan arbeitet. Die in die Wanne gelangenden Verunreinigungen werden somit kontinuierlich abgeführt durch Aufgeben auf das Obertrum der Bandmatte. Die bei der Förderbewegung in die Wanne gelangenden Blechabfälle werden dem Fördergutstrom wieder zugeführt, d. h. erneut auf das Obertrum aufgegeben. Eine vereinfachte und vereinheitlichte Abgabe von Blechabfällen, nämlich einschließlich solcher aus Reinigungsvorgängen in der Wanne, ist dadurch möglich. Als Ergebnis wird ein selbstreinigendes Schrottband erhalten.hereby is a belt conveyor created for scrap, the cleaning of the tub of impurities by bridging of flow rates by means of a steep conveyor mechanized. For steep promotion is an arcuate Ramp provided as a support member in which the band mat as a thrust member is working. The entering into the tub impurities are thus continuously dissipated by giving up on the upper strand the band mat. The during the conveying movement in the tub reaching sheet metal waste are the Fördergutstrom fed again, d. H. abandoned again on the upper run. A simplified and harmonized distribution of sheet metal waste, namely including those from cleaning operations in the tub, this is possible. As a result, a self-cleaning scrap belt obtained.

Vorzugsweise ist die Rampe schwenkbar gegenüber der Wanne angelenkt. Die Rampe kann dadurch einerseits als Puffer bei leichten Verklemmungen wirken. Von den Blechabfällen auf die Rampe wirkende Kräfte können durch einstellbare Ausweichbewegungen der Rampe federnd ausgeglichen werden. Sogar ein Lösen leichter Verklemmungen bei verschiedenen Krafteinwirkungen ist durch die bewegliche Rampe möglich. Die Gefahr von Verstopfungen ist deshalb deutlich reduziert. Für den Fall einer Verstopfung kann die Rampe andererseits aus einer Schließ-Position in eine Öffnungs-Position verschwenkt werden. Die Rampe ist klappbar zur Ausbildung eines hinreichend breiten Spaltes zwischen Wanne und Rampe, durch den die Gegenstände einer Verstopfung ausgeworfen werden können. Vorteilhaft ist insoweit, dass bei einem Auswerten der Verstopfung der Betrieb des Bandförderers nicht unterbrochen werden braucht.Preferably The ramp is pivotally hinged to the tub. The ramp can thus on the one hand as a buffer with slight jamming Act. From the sheet metal waste on the ramp acting forces can be adjusted by adjustable evasive movements of the ramp be resiliently balanced. Even a release of slight jamming at different force impacts is due to the movable ramp possible. The danger of blockages is therefore clear reduced. In case of constipation, the ramp can on the other hand, from a closed position to an open position be pivoted. The ramp is hinged to form a sufficiently wide gap between trough and ramp, through the the objects of a blockage can be ejected. It is advantageous to the extent that when evaluating the constipation the operation of the belt conveyor will not be interrupted needs.

Vorzugsweise ist die Rampe mittels einer Schwenkanordnung angeordnet, die als eine Vierpunktgelenk-Anordnung ausgebildet ist. Die Vierpunktgelenk-Anordnung ermöglicht das Verschwenken der Rampe auf einer Bahnkurve. Das An- und Abkoppeln der Rampe an die Wanne wird dadurch verbessert und vermeidet Störungen entlang dieser Anschlusszone. Dies gilt insbesondere vorzugsweise dann, wenn die Rampe einen gekrümmten Steigstreckenabschnitt aufweist, der an dem an die Wanne anschließbaren Ende einen Flachbettabschnitt aufweist. Mit diesem Flachbettabschnitt kann die Rampe unterhalb der Wanne einen Überlappungsbereich als Anschlusszone ausbilden. Auch bei Pufferbewegungen der Rampe ist die Rampe an die Wanne angeschlossen, da die Anschlusszone ein Überlappungsspiel ermöglicht.Preferably the ramp is arranged by means of a pivoting arrangement, which as a four-point joint arrangement is formed. The four-point joint arrangement allows pivoting of the ramp on a trajectory. The coupling and uncoupling of the ramp to the tub is thereby improved and avoids interference along this connection zone. This is particularly preferably when the ramp is curved Having riser section, which can be connected to the at the tub End has a flat bed section. With this flatbed section The ramp below the tub may overlap form as a connection zone. Also with buffer movements of the ramp the ramp is connected to the tub because the connection zone is an overlap game allows.

Verbessert werden kann diese Anschlusszone schließlich vorzugsweise dadurch, dass an der Wanne ein vorzugsweise schwenkbares Verschlussblech vorgesehen ist. Ein solches Verschlussblech kann einen Brückenkopf zur Rampe bilden.improves Finally, this connection zone can be preferable in that on the trough a preferably pivotable closure plate is provided. Such a closure plate may be a bridgehead to form the ramp.

Weiterhin bevorzugt ist, dass die Wanne innen auf dem Boden Leitschienen aufweist, die Wegbegrenzungen bilden, um den Blechabfällen Richtungsimpulse hin zur Mitte der Wanne zu geben. Hierdurch soll erreicht werden, dass die in die Rampe transportierten Blechabfälle sich nicht an den Randbereichen konzentrieren. Der Abwurf unter Schwerkraft von der Rampe auf das Obertrum ist dadurch verbessert.Farther it is preferred that the trough has guide rails inside on the floor, the path boundaries form to the sheet metal waste directional impulses to give to the middle of the tub. This is to be achieved that the metal waste transported into the ramp is do not concentrate on the edge areas. The release under gravity from the ramp to the upper run is improved.

Weitere Ausgestaltungen der Erfindung sind der nachfolgenden Beschreibung und den Unteransprüchen zu entnehmen.Further Embodiments of the invention are the following description and to refer to the dependent claims.

Die Erfindung wird nachstehend anhand des in den Abbildungen dargestellten Ausführungsbeispiels näher erläutert.The Invention will be described below with reference to the illustrated in the drawings Embodiment explained in more detail.

1a zeigt schematisch eine Seitenansicht eines Bandförderers, 1a shows schematically a side view of a belt conveyor,

1b zeigt einen Teilbereich der 1a in vergrößertem Maßstab, 1b shows a portion of the 1a on an enlarged scale,

2a zeigt die Seitenansicht des Bandförderers gemäß 1a ohne Traggerüstabdeckung, 2a shows the side view of the belt conveyor according to 1a without shroud cover,

2b zeigt einen Teilbereich der 2a in vergrößertem Maßstab, 2 B shows a portion of the 2a on an enlarged scale,

3 zeigt schematisch eine perspektivische Ansicht des Bandförderers gemäß 1a ohne Bandmatte, 3 schematically shows a perspective view of the belt conveyor according to 1a without ribbon,

4a bis 4e zeigen eine Kinematik einer Rampe des Bandförderers zwischen einer Schließ-Position und einer Öffnungs-Position. 4a to 4e show a kinematics of a ramp of the belt conveyor between a closed position and an open position.

1a, 1b und 2a, 2b zeigen einen Bandförderer 1 für Schrott mit einem Traggerüst 2 und einer endlosen, an dem Traggerüst 2 mit einem Obertrum und einem Untertrum umlaufenden Bandmatte 3. Es handelt sich um eine Bandmatte 3 mit vertikaler Umlenkung. Abhängig von einer Förderrichtung F ist die Bandmatte 3 an einer Umlenkeinrichtung 4 ablaufend und der anderen Umlenkeinrichtung 5 auflaufend bewegbar. 1a . 1b and 2a . 2 B show a belt conveyor 1 for scrap with a shoring 2 and an endless, on the shoring 2 with an upper strand and a lower strand revolving band mat 3 , It is a band mat 3 with vertical deflection. Depending on a conveying direction F is the band mat 3 at a deflection device 4 expiring and the other deflection 5 running upwards.

An der Bandmatte 3 sind einzelne zueinander beabstandete, gegenüber einer Bandmattenebene aufragende, quer zur Bandmatte 3 sich erstreckende Mitnehmer 6 angeordnet. Die Bandmatte 3 ist vorzugsweise ein Scharnierband mit seitlichen Borden 7, die sich bogenförmig überlappen. Die Bandmatte 3 stützt sich auf Rollen 8 ab, die an der Bandmatte 3 befestigt und entlang von Führungsschienen 9 am Traggerüst 2 umlaufend geführt sind. Als Zugmittel für ein waagerechtes oder geneigtes Fördern wird vorzugsweise eine Kette verwendet. Die auflaufende Umlenkeinrichtung 5 umfasst hier ferner vorzugsweise eine Spannstation 30, während der Antrieb der Bandmatte 3 an der ablaufenden Umlenkeinrichtung 4 erfolgt.At the band mat 3 are each spaced apart, towering over a ribbon mat plane, transverse to the ribbon mat 3 extending drivers 6 arranged. The band mat 3 is preferably a hinge with lateral ribs 7 that overlap arcuately. The band mat 3 relies on roles 8th off, on the band mat 3 attached and along guide rails 9 on the support frame 2 are guided circumferentially. As a pulling means for a horizontal or inclined conveying a chain is preferably used. The leading deflection device 5 here further preferably comprises a tensioning station 30 while driving the band mat 3 at the expiring deflection 4 he follows.

Unterhalb der Bandmatte 3 ist eine Wanne 10 angeordnet, die sich in Richtung eines Fördergutstroms längs des Untertrums der Bandmatte 3 erstreckt. Die Wanne 10, die auch als Ölwanne bezeichnet werden kann, dient zum Auffangen von mit dem Obertrum der Bandmatte 3 in den Bereich des Untertrums der Bandmatte 3 geschleppten oder sonstwie beförderten Blechabfällen, die unter Schwerkraftwirkung von der Bandmatte 3 abfallen, wenn diese umläuft.Below the band mat 3 is a tub 10 arranged in the direction of a Fördergutstroms along the lower run of the band mat 3 extends. The tub 10 , which can also be referred to as an oil pan, is used to catch up with the upper run of the band mat 3 in the area of the lower run of the band mat 3 towed or otherwise transported sheet metal waste, the gravitational effect of the band mat 3 fall off when it rotates.

Benachbart zur auflaufenden Umlenkung 5 der Bandmatte 3 ist eine Steilförderung 11 vorgesehen, die eine bogenfömige, an die Wanne 10 anschließbare Rampe 12 als Tragorgan eines zwischen Wanne 10 und Obertrum ausgebildeten Schlepp-Fördererabschnitts bildet, entlang der die Bandmatte 3 als Schuborgan arbeitet. Die Mitnehmer 6 oder mindestens einzelne der Mitnehmer 6 sind derart ausgelegt, dass sie zum Reinigen der Wanne 10 im Untertrum sind, indem sie beispielsweise über einen Boden 13 der Wanne 10 streichen, um dort liegende Blechabfälle zur Steilförderung 11 zu schleppen. Die Bandmatte 3 schleppt mit Mitnehmern 6 Blechabfälle aus der Wanne 10 durch die Steilförderung 11, wozu die Mitnehmer 6 entlang einer Innenwand eines Steigstreckenabschnitts 16 der Rampe 12 geführt sind und dort Elemente des Schuborgans des Schleppfördererabschnitts bilden.Adjacent to the incoming diversion 5 the band mat 3 is a steep promotion 11 provided that a bogenfömige, to the tub 10 connectable ramp 12 as a support member of a between tub 10 and upper run forms trained towing conveyor section, along which the band mat 3 works as a thrust member. The drivers 6 or at least some of the drivers 6 are designed to be used to clean the tub 10 in the lower strand are, for example, over a floor 13 the tub 10 paint to lying there sheet metal waste for steep conveying 11 to haul. The band mat 3 tows with carriers 6 Sheet metal waste from the tub 10 through the steep conveyor 11 what the drivers 6 along an inner wall of a climbing section 16 the ramp 12 are guided and there form elements of the thrust member of the drag conveyor section.

Die Rampe 12 ist hier vorzugsweise ein Umlenkblech, das verschwenkbar gegenüber der Wanne 10 angelenkt ist. Erzeugt wird die Schwenkbewegung durch einen Antrieb 14. Zwischen dem Antrieb 14 und der Rampe 12 ist vorzugsweise ein elastisches Element vorgesehen. Ist als Antrieb 14 beispielsweise ein Pneumatikzylinder vorgesehen, wie in den Figuren des Ausführungsbeispiels gezeigt, wird die Luftsäule des Pneumatikzylinders als elastisches Element verwendet. Die Rampe 12 ist belastungsabhängig aus einer gefederten Schließ-Position in eine Öffnungs-Position gegenüber der Wanne 10 verschwenkt. Die 4a bis 4e zeigen eine bevorzugte Kinematik der Schwenkbewegung, die nachfolgend noch beschrieben wird.The ramp 12 Here is preferably a baffle, which is pivotable relative to the tub 10 is articulated. The pivoting movement is generated by a drive 14 , Between the drive 14 and the ramp 12 an elastic element is preferably provided. Is as a drive 14 For example, provided a pneumatic cylinder, as shown in the figures of the embodiment, the air column of the pneumatic cylinder is used as an elastic element. The ramp 12 is load-dependent from a spring-loaded closing position in an opening position relative to the trough 10 pivoted. The 4a to 4e show a preferred kinematics of the pivoting movement, which will be described below.

Die Rampe 12 ist mittels einer Schwenkanordnung 15 verschwenkbar, die am oberen Rand 17 der Rampe 12 angreift und eine horizontale Schwenkachse quer zur Längserstreckung der Bandmatte 3 und der Wanne 10 aufweist. Die Rampe 12 ist vorzugsweise mittels der Schwenkanordnung 15 derart verschwenkbar, dass die Rampe 12 auf einer festlegbaren Bahnkurve verschwenkbar ist, wie die 4a bis 4e beispielhaft verdeutlichen.The ramp 12 is by means of a pivoting arrangement 15 swiveling at the top 17 the ramp 12 engages and a horizontal pivot axis transverse to the longitudinal extent of the band mat 3 and the tub 10 having. The ramp 12 is preferably by means of the pivoting arrangement 15 so swiveling that the ramp 12 is pivotable on a fixable trajectory, as the 4a to 4e exemplify.

Bevorzugt ist die Rampe 12 über eine Vierpunktgelenk-Anordnung als Schwenkanordnung 15 angelenkt. Eine solche Vierpunktgelenk-Anordnung ist dann vorzugsweise so ausgebildet, dass deren Koppel die Rampe 12 bildet, an der eine Antriebsschwinge 18 und ein Lenker 19 mit gestellfesten Gelenklagern 20, 21 direkt oder indirekt am Traggerüst 2 angreifen zum Schwenken der Rampe 12 hin zur Wanne 10 und weg von dieser. Die Geometrie der Vierpunktgelenk-Anordnung, insbesondere die Länge des Lenkers 19 und der Antriebsschwinge 18 als auch der Abstand der beweglichen Gelenklager 22, 23 (vgl. 4e) und der Abstand der gestellfesten Gelenklagern 20, 21, ist zur Einstellung einer vorbestimmbaren Bahnkurve wählbar. Eins der beiden gestellfesten Gelenklager 20, 21 verläuft ferner vorzugsweise konzentrisch zur Umlenkwelle X. Gemäß 1b ist das gestellfeste Gelenklager 20 der Antriebsschwinge 18 konzentrisch zur Umlenkwelle X.The ramp is preferred 12 via a four-point joint arrangement as a pivoting arrangement 15 hinged. Such a four-point joint arrangement is then preferably designed so that its coupling the ramp 12 forms, on which a drive swing 18 and a handlebar 19 with frame-fixed joint bearings 20 . 21 directly or indirectly on the shoring 2 attack to swing the ramp 12 to the tub 10 and away from this. The geometry of the four-point joint arrangement, in particular the length of the handlebar 19 and the drive swing 18 as well as the distance of the movable spherical plain bearings 22 . 23 (see. 4e ) and the distance of the frame-fixed joint bearings 20 . 21 , is selectable for setting a predeterminable trajectory. One of the two frame-fixed spherical plain bearings 20 . 21 furthermore preferably runs concentrically with the deflection shaft X. According to 1b is the frame-fixed joint bearing 20 the on drove swing 18 concentric with the deflection shaft X.

Die Antriebsschwinge 18 der Vierpunktgelenk-Anordnung ist vorzugsweise auf einer Umlenkwelle X der auflaufenden Umlenkeinrichtung 5 der Bandmatte 3 gestellfest gelagert, die dann auch die horizontale Schwenkachse der Rampe 12 bildet. Diese Umlenkwelle X ist vorzugsweise die Spannwelle der Spannstation 30. Durch diese Befestigung der Antriebsschwinge 18 an der als Spannwelle arbeitenden Umlenkwelle X ist die Antriebsschwinge 18 gegenüber dem Traggerüst 2 verschiebbar. Die Rampe 12 führt dann keine Relativbewegung zur Spannwelle aus, so daß unabhängig von Spannwegen der Bandmatte 3 der Abstand zwischen Rampe 12 und Bandmatte 3 gleich bleibt.The drive swing 18 the four-point joint arrangement is preferably on a deflection shaft X of the incoming deflection device 5 the band mat 3 stored frame-mounted, which then also the horizontal pivot axis of the ramp 12 forms. This deflection shaft X is preferably the tensioning shaft of the tensioning station 30 , Through this attachment of the drive rocker 18 on the deflection shaft X operating as a tensioning shaft is the drive rocker 18 opposite the support frame 2 displaceable. The ramp 12 then performs no relative movement to the clamping shaft, so that regardless of tension paths of the band mat 3 the distance between ramp 12 and ribbon mat 3 stays the same.

Die Rampe 12 weist vorzugsweise einen gekrümmten Steigstreckenabschnitt 16 auf, der an dem an die Wanne 10 anschließbaren Ende einen Flachbettabschnitt 24 aufweist. Die Rampe 12 ist in einer Schließ-Position zur Wanne 10 mit einem Teilbereich des Flachbettabschnitts 24 unter die Wanne 10 verfahrbar zum Anlegen an die Wanne 10 mit teilweiser Überlappung von Wanne 10 und Flachbettabschnitt 24.The ramp 12 preferably has a curved riser section 16 on the one to the tub 10 connectable end of a flatbed section 24 having. The ramp 12 is in a closed position to the tub 10 with a portion of the flatbed section 24 under the tub 10 movable for attachment to the tub 10 with partial overlap of tub 10 and flatbed section 24 ,

Insoweit ist besonders bevorzugt, dass die Wanne 10 endseitig benachbart zur ankoppelbaren Rampe 12 ein Verschlussblech 25 aufweist, das zur Ausbildung eines Überlappungsspiels bei lastbedingten Pufferbewegungen der Rampe 12 vorgesehen ist. Die Verschwenkbarkeit der Rampe 12 kann also in der Schließ-Position genutzt werden zum Abfedern von Belastungsspitzen durch geschleppte Blechabfälle, indem der Steigstreckenabschnitt 16 des Schleppförderabschnitts sich federnd trichterförmig weiten kann, um dadurch kleinere Verklemmungen zu lösen. Das elastische Element zwischen Antrieb 14 und Rampe 12 kann bezüglich dieser Pufferarbeit wählbar eingestellt werden.In that regard, it is particularly preferred that the tub 10 end adjacent to the dockable ramp 12 a closure sheet 25 that, to form an overlapping clearance during load-induced buffer movements of the ramp 12 is provided. The pivotability of the ramp 12 Thus, it can be used in the closing position for cushioning load peaks by towed sheet metal waste by the riser section 16 the drag conveyor section can expand resiliently funnel-shaped, thereby to solve smaller deadlocks. The elastic element between drive 14 and ramp 12 can be set selectable with respect to this buffer work.

Das Verschlussblech 25 kann über ein Scharnier an die Wanne 10 angelenkt sein. Die Drehachse 26 eines solchen Scharniers verläuft vorzugsweise quer zur Wanne 10. Das Verschlussblech ist dann drehbar angelenkt und kann durch Eigengewicht oder federbelastet nach unten schwenken, damit beim Nachgeben der Rampe 12 bei Verklemmungen die Überbrückung von der Wanne 10 zur Rampe 12 sichergestellt ist durch ein Überlappungsspiel.The closure plate 25 Can be hinged to the tub 10 be articulated. The rotation axis 26 such a hinge preferably runs transversely to the trough 10 , The closure plate is then rotatably hinged and can pivot by its own weight or spring loaded down, so when yielding the ramp 12 in case of jamming the bridging of the tub 10 to the ramp 12 is ensured by an overlap game.

Die Rampe 12 weist schließlich einen gekrümmten Steigstreckenabschnitt 16 auf, der für einen Schwerkraftabwurf der geschleppten Blechabfälle ein dem Obertrum der Bandmatte 3 zugewandtes Ende 27 aufweist, das mit Abstand zur Bandmatte 3 oberhalb des Obertrums angeordnet ist, und zwar bevor die auflaufende Bandmatte 3 in einen horizontalen Lauf nach der Umlenkung geführt ist. Das dem Obertrum zugewandte Ende 27 der Rampe 12 bildet somit ein Auflaufende, das in Förderrichtung kürzer ausgebildet ist als ein Auflaufende 28 der Bandmatte 3. Der an der Rampe 12 geschleppte Blechabfall fällt folglich unter Schwerkraftwirkung auf die Bandmatte 3 in dem Steigstreckenabschnitt 16, und zwar dann, wenn dieser abgeflacht steigt.The ramp 12 finally has a curved riser section 16 on, for a gravity release of the towed metal waste a the upper run of the band mat 3 facing end 27 has, at a distance from the band mat 3 is arranged above the upper run, and that before the tarnished band mat 3 is guided in a horizontal run after the deflection. The upper strand facing the end 27 the ramp 12 thus forms a run-end, which is shorter in the conveying direction than a casserole 28 the band mat 3 , The one at the ramp 12 towed metal waste thus falls under gravity on the belt mat 3 in the climbing section 16 , and then when it is flattened.

Wie 3 zeigt, weist die Wanne 10 auf ihrem Boden 13 einzelne zueinander beabstandete Leitschienen 29 auf, die der Bandmatte 3 zugewandt sind. Diese Leitschienen 29 sind so angeordnet, dass diese beidseitig von außen nach innen gerichtet sich erstrecken. Hierdurch ergibt sich eine Zentrierstrecke für die in der Wanne 10 von den Mitnehmern 6 geschleppten Verunreinigungen bzw. Blechabfälle.As 3 shows, points the tub 10 on her floor 13 individual spaced guide rails 29 on, the band mat 3 are facing. These rails 29 are arranged so that they extend on both sides directed from outside to inside. This results in a centering distance for in the tub 10 from the drivers 6 dragged impurities or metal waste.

Die 4a bis 4e zeigen die Kinematik der Rampe 12 zwischen einer Schließ-Position (4a) zur Wanne 10 und einer Öffnungs-Position (4e) zur Wanne 10. Die Rampe 12 ist in eine solche Öffnungs-Position verschwenkbar, um ein Blockieren des Bandförderers bei Verstopfungen zu vermeiden. Aus Sicherheitsgründen kann dann, wenn die Belastung auf die Rampe 12 einen bestimmten Schwellenwert überschreitet, die Rampe 12 öffnen, um einen Ausgabespalt zwischen der Wanne 10 und der Rampe 12 zu bilden, durch den Teile einer Verstopfung ausgegeben werden können. Bei Verwendung der erfindungsgemäßen Vierpunktgelenk-Anordnung wird ein Verschwenkungsweg der Rampe 12 so eingestellt, dass eine Anschlusszone der Rampe 12 an die Wanne 10 sicherstellt, dass kein Fördergut nach unten entweichen kann, gleichzeitig aber ein Auswurfspalt gebildet werden kann, um im Falle von starken Belastungen eine Beschädigung des Bandförderers zu vermeiden.The 4a to 4e show the kinematics of the ramp 12 between a closing position ( 4a ) to the tub 10 and an opening position ( 4e ) to the tub 10 , The ramp 12 is pivotable in such an opening position to prevent blocking of the belt conveyor in case of blockages. For safety reasons, then when the load on the ramp 12 exceeds a certain threshold, the ramp 12 open to an output gap between the tub 10 and the ramp 12 through which parts of a blockage can be dispensed. When using the four-point joint arrangement according to the invention is a Verschwenkungsweg the ramp 12 adjusted so that a connecting zone of the ramp 12 to the tub 10 ensures that no conveyed material can escape downwards, but at the same time an ejection gap can be formed in order to avoid damage to the belt conveyor in the event of heavy loads.

Die 4a bis 4e zeigen die Bewegung der Rampe 12 und die Bewegungsabläufe der möglichen Glieder der Schwenkanordnung eines Bandförderers 1 von einer Schließ-Position der Rampe 12 (4a) zu einer Öffnungs-Postion (vgl. 4e). Der Antrieb 14, der hier beispielsweise als Pneumatikzylinder ausgebildet ist, erzeugt die festgelegte Schwenkbewegung.The 4a to 4e show the movement of the ramp 12 and the movements of the possible members of the pivot assembly of a belt conveyor 1 from a closing position of the ramp 12 ( 4a ) to an opening position (cf. 4e ). The drive 14 , which is designed here for example as a pneumatic cylinder, generates the specified pivoting movement.

Die Schwenkanordnung 15 kann eine Vierpunktgelenk-Anordnung in Form einer Doppelschwinge sein. Alternativ kann als Schwenkanordnung 15 ein Schiebe-Schwenk-Mechanismus vorgesehen sein.The swivel arrangement 15 may be a four-point joint arrangement in the form of a double rocker. Alternatively, as a pivoting arrangement 15 a sliding-pivot mechanism may be provided.

ZITATE ENTHALTEN IN DER BESCHREIBUNGQUOTES INCLUDE IN THE DESCRIPTION

Diese Liste der vom Anmelder aufgeführten Dokumente wurde automatisiert erzeugt und ist ausschließlich zur besseren Information des Lesers aufgenommen. Die Liste ist nicht Bestandteil der deutschen Patent- bzw. Gebrauchsmusteranmeldung. Das DPMA übernimmt keinerlei Haftung für etwaige Fehler oder Auslassungen.This list The documents listed by the applicant have been automated generated and is solely for better information recorded by the reader. The list is not part of the German Patent or utility model application. The DPMA takes over no liability for any errors or omissions.

Zitierte PatentliteraturCited patent literature

  • - DE 10304983 B4 [0002] - DE 10304983 B4 [0002]
  • - DE 10304984 B4 [0002] - DE 10304984 B4 [0002]

Claims (16)

Bandförderer für Schrott mit einer endlosen, an einem Traggerüst (2) mit einem Obertrum und einem Untertrum umlaufenden Bandmatte (3), die abhängig von einer Förderrichtung (F) an einer Umlenkeinrichtung (4) ablaufend und der anderen Umlenkeinrichtung (5) auflaufend bewegbar ist und an der einzelne zueinander beabstandete, gegenüber einer Bandmattenebene aufragende, quer zur Bandmatte (3) sich erstreckende Mitnehmer (6) angeordnet sind, und mit einer unterhalb der Bandmatte (3) angeordneten Wanne (10), dadurch gekennzeichnet, dass benachbart zur auflaufenden Umlenkung (5) der Bandmatte (3) eine Steilförderung (11) vorgesehen ist, die eine bogenfömige, an die Wanne (10) anschließbare Rampe (12) als Tragorgan eines zwischen Wanne (10) und Obertrum der Bandmatte (3) ausgebildeten Schleppfördererabschnitts bildet, entlang der die Bandmatte (3) als Schuborgan arbeitet.Belt conveyor for scrap with an endless, on a shoring ( 2 ) with an upper run and a lower run revolving band mat ( 3 ), which depend on a conveying direction (F) on a deflection device ( 4 ) and the other deflection device ( 5 ) is auflaufend movable and at the individual spaced apart, towering over a ribbon mat plane, transverse to the ribbon mat ( 3 ) extending drivers ( 6 ) are arranged, and with a below the band mat ( 3 ) arranged tub ( 10 ), characterized in that adjacent to the incoming deflection ( 5 ) of the band mat ( 3 ) a steep conveyor ( 11 ), which is a bogenfömige, to the tub ( 10 ) connectable ramp ( 12 ) as a support member of a between tub ( 10 ) and upper run of the band mat ( 3 ) formed Schleppfördererabschnitts along which the band mat ( 3 ) works as a thrust member. Bandförderer nach Anspruch 1, dadurch gekennzeichnet, dass die Rampe (12) verschwenkbar gegenüber der Wanne (10) angelenkt ist.Belt conveyor according to claim 1, characterized in that the ramp ( 12 ) pivotable relative to the tub ( 10 ) is articulated. Bandförderer nach Anspruch 2, dadurch gekennzeichnet, dass ein Antrieb (14) für die Schwenkbewegung vorgesehen ist, der die Rampe (12) belastungsabhängig aus einer gefederten Schließ-Position in eine Öffnungs-Position gegenüber der Wanne (10) verschwenkt.Belt conveyor according to claim 2, characterized in that a drive ( 14 ) is provided for the pivoting movement of the ramp ( 12 ) Depending on the load from a spring-loaded closing position into an opening position opposite the trough ( 10 ) pivots. Bandförderer nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass die Rampe (12) mittels einer Schwenkanordnung (15) verschwenkbar ist, die eine am Traggerüst (2) direkt oder indirekt gelagerte horizontale Schwenkachse quer zur Längserstreckung der Wanne (10) aufweist.Belt conveyor according to one of claims 1 to 3, characterized in that the ramp ( 12 ) by means of a pivoting arrangement ( 15 ) is pivotable, the one on the support frame ( 2 ) directly or indirectly mounted horizontal pivot axis transverse to the longitudinal extent of the tub ( 10 ) having. Bandförderer nach einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, dass die Rampe (12) mittels einer Schwenkanordnung (15) verschwenkbar ist, die die Rampe (12) auf einer Bahnkurve verschwenkt.Belt conveyor according to one of claims 1 to 4, characterized in that the ramp ( 12 ) by means of a pivoting arrangement ( 15 ), which is the ramp ( 12 ) pivoted on a trajectory. Bandförderer nach einem der Ansprüche 1 bis 5, dadurch gekennzeichnet, dass die Rampe (12) über eine Vierpunktgelenk-Anordnung angeordnet ist.Belt conveyor according to one of claims 1 to 5, characterized in that the ramp ( 12 ) is arranged via a four-point joint arrangement. Bandförderer nach Anspruch 6, dadurch gekennzeichnet, dass die Schwenkanordnung (15) eine Vierpunktgelenk-Anordnung ist, deren Koppel die Rampe (12) bildet, an der eine Antriebsschwinge (18) und ein Lenker (19) mit gestellfesten Gelenklagern (20, 21) angreifen zum Schwenken der Rampe (12) hin zur Wanne (10) und weg von dieser.Belt conveyor according to claim 6, characterized in that the pivoting arrangement ( 15 ) is a four-point joint arrangement whose coupling the ramp ( 12 ), on which a drive rocker ( 18 ) and a handlebar ( 19 ) with frame-fixed joint bearings ( 20 . 21 ) to swivel the ramp ( 12 ) to the tub ( 10 ) and away from this. Bandförderer nach Anspruch 6 oder 7, dadurch gekennzeichnet, dass die Vierpunktgelenk-Anordnung eine Antriebsschwinge (18) aufweist, die auf der Umlenkwelle (X) der auflaufenden Umlenkeinrichtung (5) der Bandmatte (3) gestellfest gelagert ist.Belt conveyor according to claim 6 or 7, characterized in that the four-point joint arrangement a drive rocker ( 18 ), which on the deflection shaft (X) of the approaching deflection ( 5 ) of the band mat ( 3 ) is mounted fixed to the frame. Bandförderer nach Anspruch 8, dadurch gekennzeichnet, dass die Länge des Lenkers (19) und der Antriebsschwinge (18) als auch der Abstand der beweglichen Gelenklager (22, 23) und der Abstand der gestellfesten Gelenklager (20, 21) wählbar sind zur Einstellung einer Bahnkurve.Belt conveyor according to claim 8, characterized in that the length of the handlebar ( 19 ) and the drive rocker ( 18 ) as well as the distance of the movable spherical plain bearings ( 22 . 23 ) and the distance between the frame-fixed spherical plain bearings ( 20 . 21 ) are selectable for setting a trajectory. Bandförderer nach einem der Ansprüche 1 bis 9, dadurch gekennzeichnet, dass die Rampe (12) einen gekrümmten Steigstreckenabschnitt (16) aufweist, der an dem an die Wanne (10) anschließbaren Ende einen Flachbettabschnitt (24) aufweist.Belt conveyor according to one of claims 1 to 9, characterized in that the ramp ( 12 ) a curved riser section ( 16 ), which on the to the tub ( 10 ) connectable end a flat bed section ( 24 ) having. Bandförderer nach Anspruch 10, dadurch gekennzeichnet, dass die Rampe (12) in einer Schließstellung zur Wanne (10) mit einem Teilbereich des Flachbettabschnitts (24) unter die Wanne (10) verfahrbar ist zum Anlegen an die Wanne (10) unter Überlappung.Belt conveyor according to claim 10, characterized in that the ramp ( 12 ) in a closed position to the tub ( 10 ) with a partial region of the flatbed section ( 24 ) under the tub ( 10 ) is movable for application to the tub ( 10 ) under overlapping. Bandförderer nach einem der Ansprüche 1 bis 11, dadurch gekennzeichnet, dass die Wanne (10) endseitig benachbart zur ankoppelbaren Rampe (12) ein Verschlussblech (25) aufweist, das zur Ausbildung eines Überlappungsspiels bei lastbedingten Pufferbewegungen der Rampe (12) vorgesehen ist.Belt conveyor according to one of claims 1 to 11, characterized in that the tub ( 10 ) at the end adjacent to the dockable ramp ( 12 ) a closure sheet ( 25 ), which is used to form an overlapping clearance during load-induced buffer movements of the ramp ( 12 ) is provided. Bandförderer nach Anspruch 12, dadurch gekennzeichnet, dass das Verschlussblech (25) über ein Scharnier an der Wanne (10) angelenkt und für eine durch Schwerkraft oder Federbelastung erzeugbare Auflast im Bereich des Überlappungsspiels ausgebildet ist.Belt conveyor according to claim 12, characterized in that the closure plate ( 25 ) via a hinge on the tub ( 10 ) is articulated and designed for a load can be generated by gravity or spring load in the overlapping game. Bandförderer nach einem der Ansprüche 1 bis 13, dadurch gekennzeichnet, dass die Rampe (12) einen gekrümmten Steigstreckenabschnitt (16) aufweist, der für einen Schwerkraftabwurf an dem dem Obertrum zugewandten Ende (27) mit Abstand oberhalb des Obertrums geführt ist.Belt conveyor according to one of claims 1 to 13, characterized in that the ramp ( 12 ) a curved riser section ( 16 ), which is for a gravity release at the upper strand facing the end ( 27 ) is guided at a distance above the upper strand. Bandförderer nach Anspruch 14, dadurch gekennzeichnet, dass das dem Obertrum zugewandte Ende (27) der Rampe (12) ein Auflaufende bildet, das in Förderrichtung (F) kürzer ausgebildet ist als ein Auflaufende (28) der Bandmatte (3).Belt conveyor according to claim 14, characterized in that the upper strand facing the end ( 27 ) of the ramp ( 12 ) forms a run-up end, which is shorter in the conveying direction (F) than a run-end ( 28 ) of the band mat ( 3 ). Bandförderer nach einem der Ansprüche 1 bis 15, dadurch gekennzeichnet, dass einzelne zueinander beabstandete Leitschienen (29) auf einem der Bandmatte zugewandten Boden (13) der Wanne (10) angeordnet sind, die beidseitig von außen nach innen gerichtet sich erstrecken in Richtung auf die auflaufende Umlenkeinrichtung (5).Belt conveyor according to one of claims 1 to 15, characterized in that individual mutually spaced guide rails ( 29 ) on a mat ( 13 ) of the tub ( 10 ) are arranged, which extend on both sides directed from the outside inwards in the direction of the incoming deflection ( 5 ).
DE200910005238 2009-01-20 2009-01-20 Belt conveyor for scrap Expired - Fee Related DE102009005238B4 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE200910005238 DE102009005238B4 (en) 2009-01-20 2009-01-20 Belt conveyor for scrap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE200910005238 DE102009005238B4 (en) 2009-01-20 2009-01-20 Belt conveyor for scrap

Publications (2)

Publication Number Publication Date
DE102009005238A1 true DE102009005238A1 (en) 2010-07-29
DE102009005238B4 DE102009005238B4 (en) 2010-12-02

Family

ID=42282466

Family Applications (1)

Application Number Title Priority Date Filing Date
DE200910005238 Expired - Fee Related DE102009005238B4 (en) 2009-01-20 2009-01-20 Belt conveyor for scrap

Country Status (1)

Country Link
DE (1) DE102009005238B4 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105600365A (en) * 2015-11-03 2016-05-25 靖江市恩菲环境工程技术研究所 Belt cleaning dedusting machine set

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3405659A1 (en) * 1984-02-17 1985-08-22 IEM Fördertechnik GmbH, 8581 Kastl Corrugated edge belt conveyor with dirt returning device
DE10304983B4 (en) 2002-11-21 2005-02-10 Bürener Maschinenfabrik GmbH Belt conveyor for scrap
DE10304984B4 (en) 2002-11-21 2005-03-17 Bürener Maschinenfabrik GmbH Cleaning device for plate belt conveyor
DE60216925T2 (en) * 2001-07-24 2007-10-04 Magaldi Industrie S.R.L. SELF-CLEANING INTEGRATED BELT CONVEYOR FOR BULBS

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3405659A1 (en) * 1984-02-17 1985-08-22 IEM Fördertechnik GmbH, 8581 Kastl Corrugated edge belt conveyor with dirt returning device
DE60216925T2 (en) * 2001-07-24 2007-10-04 Magaldi Industrie S.R.L. SELF-CLEANING INTEGRATED BELT CONVEYOR FOR BULBS
DE10304983B4 (en) 2002-11-21 2005-02-10 Bürener Maschinenfabrik GmbH Belt conveyor for scrap
DE10304984B4 (en) 2002-11-21 2005-03-17 Bürener Maschinenfabrik GmbH Cleaning device for plate belt conveyor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105600365A (en) * 2015-11-03 2016-05-25 靖江市恩菲环境工程技术研究所 Belt cleaning dedusting machine set
CN105600365B (en) * 2015-11-03 2017-11-07 靖江市恩菲环境工程技术研究所 A kind of clean dust removal unit of belt

Also Published As

Publication number Publication date
DE102009005238B4 (en) 2010-12-02

Similar Documents

Publication Publication Date Title
EP3216920B1 (en) Milling machine with a conveyor
DE102012212518A1 (en) folding containers
EP3009379B1 (en) Conveying device with an extended conveying body
EP3868958A1 (en) Material transfer device for a ground milling machine
DE102007006795B3 (en) Dust-free bulk material transfer device e.g. for ship loader, has annular seal provided between transfer chute and rotational cute
EP3748095B1 (en) Rake device mountable at an angle in an open channel
DE102009005238B4 (en) Belt conveyor for scrap
DE2654475A1 (en) COMPUTER SYSTEM
DE2945213C2 (en) Conveyor track with input and ejection devices
DE4210570C2 (en) Continuous jaw crusher
EP1213390A2 (en) Feeding apparatus
DE3501509C2 (en) Conveyor with feeder and passage crusher for tunneling of underground operations
DE2815480A1 (en) UNLOADING DEVICE FOR SHIPS, BUNKERS, STORAGE AREAS OR DGL.
EP0384118B1 (en) Device for removing material from a stock pile
DE627608C (en) Device for picking up and conveying bulk goods
AT405943B (en) DEVICE FOR THE CONTROLLED COOLING OF HOT BRIQUETTED DIRECTLY REDUCED IRON SPONGE
DE10304984B4 (en) Cleaning device for plate belt conveyor
DE3008676A1 (en) BELT CONVEYOR
DE94215C (en)
DE19853519B4 (en) Device for stripping transported goods
DE19705426A1 (en) Cleaning appliance for cattle stall manger
DE10115071C2 (en) Gutauforgan for a continuous ship unloader
DE102011113422A1 (en) Grave head for receiving bulk material for ship unloading plant, has twin guide wheel that is swung at end of shovel string cylinder and another end of shovel string cylinder that is linked to support unit
DE95863C (en)
DE8119656U1 (en) Transport tray with a sliding roof

Legal Events

Date Code Title Description
OP8 Request for examination as to paragraph 44 patent law
8364 No opposition during term of opposition
R020 Patent grant now final

Effective date: 20110302

R082 Change of representative

Representative=s name: PATENT- UND RECHTSANWAELTE LOESENBECK, SPECHT,, DE

Representative=s name: PATENT- UND RECHTSANWAELTE LOESENBECK, SPECHT, DAN

R119 Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee