CZ20041154A3 - Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same - Google Patents

Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same Download PDF

Info

Publication number
CZ20041154A3
CZ20041154A3 CZ20041154A CZ20041154A CZ20041154A3 CZ 20041154 A3 CZ20041154 A3 CZ 20041154A3 CZ 20041154 A CZ20041154 A CZ 20041154A CZ 20041154 A CZ20041154 A CZ 20041154A CZ 20041154 A3 CZ20041154 A3 CZ 20041154A3
Authority
CZ
Czechia
Prior art keywords
block
capacity
production
modular
tpv
Prior art date
Application number
CZ20041154A
Other languages
Czech (cs)
Other versions
CZ298013B6 (en
Inventor
Votruba@Pavel
Original Assignee
Votruba@Pavel
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Votruba@Pavel filed Critical Votruba@Pavel
Priority to CZ20041154A priority Critical patent/CZ298013B6/en
Priority to CZ200416109U priority patent/CZ15451U1/en
Publication of CZ20041154A3 publication Critical patent/CZ20041154A3/en
Publication of CZ298013B6 publication Critical patent/CZ298013B6/en

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Zpusob automatizované vícemodulární regulace prípravné fáze výroby spocívá v tom, ze se vytvorí normativy a kvantitativní hodnoty technologických postupu, konstrukce náradí a výroby náradí, poté se vytvorí soubor vstupních dat technologických postupu, konstrukce náradí a výroby náradí nacez se provádí identifikace, lokalizace, registrace a kvantifikace casových, kapacitních a hodnotových disproporcí, které se dále zobrazují a korigují a regulujíinteraktivními zmenami. K provádení zpusobu slouzí systém sestávající z jednoho bloku normativní matice a dalsího bloku výrobkové matice, které jsou propojeny s modulární formací histogramu kapacit, pricemz vstup jednoho bloku je pripojen k zobrazovací jednotce termínového lhutového diagramu, vstupdalsího bloku je pripojen k bloku s inovacním programem a/nebo prubehem zakázek a výstup z modulární formace histogramu kapacit je pripojen k porovnávacímu modulárnímu clenu prvku pozadované kapacityP a reálné kapacity R, a dále je k nemu pripojen blok technologické prípravy výroby a/nebo blok konstrukcní prípravy výroby.The method of automated multi-modular regulation of the preparatory phase of production consists in the creation of normatives and quantitative values of technological processes, construction of tools and production of tools, then a set of input data of technological processes, construction of tools and production of tools is carried out identification, localization, registration and quantification of time, capacity and value disproportions, which are further displayed and corrected and regulated by interactive changes. To perform the method, a system consisting of one block of a normative matrix and another block of a product matrix, which are coupled to a modular capacitance histogram formation, is used, wherein the input of one block is connected to the display unit of the term bar chart, the input block is connected to the block with the innovation program and / or or the progress of the orders, and the output of the modular capacity histogram formation is connected to the comparative modular member of the required capacity capacitor P and the real capacity R, and a manufacturing process block and / or a manufacturing design block is attached thereto.

Description

(57) Anotace:(57)

Způsob automatizované vícemodulární regulace přípravné fáze výroby spočívá v tom, že se vytvoří normativy a kvantitativní hodnoty technologických postupů, konstrukce nářadí a výroby nářadí, poté se vytvoří soubor vstupních dat technologických postupů, konstrukce nářadí a výroby nářadí načež se provádí identifikace, lokalizace, registrace a kvantifikace časových, kapacitních a hodnotových disproporcí, které se dále zobrazují a korigují a regulují interaktivními změnami. K provádění způsobu slouží systém sestávající z jednoho bloku normativní matice a dalšího bloku výrobkové matice, které jsou propojeny s modulární formací histogramu kapacit, přičemž vstup jednoho blokuje připojen k zobrazovací jednotce termínového lhůtového diagramu, vstup dalšího blokuje připojen k bloku s inovačním programem a/nebo průběhem zakázek a výstup z modulární formace histogramu kapacit je připojen k porovnávacímu modulárnímu členu prvku požadované kapacity P a reálné kapacity R, a dále je k němu připojen blok technologické přípravy výroby a/nebo blok konstrukční přípravy výroby.The method of automated multi-module regulation of the preparatory phase of production consists in creating normative and quantitative values of technological processes, tool design and tool manufacturing, then creating a set of process data input, tool design and tool manufacturing, followed by identification, location, registration and quantification of time, capacity and value disproportions, which are further displayed and corrected and regulated by interactive changes. To perform the method, a system consisting of one normative matrix block and another product matrix block interconnected with a modular capacity histogram formation is used, wherein the input of one block is coupled to the deadline display unit, the input of another block is coupled to the innovation program block and / or In the course of the orders, the output of the modular capacity histogram formation is connected to the comparator modular member of the required capacity P element and the real capacity R, and further connected to a technological preparation block and / or a structural preparation block.

·* · ' • · · • 4 • · ···· ·· * · '· · · · 4 · · ···· ·

TyYou

Způsob automatizované vícemodulární regulace přípravné fáze výroby včetně diagnostiky a systém k provádění tohoto způsobu.A method of automated multi-module control of the preparatory stage of production including diagnostics and a system for carrying out this method.

Oblast technikyTechnical field

Vynález se týká způsobu automatizované vícemodulární regulace přípravné fáze výroby včetně diagnostiky a systému k provádění tohoto způsobu (dále AVDRS).The present invention relates to a method of automated multi-modular control of a preparatory production phase including diagnostics and a system for performing the method (hereinafter referred to as AVDRS).

Dosavadní stavBackground

Stav technické přípravy (TPV) a jejího řízení je vymezen obvykle dvanácti základními etapami a přibližně dvěma sty základními činnostmi evidovanými, ze kterých hlavní činnosti jsou kontrolované a regulované. Tato charakteristika TPV se vztahuje na středně velký podnik s kusovou a malosériovou výrobou. Z uvedených dvanácti základních etap je tři až pět etap kritických a tvoří kritickou cestu TPV.The state of technical preparation (TPV) and its management is usually defined by twelve basic stages and approximately two hundred basic activities recorded, of which the main activities are controlled and regulated. This TPV characteristic refers to a medium-sized enterprise with single-piece and small-batch production. Of the twelve basic stages, three to five are critical and form the critical path of TPV.

Kvalitu inovací i technologických plnění termínů a výši výrobních nákladů nejvíce ovlivňují tři kritické etapy na konci cyklu TPV ve fázi transferu technologií, které jsou uvedené v chronologickém pořadí: zpracování technologických postupů včetně technicko hospodářských norem (THN), konstrukce speciálního nářadí a jednoúčelových strojů (JÚS) a výroba speciálního nářadí a JÚS.The quality of innovations and technological fulfillment of deadlines and the level of production costs are most influenced by three critical stages at the end of the TPV cycle in the phase of technology transfer, which are listed in chronological order: elaboration of technological procedures including technical economic standards (THN), special tools and single-purpose machines ) and production of special tools and JÚS.

-2Do specifikovaných kritických etap na konci cyklu TPV se kumuluji časové, kapacitní a hodnotové skluzy a tím se zkracuje průměrná doba a limituje možnost plnění termínů zejména v etapě výroba speciálního nářadí a JÚS a tím se podstatně snižuje možnost kompletovat a vybavit výrobu již v prvním roce po zavedení inovovaného výrobku úplnou sadou speciálního nářadí a JÚS tak, jak to bylo specifikováno v technologických postupech pro zavedenou a opakovanou výrobu inovovaného výrobku.-2The specified critical stages at the end of the TPV cycle accumulate time, capacity and value slips, thus reducing the average time and limiting the possibility of meeting deadlines, especially in the stage of special tool production and JÚS, thus significantly reducing the possibility to complete and equip production in the first year after the introduction of the innovated product with a complete set of special tools and JÚS as specified in the technological procedures for the established and repeated production of the innovated product.

Po privatizaci průmyslových podniků odešla řada kvalifikovaných pracovníků na lépe placená místa do zahraničních firem a následkem toho mnohdy až rapidně poklesla úroveň normativní základny pro kritické etapy TPV a lhůtové plánování etap TPV se často provádělo bez kapacitní bilance plánů TPV. Za těchto okolností splnitelnost takto postavených plánů TPV a ročních programů inovací byla a je stále nepřesná a nejistá. Zejména přesné zjištění limitujících faktorů časových a kapacitních, které určují realizovatelnost inovace výrobku ještě ve stanoveném termínu a kvalitě buď s nasazením přesčasů nebo dokonce kooperací v jiném podniku, je v malých a středních podnicích do 250 zaměstnanců jen obtížně zjistitelné v důsledku nízké úrovně normativní základny TPV a nepřesné nebo chybějící kapacitní bilance kritických etap TPV.After the privatization of industrial enterprises, many qualified workers left for better-paid jobs to foreign companies, and as a result, the level of normative basis for critical stages of TPVs often dropped and the TPV stages scheduling was often carried out without a capacity balance of TPVs. In these circumstances, the feasibility of TPVs and annual innovation programs constructed in this way has been and is still inaccurate and uncertain. In particular, the accurate identification of time and capacity constraints that determine the feasibility of product innovation within a set deadline and quality, either with overtime or even collaboration in another enterprise, is difficult to detect in small and medium-sized enterprises with up to 250 employees. and inaccurate or missing capacity balances of critical stages of TPV.

U větších podniků nad 250 zaměstnanců, kde byly zavedené komplexní systémy řízení výroby, se průchodnost předvýrobními kritickými etapami TPV nezjišťuje buď vůbec nebo jen nepřesně, takže rizika neplnění termínů i kvality inovovaných výrobků se zamlžují a to následně vede ke značným ztrátám na zisku, neplnění smluvních podmínek nebo dokonce k bankrotům průmyslových podniků. Pokud se vůbec kapacitní bilance provádí pak obvykle lokálně za celkovou kapacitu TPV, což nezajišťuje průchodnost kritickými etapami na konci cyklu TPV.For larger enterprises with more than 250 employees, where comprehensive production management systems have been implemented, the throughput of pre-production critical stages of TPV is not determined at all or only inaccurately, so the risks of non-fulfillment of deadlines and quality of innovated products become blurred. or even bankruptcy of industrial enterprises. If the capacity balance is performed at all then it is usually locally for the total capacity of the TPV, which does not ensure throughput through the critical stages at the end of the TPV cycle.

-3 Základním cílem inovace řízení TPV včetně fáze transferu technologií je podstatně zvýšit přesnost kvantifikace skutečných zdrojů reálné kapacity R určené a vyčleněné pro inovace výrobků a technologií a to především ve třech kritických etapách na konci cyklu TPV, kde dochází nejčastěji k přetížení, disproporcím a napětí mezi reálnou podnikovou kapacitou R a požadovanými kapacitními zdroji P pro plnění termínu a kvality zakázek.-3 The basic objective of TPV management innovation, including the technology transfer phase, is to significantly increase the accuracy of quantification of the actual R capacity resources designed and earmarked for product and technology innovation, especially in the three critical stages at the end of the TPV cycle where congestion, disproportions and stress are most common. between the real business capacity R and the required capacity resources P to meet the deadline and quality of orders.

Jako příklad z konkrétní podnikové praxe lze uvést statisticky zjištěné následující hodnoty:As an example of a particular business practice, the following values can be found:

1. Zpracování Tg postupů vč. THN: Ri = 0,4 Tx 1. Processing of Tg procedures incl. THN: R 1 = 0.4 T x

2. konstrukce spec. nářadí a JÚS R2 = 0,8 T2 2. construction spec. tools and JÚS R 2 = 0.8 T 2

3.. výroba spec. nářadí a JÚS ·. R3 = 0,61 T3 3 .. production spec. tools and JÚS. R 3 = 0.61 T 3

Tímto opatřením se podstatně zvýšila přesnost určení skutečných limitujících faktorů kapacitních bilancí, zejména u kritických etap na konci cyklu TPV a zejména ve fázi transferu technologií.This measure has significantly improved the accuracy of the determination of the actual limiting factors of capacity balances, especially for the critical stages at the end of the TPV cycle and in particular in the technology transfer phase.

Rovněž zakázkami a inovacemi požadované kapacitní zdroje P prošly náročnou zpřesňující specifikací na základě klasifikace a třídění nově konstruovaných součástí a speciálních nástrojů i JUS do skupin dle konstrukčně - technologické složitosti byly vytvořeny soubory nej častěji používaných hodnotových rozměrů, t j. soustav, hodnotových kalibrů a impulsů, sestavených do matice hodnotové - normativní a odpovídající matice množstevní, tj. soustava četnosti hodnotových impulsů.Also, the required capacity sources P have undergone demanding specification specifications based on the classification and sorting of newly designed components and special tools and JUS into groups according to the construction-technological complexity. The sets of the most frequently used value dimensions, ie systems, value gauges and impulses , compiled into a value matrix - normative and corresponding quantity matrix, ie a system of frequency of value pulses.

-4Výběr správných hodnot a pronásobením obou matic provedené a automatizované minipočítačem umožnily identifikovat i kvantifikovat neviditelné a nehmotné časové a kapacitní disproporce, sestavit jejich průběh v ročním cyklu pomocí minipočítače, eventuálně v tištěné podobě jako technická dokumentace.-4The selection of correct values and multiplication of both matrices made and automated by the minicomputer enabled to identify and quantify invisible and intangible time and capacity disproportions, to compile their course in an annual cycle using a minicomputer, possibly in printed form as technical documentation.

Navíc takto již přesně identifikované a změřené disproporce je možné automatizovaně s využitím minipočítače korigovat a regulovat interaktivními změnami a to obvykle bez nároku na kapacitní nebo finanční zdroje.In addition, such precisely identified and measured disproportions can be automatically corrected and controlled by means of a minicomputer by interactive changes, usually without the need for capacity or financial resources.

Podstata technického řešeníThe essence of the technical solution

V počáteční výchozí fázi zavádění řízení systému TPV funguje první stupeň inovace analogicky jako automatizovaný mikrometr, který pomocí programovatelných funkcí minipočítače automatizuje cyklus vyhledávání, třídění a řazení hodnotových impulsů a po zjištění četnosti jejich výskytu provádí změření a sumarizaci naměřených hodnot a následnou kvantifikaci a zobrazení průběhu disproporcí v ročním cyklu. Automatizovaně prováděné interaktivní změny regulují disproporce a zachovávají stav rovnováhy a adaptivity v přípravné i realizační fázi hmotných, tj. technických systémů.In the initial initial phase of TPV control implementation, the first stage of innovation works analogously to an automated micrometer, which uses programmable minicomputer functions to automate the cycle of searching, sorting and sorting value pulses and measuring and summarizing the measured values. in the annual cycle. Automatically implemented interactive changes regulate disproportions and maintain the state of equilibrium and adaptivity in the preparatory and implementation phases of tangible, ie technical systems.

Uvedená metoda automatizované regulace interaktivními změnami umožňuje korigovat přetížení a disproporce preventivně ještě před tím, než včas zjištěné a změřené disproporce způsobí ztráty anebo vznik skrytých vad ve hmotném výrobním procesu, tj . obrábění, tváření, montáž apod., zejména nedostatečnou vybaveností výroby speciálními nástroji, JÚS a mechanizačními prostředky pro operační a mezioperační manipulaci, jako jsou upínače, nakladače, zásobníky, válečkové tratě apod. A právěThis method of automated control by interactive changes makes it possible to prevent overloads and disproportions preventively before timely detected and measured disproportions cause losses or hidden defects in the material production process, ie. machining, forming, assembly, etc., especially inadequate production equipment with special tools, JÚS and mechanization means for operational and in-operation handling, such as clamps, loaders, magazines, roller tracks, etc. And just

-5• · • 4 ·· · · 4 • · ··· uvedené zpřesnění výpočtu a zviditelnění i změření hodnot požadovaných, reálných a teoretických P,R,T a následně i průběhu napětí P/R umožňuje korigování disproporcí preventivně v tzv. inkubační době, což je jednou ze základních výhod ve srovnání s dosavadním stavem regulace a řízení TPV zejména ve fázi transferu technologie.-5 • · • 4 · · · · 4 · · ··· specified precision of calculation and visibility and measurement of required, real and theoretical P, R, T and consequently also the course of P / R voltage allows correction of disproportions preventively in so-called incubation This is one of the basic advantages compared to the current state of TPV regulation and control, especially in the technology transfer phase.

Hlavním přínosem řešení je možnost včas a přesně identifikovat změřit a diagnostikovat výskyt časových, kapacitních a hodnotových disproporcí v technické přípravě výroby TPV se zaměřením na fázi transferu technologií. Zároveň zjištěnou, lokalizovanou, kvantifikovanou a zobrazenou disproporcí, která je v TPV obvykle nehmotná, neviditelná a těžko zjistitelná, automatizovaně, rychle, přesně a efektivně regulovat.The main benefit of the solution is the possibility to identify in time and accurately measure and diagnose the occurrence of time, capacity and value disproportions in the technical preparation of TPV production with a focus on the technology transfer phase. At the same time, the detected, localized, quantified and depicted disproportion, which in TPV is usually intangible, invisible and difficult to detect, automated, fast, accurate and effective.

Uvedené systémové řešení umožňuje kombinaci interaktivní regulace s automatickým adaptivním seřízením optimálního stavu rovnováhy na kritické cestě TPV zejména u nejčastěji přetěžovaných kritických etap na konci cyklu TPV a volbu optimální metody regulace s ohledem na typ a stupeň disproporce.This system solution enables the combination of interactive control with automatic adaptive adjustment of the optimal equilibrium state on the critical TPV path, especially for the most overloaded critical stages at the end of the TPV cycle and selection of the optimal control method with respect to the type and degree of disproportion.

sníženou kvalitou výrobků a z tohoreduced product quality and from that

Právě včasná a preventivní identifikace typu disproporce a přesná kvantifikace stupně disproporce umožňuje správné řazení regulačních opatření a časově, kapacitně a hodnotově chránit podnik před neplněním termínu zakázky, zakázky a skrytými vadami inovovaných plynoucími důsledky jako ztráty adaptibility podniku v důsledku přetížení předvýrobní fáze, ztráty úvěru u banky, ztráty dobrých partnerů a odběratelů nebo i bankrotem. Systémová integrace a řízení předvýrobní fáze zejména v oblasti transferu technologií předchází riziku „inverzního efektu ztrát inverzního • φ φ φ φ φ φφφφ φ φφ • φφφ φφ φIt is precisely the timely and preventive identification of the type of disproportion and the precise quantification of the degree of disproportion that enables the correct ordering of regulatory measures and time, capacity and value protection to protect the company against the deadline of the contract, the contract and hidden banks, loss of good partners and customers or even bankruptcy. System integration and pre-production phase management, especially in the field of technology transfer, prevents the risk of the “inverse effect of the loss of inverse • • • • • • • • • • • • • • • • • • •

-6v důsledku neprůchodnosti na kritické cestě TPV způsobené nehmotnými nebo jen obtížně zjistitelnými disproporcemi ve srovnání s disproporcemi v hmotné výrobní sféře.-6 due to obstruction on the critical path of TPV caused by intangible or hard to detect disproportions compared to disproportions in the material manufacturing sphere.

Proto je zde větší riziko zneužití nekalou konkurencí a právě z těchto důvodů navrhovaný systém integrace řízení TPV podstatně zvyšuje finanční a ekonomickou bezpečnost. AVDRS umožňuje kvalifikovaný výběr i spolehlivé partnerství zejména exportujících podniků se zahraničními podniky především v EU a v případě potřeby zahraničního partnera umožňuje zkrátit průběžnou dobu i termíny zakázky v předvýrobní fázi až na jednu polovinu.Therefore, there is a greater risk of abuse by unfair competition and it is for these reasons that the proposed TPV management integration system significantly increases financial and economic security. AVDRS enables qualified selection as well as reliable partnership of mainly exporting companies with foreign companies mainly in the EU and in case of need of foreign partner it is possible to shorten the lead time and order dates in the pre-production phase up to one half.

V období vstupu nových států do EU, zejména u exportujících podniků a v bankovní úvěrové sféře, je AVDRS přesným a rychlým zdrojem číselných hodnot a informací o schopnosti vývozce dostát svým závazkům ze smlouvy o vývozu. AVDRS především z pohledu eliminace rizik v předvýrobní a předexportní fázi zabezpečuje průběh celé zakázky kritickými místy a zejména u malých středních podniků pomáhá zvýšit finanční a ekonomickou bezpečnost v nejrizikovějších článcích řetězce na sebe navazujících etap realizace vývozního případu zakončeného vývozem zboží.At the time of the accession of new states to the EU, especially in exporting companies and in the banking credit sector, AVDRS is an accurate and fast source of numerical values and information on the exporter's ability to meet its obligations under the export contract. AVDRS, especially from the point of view of risk elimination in the pre-production and pre-export phases, ensures the entire order process through critical points and helps to increase financial and economic security in the most risky links of the chain.

Elementární vertikální integrace umožňuje lokalizaci, identifikaci, zobrazení, kvantifikaci a regulaci neviditelných, nehmotných a neelektrických odchylek a disproporcí i určení stupně přetížení a realizaci odpovídajících technických a organizačních opatření k uvedení systému do rovnováhy nebo alespoň do adaptivního stavu systému a průchodnosti kritickými etapami na kritické cestě TPV.Elemental vertical integration enables the localization, identification, display, quantification and control of invisible, intangible and non-electrical deviations and disproportions, as well as determining the degree of congestion and implementing appropriate technical and organizational measures to balance the system or at least adaptive state of the system and TPV.

•· ·· 9 · ··· • · · · · · ·· 9 9 9• 9 9 9

9 9 9 9 9 9 9 99 9 9 9 9

9999 9 · ·· ····· • · · · 9 · · ···· ·· ··· ··« ·· «9999 9 · ····································

-7Horizontální integrace funguje jako pružné propojení přípravné a realizační fáze technologické přípravy výroby TgPV, konstrukční přípravy výroby KPV, materiálně technického zabezpečení MTZ a náběhu nových výrob NNV pouhým rozšířením a odladěním vstupních dat horizontálně propojených modulů - fází etap TPV, TgPV (Ml), KPV (M2), MTZ (M3) a NNV (M4) .-7Horizontal integration works as a flexible interconnection of the preparatory and realization phase of technological preparation of TgPV production, construction preparation of KPV production, material technical support of MTZ and start of new LV production by simply expanding and debugging input data of horizontally connected modules (M2), MTZ (M3), and NNV (M4).

Kombinací elementární vertikální integrace a zvoleného rozsahu horizontální integrace TgPV, KPV, MTZ a NNV se zaměřuje na korigování disproporcí v předvýrobní fázi a ztrát ve výrobní fázi především hodnotových a to ještě před jejich zhmotněním a vznikem jak v předvýrobní tak i výrobní fázi, čímž se korigují preventivně značné ztráty ještě před vznikem přetížení výrobní fáze a to především interaktivními změnami bez zvýšení nároků na technické a finanční zdroje optimalizací využití stávajících zdrojů a kapacit.Combining elementary vertical integration and a selected range of horizontal integration TgPV, KPV, MTZ and NNV focuses on correcting disproportions in the pre-production phase and losses in the production phase, especially value, before their materialization and formation in both pre-production and production phase, thereby correcting preventively significant losses before the overload of the production phase, mainly through interactive changes without increasing the demand for technical and financial resources by optimizing the use of existing resources and capacities.

Uvedené technické řešení umožňuje preventivně a ještě v předstihu realizovat technická i organizační regulační opatření s ohledem na zjištěný stupeň odchylky. Výše úspor v prvním roce zavedení se odhaduje na 5 % roční výroby zboží.The above-mentioned technical solution enables preventive and even in advance implementation of technical and organizational regulatory measures with regard to the detected degree of deviation. The savings in the first year of introduction are estimated at 5% of annual production of goods.

V bankovní i podnikové praxi v návaznosti na mezinárodní normy jakosti uvedený systém umožňuje ještě před navázáním smluvních vztahů prokázat způsobilost ke splnění hlavních smluvních podmínek, kterými jsou termín zakázky i kvalita včetně dohodnutých technických parametrů.In banking and business practice, in relation to international quality standards, the system enables to prove the ability to fulfill the main contractual conditions, which are the contract term and quality, including agreed technical parameters, before establishing contractual relations.

Přehled obrázků na výkresechBRIEF DESCRIPTION OF THE DRAWINGS

Vynález bude podrobněji popsán na příkladech konkrétního provedení s pomocí přiložených výkresů, kde je na obr. 1 je znázorněno schéma realizačního modelu, na obr. 2 je znázorněnoBRIEF DESCRIPTION OF THE DRAWINGS The invention will now be described in more detail by way of example with reference to the accompanying drawings, in which: Figure 1 shows a schematic of an implementation model;

-8schéma funkčního a informačního propojení a na obr. 3 a 4 jsou znázorněna schéma zapojení systému.Fig. 3 is a schematic diagram of the functional and information interconnection; and Figs.

Příklady provedení technického řešeníExamples of technical solution

Příklad 1Example 1

Postupná realizace přímo ve výrobním podniku, přičemž průběžná doba realizace je 6 měsíců až 3 roky, dle rozsahu řešení.Gradual realization directly in the manufacturing company, with a continuous realization period of 6 months to 3 years, depending on the scope of the solution.

Řešení bude popsáno na příkladném podniku střední velikosti bez pobočných závodů s vlastní výzkumně - vývojovou základnou, který je výrobcem textilních strojů. Maloprůměrové textilní stroje se dělí do řady typů, které se dále člení na jednotlivé typorozměry dle velikosti a dle jemnosti úpletu. Tím je určen i typ výroby, kterou lze charakterizovat jako malosériovou nepravidelně opakovanou, přičemž velikost výrobních sérií se pohybuje od 10 do 160 ks. Z hlediska inovačního tempa lze hovořit o průměrně čtyřech ověřovacích sériích nových typů textilních strojů ročně. Hmotnost kompletního stroje, který je sestaven asi ze tří tisíc vyráběných a nakupovaných dílců, se pohybuje v rozmezí od 200 do 400 kg.The solution will be described in an exemplary medium-sized enterprise without branch plants with its own R&D base, which is a manufacturer of textile machines. Small diameter textile machines are divided into a number of types, which are further subdivided into individual types according to the size and fineness of the fabric. This also determines the type of production, which can be characterized as small-series irregularly repeated, while the size of production series ranges from 10 to 160 pieces. In terms of innovation pace, we can speak of an average of four verification series of new types of textile machines per year. The weight of the complete machine, which consists of about three thousand manufactured and purchased parts, ranges from 200 to 400 kg.

Útvar technické přípravy výroby je součástí technického úseku a zabezpečuje technologickou přípravu výroby, včetně výroby a hospodaření nářadím, podle konstrukční dokumentace převzaté z úseku pro rozvoj techniky. Plánování TPV je prováděno na základě inovačního programu a plánu výroby. Vzhledem k nestabilitě požadavků na sortiment textilních strojů je detailně zpracováván pouze roční plán TPV. Kapacitní bilancování je prováděno jen u kritických etap, které rozhodujícím způsobem ovlivňují průběžnou dobu technologické • · · · · · · · * • ··· · · · · · · ···» • · · · · · · ···· ·· ··· ··· ·· ·The Technical Production Preparation Unit is a part of the Technical Department and provides technological preparation of production, including production and tool management, according to the design documentation taken from the Technical Development Department. TPV planning is carried out on the basis of an innovative program and a production plan. Due to the instability of requirements for the assortment of textile machines, only the annual TPV plan is elaborated in detail. Capacitive balancing is only carried out at critical stages that have a decisive impact on the continuous technological time. · · · ··· · · · · · ··· · · · · · · · ·· ··· ··· ·· ·

-9přípravy výroby. V podmínkách konkrétního podniku jsou to tyto kritické etapy: technologické postupy součástí včetně THN, konstrukce speciálního nářadí a výroba speciálního nářadí.-9Preparation production. In the conditions of a particular company these are the following critical stages: technological procedures of components including THN, construction of special tools and production of special tools.

Základním předpokladem pro sestavení plánu a bilancování kapacit jsou normativy pracnosti výše uvedených kritických etap TPV, které byly stanoveny rozborem a vhodným tříděním údajů obsažených v dosavadní evidenci. Normativy pracnosti technologických postupů udávají průměrnou pracnost zpracování technologického postupu, včetně stanovení THN-Materiálové a THN-Výkonové v hodinách pro tři skupiny součásti a tři třídy jejich složitosti. Normativy pracnosti konstrukce speciálního nářadí udávají průměrnou pracnost zpracování konstrukční dokumentace v hodinách na druh speciálního nářadí v členění na 5 skupin a 3 třídy složitosti. Obdobně jsou stanoveny normativy pracnosti výroby speciálního nářadí s tím, že normativní hodnoty jsou uváděny v normohodinách na kus speciálního nářadí.The basic prerequisite for drawing up the plan and balancing capacities are the labor intensive norms of the above-mentioned critical stages of TPV, which were determined by analysis and appropriate sorting of data contained in the existing records. Technological workmanship standards specify the average workmanship workmanship, including the determination of THN-Material and THN-Power in hours for three component groups and three classes of complexity. Standards of labor intensive construction of special tools indicate the average labor intensive of design documentation in hours per kind of special tool divided into 5 groups and 3 complexity classes. Similarly, norms of labor intensive production of special tools are set, with normative values given in norm-hours per piece of special tools.

Neméně důležité je stanovení disponibilních zdrojů, které jsou pro bilancování etapy TPV k dispozici. Základem je teoretická disponibilní kapacita, která je dána plánovaným počtem pracovníků zabezpečujících danou etapu s efektivním fondem pracovníka, přičemž rozdělení kapacity do jednotlivých měsíců je prováděno dle plánovacího kalendáře.Equally important is the determination of the available resources available for balancing the TPV stage. The basis is the theoretical available capacity, which is given by the planned number of employees providing the given stage with an effective employee fund, while the allocation of capacity into individual months is carried out according to the planning calendar.

Reálná disponibilní kapacita R je určena podílem z teoretické kapacity T, který byl dle dosavadního statistického sledování ve vybraném podniku stanoven takto: Technologické postupy součástí Ri - 0,43 TiThe real available capacity R is determined by the ratio of the theoretical capacity T, which was determined according to the previous statistical monitoring in the selected company as follows: Technological procedures of components Ri - 0,43 Ti

Konstrukce speciálního nářadí R2 - 0,80 T2 Design of special tools R 2 - 0,80 T 2

Výroba speciálního nářadí R3 - 0,61 T3 • 9 • 99 • 999 ··· · ··Production of special tools R 3 - 0,61 T 3 • 9 • 99 • 999 ··· · ··

-10Teoretické disponibilní kapacity, přičemž zbytková kapacita je určena na zajišťování ostatních úkolů. Vlastní zpracování ročního lhůtového plánu TPV s kapacitní bilancí je prováděno na stolním počítači.-10Theoretical available capacities, with residual capacity dedicated to other tasks. The actual elaboration of the annual schedule of TPV with a capacity balance is performed on a desktop computer.

Příprava vstupních dat, které zahrnují informace o věcných úkolech kritických etap TPV a jejich termínovém zajištění jsou získávány následovně. Věcné úkoly TPV jsou převzaty z plánu TPV a upřesňovány při konstrukčně technologických prověrkách. Úkoly technologické obsluhy výroby jsou kvalifikovány na základě statistických údajů. Pro jednotlivé plánované etapy TPV jsou použity následující plánovací jednice. Technologické postupy součástí - počet součástí - počet součástí vyráběných, konstrukce speciálního nářadí - počet druhů speciálního nářadí, výroba speciálního nářadí. Požadované termíny realizace úkolů TPV jsou převzaty z lhůtového plánu výroby a na základě zkušeností je proveden návrh na zahájení a ukončení jednotlivých etap. Uvedená data jsou zaznamenávána do univerzálního formuláře dle jednotlivých úkolů, čímž je vytvořena stavebnicová organizace vstupních dat umožňující jejich rychlou přípravu při změně plánu.The preparation of input data, which includes information on the material tasks of the critical stages of the TPV and their timing is obtained as follows. Substantive tasks of TPV are taken over from the TPV plan and specified during construction-technological checks. The tasks of the technological service of production are qualified on the basis of statistical data. The following planning units are used for individual planned stages of TPV. Technological procedures of parts - number of parts - number of parts produced, construction of special tools - number of types of special tools, production of special tools. The required deadlines for the implementation of TPV tasks are taken from the production schedule and based on experience, a proposal is made to start and end individual stages. These data are recorded in a universal form according to individual tasks, which creates a modular organization of input data allowing their rapid preparation when changing plans.

Po zadání vstupních dat a jejich případné úpravě se provede vlastní kapacitní propočet s tím, že na displeji se zobrazí rozpory mezi požadovanou a reálnou kapacitou v jednotlivých měsících, vyjádřené v procentech. Zde má uživatel možnost rozhodnout, zda navržený plán vyhovuje nebo ne. Pokud je plán nevyhovující, tj . kapacitní rozpory jsou příliš vysoké, může uživatel provést korekce přesouváním začátků i konců časových úseček jednotlivých úkolů. Potom se znovu provede kapacitní propočet a výstup nových hodnot na displeji. Jakmile je vytvořen vyhovující plán, vytiskne se na tiskárně tisková sestava plánu TPV.After entering the input data and eventually adjusting it, the actual capacity calculation is performed with the display showing the discrepancies between the required and real capacity in individual months, expressed as a percentage. Here, the user has the option to decide whether the proposed plan fits or not. If the plan is unsatisfactory, ie. the capacity discrepancies are too high, the user can make corrections by shifting the start and end times of individual tasks. Then the capacitive calculation and the new values are displayed again. Once a satisfactory layout has been created, a TPV layout report is printed to the printer.

·«· ·· 9 9 99 · « 9 9 9 99 · 9 9 99· «9 9 99 ·« 9 9 9 99 · 9 9 99

999 9 9 9999999 9 9 9999

9999 9 9 99 · ···9999 9 9 99 · ···

9 9 9 9 9 99 9 9 9 9

9999 99 999 999 99 99999 99 999 999 99

-11 Tisk plánu TPV je prováděn pro každou kritickou etapu TPV odděleně na třech listech. Obsahuje tisk vstupních dat a dále výstupní údaje v následujícím uspořádání: úsečkový plán dané etapy TPV, grafické znázornění porovnání požadované, reálné a teoretické kapacity v jednotlivých měsících a za rok, s výpisem použitých normativů přednosti.-11 Printing of the TPV plan is performed for each critical stage of the TPV separately on three sheets. It includes printing of input data and output data in the following arrangement: a line plan of the given TPV stage, a graphical representation of the comparison of required, real and theoretical capacity in individual months and per year, with a listing of used normatives of priority.

Takto zpracované tiskové sestavy obdrží vedoucí zabezpečující příslušné etapy, dále plánovač TPV s vedoucí útvaru TPV.The press reports prepared in this way will be received by the head of the relevant stages, as well as the TPV planner with the head of the TPV department.

Běžná kontrola plnění plánu je prováděna na pravidelných dispečincích TPV jednou týdně ve fyzických jednotkách plánovacích jednicích - dle jednotlivých úkolů. Jednou měsíčně je dispečink spojen s vykazováním skutečně dosažených výsledků v plánovacích jednicích, odpracovaných hodinách celkem a na plánovaných úkolech v členění dle skupin a tříd složitosti bez ohledu na jednotlivé úkoly. Vykazování je prováděno na univerzálním formuláři, který je rovněž používán pro zápis vstupních dat.Routine checking of plan fulfillment is performed at regular TPV control rooms once a week in physical units of planning units - according to individual tasks. Once a month, the dispatching center is associated with reporting the actual results in planning units, hours worked in total and planned tasks broken down by groups and complexity classes regardless of individual tasks. Reporting is performed on a universal form that is also used to write input data.

Při kontrole plnění plánu přistupuje aktualizace plánu na základě skutečně dosahovaných výsledků. Aktualizace plánu TPV je rovněž prováděna při každé významné změně plánu TPV a plánu výroby. Aktualizace normativů a disponibilních kapacit je prováděna lx ročně na základě souboru měsíčních výkazů a plánu práce.When reviewing plan fulfillment, the plan update is based on actual results. The TPV plan update is also performed whenever a significant change to the TPV plan and production plan is made. Norms and available capacities are updated once a year on the basis of a set of monthly statements and a work plan.

I když popsaná metoda je spojena se zjednodušením celé problematiky, přináší podstatné zpřesnění plánu TPV » a v nejdůležitějších kritických etapách se odhalují se značnou ·Although the method described is connected with simplification of the whole issue, it brings a substantial refinement of the TPV plan »and in the most important critical phases they reveal a considerable ·

9 ··· 9 »9 ··· 9 »

* 9 · • 9 9 9* 9 · 9 9 9

9 9 9999 • · · ·· 4 přesností úzká místa jak z hlediska věcného tak časového v předstihu až jednoho roku.9 9 9999 • · · ·· 4 accuracy of the bottlenecks, both factually and temporally, up to one year ahead.

Dalším přínosem je rychlost zpracování plánu TPV při změnách programu inovací a plánu výroby, ke kterým při výrobě textilních strojů často dochází. Nový roční plán TPV dle popsané metody lze zpracovat prakticky v jedné směně, kdy změnu vstupních dat díky jejich stavebnicovému uspořádání lze zpracovat asi za 8 hodin a vlastní sestavení plánu na počítači včetně úpravy úseček interaktivním způsobem a tisku v průběhu jedné hodiny.Another benefit is the speed with which the TPV is processed in the case of changes to the innovation program and production plan, which often occur in the manufacture of textile machinery. The new annual TPV plan according to the described method can be processed in practically one shift, when the change of input data due to their modular arrangement can be processed in about 8 hours and the actual compilation of the plan on the computer, including editing lines in an interactive way and printing in one hour.

Zpřesnění plánu TPV a možnost jeho rychlé aktualizace umožňují účinnější regulaci průběhu technické přípravy výroby. Celý systém plánování a aktualizace normativní základny včetně ověřování reálných kapacit na základě vykazování skutečných výsledků vede k trvalému zpřesňování výchozí základny a tím i p1ánování TPV.The refinement of the TPV plan and the possibility of its rapid update allow more efficient regulation of the technical preparation process. The whole system of planning and updating of the normative base, including the verification of real capacities based on the reporting of actual results, leads to a permanent refinement of the starting base and thus the planning of TPV.

Příklad 2Example 2

Realizace prvního stupně automatizovaného vícemodulárního regulačního a řídícího systému ve fázi transferu technologií metodou na klíč, přičemž průběžná doba realizace je 2 až 4 týdny po dodání výchozího souboru informací.Implementation of the first stage of an automated multi-module control and regulation system in the turn-key technology transfer phase, with an ongoing implementation time of 2 to 4 weeks after delivery of the initial set of information.

Řešení formou na klíč bude popsáno na příkladu strojírenského podniku do 250 zaměstnanců, který je výrobcem motocyklů vyráběných z 80 % na export s inovačním cyklem 3 až 5 měsíců.The turnkey solution will be described on the example of an engineering company with up to 250 employees, which is the manufacturer of motorcycles produced 80% for export with an innovation cycle of 3 to 5 months.

Jednotlivé realizační kroky a činnosti byly provedeny v následujícím pořadí:The individual implementation steps and activities were carried out in the following order:

• ··· 4• ··· 4

44

4444 444444 44

-13všeobecná konstrukčně - technologická charakteristika výroby a výrobků, úrovně jejich technické vybavenosti a výběr typových představitelů;-13General structural and technological characteristics of production and products, level of their technical equipment and selection of type representatives;

vytvoření a doplnění souborů normativních hodnot pro kritické etapy v rámci stávající normativní základny; sestavení výchozího souboru vstupních dat;the creation and completion of sets of normative values for the critical stages within the existing normative base; building a default input data set;

instalace softwarového vybavení AVDRS do podnikového počítače;installing AVDRS software on a corporate computer;

seřízení softwarového vybavení AVDRS na vstupní data a limitující faktory podniku;adjusting AVDRS software to input data and business constraints;

automatizované vytištění protokolů o způsobilosti PZ pro kritické etapy TgPV včetně transferu technologií a plánovací dokumentace plánu TgPV včetně nářaďovny v ročním průběhu programu inovací a to v následujícím členění:automated printing of protocols on the eligibility of PZ for critical stages of TgPV including technology transfer and planning documentation of the TgPV plan including tools in the annual course of the innovation program as follows:

1. technologické postupy včetně THN, protokol o způsobilosti PZ-1, technologický postup TP;1. technological procedures including THN, PZ-1 eligibility protocol, TP technological procedure;

2. konstrukce speciálního nářadí včetně JÚS, protokol o způsobilostí PZ-2, kontrola nářadí KN;2. construction of special tools including JÚS, certificate of competence PZ-2, inspection of KN tools;

3. nářaďovna, výroba speciálního nářadí včetně JÚS, protokol o způsobilosti PZ-3, výroba nářadí VN.3rd tool shop, production of special tools including JÚS, certificate of competence PZ-3, production tools HV.

Přičemž všechny obsahují lhůtový diagram ročního plánu, kapacitní bilanci hodnot P,R,T a histogram kapacit P,R,T;All of which contain a time schedule of the annual plan, a capacity balance of P, R, T values and a histogram of P, R, T capacities;

návrh a provedení interaktivních změn IZ;design and implementation of interactive changes to IT;

přezkoušení a ověření přesnosti i funkčnosti automatizovaně zpracovaných dokladů, dokumentace a hodnot; předání podnikového počítače zpět do realizačního podniku a zaškolení obsluhy na instalované softwarové vybavení AVDRS;testing and verifying the accuracy and functionality of automated documents, documentation and values; handing over the company computer back to the implementation company and training the staff on the installed AVDRS software;

vyhodnocení funkčnosti a přesnosti AVDRS v provozních podmínkách, včetně návrhu na opatření a závěry i reference včetně začlenění AVDRS do stávající organizace a řízení podniku.evaluation of the functionality and accuracy of AVDRS in operational conditions, including design of measures and conclusions as well as references, including the incorporation of AVDRS into existing organization and business management.

-14Pracovníci realizačního podniku se podíleli na zavedení AVDRS v následující krocích a činnostech: spolupráce na sestavení výchozího souboru informací pro AVDRS, zajištění a provedení začlenění AVDRS do stávajícího systému řízení podniku, provedení zkoušení, ověřování a testování funkčnosti a přesnosti výsledků AVDRS v provozních podmínkách a průběžně 3 až 6 měsíců po zavedení AVDRS zpřesňovali a odlaďovali výchozí soubor vstupních dat a normativní základnu podniku.-14 Implementing company staff participated in the implementation of AVDRS in the following steps and activities: collaboration to build the default AVDRS information set, ensuring and implementing the integration of AVDRS into the existing business management system, testing, verifying and testing the functionality and accuracy of AVDRS results in operating conditions; continuously 3 to 6 months after the introduction of AVDRS, they refined and tuned the initial set of input data and the normative base of the company.

Průmyslová využitelnostIndustrial applicability

Způsob automatizované vícemodulární regulace přípravné fáze výroby včetně diagnostiky podle tohoto vynálezu nalezne uplatnění zejména u menších a středních výrobních podniků.The method of automated multi-module control of the pre-production stage including diagnostics according to the present invention will find application especially in small and medium-sized production companies.

Ty Ί-tsvYou Ί-tsv

Claims (4)

PATENTOVÉ NÁROKYPATENT CLAIMS 1. Způsob automatizované vícemodulární regulace přípravné fáze výroby včetně diagnostiky, vyznačující se tím, že se vytvoří normativy a kvantitativní hodnoty technologických postupů, konstrukce nářadí a výroby nářadí, poté se vytvoří soubor vstupních dat technologických postupů, konstrukce nářadí a výroby nářadí načež se provádí identifikace, lokalizace, registrace a kvantifikace časových, kapacitních a hodnotových disproporcí, které se dále zobrazují a korigují a regulují interaktivními změnami.1. A method of automated multi-module control of the preparatory stage of production, including diagnostics, characterized in that normative and quantitative values of technological processes, tool design and tool manufacturing are created, then a set of input data of technological processes, tool design and tool manufacturing is generated. , localization, registration and quantification of time, capacity and value disproportions, which are further displayed and corrected and regulated by interactive changes. 2. Způsob podle nároku 1, vyznačující se tím, že kvantifikace disproporcí se provádí sčítáním hodnotových impulsů sestavených v normativní matici a výrobkové matici.Method according to claim 1, characterized in that the quantification of the disproportions is performed by summing the value pulses assembled in the normative matrix and the product matrix. 3. Systém k provádění způsobu podle kteréhokoli z výše uvedených nároků, sestávající z jednoho bloku normativní matice a dalšího bloku výrobkové matice, které jsou propojeny s modulární formací histogramu kapacit, přičemž vstup jednoho bloku je připojen k zobrazovací jednotce termínového lhůtového diagramu, vstup dalšího bloku je připojen k bloku s inovačním programem a/nebo průběhem zakázek a výstup z modulární formace histogramu kapacit je připojen k porovnávacímu modulárnímu členu prvku požadované kapacity P a reálné kapacity R, vyznačující se tím, že je k němu připojen blok technologické přípravy výroby a/nebo blok konstrukční přípravy výroby.A system for carrying out the method according to any of the above claims, consisting of one normative matrix block and another product matrix block that are connected to a modular capacity histogram formation, wherein the input of one block is connected to the term time chart display unit, the input of another block is connected to a block with an innovative program and / or order flow and the output of the modular capacity histogram formation is connected to a comparator modular member of the required capacity P element and the real capacity R, characterized by being connected to the technological preparation block and / or block of structural preparation of production. 4. Systém podle nároku 3, vyznačující se tím, že je k němu připojen blok materiálně technického zabezpečení a/nebo blok náběhu nové výroby.System according to claim 3, characterized in that a material-security block and / or a new production start-up block is connected thereto. •· · · · ···· • ··· · · · · · · ···· • · · · · · · ···· «· ··· ··· ·· ·· · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · · - 165. Systém podle nároku 3 nebo 4, vyznačující se tím, že modulární formace histogramu zakázek obsahuje kapacitní bilanci a k výstupu porovnávacího modulárního členu je připojen optimalizační člen pro automatické seřízení rovnováhy systému na jeho kritické cestě.The system of claim 3 or 4, wherein the modular order histogram formation comprises a capacity balance and an output of the comparator modular member is coupled to an optimization member for automatically adjusting the system equilibrium on its critical path. • · · · · 1 >0 Xecq ~ 4ÍSV• · · · · 1> 0 Xecq ~ 4SET 9····· • ·9 ····· · · 4/4 « · ··· ·4/4 «· ··· · PZ1P = Průběh zakázek a inovačního programuPZ1P = Progress of orders and innovation program PL « Plánovač TPV, který provádí také interaktivní změnyPL «TPV scheduler, which also makes interactive changes TLD = Terminový lhůtový diagram včetně priorit výrobku a zakázekTLD = Deadline chart including product priorities and orders UPTPV = Úkoly pracovníkům TPVUPTPV = Tasks for TPV staff MM » normativní matice VM « výrobková maticeMM »normative matrix VM« product matrix HK « Histogram kapacitHK «Histogram of capacities P « požadovaná kapa oitaP «required capacity oita
CZ20041154A 2004-11-29 2004-11-29 Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same CZ298013B6 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CZ20041154A CZ298013B6 (en) 2004-11-29 2004-11-29 Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same
CZ200416109U CZ15451U1 (en) 2004-11-29 2004-11-29 System for carrying out automated multi-modular control of manufacture preparation phase including diagnostics

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CZ20041154A CZ298013B6 (en) 2004-11-29 2004-11-29 Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same

Publications (2)

Publication Number Publication Date
CZ20041154A3 true CZ20041154A3 (en) 2006-07-12
CZ298013B6 CZ298013B6 (en) 2007-05-23

Family

ID=34706121

Family Applications (2)

Application Number Title Priority Date Filing Date
CZ200416109U CZ15451U1 (en) 2004-11-29 2004-11-29 System for carrying out automated multi-modular control of manufacture preparation phase including diagnostics
CZ20041154A CZ298013B6 (en) 2004-11-29 2004-11-29 Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CZ200416109U CZ15451U1 (en) 2004-11-29 2004-11-29 System for carrying out automated multi-modular control of manufacture preparation phase including diagnostics

Country Status (1)

Country Link
CZ (2) CZ15451U1 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5469361A (en) * 1991-08-08 1995-11-21 The Board Of Regents Acting For And On Behalf Of The University Of Michigan Generic cell controlling method and apparatus for computer integrated manufacturing system
US5881115A (en) * 1997-11-07 1999-03-09 Cbs Corporation Method and system for automatically executing multiple procedures for a complex process facility
AU1115700A (en) * 1998-10-16 2000-05-08 Iconics, Inc. Process control

Also Published As

Publication number Publication date
CZ298013B6 (en) 2007-05-23
CZ15451U1 (en) 2005-05-30

Similar Documents

Publication Publication Date Title
Wiendahl Load-oriented manufacturing control
Kelley Productivity and information technology: The elusive connection
Liu et al. An integrated production and delay-time based preventive maintenance planning model for a multi-product production system
Liu et al. An integrated preventive maintenance and production planning model with sequence‐dependent setup costs and times
KR100425910B1 (en) Enterprise Resource Planning Method and System for performing original cost control using quality control and productivity control
Facchinetti et al. Application of the overall equipment effectiveness to a service company
KR20150049077A (en) Digital Manufacturing Optimization System for Scenario Simulation and Discovering Bottleneck Processes Based
Portioli‐Staudacher et al. Integrated maintenance and production planning: a model to include rescheduling costs
Starczyk-Kołbyk et al. Use of the EVM method for analysis of extending the construction project duration as a result of realization disturbances-case study
CZ20041154A3 (en) Method of automated multi-modular control of manufacture preparative phase including diagnostics and system for making the same
Müller et al. Simulation based online production planning
Zülch et al. Approach for personnel development planning based on the technology calendar concept
CN115099638A (en) Advanced intelligent APS system applied to papermaking production and control method thereof
Tinh et al. Application of Industrial Engineering Technique for Better Productivity in Garment Industry
Primrose et al. The use of a conceptual model to evaluate financially flexible manufacturing system projects
US20070255605A1 (en) Multi-period financial simulator of a manufacturing operation
Afriansyah et al. Production planning and control system with just in time and lean production: a review
Amira et al. Study of Parameters Influencing the Production and Improvement of the Launch System in a Production Department: Case Study in the Clothing Industry in Tunisia
Leitch et al. Opportunity costing decision heuristics for product acceptance decisions
Wicaksono et al. An Automated Information System for Medium to Short-Term Manpower Capacity Planning in Make-To-Order Manufacturing
Kletti et al. Application Concept–Horizontal and Vertical Integration
Salih et al. The application of six sigma-supported expert system in construction projects
Rema Modeling cost of quality in the construction industry a closer look at the procurement process using system dynamics
Łapuńka et al. Planning production preparation processesusing the critical chain method
CN113627873B (en) Project type enterprise financial moon knot automatic system based on SAP and use method