DE102004059646A1 - Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis - Google Patents

Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis Download PDF

Info

Publication number
DE102004059646A1
DE102004059646A1 DE200410059646 DE102004059646A DE102004059646A1 DE 102004059646 A1 DE102004059646 A1 DE 102004059646A1 DE 200410059646 DE200410059646 DE 200410059646 DE 102004059646 A DE102004059646 A DE 102004059646A DE 102004059646 A1 DE102004059646 A1 DE 102004059646A1
Authority
DE
Germany
Prior art keywords
rod
container
arrangement according
bulk material
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
DE200410059646
Other languages
German (de)
Inventor
Georg Unterholzner
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Unterholzner Adolf & Co oHG
Unterholzner Adolf & Co Ohg Tscherms
Original Assignee
Unterholzner Adolf & Co oHG
Unterholzner Adolf & Co Ohg Tscherms
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Unterholzner Adolf & Co oHG, Unterholzner Adolf & Co Ohg Tscherms filed Critical Unterholzner Adolf & Co oHG
Priority to DE200410059646 priority Critical patent/DE102004059646A1/en
Publication of DE102004059646A1 publication Critical patent/DE102004059646A1/en
Ceased legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D88/00Large containers
    • B65D88/54Large containers characterised by means facilitating filling or emptying
    • B65D88/64Large containers characterised by means facilitating filling or emptying preventing bridge formation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Screw Conveyors (AREA)
  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)

Abstract

Arrangement (10) has cylinder shaped conveying element (18) whose one part is projected in container (12). Conveying element transports a part of bulk material, which is present in opening (26) in conveying element, at its longitudinal axis. Rod shaped movable element (28a-28f) is arranged such that a part of its end protrudes in opening of conveying element and which moves the end at its longitudinal axis.

Description

Die Erfindung betrifft eine Anordnung zum Fördern von Schüttgut aus einem Behälter, die ein zylinderförmiges Förderelement enthält, von dem zumindest ein Teil in den Behälter ragt. Das Förderelement fördert bei einer Drehbewegung um seine Längsachse einen Teil des Schüttguts, das sich in einer im zylinderförmigen Förderelement vorhandenen Öffnung befindet, aus dem Behälter heraus.The The invention relates to an arrangement for conveying bulk material a container, the one cylindrical impeller contains at least part of which projects into the container. The conveying element promotes during a rotary movement about its longitudinal axis a part of the bulk material, which is in a cylindrical shape impeller existing opening is located, out of the container out.

Bei bekannten Lager- und Fördereinrichtungen für Schüttgüter, wie zum Beispiel Mehl, Salz, Backmittel, Malzmehl und andere vorzugsweise feinkörnige oder pulverförmige Schüttgüter, werden in Vorratsbehältern zwischengelagert, aus denen sie mit Hilfe eines Förderelements herausgefördert werden. Solche Förderelemente sind vorzugsweise Schraubenförderer oder Schaufelräder, die auch als zylinderförmige Förderelemente bezeichnet werden. Vorzugsweise sind diese Förderelemente im unteren Bereich des Vorratsbehälters angeordnet. Das über und neben dem Förderelement befindliche Schüttgut rutscht vorzugsweise über schräg angeordnete Wände des Vorratsbehälters in Öffnungen des Förderele ments. Beispielsweise liegt eine Dosierschnecke eines Schneckenförderers am Behälterboden und der Vorratsbehälter ist bis zu dessen oberen Rand gefüllt. Bei einer Entnahme von Schüttgut im unteren Bereich des Behälters kann das darüber liegende Schüttgut so genannte Brücken bilden, so dass dieses Schüttgut nicht von alleine nachrutscht oder nachströmt. Dadurch kann kein Schüttgut im Bereich der Förderschnecke zum Herausfördern aus dem Behälter vorhanden sein, obwohl noch ausreichend Schüttgut im Behälter vorhanden ist. Diese Brückenbildung kann somit bewirken, dass in einem Bereich um die Förderschnecke ein Tunnel im Schüttgut geformt wird, so dass das darüber liegende Schüttgut nicht mehr in den unteren Bereich des Vorratsbehälters nachströmt. Das Strömen von Schüttgut wird auch als Fluss bezeichnet.at known storage and conveying equipment for bulk goods, like for example flour, salt, baking agent, malt flour and others preferably fine-grained or powdery Bulk goods, will be in storage containers stored, from which they are using a conveying element conveyed out become. Such conveying elements are preferably screw conveyors or paddle wheels, which is also cylindrical conveying elements be designated. Preferably, these conveying elements are in the lower region of the storage container arranged. That over and next to the conveyor element located bulk material slips preferably over aslant arranged walls of the storage container in openings the funding element. For example, there is a metering screw of a screw conveyor at the bottom of the container and the reservoir is filled to its upper edge. At a withdrawal of bulk in the lower part of the container can that be about it lying bulk material so-called bridges form, so this bulk material does not slip by itself or nachströmt. As a result, no bulk material in the Area of the screw conveyor to promote from the container be present, although still sufficient bulk material in the container available is. This bridge formation can thus cause in an area around the screw conveyor a tunnel in the bulk material is shaped, so that's about it not lying bulk material flows more into the lower area of the reservoir. The Stream of bulk material is also called a river.

Aufgabe der Erfindung ist es, eine Anordnung zum Fördern von Schüttgut aus einem Behälter anzugeben, durch die ein Vorratsbehälter auch dann nahezu vollständig entleert werden kann, wenn das daran befindliche Schüttgut zu einer Brückenbildung neigt.task The invention is an arrangement for conveying bulk material indicate a container through the a reservoir even then almost completely can be emptied when the bulk material is to a bridge formation tends.

Diese Aufgabe wird durch eine Anordnung zum Fördern von Schüttgut aus einem Behälter mit den Merkmalen des Anspruchs 1 gelöst. Vorteilhafte Weiterbildungen der Erfindung sind in den abhängigen Ansprüchen angegeben.These Task is characterized by an arrangement for conveying bulk material a container solved with the features of claim 1. Advantageous developments of the invention are in the dependent claims specified.

Durch eine Anordnung zum Fördern von Schüttgut aus einem Behälter mit den Merkmalen des Anspruchs 1 ist es möglich, insbesondere zur Brückenbildung neigendes Schüttgut aufzulockern oder zumindest ausgebildete Brücken zu durchbrechen. Dadurch kann das gesamte im Vorratsbehälter vorhandene Schüttgut zum Förderelement gelangen und durch dessen Drehbewegung aus dem Behälter gefördert werden. Dies ist insbesondere dann sinnvoll, wenn zur Brückenbildung neigendes Schüttgut über einen längeren Zeitraum im Behälter gelagert worden ist, wodurch die Brückenbildung begünstigt ist. Auch können mit Hilfe der erfindungsgemäßen Anordnung Verklumpungen im Schüttgut zumindest gelöst oder sogar beseitigt werden.By an arrangement for conveying of bulk material from a container with the features of claim 1 it is possible, in particular for bridging tilting bulk material to loosen up or break at least trained bridges. Thereby can the entire existing in the reservoir bulk to the conveyor element reach and be promoted by the rotational movement of the container. This is particularly useful when approaching bridging bulk material over a longer Period in the container has been stored, whereby the bridging is favored. Also can with the aid of the arrangement according to the invention Clumping in the bulk material at least solved or even eliminated.

Zum besseren Verständnis der vorliegenden Erfindung wird im Folgenden auf die in den Zeichnungen dargestellten bevorzugten Ausführungsbeispiele Bezug genommen, die an Hand spezifischer Terminologie beschrieben sind. Es sei jedoch darauf hingewiesen, dass der Schutzumfang der Erfindung dadurch nicht eingeschränkt werden soll, da derartige Veränderungen und weitere Modifizierungen an den gezeigten Vorrichtungen und den Verfahren sowie derartige weitere Anwendungen der Erfindung, wie sie darin aufgezeigt sind, als übliches derzeitiges oder künftiges Fachwissen eines zuständigen Fachmanns angesehen werden. Die Figuren zeigen Ausführungsbeispiele der Erfindung, nämlich:To the better understanding The present invention is described below in the drawings illustrated preferred embodiments reference taken from specific terminology. It should be noted, however, that the scope of the invention not restricted should be, because such changes and further modifications to the devices shown and the Method and such other applications of the invention as they in it are shown as usual current or future Expertise of a competent Be considered professional. The figures show exemplary embodiments of the invention, namely:

1 eine Schnittdarstellung eines Vorratsbehälters mit einer erfindungsgemäßen Anordnung zum Fördern von Schüttgut aus diesem Behälter gemäß einer ersten Ausführungsform der Erfindung; 1 a sectional view of a storage container with an inventive arrangement for conveying bulk material from this container according to a first embodiment of the invention;

2 einen Vorratsbehälter mit einer erfindungsgemäßen Anordnung zum Fördern von Schüttgut aus einem Behälter gemäß einer zweiten Ausführungsform der Erfindung; 2 a reservoir with an inventive arrangement for conveying bulk material from a container according to a second embodiment of the invention;

3 eine Schnittdarstellung des Vorratsbehälters mit der erfindungsgemäßen Anordnung nach 2 entlang der Schnittebene A-A; 3 a sectional view of the reservoir with the inventive arrangement according to 2 along the cutting plane AA;

4 eine Schnittdarstellung des Vorratsbehälters mit der erfindungsgemäßen Anordnung nach 2 entlang der Schnittebene B-B. 4 a sectional view of the reservoir with the inventive arrangement according to 2 along the section plane BB.

In 1 ist ein Längsschnitt einer Anordnung zum Aufbewahren und Fördern von Schüttgut dargestellt. Die Anordnung 10 umfasst einen Behälter 12, der mit dem Schüttgut 14 gefüllt ist. Vorzugsweise wird das Schüttgut 14 vom oberen Rand 16 des Behälters 12 her in diesen eingefüllt. Auf diese Weise wird der Behälter 12 vorzugsweise vollständig mit Schüttgut gefüllt, d.h. bis zum oberen Rand 16 bzw. bis kurz vor dem Erreichen des oberen Randes 16. Im unteren Bereich der Anordnung 10 ist ein Förderelement 18 angeordnet, mit dem das im Behälter 12 vorhandene Schüttgut 14 aus dem Behälter 12 gefördert und die an einer Ent nahmestelle 20 der Anordnung 10 entnommene Menge Schüttgut dosiert werden kann. Das Förderelement 18 enthält eine im Wesentlichen waagerecht angeordnete Förderschnecke 22, die im unteren Bereich des Behälters 12 angeordnet ist. Zwischen der spiralförmigen Wandung der Förderschnecke sind Zwischenräume 26 gebildet, in die Schüttgut 14 aus dem oberen Teil des Behälters 12 in diese Zwischenräume 26 nachrutschen kann. Die Zwischenräume 26 werden allgemein als Öffnungen 26 des Förderelements 18 bezeichnet.In 1 is a longitudinal section of an arrangement for storing and conveying of bulk material shown. The order 10 includes a container 12 that with the bulk 14 is filled. Preferably, the bulk material 14 from the top 16 of the container 12 filled in here. In this way the container becomes 12 preferably completely filled with bulk material, ie up to the upper edge 16 or until shortly before reaching the upper edge 16 , In the lower part of the arrangement 10 is a conveyor element 18 arranged, with which in the container 12 existing bulk material 14 from the container 12 promoted and taken to a Ent 20 the arrangement 10 removed amount of bulk material can be dosed. The conveying element 18 contains a substantially horizontally arranged screw conveyor 22 at the bottom of the container 12 is arranged. Between the spiral wall of the screw conveyor are gaps 26 formed into the bulk material 14 from the upper part of the container 12 in these spaces 26 can slip. The gaps 26 are commonly called openings 26 of the conveyor element 18 designated.

Bei einer Drehbewegung der Förderschnecke 22 in einer vorbestimmten Drehrichtung wird das in den Zwischenräumen 26 befindliche Schüttgut 14 in Richtung der Entnahmestelle 20 aus dem Behälter 12 heraus gefördert. Die Förderschnecke 22 wird von einer nicht dargestellten Antriebseinheit angetrieben, die insbesondere die Antriebsgeschwindigkeit und die Zeitdauer des Antriebs der Förderschnecke 22 derart steuern kann, dass die Förderschnecke auch insbesondere eine Drehbewegung um einen Winkelbereich, z. B. um 90°, ausführt. Dadurch können auch relativ geringe Mengen Schüttgut 14 aus dem Behälter 12 entnommen werden.During a rotary movement of the screw conveyor 22 in a predetermined direction of rotation that will be in the spaces between 26 Bulk goods located 14 in the direction of the sampling point 20 from the container 12 sponsored out. The screw conveyor 22 is driven by a drive unit, not shown, in particular the drive speed and the duration of the drive of the screw conveyor 22 can control such that the screw conveyor in particular a rotational movement about an angular range, z. B. by 90 °, executes. This also allows relatively small amounts of bulk material 14 from the container 12 be removed.

Ferner enthält die Anordnung 10 stabförmige Elemente 28a bis 28f, die mit einem Ende mit einem im oberen Bereich des Behälters 12 quer angeordneten Verbindungselement 30 fest verbunden sind. Das Verbindungselement 30 erstreckt sich zwischen zwei Seitenwänden 32, 34 des Behälters 12 und ist mit diesen fest verbunden. Im Ausführungsbeispiel nach 1 ist das Verbindungselement 30 mit Hilfe einer Schraubverbindung mit den Seitenwänden 32, 34 derart fest verbunden, dass die Stirnflächen des Verbindungselements 30 flächig an den Seitenwänden 32, 34 anliegen. Alternativ kann das Verbindungselement auch auf andere geeignete Art und Weise mit mindestens einer Seitenwand 32, 34 verbunden sein, beispielsweise mit Hilfe einer Niet- oder Schweißverbindung. Die stabförmigen Elemente 28a, 28f sind mit dem Verbindungselement 30 derart fest verbunden, dass sie am Verbindungselement 30 mit einem Ende eingespannt sind.Furthermore, the arrangement contains 10 rod-shaped elements 28a to 28f that has one end with one in the top of the container 12 transversely arranged connecting element 30 are firmly connected. The connecting element 30 extends between two side walls 32 . 34 of the container 12 and is firmly connected to them. In the embodiment according to 1 is the connecting element 30 by means of a screw connection with the side walls 32 . 34 firmly connected such that the end faces of the connecting element 30 flat on the side walls 32 . 34 issue. Alternatively, the connecting element may also be in any other suitable manner with at least one side wall 32 . 34 be connected, for example by means of a rivet or welded connection. The rod-shaped elements 28a . 28f are with the connecting element 30 firmly connected so that they on the connecting element 30 are clamped with one end.

Das gegenüberliegende Ende der stabförmigen Elemente 28a bis 28f ragt von oben in den Fördergang der Förderschnecke 22 hinein. Dadurch werden die einzelnen Elemente 28a bis 28f bei einer Drehbewegung der Förderschnecke 22 durch den Eingriff der spiralförmigen Wandung 24 in die Enden der stabförmigen Elemente 28a bis 28f zumindest in Drehrichtung der Förderschnecke 22 ausgelenkt. Beim Auslenken gleitet die spiralförmige Wandung 24 der Förderschnecke 22 am stabförmigen Element 28a bis 28f entlang bis zu dessen Ende, wodurch das stabförmige Element 28a bis 28f über den Kamm der spiralförmigen Wandung 24 gleitet und in den hinter der spiralförmigen Wandung 24 liegenden Zwischenraum 26 hineinspringt. Die stabförmigen Elemente 28a bis 28f sind elastisch verformbar, so dass beim Auslenken des stabförmigen Elements 28a bis 28f eine Rückstellkraft erzeugt wird, durch die das stabförmige Element 28a bis 28f bestrebt ist, in seine Ausgangslage zurückzukehren, in der die Längsachse des stabförmigen Elements 28a bis 28f senkrecht angeordnet ist.The opposite end of the rod-shaped elements 28a to 28f protrudes from above into the feed of the screw conveyor 22 into it. This will make the individual elements 28a to 28f during a rotary movement of the screw conveyor 22 by the engagement of the spiral wall 24 in the ends of the rod-shaped elements 28a to 28f at least in the direction of rotation of the screw conveyor 22 deflected. When deflecting slides the spiral wall 24 the screw conveyor 22 on the rod-shaped element 28a to 28f along to its end, whereby the rod-shaped element 28a to 28f over the crest of the spiral wall 24 slides and into the behind the spiral wall 24 lying gap 26 into jumps. The rod-shaped elements 28a to 28f are elastically deformable, so that when deflecting the rod-shaped element 28a to 28f a restoring force is generated by which the rod-shaped element 28a to 28f endeavors to return to its initial position, in which the longitudinal axis of the rod-shaped element 28a to 28f is arranged vertically.

Durch das Auslenken und/oder Rückspringen der stabförmigen Elemente 28a bis 28f wird eine Kraft auf das Verbindungselement 30 übertragen, die das Verbindungselement 30 weiter auf zumindest die mit dem Verbindungselement 30 verbundenen Seitenwände 32, 34 teilweise überträgt. Sowohl durch das Auslenken der stabförmigen Elemente 28a bis 28f selbst als auch durch das Übertragen der beim Auslenken und Rückstellen der stabförmigen Elemente 28a bis 28f auftretenden Kräfte wird das im Behälter 12 befindliche Schüttgut 14 bewegt, und/oder es wird eine Kraft auf das Schüttgut ausgeübt, durch die Brückenbildungen und Verklumpungen des Schüttguts 14 im Behälter 12 gelöst und somit beseitigt werden. Dadurch kann das gesamte im Behälter 12 befindliche Schüttgut 14 in den Bereich der Förderschnecke 22 nachrutschen, wodurch der Behälter 12 nahezu vollständig entleert werden kann. Somit kann der Behälter 12 ohne zusätzliche Maßnahmen, wie zum Beispiel Rüttler oder Rührwerke, vollständig entleert werden, auch wenn das zu fördernde Schüttgut 14 zu Brückenbildung neigt.By deflecting and / or returning the rod-shaped elements 28a to 28f becomes a force on the connecting element 30 transferring the connecting element 30 continue on at least the one with the connecting element 30 connected side walls 32 . 34 partially transfers. Both by the deflection of the rod-shaped elements 28a to 28f itself as well as by the transfer of the deflection and return of the rod-shaped elements 28a to 28f occurring forces that is in the container 12 Bulk goods located 14 moves, and / or a force is exerted on the bulk material, by the bridging and clumping of the bulk material 14 in the container 12 solved and thus eliminated. This allows the whole in the container 12 Bulk goods located 14 in the area of the screw conveyor 22 slipping, causing the container 12 can be almost completely emptied. Thus, the container 12 without additional measures, such as vibrators or agitators, are completely emptied, even if the bulk material to be transported 14 tends to bridging.

Bei anderen Ausführungsbeispielen kann die Förderschnecke 22 kürzer ausgebildet sein und sich nicht von der Entnahmestelle 20 bis zur gegenüberliegenden Seitenwand 34 des Behälters 12 erstrecken, sondern nur in einem Teilbereich des Behälters. Ferner kann zumindest eine Wand des Behälters 12 derart schräg zulaufend angeordnet sein, dass das im Behälter 12 befindliche Schüttgut 14 zu den Zwischenräumen 26 der Förderschnecke 22 geführt ist. Alternativ zur Förderschnecke 22 kann auch ein Schaufelrad vorgesehen sein, das beispielsweise zwischen den Seitenwänden 32 und 34 angeordnet ist. Das Schaufelrad könnte dabei als Zellradschleuse ausgebildet sein, wodurch der Behälterinnenraum auch luftdicht zur Entnahmestelle 20 hin abgeschottet werden kann. Vorzugsweise ist die Längsachse des Schaufelrades vertikal angeordnet, so dass eine Vertikal-Zellradschleuse gebildet ist.In other embodiments, the screw conveyor 22 be formed shorter and not from the sampling point 20 to the opposite side wall 34 of the container 12 extend, but only in a portion of the container. Furthermore, at least one wall of the container 12 be arranged tapered so that in the container 12 Bulk goods located 14 to the interstices 26 the screw conveyor 22 is guided. Alternative to the screw conveyor 22 can also be provided a paddle wheel, for example, between the side walls 32 and 34 is arranged. The paddle wheel could be designed as a rotary valve, whereby the container interior also airtight to the sampling point 20 can be sealed off. Preferably, the longitudinal axis of the impeller is arranged vertically, so that a vertical rotary valve is formed.

In 2 ist eine Anordnung 40 ähnlich der Anordnung 10 nach 1 dargestellt. Gleiche Elemente haben gleiche Bezugszeichen. Die Förderschnecke 22 der Anordnung 40 hat eine gewundene spiralförmige Wandung 42, die im Unterschied zur spiralförmigen Wandung 24 nach 1 eine gleichmäßige Steigung hat. Weitere Modifizierungen in der Art der Ausführung der spiralförmigen Wandung, der Förderschnecke und/oder des Zellrades insbesondere mit vorteilhaften Wirkungen im Zusammenhang mit dem zu fördernden Schüttgut 14 können verwendet werden.In 2 is an arrangement 40 similar to the arrangement 10 to 1 shown. Like elements have the same reference numerals. The screw conveyor 22 the arrangement 40 has a winding spiral wall 42 that in contrast to spiral wall 24 to 1 has a uniform slope. Further modifications in the manner of execution of the spiral wall, the screw conveyor and / or the cellular wheel, in particular with advantageous effects in connection with the bulk material to be conveyed 14 can be used.

In 3 ist eine Schnittdarstellung der Anordnung 40 entlang der Schnittebene A-A nach 2 dargestellt. In 4 ist eine Schnittdarstellung der Anordnung 40 entlang der Schnittebene B-B nach 2 dargestellt.In 3 is a sectional view of the arrangement 40 along the cutting plane AA after 2 shown. In 4 is a sectional view of the arrangement 40 along the section plane BB to 2 shown.

Die stabförmigen Elemente 28a bis 28f können beispielsweise einen runden, einen ovalen, einen quadratischen oder einen rechteckigen Querschnitt haben. Ferner müssen die stabförmigen Elemente 28a bis 28f nicht senkrecht angeordnet sein und können auch direkt, d.h. ohne das Verbindungselement 30 mit mindestens einer Behälterwand 32, 34 verbunden sein. Ferner müssen die stabförmigen Elemente 28a bis 28f nicht zwingend mit einem Ende eingespannt sein. Vielmehr können sie auch in einem Bereich entlang des stabförmigen Elements 28a bis 28f eingespannt sein. Alternativ können die stabförmigen Elemente 28a bis 28f dreh bar angeordnet sein, so dass sie ausgelenkt werden, wobei sie vorzugsweise durch ihre Gewichtskraft und/oder eine Federkraft in eine Ausgangslage gebracht werden. Ferner ist es möglich, dass das Förderelement 18 auch Bohrungen oder anders geformte Öffnungen enthält, in die das zu fördernde Schüttgut 14 hineinrutscht und über die das zu fördernde Schüttgut 14 aus dem Behälter 12 transportiert wird. Vorzugsweise greifen die stabförmigen Elemente 28a bis 28f dann in diese Öffnungen ein. Bei entsprechender Dimensionierung der Wandung 24 der Förderschnecke 22, der Länge, dem Querschnitt und dem Durchmesser der stabförmigen Elemente 28a bis 28f werden die Seitenwände 32, 34 des Behälters 12 zum Vibrieren angeregt, wodurch auch weitere Wände des Behälters 12 in Vibration versetzt werden können.The rod-shaped elements 28a to 28f For example, they may have a round, an oval, a square or a rectangular cross section. Furthermore, the rod-shaped elements must 28a to 28f can not be arranged vertically and can also directly, ie without the connecting element 30 with at least one container wall 32 . 34 be connected. Furthermore, the rod-shaped elements must 28a to 28f not necessarily be clamped with an end. Rather, they can also be in an area along the rod-shaped element 28a to 28f be clamped. Alternatively, the rod-shaped elements 28a to 28f be arranged rotating bar so that they are deflected, whereby they are preferably brought by their weight and / or a spring force in an initial position. Furthermore, it is possible that the conveying element 18 Also contains holes or other shaped openings into which the bulk material to be delivered 14 slips in and over the the bulk material to be conveyed 14 from the container 12 is transported. Preferably, the rod-shaped elements engage 28a to 28f then into these openings. With appropriate dimensioning of the wall 24 the screw conveyor 22 , the length, the cross section and the diameter of the rod-shaped elements 28a to 28f become the sidewalls 32 . 34 of the container 12 stimulated to vibrate, causing more walls of the container 12 can be vibrated.

Die Anordnungen 10, 40 nach den 1 und 2 eignen sich insbesondere zum Fördern von Schüttgut 14 in Form von pulverförmigem Material, insbesondere Lebensmitteln, wie Mehl, Salz, Backmittel, Kakao, Zucker, Malzmehl aber auch von grobkörnigen Lebensmitteln, wie zum Beispiel Getreidekörnern, Mais, Bohnen, Kaffee und dergleichen. Vorzugsweise sind die Längsachsen der Förderelemente 18 waagerecht angeordnet und die stabförmigen Elemente 28a bis 28f orthogonal zu dieser Längsachse. Besonders vorteilhaft ist es, die stabförmigen Elemente 28a bis 28f senkrecht nebeneinander mit einem vorbestimmten Abstand zueinander anzuordnen. Die stabförmigen Elemente 28a bis 28f können dann im Ruhezustand in einer Ebene liegen.The arrangements 10 . 40 after the 1 and 2 are particularly suitable for conveying bulk material 14 in the form of powdery material, in particular food, such as flour, salt, baking agent, cocoa, sugar, malt flour but also of coarse-grained foods, such as cereal grains, corn, beans, coffee and the like. Preferably, the longitudinal axes of the conveying elements 18 arranged horizontally and the rod-shaped elements 28a to 28f orthogonal to this longitudinal axis. It is particularly advantageous, the rod-shaped elements 28a to 28f perpendicular to each other with a predetermined distance to each other to order. The rod-shaped elements 28a to 28f can then lie in a resting state in a plane.

Obgleich in den Zeichnungen und in der vorhergehenden Beschreibung bevorzugte Ausführungsbeispiele aufgezeigt und detailliert beschrieben worden sind, sollten sie lediglich als rein beispielhaft und die Erfindung nicht einschränkend angesehen werden. Es wird darauf hingewiesen, dass nur die bevorzugten Ausführungsbeispiele dargestellt und beschrieben sind und sämtliche Veränderungen und Modifizierungen, die derzeit und zukünftig im Schutzumfang der Erfindung liegen, geschützt werden sollen.Although in the drawings and in the foregoing description preferred embodiments have been shown and described in detail, they should merely as purely exemplary and not limiting the invention. It should be noted that only the preferred embodiments shown and described and all changes and modifications, currently and in the future are within the scope of the invention, to be protected.

10, 4010 40
Anordnungarrangement
1212
Behältercontainer
1414
Schüttgutbulk
1616
oberer Randupper edge
1818
Förderelementimpeller
2020
Entnahmestellesampling point
2222
FörderschneckeAuger
24, 4024 40
spiralförmige Wandungspiral wall
2626
Zwischenräume, ÖffnungInterspaces, opening
28a bis 28f28a to 28f
stabförmiges Elementrod-shaped element
3030
Verbindungselementconnecting element
32, 3432 34
SeitenwandSide wall
A-A, B-BA-A, B-B
Schnittebenecutting plane

Claims (17)

Anordnung zum Fördern von Schüttgut aus einem Behälter, mit einem zylinderförmigen Förderelement (18), von dem zumindest ein Teil in den Behälter (12) ragt, wobei das Förderelement (18) bei einer Drehbewegung um seine Längsachse einen Teil des Schüttguts (14), das sich in einer im zylinderförmigen Förderelement (18) vorhandenen Öffnung (26) befindet, aus dem Behälter (12) herausfördert; mit mindestens einem stabförmigen auslenkbaren Element (28a bis 28f), das derart angeordnet ist, dass zumindest ein Teil eines Endes des stabförmigen Elements (28a bis 28f) in die Öffnung (26) des Förderelements (18) ragt; wobei das stabförmige Element (28a bis 28f) derart angeordnet ist, dass das Förderelement (18) bei einer Drehbewegung um dessen Längsachse das in dessen Öffnung (26) eingreifende Ende des stabförmigen Elements (28a bis 28f) auslenkt.Arrangement for conveying bulk material out of a container, with a cylindrical conveying element ( 18 ), of which at least a part of the container ( 12 ) protrudes, wherein the conveying element ( 18 ) during a rotary movement about its longitudinal axis a part of the bulk material ( 14 ), which in a cylindrical conveying element ( 18 ) existing opening ( 26 ), from the container ( 12 ); with at least one rod-shaped deflectable element ( 28a to 28f ) arranged such that at least a part of one end of the rod-shaped element ( 28a to 28f ) in the opening ( 26 ) of the conveyor element ( 18 protrudes; the rod-shaped element ( 28a to 28f ) is arranged such that the conveying element ( 18 ) in a rotational movement about its longitudinal axis in the opening ( 26 ) engaging end of the rod-shaped element ( 28a to 28f ) deflects. Anordnung nach Anspruch 1, dadurch gekennzeichnet, dass das Förderelement eine Förderschnecke (22) ist, wobei die Öffnung der spiralförmige Zwischenraum (26) der Förderschnecke (22) ist.Arrangement according to claim 1, characterized in that the conveying element is a screw conveyor ( 22 ), wherein the opening of the spiral-shaped gap ( 26 ) of the screw conveyor ( 22 ). Anordnung nach Anspruch 1, dadurch gekennzeichnet, dass das Förderelement ein Schaufelrad ist, wobei die Öffnung durch die Zwischenräume zwischen den benachbarten Schaufelblättern des Schaufelrads erzeugt ist.Arrangement according to claim 1, characterized that the conveying element a paddle wheel is, the opening through the gaps generated between the adjacent blades of the paddle wheel is. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass die stabförmigen Elemente (28a bis 28f) einen runden, quadratischen und/oder rechteckigen Querschnitt haben.Arrangement according to one of the preceding claims, characterized in that the rod-shaped elements ( 28a to 28f ) have a round, square and / or rectangular cross-section. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass die stabförmigen Elemente (28a bis 28f) in einem von dem eingreifenden Ende entfernten Bereich eingespannt sind.Arrangement according to one of the preceding claims, characterized in that the rod-shaped elements ( 28a to 28f ) are clamped in an area remote from the engaging end. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass auf das stabförmige Element (28a bis 28f) im ausgelenktem Zustand eine Rückstellkraft wirkt, durch die das stabförmige Element (28a bis 28f) bestrebt ist, seine Ausgangslage einzunehmen.Arrangement according to one of the preceding claims, characterized in that on the rod-shaped element ( 28a to 28f ) in the deflected state a restoring force acts, by which the rod-shaped element ( 28a to 28f ) endeavors to assume its starting position. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das Ende des stabförmigen Elements (28a bis 28f) soweit ausgelenkt wird, bis es nicht mehr in die Öffnung (26) eingreift, und dass es vorzugsweise anschließend durch eine Rückstellkraft in eine weitere Öffnung oder in dieselbe Öffnung (26) eingreift.Arrangement according to one of the preceding claims, characterized in that the end of the rod-shaped element ( 28a to 28f ) as far as it is not in the opening ( 26 ) engages, and that it is preferably then by a restoring force in another opening or in the same opening ( 26 ) intervenes. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das stabförmige Element (28a bis 28f) elastisch verformbar ist.Arrangement according to one of the preceding claims, characterized in that the rod-shaped element ( 28a to 28f ) is elastically deformable. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass zumindest ein Teil des Förderelements (18) in einem unteren Bereich des Behälters (12) angeordnet ist.Arrangement according to one of the preceding claims, characterized in that at least a part of the conveying element ( 18 ) in a lower region of the container ( 12 ) is arranged. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass zumindest eine Behälterwand (32, 34) schräg zulaufend zum Förderelement (18) hin angeordnet ist, so dass Schüttgut (14) vorzugsweise zum Förderelement (18) hinrutscht.Arrangement according to one of the preceding claims, characterized in that at least one container wall ( 32 . 34 ) tapered to the conveyor element ( 18 ), so that bulk material ( 14 ) preferably to the conveying element ( 18 ) slips. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das stabförmige Element (28a bis 28f) durch das Auslenken und/oder das Hineingleiten des Endes des stabförmigen Elements (28a bis 28f) in eine weitere Öffnung oder in dieselbe Öffnung (26) zumindest durch Wiederholen dieses Vorgangs vibriert.Arrangement according to one of the preceding claims, characterized in that the rod-shaped element ( 28a to 28f ) by the deflection and / or the sliding in of the end of the rod-shaped element ( 28a to 28f ) into another opening or into the same opening ( 26 ) vibrates at least by repeating this process. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das stabförmige Element (28a bis 28f) mit einer Behälterwand (32,34), vorzugsweise über ein Verbindungselement (30) verbunden ist, wobei beim Auslenken und/oder Zurückstellen des stabförmigen Elements (28a bis 28f) eine Kraft auf diese Behälterwand (32, 34) übertragen wird, wodurch diese Behälterwand (32,34) vorzugsweise vibriert.Arrangement according to one of the preceding claims, characterized in that the rod-shaped element ( 28a to 28f ) with a container wall ( 32 . 34 ), preferably via a connecting element ( 30 ), wherein upon deflection and / or resetting of the rod-shaped element ( 28a to 28f ) a force on this container wall ( 32 . 34 ), whereby this container wall ( 32 . 34 ) preferably vibrates. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das Schüttgut (14) ein pulverförmiges Material, insbesondere Mehl, Salz, Backmittel, Malzmehl, Zucker und ähnliches ist.Arrangement according to one of the preceding claims, characterized in that the bulk material ( 14 ) is a powdery material, in particular flour, salt, baking agent, malt flour, sugar and the like. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass das stabförmige Element (28a bis 28f) im Wesentlichen orthogonal zur Längsachse des zylinderförmigen Förderelements (22) angeordnet ist, vorzugsweise senkrecht.Arrangement according to one of the preceding claims, characterized in that the rod-shaped element ( 28a to 28f ) substantially orthogonal to the longitudinal axis of the cylindrical conveying element ( 22 ) is arranged, preferably vertically. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass mehrere stabförmige Elemente (28a bis 28f) vorgesehen sind, deren Längsachsen im Wesentlichen parallel verlaufen und in einem vorbestimmten Abstand zueinander angeordnet sind, wobei die Längsachsen der stabförmigen Elemente (28a bis 28f) vorzugsweise in Ruhelage in einer Ebene liegen.Arrangement according to one of the preceding claims, characterized in that a plurality of rod-shaped elements ( 28a to 28f ) are provided whose longitudinal axes are substantially parallel and are arranged at a predetermined distance from each other, wherein the longitudinal axes of the rod-shaped elements ( 28a to 28f ) are preferably in rest position in a plane. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass mit Hilfe des Förderelements (22) in dessen Öffnung befindliches Schüttgut (14) aus dem Behälter (12) förderbar ist.Arrangement according to one of the preceding claims, characterized in that by means of the conveying element ( 22 ) located in its opening bulk material ( 14 ) from the container ( 12 ) is eligible. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, dass mit Hilfe der eingestellten Drehzahl bzw. mit Hilfe des angesteuerten Drehwinkels die aus dem Behälter (12) entnommene Menge Schüttgut (14) gesteuert und/oder dosierbar ist.Arrangement according to one of the preceding claims, characterized in that with the aid of the set speed or with the help of the controlled rotation angle from the container ( 12 ) amount of bulk material ( 14 ) is controlled and / or metered.
DE200410059646 2004-12-10 2004-12-10 Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis Ceased DE102004059646A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE200410059646 DE102004059646A1 (en) 2004-12-10 2004-12-10 Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE200410059646 DE102004059646A1 (en) 2004-12-10 2004-12-10 Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis

Publications (1)

Publication Number Publication Date
DE102004059646A1 true DE102004059646A1 (en) 2006-06-14

Family

ID=36500206

Family Applications (1)

Application Number Title Priority Date Filing Date
DE200410059646 Ceased DE102004059646A1 (en) 2004-12-10 2004-12-10 Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis

Country Status (1)

Country Link
DE (1) DE102004059646A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2314184A3 (en) * 2009-10-21 2012-02-15 Eugster/Frismag AG Instant powder conveying device for a drink preparation device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1171088A (en) * 1967-05-04 1969-11-19 Westinghouse Electric Corp Powder Dispenser.
DE1556721A1 (en) * 1967-11-03 1970-03-12 Columware Inc Dispensing device for material powder
FR2177486A1 (en) * 1972-03-27 1973-11-09 Cohen Raymond
JPS61169422A (en) * 1985-01-23 1986-07-31 Fuji Xerox Co Ltd Toner feeder

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1171088A (en) * 1967-05-04 1969-11-19 Westinghouse Electric Corp Powder Dispenser.
DE1556721A1 (en) * 1967-11-03 1970-03-12 Columware Inc Dispensing device for material powder
FR2177486A1 (en) * 1972-03-27 1973-11-09 Cohen Raymond
JPS61169422A (en) * 1985-01-23 1986-07-31 Fuji Xerox Co Ltd Toner feeder

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2314184A3 (en) * 2009-10-21 2012-02-15 Eugster/Frismag AG Instant powder conveying device for a drink preparation device
US8418838B2 (en) 2009-10-21 2013-04-16 Eugster/Frismag Ag Instant powder conveyor device of a drinks preparing machine

Similar Documents

Publication Publication Date Title
EP1931951B1 (en) Dosing device for powdery or pasty substances
EP1175828B1 (en) Vertical axis fodder mixer
DE69314667T2 (en) FEED CONVEYOR
DE102011010928A1 (en) Apparatus and method for protecting living beings and objects from spillage
EP1931952A1 (en) Dosing device for powdery or pasty substances
EP2458345A1 (en) Metering device
DE10137843A1 (en) Device for sorting and transporting bulk goods
EP1627832B1 (en) Bunker for bulk material comprising a propulsive device
DE102004059646A1 (en) Arrangement for conveying bulk material e.g. container has cylinder shaped conveying element whose one part is projected in container whereby conveying element transports a part of bulk material at its longitudinal axis
DE102004040731A1 (en) Storing and transporting container for bulk material, especially push-bottom hopper, for bulk material has push elements movable relative to one another with drive of one element controlled independently of drive of other
EP0434995B1 (en) Silo with a discharging device
EP2243544A1 (en) Device for mixing bulk material
DE4230247A1 (en) Filling device for valve bags in particular
DE2622630A1 (en) DEVICE FOR DISCHARGING POWDERED OR GRAINY MATERIAL
DE3685974T2 (en) ROTATABLE CONNECTED RIGID CELL CHAINS.
DE3144305C2 (en) Device for mixing granular or powdered material
DE2951300C2 (en) Silo discharge device for free-flowing, powdery to granular solids
DE3244552A1 (en) Device for discharging sticky material from an upright container
WO2000002799A1 (en) Device for obtaining a continuous material flow in bulk goods
DE19750074C1 (en) Metered feed for dry fodder
DE19900176A1 (en) Conveyor
DE3131469A1 (en) "CONVEYOR FOR CONFECTIONERY"
DE2132903C3 (en) Transport container for bulk goods that are difficult to flow
DE10259198B4 (en) Apparatus for the handling of bulk goods of transport vehicles
DE1279546B (en) Funnel for bulk goods with a shaking device

Legal Events

Date Code Title Description
OP8 Request for examination as to paragraph 44 patent law
8131 Rejection