CN2863875Y - 一种桥梁空心板的连接结构 - Google Patents

一种桥梁空心板的连接结构 Download PDF

Info

Publication number
CN2863875Y
CN2863875Y CN 200620078448 CN200620078448U CN2863875Y CN 2863875 Y CN2863875 Y CN 2863875Y CN 200620078448 CN200620078448 CN 200620078448 CN 200620078448 U CN200620078448 U CN 200620078448U CN 2863875 Y CN2863875 Y CN 2863875Y
Authority
CN
China
Prior art keywords
bridge
hollow slab
connecting structure
syndeton
bridge hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200620078448
Other languages
English (en)
Inventor
刘景刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Consultants Co Ltd
China Road and Bridge Corp
Original Assignee
Zhongjiao No1 Highway Prospecting Designing Inst
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongjiao No1 Highway Prospecting Designing Inst filed Critical Zhongjiao No1 Highway Prospecting Designing Inst
Priority to CN 200620078448 priority Critical patent/CN2863875Y/zh
Application granted granted Critical
Publication of CN2863875Y publication Critical patent/CN2863875Y/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型涉及桥梁建设中构件结构技术领域,具体涉及一种桥梁空心板的连接结构。本实用新型的目的是要提供一种桥梁空心板的连接结构,以克服现有技术存在的单板受力引起桥梁出现纵向破坏的问题。为克服现有技术存在的问题,本实用新型的技术解决方案是:一种桥梁空心板的连接结构,包括空心板,其特殊之处在于,所述角钢沿空心板的纵向分段预埋在板底直角处,所述角钢之间通过钢板焊接连接。

Description

一种桥梁空心板的连接结构
所属技术领域:
本实用新型涉及桥梁建设中构件结构技术领域,具体涉及一种桥梁空心板的连接结构。
背景技术:
在国内已建成的高速公路及一般公路上,由于交通量的增长及重型车辆的大幅度增加,桥梁出现纵向破坏、即单板受力问题是众多病害中对安全影响最大的病害之一。究其原因,是因为所采用的预制混凝土空心板的连接结构不合理,常见的空心板的横向联结多以板上端设小铰缝与桥面板共同受力,即采用齿口联结的结构。该结构在车辆动力小、载重小的情况下可保证使用,但随着国内的改革开放,高速公路、专用公路的相继建设,国内的多个项目的空心板桥上危害开始出现,由单板受力而引发的桥面破坏,结构安全性等问题暴露出来,进而引发的粘贴钢板、碳纤维、横向施加体外预应力等加固技术相继出现,其最终结果是大大增加了养护成本。
发明内容:
本实用新型的目的是要提供一种桥梁空心板的连接结构,以克服现有技术存在的单板受力引起桥梁出现纵向破坏的问题。
为克服现有技术存在的问题,本实用新型的技术解决方案是:一种桥梁空心板的连接结构,包括空心板1,其特殊之处在于,所述角钢2沿空心板1的纵向分段预埋在板底直角处,所述角钢2之间通过钢板3焊接连接。
上述角钢2每隔1.5~2.0m预埋。使施工简单化。
上述钢板3外侧为砂浆填充部。使该结构连接的更紧密。
与现有技术相比,本实用新型的优点是:
本结构与常规的预制空心板的连接结构相比,增加了在下部预埋角钢及角钢与插入钢板的焊接。本连接结构可有效提高连接板的横向刚度,保证整体结构安全及结构的寿命,避免大量的工程养护费用,有很好的社会价值。本连接结构在有效提高预制空心板之间的横向刚度的同时,因结构简单,施工容易,可有效降低制造成本,工程投入少。
附图说明:
图1是本实用新型的结构图;
图2是图1的A-A剖视图;
图3是图1的B-B剖视图。
具体实施方式:
下面将结合附图对本实用新型做详细描述。
一种桥梁空心板的连接结构,包括空心板1、角钢2和连接用钢板3。所说的角钢2沿空心板1的纵向每隔1.5~2.0m分段预埋在板底直角处,角钢2之间通过钢板3焊接连接,钢板3外侧为砂浆填充部。
施工时,预埋着角钢2的空心板1(角钢与空心板内钢筋绑扎)对接,在它们之间插入10mm厚的钢板,与两侧预制板预埋的角钢焊接。铰缝内通过大企口段焊接,然后进行砂浆填缝。以后按常规操作,浇筑企口混凝土,板底出露部分涂防锈漆后再涂环氧砂浆防腐,并使外观一致。

Claims (3)

1、一种桥梁空心板的连接结构,包括空心板(1),其特征在于,所述角钢(2)沿空心板(1)的纵向分段预埋在板底直角处,所述角钢(2)之间通过钢板(3)焊接连接。
2、如权利要求1所述的一种桥梁空心板的连接结构,其特征在于:所述角钢(2)每隔1.5~2.0m预埋。
3、如权利要求1或2所述的一种桥梁空心板的连接结构,其特征在于:所述钢板(3)外侧为砂浆填充部。
CN 200620078448 2006-02-23 2006-02-23 一种桥梁空心板的连接结构 Expired - Lifetime CN2863875Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620078448 CN2863875Y (zh) 2006-02-23 2006-02-23 一种桥梁空心板的连接结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620078448 CN2863875Y (zh) 2006-02-23 2006-02-23 一种桥梁空心板的连接结构

Publications (1)

Publication Number Publication Date
CN2863875Y true CN2863875Y (zh) 2007-01-31

Family

ID=37676328

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620078448 Expired - Lifetime CN2863875Y (zh) 2006-02-23 2006-02-23 一种桥梁空心板的连接结构

Country Status (1)

Country Link
CN (1) CN2863875Y (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587267A (zh) * 2012-04-06 2012-07-18 浙江大学 一种中设横隔张拉装配的预应力空心板梁桥及施工方法
CN103061271A (zh) * 2012-12-25 2013-04-24 中铁大桥勘测设计院集团有限公司 空心板桥单板受力加固方法
CN104074127A (zh) * 2014-06-30 2014-10-01 郑州大学 装配式空心板桥及其建造方法
CN107299592A (zh) * 2016-04-15 2017-10-27 塞莱默水处理齐利诺普尔有限公司 用于过滤器暗渠排水块的灌浆桥
CN109457630A (zh) * 2018-12-19 2019-03-12 贝正河北工程技术有限公司 一种空心板梁桥横向预应力摩擦板加固结构
CN109518585A (zh) * 2019-01-14 2019-03-26 中铁二院工程集团有限责任公司 一种全装配式钢-砼结合梁及其施工方法

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587267A (zh) * 2012-04-06 2012-07-18 浙江大学 一种中设横隔张拉装配的预应力空心板梁桥及施工方法
CN103061271A (zh) * 2012-12-25 2013-04-24 中铁大桥勘测设计院集团有限公司 空心板桥单板受力加固方法
CN104074127A (zh) * 2014-06-30 2014-10-01 郑州大学 装配式空心板桥及其建造方法
CN104074127B (zh) * 2014-06-30 2015-11-18 郑州大学 装配式空心板桥及其建造方法
CN107299592A (zh) * 2016-04-15 2017-10-27 塞莱默水处理齐利诺普尔有限公司 用于过滤器暗渠排水块的灌浆桥
CN107299592B (zh) * 2016-04-15 2020-09-18 塞莱默水处理齐利诺普尔有限公司 用于过滤器暗渠排水块的灌浆桥
CN109457630A (zh) * 2018-12-19 2019-03-12 贝正河北工程技术有限公司 一种空心板梁桥横向预应力摩擦板加固结构
CN109518585A (zh) * 2019-01-14 2019-03-26 中铁二院工程集团有限责任公司 一种全装配式钢-砼结合梁及其施工方法

Similar Documents

Publication Publication Date Title
CN2863875Y (zh) 一种桥梁空心板的连接结构
CN201172796Y (zh) 纵肋上置的钢箱梁桥面结构
CN105544385B (zh) 一种预制节段式混凝土桥梁的接缝构造
CN102330408A (zh) 一种桥梁
CN108442237A (zh) 一种预制桥墩和预制承台快速拼接的构造及其施工方法
CN201183656Y (zh) 一种集装箱底架结构
CN111270567B (zh) 一种梁端挡砟及轨枕系统一体化装置
CN102367649B (zh) 设开孔钢板连接件的钢木组合桥梁结构
CN210262769U (zh) 一种空心板桥梁加固加宽结构
CN103614975A (zh) 针对失效后的装配式空心板梁铰缝的剪力键加固方法
CN203334270U (zh) 一种可装配埋入式预制空心地下连续墙
CN103485333A (zh) 波形空心钢管摩擦桩及施工方法
CN202187278U (zh) 一种桥梁
CN207619818U (zh) 一种桥梁的混凝土的抗剪组合结构
CN103669193B (zh) 一种横向拼装波形钢腹板组合t梁及施工方法
CN2778930Y (zh) 一种钢筋混凝土空心预制构件板
CN208996310U (zh) 一种预制构造柱连接结构
CN207672356U (zh) 一种预制混凝土路面板拼装连接结构
CN204589832U (zh) 带有环向加强拼接结构的高填方波纹钢管涵洞
CN1651677A (zh) 一种带肋钢筋混凝土预制构件板
CN206503063U (zh) 预制组合型波形钢腹板t梁桥
CN205975381U (zh) 一种连续刚构桥合龙段顶推反力架结构
CN205223830U (zh) 新型钢板剪力连接件
CN205999792U (zh) 拼接式架桥结构
CN209741685U (zh) 一种道路桥梁裂缝加固结构

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee

Owner name: THE FIRST HIGHWAY SURVEY + DESIGN INSTITUTE OF CHI

Free format text: FORMER NAME: THE FIRST HIGHWAY SURVEY + DESIGN INSTITUTE OF CHINA

CP03 Change of name, title or address

Address after: No. two, 63, science and technology development road, hi tech Development Zone, Shaanxi, Xi'an, China: 710075

Patentee after: CCCC FIRST HIGHWAY CONSULTANTS Co.,Ltd.

Address before: No. two, 63, science and technology development road, hi tech Development Zone, Shaanxi, Xi'an, China: 710075

Patentee before: The First Highway Survey & Design Institute of China

TR01 Transfer of patent right

Effective date of registration: 20090710

Address after: No. two, 63, science and technology development road, hi tech Development Zone, Shaanxi, Xi'an, China: 710075

Co-patentee after: CHINA ROAD & BRIDGE Corp.

Patentee after: CCCC FIRST HIGHWAY CONSULTANTS Co.,Ltd.

Address before: No. two, 63, science and technology development road, hi tech Development Zone, Shaanxi, Xi'an, China: 710075

Patentee before: CCCC FIRST HIGHWAY CONSULTANTS Co.,Ltd.

CX01 Expiry of patent term

Granted publication date: 20070131

EXPY Termination of patent right or utility model