CN2858955Y - Slip casting overlength anchor bar - Google Patents
Slip casting overlength anchor bar Download PDFInfo
- Publication number
- CN2858955Y CN2858955Y CN 200520125783 CN200520125783U CN2858955Y CN 2858955 Y CN2858955 Y CN 2858955Y CN 200520125783 CN200520125783 CN 200520125783 CN 200520125783 U CN200520125783 U CN 200520125783U CN 2858955 Y CN2858955 Y CN 2858955Y
- Authority
- CN
- China
- Prior art keywords
- anchor bar
- slip casting
- anchor pole
- stack
- grouting pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
A slip casting over length anchor bar comprising an anchor bar (3), whose upper end is fixed and connected with an exhaust pipe (2). The anchor bar (3) and exhaust pipe (2) are connected with a grouting pipe (1) by wooden seal plug (4). The utility model has convenient construction, safety and reliability, long acting time, decreased loss rate, improved working efficiency and is especially suitable for supporting use in down-well operation when the stope roof is exposed with large area and long time in the mine with high mechanization degree.
Description
Affiliated technical field:
The utility model relates to a kind of mine support equipment, and particularly a kind of long-time top board of higher down-hole, the mine large tracts of land of mechanization degree that is used for exposes the anchor pole that stope carries out supporting
Background technology:
The mine that present domestic orebody thickness is higher, trend is long generally adopts the large-scale mobile equipment in down-hole to construct, this just requires stope and down-hole part exposed area and highly increases, adopt traditional support pattern that its top board safeguarded that reinforcement effect is not obvious, the tradition rock-bolt length generally is not more than three meters, and rock joint or tomography bigger in the stope are difficult to use traditional anchor pole to reinforce.Caused the working environment poor stability, the some column bleed is excessive in the stope, and the utilization rate reduction of main equipment etc. has a strong impact on the situation of the rate of recovery and operating efficiency.
The invention task:
The purpose of this utility model will provide a kind of exactly and be applicable to that stope top board exposed area is big, the time is long, and top board has than the mine of major fault and uses, the slip casting extra long anchor bar of have easy construction, safe and reliable, long action time, reduction loss late, increasing work efficiency.
The purpose of this utility model is achieved in that a kind of slip casting extra long anchor bar, form by anchor pole (3), the fixedly connected stack in upper end (2) that it is characterized in that described anchor pole (3), anchor pole (3), stack (2) connect Grouting Pipe (1) by wooden shutoff plug (4).
An optimum implementation of the present utility model: stack (2) adopts the PE plastics to make, and Grouting Pipe (1) adopts the PVC plastics to make, and anchor pole (3) adopts screw-thread steel.
The utility model compared with prior art has the following advantages:
1, because the form of structure that has adopted anchor pole (3), stack (2) to connect by wooden shutoff plug (4), thereby, it is long that the length of anchor pole (3) can reach 12m, can effectively suspend in midair big joint, tomography, once construction can be played good supporting effect to 4~5 layering stope top boards, easy construction, safe and reliable, long action time, reduction loss late.
2, construction speed is fast, can reach 50~60m/ days in the practice of construction, can satisfy the needs of rapid construction, increases work efficiency.
Accompanying drawing and drawing explanation:
Figure: be the utility model concrete structure schematic diagram.
1, Grouting Pipe 2, stack 3, anchor pole 4, wooden shutoff plug
The specific embodiment:
It is the 9mm screw-thread steel that anchor pole (3) adopts diameter, long 12m, fixedly connected in the top stack (2), stack (2) employing has certain compressive strength PE plastics makes, and internal diameter is 10mm, is connected wooden shutoff plug (4) on the outer wall of stack (2) and anchor pole (3), wooden shutoff plug (4) connects the outer wall of Grouting Pipe (1), Grouting Pipe (1) adopts internal diameter 20mm, wall thickness 4mm, and length is that the PVC plastics of 15m are made.
During use, anchor pole (3), stack (2), Grouting Pipe (1) are passed wooden shutoff plug (4), and the good boring of prior brill is put in the upper end of anchor pole (3), seals the lower end of boring with wooden shutoff plug (4), by Grouting Pipe (1) slip casting in the hole, get final product until filling with.
Claims (3)
1, a kind of slip casting extra long anchor bar is made up of anchor pole (3), it is characterized in that the fixedly connected stack in upper end (2) of described anchor pole (3), and anchor pole (3), stack (2) connect Grouting Pipe (1) by wooden shutoff plug (4).
2, slip casting extra long anchor bar according to claim 1 is characterized in that described stack (2) adopts the PE plastics to make, and Grouting Pipe (1) adopts the PVC plastics to make.
3, slip casting extra long anchor bar according to claim 1 and 2 is characterized in that described anchor pole (3) adopts screw-thread steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200520125783 CN2858955Y (en) | 2005-12-14 | 2005-12-14 | Slip casting overlength anchor bar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200520125783 CN2858955Y (en) | 2005-12-14 | 2005-12-14 | Slip casting overlength anchor bar |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2858955Y true CN2858955Y (en) | 2007-01-17 |
Family
ID=37611815
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200520125783 Expired - Fee Related CN2858955Y (en) | 2005-12-14 | 2005-12-14 | Slip casting overlength anchor bar |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2858955Y (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104632260A (en) * | 2015-03-19 | 2015-05-20 | 中国长江三峡集团公司 | High-compactness anchor rod grouting method |
CN106869978A (en) * | 2017-03-14 | 2017-06-20 | 中国十七冶集团有限公司 | A kind of tunnel hollow grouting anchor of the simple automatic exhaust device of band |
CN106907167A (en) * | 2017-05-03 | 2017-06-30 | 刘伟 | To long anchor cable gradation mortar depositing construction structure and its construction method on stope in hole |
-
2005
- 2005-12-14 CN CN 200520125783 patent/CN2858955Y/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104632260A (en) * | 2015-03-19 | 2015-05-20 | 中国长江三峡集团公司 | High-compactness anchor rod grouting method |
CN106869978A (en) * | 2017-03-14 | 2017-06-20 | 中国十七冶集团有限公司 | A kind of tunnel hollow grouting anchor of the simple automatic exhaust device of band |
CN106907167A (en) * | 2017-05-03 | 2017-06-30 | 刘伟 | To long anchor cable gradation mortar depositing construction structure and its construction method on stope in hole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102383828B (en) | Refection reducing and outburst eliminating method for deep-hole hydraulic fracture driving gas shallow hole extraction | |
CN101798931B (en) | Construction technology method of large-scale lead pipe roofs of tunnels and underground engineering without workshops | |
CN103306714B (en) | Coal seam group with near interval Di Chou holes in lane the mash gas harnessing method in a hole three | |
CN105239983B (en) | A kind of presplitting weakens anti-reflection method with the low air permeability coal seam that high pressure water injection is combined | |
CN201407053Y (en) | Support and waterproof structure for metro tunnel of tunnel boring machine construction | |
CN206957683U (en) | A kind of coal seam pressure relief and permeability improvement system | |
CN1982651A (en) | Method for mining ultra-long roofbolt slip casting with top plate large-area and long-time exposed under mining well | |
CN202851078U (en) | High water material filling column bag body | |
CN103939135A (en) | Rapid construction method for support dismantling channel of fully mechanized coal mining face | |
CN2858955Y (en) | Slip casting overlength anchor bar | |
CN203531877U (en) | Underground coal mine fracturing connecting device | |
CN204532364U (en) | Tunneling boring rock tunnel development machine engineering method subway tunnel pressure release type liner structure | |
CN116146160A (en) | Liquid CO 2 Alkaline water fracturing permeability-increasing gas extraction and coal seam water injection method | |
CN204941551U (en) | A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction | |
CN204252393U (en) | Corrugated steel web-compound section, concrete filled steel tube edge of a wing cross section column | |
CN201635074U (en) | Ground anchor | |
CN204174638U (en) | Underground structure ruggedized construction | |
CN201057037Y (en) | One-time lifted fracturing string of horizontal well | |
CN203583501U (en) | Deep-layer shear resistant device capable of preventing rock sliding | |
CN201132957Y (en) | Roof bolt | |
CN101387203A (en) | Rapid dust removal method and device in tunnel | |
CN206205937U (en) | A kind of post-grouting device of oil storage cavern | |
CN211314247U (en) | Tunnel country rock bolt-grouting supporting construction based on laser positioning | |
CN108533223A (en) | A kind of underground goaf residual coal bed gas methane drainage and utilization project system | |
CN204591240U (en) | Natural gas well pressure break or acidifying foam return comb post |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |