CN2934354Y CN 200620021286 CN200620021286U CN2934354Y CN 2934354 Y CN2934354 Y CN 2934354Y CN 200620021286 CN200620021286 CN 200620021286 CN 200620021286 U CN200620021286 U CN 200620021286U CN 2934354 Y CN2934354 Y CN 2934354Y
Authority
CN
China
Prior art keywords
pile
concrete
gravel
pipe
concrete pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200620021286
Other languages
Chinese (zh)
Inventor
翟向滨
翟宇思
翟宇飞
翟宇红
张宇
Original Assignee
翟向滨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 翟向滨 filed Critical 翟向滨
Priority to CN 200620021286 priority Critical patent/CN2934354Y/en
Application granted granted Critical
Publication of CN2934354Y publication Critical patent/CN2934354Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a construction device for the rear concrete and gravel pouring after the end of the gravel feeding pile of the center pump of the center drilling tool. The existing devices has the problem that the concrete pouring pipe device is too complicated and big, the reliability of the concrete pouring pipe device is bad, the concrete pouring pipe is not easy to detach from the pulse extract pipe, the pulse extraction device vibrate in the bore with gravel and is easy to sink the gravel down to the bottom of the pile to make the pulse extract pipe and the concrete pouring pipe impossible to reach the bottom of the pile, the outside of the concrete pouring pipe is wrapped by the gravel even when the few crush stones at the bottom of the concrete pouring pipe is provided and no matter if the concrete pouring pipe reaches the bottom of the pile, and the concrete pouring pipe is prone to jam to make the concrete pouring at the bottom of the hole impossible when the strength of the gravel is more than 30 percent. So a construction device for the rear concrete and gravel pouring after the end of the gravel feeding pile of the center pump of the center drilling tool. The device is suitable for the construction of the base pile.

Description

The construction equipment of drilling tool center pumping concrete post grouting under pile concrete filling pile
Technical field:
The utility model relates to a kind of pile foundation construction device, is specifically related to the construction equipment of a kind of drilling tool center pumping concrete post grouting under pile concrete filling pile.
Background technology:
The stake side of extensive use at present, the pile bottom post grouting concrete filling pile is all realized under dried operation pore-forming or mud off pore-forming technique, though it has solved end load and the side frictional resistance problem that improves stake.But once finish promptly " bore and irritate unification " owing to can not realize boring and concrete pouring in the work progress.So its complex process, speed of application is slow, contaminated environment, quality control difficulty.And the various spiral drills center pumping concrete filling pile of using in recent years, as CFG stake, superfluidity stake etc., because its technology particularity, its stake end and side frictional resistance are all lower.In order to solve the problems referred to above of spiral drill center pumping concrete filling pile, many knowledgeable people have dropped into a large amount of financial resources energy, research and develop, as penetrate slurry expanded bore pile, rotary-jetting bottom-expanding pile, expand end agitation pile etc., all because its device structure is too complicated, technology is restive, so use lessly, and existing some device exists 1, the slip casting tube apparatus is too complicated huge down, following slip casting pipe unit poor reliability, Grouting Pipe is difficult for breaking away from the shake tube pulling; 2, the shake pulling device vibrates in the hole of concrete is arranged, and very easily concrete is caused from rare, and gravel sinks to the stake bottom, shakes tube pulling like this and can not reach the stake bottom, so Grouting Pipe can not arrive the stake bottom; Though 3, a small amount of rubble is arranged at the Grouting Pipe bottom, but at the bottom of no matter whether Grouting Pipe arrives, the Grouting Pipe outside is to be wrapped up by concrete, when reaching 30%~100%, easily cause concrete strength Grouting Pipe to block, hole-bottom slurry-injection such as can not realize at shortcoming, also exist in the prior art in addition a kind of to behind the pump-injecting concrete pile of auger stem center to a kind of remedial measure at the bottom of the stake, it is lowered to the Grouting Pipe degree of depth certain limit, slip casting is slip casting immediately when pile, so be not grouting behind shaft or drift lining worker method, its slip casting effect does not far reach the grouting behind shaft or drift lining method.
Summary of the invention:
The purpose of this utility model provides a kind of drilling tool center pumping concrete filling pile that can reach and has the construction equipment of the drilling tool center pumping concrete post grouting under pile concrete filling pile of pouring mortar pile afterwards concurrently.
Above-mentioned purpose realizes by following technical scheme:
The construction equipment of a kind of drilling tool center pumping concrete post grouting under pile concrete filling pile, its composition comprises: drill bit, Grouting Pipe has the grout outlet that links to each other with described Grouting Pipe on the described drill bit.
The construction equipment of above-mentioned drilling tool center pumping concrete post grouting under pile concrete filling pile, described Grouting Pipe is full helical blade or part helical blade.
The construction equipment of above-mentioned drilling tool center pumping concrete post grouting under pile concrete filling pile, described Grouting Pipe is by forming with the steel pipe of diameter or different-diameter.
The beneficial effects of the utility model:
1. the utility model product, but the steel pipe merogenesis be lowered in the hole, the thickness of steel pipe diameter can reduce, cost reduces equally, in the following original soil layer, can guarantee that grouting port is not blocked by concrete at the bottom of Grouting Pipe is lowered to, Grouting Pipe is unimpeded, because Grouting Pipe is provided with drill bit, can select helical blade as required for use again, following Grouting Pipe speed is fast, simple to operate, it is fast to pierce Grouting Pipe speed with rig, and the degree of depth is reliable.
2. the utility model product by rig or manually drive the rotation of pile end grouting pipe and pierce, in the following original soil layer, can hold primitive soil to reinforce to stake at the bottom of reaching always.
3. use the utility model product, can realize " bore and irritate unification ", have the characteristics that back pouring mortar pile bearing capacity increases substantially again, the inventive method construction equipment mature and reliable and simple.
Description of drawings:
Accompanying drawing 1 is the structural representation of this product.
The specific embodiment:
Embodiment 1:
The construction equipment of a kind of drilling tool center pumping concrete post grouting under pile concrete filling pile, its composition comprises: drill bit 4, Grouting Pipe 1 has the grout outlet 3 that links to each other with described Grouting Pipe 1 on the described drill bit 4, when pumping concrete material to specified altitude, drilling tool is proposed; With the effective rig of pile end grouting or manually pierce injected the concrete material the stake hole below original soil layer, go into slurries by the grout outlet of Grouting Pipe to the stake rising pouring length of time of concrete as required.
Embodiment 2:
The construction equipment of embodiment 1 described drilling tool center pumping concrete post grouting under pile concrete filling pile, described Grouting Pipe is full helical blade or part helical blade, selects the form of the helical blade 2 on the Grouting Pipe as required.
Embodiment 3:
The construction equipment of embodiment 1 described drilling tool center pumping concrete post grouting under pile concrete filling pile, described Grouting Pipe 1 is by forming with the steel pipe of diameter or different-diameter.

Claims (3)

1. the construction equipment of a drilling tool center pumping concrete post grouting under pile concrete filling pile, its composition comprises: drill bit, Grouting Pipe is characterized in that: have the grout outlet that links to each other with described Grouting Pipe on the described drill bit.
2. the construction equipment of drilling tool according to claim 1 center pumping concrete post grouting under pile concrete filling pile, it is characterized in that: described Grouting Pipe is full helical blade or part helical blade.
3. the construction equipment of drilling tool according to claim 1 and 2 center pumping concrete post grouting under pile concrete filling pile, it is characterized in that: described Grouting Pipe is by forming with the steel pipe of diameter or different-diameter.
CN 200620021286 2006-07-25 2006-07-25 Construction device for drill center pumping concrete to stake end and mortar intrusion for concrete perfusion stake Expired - Fee Related CN2934354Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620021286 CN2934354Y (en) 2006-07-25 2006-07-25 Construction device for drill center pumping concrete to stake end and mortar intrusion for concrete perfusion stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620021286 CN2934354Y (en) 2006-07-25 2006-07-25 Construction device for drill center pumping concrete to stake end and mortar intrusion for concrete perfusion stake

Publications (1)

Publication Number Publication Date
CN2934354Y true CN2934354Y (en) 2007-08-15

Family

ID=38351043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620021286 Expired - Fee Related CN2934354Y (en) 2006-07-25 2006-07-25 Construction device for drill center pumping concrete to stake end and mortar intrusion for concrete perfusion stake

Country Status (1)

Country Link
CN (1) CN2934354Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120714A (en) * 2016-08-22 2016-11-16 上海岩土工程勘察设计研究院有限公司 A kind of device improving hollow pile bearing capacity and using method thereof
CN106759290A (en) * 2017-03-19 2017-05-31 马鞍山宏泰建材股份有限公司 A kind of grouting behind shaft or drift lining pile foundation and its grouting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120714A (en) * 2016-08-22 2016-11-16 上海岩土工程勘察设计研究院有限公司 A kind of device improving hollow pile bearing capacity and using method thereof
CN106759290A (en) * 2017-03-19 2017-05-31 马鞍山宏泰建材股份有限公司 A kind of grouting behind shaft or drift lining pile foundation and its grouting method

Similar Documents

Publication Publication Date Title
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN100519951C (en) Construction method for increasing dry auger boring pouring pile bearing capacity
CN109723373B (en) Hole forming construction process for rotary drilling bored pile in slightly weathered granite stratum
CN104763345A (en) Construction device and method for building foundation
CN103758549A (en) Sequential filling-anchoring prestress full-length anchorage supporting method on basis of paste materials
Brown Practical considerations in the selection and use of continuous flight auger and drilled displacement piles
CN100494617C (en) Construction method of center mounting type anchor drill
CN101225740A (en) Annular filling method for space between freezing pipe and surrounding rock
CN105040695A (en) Anchor rod structure capable of integrally working and construction method
CN101100858A (en) Construction method for drilling tool center pumping concrete post mudjack concrete pouring pile and construction device thereof
CN201753445U (en) Uplift-resistant pile structure
CN105297710A (en) High-pressure-jetting cement soil twist drill and reamed reinforced concrete grouting combined pile and manufacturing method
CN2934354Y (en) Construction device for drill center pumping concrete to stake end and mortar intrusion for concrete perfusion stake
CN103410542B (en) Device and method for improving hole forming efficiency and anchoring performance of anchor rod and anchor cable of roadway floor
CN101768973B (en) Method and equipment for setting rotary-jet steel strand ground anchor
CN207988946U (en) A kind of drilling follow pile pile drilling machine with reamer
CN205100208U (en) Crowded, reaming reinforced concrete bored concrete pile composite pile of high water spray earth anger
CN101974904B (en) Screw anchor rod and processing method using screw anchor rod
CN114991774A (en) Ground subsection descending type grouting method for crushed andesite basalt stratum
CN205400767U (en) A pore -forming device that is used for stock or anchor rope of rubble soil layer
CN102359107B (en) Stiffening pile for reclaiming reinforcing body
CN205713988U (en) A kind of efficient rotary digs rock drill bit
CN102080376B (en) Built-in composite anchor rod construction method and composite anchor rod drilling tool used by same
KR101337223B1 (en) Apparatus Equipped with Double Casing for Inserting Plastic Drain Board and Process thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070815