CS202322B1 - Mine sinking set part. for driving vertical mining workings - Google Patents

Mine sinking set part. for driving vertical mining workings Download PDF

Info

Publication number
CS202322B1
CS202322B1 CS630078A CS630078A CS202322B1 CS 202322 B1 CS202322 B1 CS 202322B1 CS 630078 A CS630078 A CS 630078A CS 630078 A CS630078 A CS 630078A CS 202322 B1 CS202322 B1 CS 202322B1
Authority
CS
Czechoslovakia
Prior art keywords
platform
main
mine
main platform
pillar
Prior art date
Application number
CS630078A
Other languages
Czech (cs)
Inventor
Jindrich Pozivil
Original Assignee
Jindrich Pozivil
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jindrich Pozivil filed Critical Jindrich Pozivil
Priority to CS630078A priority Critical patent/CS202322B1/en
Publication of CS202322B1 publication Critical patent/CS202322B1/en

Links

Description

Vynález řeší důlní hloubící soupravu pro raženi vertikálních důlních děl.The invention provides a mining excavation kit for driving vertical mine workings.

Hloubeni vertikálních důlních děl zahrnuje následující základní procesy: vrtáni horniny a trhači práce, odkliz horniny, těženi horniny, vyztužování a vyatrojování jámy. Každý z těchto procesů je složitým komplexem prací, pro jejichž provedeni je třeba dobrého β bez poruch pracujícího zařizeni.The excavation of vertical mine workings involves the following basic processes: rock drilling and shredding, rock removal, rock mining, pit reinforcement and excavation. Each of these processes is a complex complex of work that requires a good β without the failure of the working equipment.

Pro vrtáni otvorů, určených pro trhači práce při hloubení jam jsou nejobvykleji používána zařizeni známá z vrtání horizontálních důlních děl. Klasickým a nejjednodušším je používání ručních vrtacích zařizeni, která jsou vybavena různými přípravky a doplňky. Mechanizovaná vrtací zařizeni pro hloubeni jam jeou řešena na principech převzatých z mechanizovaného vrtáni chodeb, to je vrtacími lafetami, umístěnými prostřednictvím nosných ramen na závěsném středovém sloupu. Po trhacích procesech jaou na čelbu spuštěna nakládací a odtěžovaci zařizeni.For drilling holes intended for shredders in excavating pits, devices known from horizontal mine workings are most commonly used. The classic and easiest is to use hand drilling equipment, which is equipped with various jigs and accessories. Mechanized drilling equipment for excavation of pits is solved on the principles taken from mechanized drilling of corridors, that is drilling carriages placed by means of supporting arms on the suspension center column. After the blasting processes, the loading and unloading devices are lowered onto the face.

Nevýhodou dosud používaných hloubících zařizeni je především jejich omezená výkonnost, vyplývající z nutnosti střídavě vytahovat a spouštět vrtací a nakládací zařízeni. Závažnou nevýhodou těchto zařizeni je to, že neumožňuji plynule přejit z hloubení jámy plným profilem na hloubeni jámy přibirkou do předraženého důlního díla.The disadvantage of the excavating devices used hitherto is mainly their limited performance, resulting from the necessity to alternately pull and lower the drilling and loading equipment. A serious disadvantage of these devices is that they do not allow for a smooth transition from a full-profile pit to a pit to be over-loaded into an overpriced mine.

Uvedené nedostatky odstraňuje důlní hloubici souprava podle vynálezu. 3eji podetataThese drawbacks are overcome by the mining digging set according to the invention. 3eji podetata

202 322202 322

202 322 spočívá v tom, že pozůstává ze dvou nad sebou umístěných plošin, a to z hlavni plošiny a montážní plošiny. Mezi montážní plošinou a hlavni plošinou je umístěn závěsný pilon, opatřeny na svém horním konci nosným závěsem. Při okraji hlavní plošiny je proveden nejméně jeden hlavni odklápěcí segment a na apodnl straně této hlavni plošiny jeou připevněny vodici dráhy, na kterých jaou zavěšeny přaetavitelně vrtací jednotky. K hlavni plošině může být prostřednictvím dolních stojin připevněna dolní plošina, va které je proveden centrální poklop a při jejím okraji nejméně jeden dolní odklápěcí segment. V závěsném pilonu může byt auvně uloženo rameno drapákového nakladače. V horni čáati závěsného pilonu je uložena pomocná kladka, přes kterou je vedeno lano spojující horni konec ramena drapákového nakladače a vrátkem, připevněným na hlavni plošině. Mezi montážní plošinou a hlavni plošinou můžou být upevněny zpevňovací stojiny. Na hlavni plošině je možno umlátit čerpací agfagát, □ůlnl hloubící souprava podle vynálezu je ucelenou technologickou jednotkou, umožňující provádět vrtáci práce, nakládáni a těženi rozpojené horniny, čerpáni důlních vod, vyetužováni a vystrojováni nově budované důlní jámy. Při tom podstatně ulehčuje fyzickou namahavoat vrtacích prací, zejména při hloubeni jámy přibirkou do předraženého důlního díla. Hloubící souprava umožňuje plynule přejit z hloubeni jámy plným profilem na hloubeni do předraženého důlního díla bez náročných úprav. Hloubíc! souprava umožňuje provádět práce spojené a hloubením ve srovnáni a dosud používanými zařízeními daleko bezpečněji a kulturněji.202 322 consists of two superimposed platforms, the main platform and the assembly platform. Between the mounting platform and the main platform there is a suspension pillar, provided at its upper end with a supporting suspension. At least one main hinged segment is provided at the edge of the main platform and guide tracks are mounted on the lower side of the main platform on which the drilling units are removably hinged. A lower platform can be attached to the main platform by means of lower uprights in which a central hatch is provided and at least one lower hinged segment at its edge. The grab loader arm can be mounted in the lifting pillar. An auxiliary pulley is mounted in the upper part of the suspension pilon, through which a rope connecting the upper end of the grab loader arm and the winch mounted on the main platform is guided. Stiffening struts may be attached between the mounting platform and the main platform. The pumping aggregate according to the invention is a complete technological unit enabling drilling, loading and extraction of uncoupled rock, pumping of mine water, excavation and equipping of a newly built mine pit. In doing so, it makes it much easier for the drilling work to be carried out physically, in particular when excavating a pit with a nail to an overpriced mine. The trenching kit allows for a smooth transition from a full-profile excavation to a overpriced mine without demanding modifications. Hloubíc! the kit makes it possible to carry out the work associated with excavation in a more secure and cultural way compared to the hitherto used equipment.

Na přiloženém výkrese je v podélném řezu důlní jámou schematicky znázorněno příkladné provedeni důlní hloubící soupravy podle vynálezu.In the accompanying drawing, a longitudinal section of a mine pit schematically shows an exemplary embodiment of a mine excavation kit according to the invention.

Důlní hloubící souprava pozůstává za tří nad sebou umístěných plošin 10, 20, 50, a to z hlavni plošiny 10, horni montážní plošiny 20 a dolní plošiny 60. Mezi montážní plošinou 20 a hlavni plošinou 10 je umístěn závěsný pilon 30 opatřený na svém horním konci nosným závěsem 31. Dolní plošina 50 je k hlavni plošině 10 připevněna prostřednictvím dolních stojin 51. Mezi montážní plošinou 20 a hlavni plošinou 10 jsou upevněny zpevňovacl stojiny 21. Všechny plošiny 10, 20, 50 jsou roštové konstrukce. Na apodnl straně hlavní plošiny 10 jsou upraveny vodici dráhy 12, na kterých jsou zavěšeny přaetavitelně vrtací jednotky 40. V horní čáati závěsného pilonu 30 je uložena pomocné kladka 32, přee kterou je vedeno lano 62, spojující horni konec ramena 61 drapákového nakladače 60 a vrátkem 63. připevněným na hlavni plošině 10. Rameno 61 drapákového nakladače 60 je v klidové poloze uloženo v závěsném pilonu 30. Při okraji hlavni plošiny 10 je proveden hlavni odklápěcí segment 11, v dolní plošině 50 ja proveden centrální poklop 53 a při jejím okraji dolní odklápěcí segment 52. Mezi odklápěcími segmenty 11 a 52 může být provedena mechanická vazba. Na hlavni plošině 10 ja upevněn čerpací agregát 70. Hloubící soupravě je zavěšena na těžním laně 80. Na hlavni plošině 10 jaou upraveny nezakreslené rozpěrné aretačni prvky.The mining trench consists of three superposed platforms 10, 20, 50, consisting of the main platform 10, the upper assembly platform 20 and the lower platform 60. Between the assembly platform 20 and the main platform 10 is a suspension pillar 30 provided at its upper end The lower platform 50 is secured to the main platform 10 by means of lower webs 51. Between the mounting platform 20 and the main platform 10, reinforcing webs 21 are fastened. All platforms 10, 20, 50 are slatted structures. On the bottom side of the main platform 10, guide tracks 12 are provided on which the drilling units 40 are hinged. The auxiliary pulley 32 is mounted in the upper part of the suspension pillar 30, through which a rope 62 is connected. 63. mounted on the main platform 10. The arm 61 of the grab loader 60 is in the rest position housed in the suspension pillar 30. At the edge of the main platform 10, a main hinged segment 11 is provided, lower platform 50 is provided with a central hatch 53. A mechanical coupling can be made between the hinged segments 11 and 52. A pumping unit 70 is mounted on the main platform 10. The dredging assembly is suspended on a hoisting rope 80. On the main platform 10, underslung spacer elements are provided.

Před vrtacími pracemi je důlní hloubící souprava spuštěna do hloubané jámy tak, že dolní plošina 50 je v těsné blízkosti čelby. Osádka provádí vrtací práce z dolní plo3 siny 50 vrtacími jednotkami 40 zavěšenými přestavitelné na vodicích drahách 12, upevněných na spodní straně hlavni plošiny 10. Vrtáni je prováděno otvory v roštová podlaze dolní plošiny 50. Vrtáci jednotky 40 je možno posunovat po kruhových, případně čtvercových vodicích drahách 12 a vyklápět v libovolném směru. Tímto uspořádáním je možno vrtat v kterémkoliv místě čelby. Před provedením trhacích prací je důlní hloubící souprava vytažena do bezpečné vzdálenosti a po jejich provedení znovu spuštěna. Nakládáni uvolněná horniny je prováděno drapákovým nakladačem 60, epuštěným centrálním poklopem 53 pod důlní hloubici soupravu. Hornina je nakládána do těžební nádoby, spuštěné pod důlní hloubici soupravu hlavním odklápěcím segmentem 11 a dolním odklápěcím segmentem 52. Vystužování jámy je prováděno z dolní plošiny 50. Vystrojování jámy je prováděno z horní montážní plošiny '20. Při hloubení jámy plným výlomem je možno od hloubící soupravy odpojit dolní plošinu 50 a dolní stojiny 51.Prior to drilling, the mining dredging set is lowered into the excavated pit so that the lower platform 50 is in close proximity to the face. The crew carries out drilling operations from the lower deck 50 by drilling units 40 suspended on the guide rails 12 mounted on the lower side of the main deck 10. Drilling is effected by holes in the slatted floor of the lower deck 50. The drilling units 40 can be moved along circular or square guide tracks 12 and tilt in any direction. By this arrangement it is possible to drill at any point of the face. Before the blasting operations are carried out, the mining dredging set is pulled to a safe distance and lowered again after they have been carried out. Loading of the loose rock is carried out by a grab loader 60, dropped through the central hatch 53 below the mining trench set. The rock is loaded into a mining vessel lowered below the mining trench by the main hinged segment 11 and the lower hinged segment 52. The pit is reinforced from the lower platform 50. The pit is constructed from the upper assembly platform 20. When digging the pit with full excavation, the lower platform 50 and lower webs 51 can be detached from the digging rig.

Přednosti důlní hloubící soupravy podle vynálezu vyniknou obzvláště při přechodu z hloubeni důlní jámy plným profilem na hloubeni přibirkou do předraženého evielěho důlního díla.The advantages of the mine digging set according to the invention are particularly evident when moving from a full-profile mine excavation to a overpriced mine workpiece.

Claims (6)

PŘEDMĚT VYNÁLEZUSUBJECT OF THE INVENTION 1. Důlní hloubící souprava, zejména pro raženi vertikálních důlních děl, vyznačená tim, ie pozůstává ze dvou nad sebou umístěných plošin (10, 20), a to z hlavni plošiny (10) a horní montážní plošiny (20), přičemž mezi montážní plošinou (20) a hlavni plošinou (10) je umístěn závěsný pilon (30), opatřený na svém horním konci nosným závěsem (31), přičemž dále při okraji hlavni plošiny (10) je proveden nejméně jeden hlavni odklápěcí segment (11) a na spodní straně této hlavni plošiny (10) jaou připevněny vodici dráhy (12), na kterých jsou zavěšeny přestavitelné vrtací jednotky (40).A mine excavation rig, in particular for driving vertical mine workings, characterized in that it consists of two superposed platforms (10, 20), namely a main platform (10) and an upper assembly platform (20), wherein between the assembly platform (20) and a main pillar (10) is provided with a pendant pillar (30) provided with a support hinge (31) at its upper end, further comprising at least one main hinged segment (11) at the lower end of the main platform (10) and on the side of this main platform (10) are guided tracks (12) on which the adjustable drill units (40) are suspended. 2. Důlní hloubici souprava podle bodu 1, vyznačená tim, že k hlavni plošině (10) je prostřednictvím dolních stojin (51) připevněna dolní plošina (50), ve které je proveden centrální poklop (53) a při jejím okraji nejméně jeden dolni odklápěcí segment (52).Mine digging assembly according to claim 1, characterized in that a lower platform (50) is fixed to the main platform (10) by means of lower uprights (51), in which a central hatch (53) is provided and at least one lower hinged at its edge. segment (52). 3. Důlni hloubici souprava podle bodu 1, vyznačená tim, že v závěsném pilonu (30) je suvně uloženo rameno (61) drapákového nakladače (60).Mine digging assembly according to claim 1, characterized in that the arm (61) of the grab loader (60) is slidably mounted in the suspension pillar (30). 4. Důlní hloubici souprava podle bodu 1, vyznačená tim, že v horní části závěsného pilonu (30) je uložena pomocná kladka (32), přes kterou je vedeno lano (62), spojujíc! horni konec ramena (61) drapákového nakladače (60) s vrátkem (63), připevněným na hlavní plošině (10).4. A mining trench according to claim 1, characterized in that an upper roller (30) is provided with an auxiliary pulley (32) through which the rope (62) is connected, connecting it. the upper end of the arm (61) of the grab loader (60) with the winch (63) mounted on the main platform (10). 5. Oůlni hloubici souprava podle bodu 1, vyznačená tím, že mezi montážní plošinou (20) a hlavni plošinou (10) jaou upevněny zpevňovaci stojiny (21).A digging assembly according to claim 1, characterized in that reinforcing legs (21) are fastened between the mounting platform (20) and the main platform (10). 6. Důlni hloubici souprava podle bodu 1, vyznačená tim, že na hlavni plošině (10) je umi8těn čerpací agregát (70).6. The mining trench according to claim 1, characterized in that a pump assembly (70) is mounted on the main platform (10).
CS630078A 1978-09-29 1978-09-29 Mine sinking set part. for driving vertical mining workings CS202322B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CS630078A CS202322B1 (en) 1978-09-29 1978-09-29 Mine sinking set part. for driving vertical mining workings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CS630078A CS202322B1 (en) 1978-09-29 1978-09-29 Mine sinking set part. for driving vertical mining workings

Publications (1)

Publication Number Publication Date
CS202322B1 true CS202322B1 (en) 1980-12-31

Family

ID=5409721

Family Applications (1)

Application Number Title Priority Date Filing Date
CS630078A CS202322B1 (en) 1978-09-29 1978-09-29 Mine sinking set part. for driving vertical mining workings

Country Status (1)

Country Link
CS (1) CS202322B1 (en)

Similar Documents

Publication Publication Date Title
WO2015127808A1 (en) Center-pillared full-face shaft drilling machine
CN106761763A (en) A kind of novel silo development machine and its construction method
RU2592580C1 (en) Method of well shaft construction, shaft sinking combine, rock destruction unit and reinforcing support erection device (versions)
RU2600807C1 (en) Shaft sinking combine
CN211342765U (en) Multifunctional impact type hydraulic drill carriage suitable for rock roadway working face construction
US3516183A (en) Grab with adjustable guide mast
RU2358107C2 (en) Drilling facility for shaft deepening and method of shaft deepening
RU137573U1 (en) MECHANIZED COMPLEX FOR PERFORMING VERTICAL TRUNKS OF MINING ENTERPRISES
US2326172A (en) Shaft sinking apparatus
CS202322B1 (en) Mine sinking set part. for driving vertical mining workings
JP2797244B2 (en) Shaft excavation device and shaft construction method
US2889898A (en) Combination oil well derrick and tilting construction boom
RU2026982C1 (en) Shaft-sinking set
RU2455489C1 (en) Shaft drill loader
RU2547851C1 (en) Method of cyclic sinking of vertical mine shafts and device for its implementation
RU2039280C1 (en) Excavating and loading complex for opencast mining
SU1752964A1 (en) Apparatus for making mine shafts
SU750078A1 (en) Machinery set for sinking vertical mine workings
SU771341A1 (en) Mining machine feed mechanism
US2472359A (en) Oil well drilling apparatus having crown block movable lengthwise of mast
US3008549A (en) Method and apparatus for tilting a mast
JP2005336915A (en) Shaft excavation device
CN215718927U (en) Tunnel operation bridge convenient to lifesaving
RU2079663C1 (en) Drilling-supporting-cleaning module
RU2608086C1 (en) Complex for tunneling of vertical mine workings in quaternary deposits