CN2670881Y - Vertical sintering furnace - Google Patents
Vertical sintering furnace Download PDFInfo
- Publication number
- CN2670881Y CN2670881Y CN 200320124143 CN200320124143U CN2670881Y CN 2670881 Y CN2670881 Y CN 2670881Y CN 200320124143 CN200320124143 CN 200320124143 CN 200320124143 U CN200320124143 U CN 200320124143U CN 2670881 Y CN2670881 Y CN 2670881Y
- Authority
- CN
- China
- Prior art keywords
- furnace
- heater
- tail gas
- vertical sintering
- feed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Abstract
The utility model relates to a vertical sintering furnace which is used to burn the solid particulates with the corrosive medium at high-temperature condition in particular to a vertical sintering furnace used for the accelerant sintering and treating. The vertical sintering furnace comprises that a sintering system is composed of a furnace with a thermal insulating sleeve clamp, a hot air inlet, a discharge port and a feed inlet which are arranged at the lower part of the furnace. The feature is that a feeding system with a cooling air port is arranged at one side of the furnace and the exhaust gas processing systems are arranged at the other side and on the upper part of the furnace. The feeding system is composed of a feed bin and a feed tube. The feed tube which is connected with the furnace is arranged at the lower part of the feed bin. The exhaust gas processing system is composed of an exhaust gas filter device and a separating device for the air and the material. The exhaust gas filter device is arranged on the upper part of the furnace. The separating device for the air and the material is arranged at one side of the furnace. The qualification rate of the vertical sintering furnace can reach 100 percent. The average overhaul period of the vertical sintering furnace is 120days. The vertical sintering furnace saves about 140000 Yuan repairing expense. The vertical sintering furnace avoids about 180 hours for checking.
Description
Technical field
The present invention relates to a kind of vertical roasting stove that is used to contain solid particulate matter roasting under hot conditions of Korrosionsmedium.Refer in particular to a kind of vertical roasting stove that is used for the catalyst calcination process.
Background technology
At present, high-temperature roasting is the critical process in the oil refining catalyst preparation process.It directly influences the various physical and chemical performances of catalyst.But because sintering temperature height (about 500 ℃-650 ℃) contains certain Korrosionsmedium (as chlorion, water vapour etc.) again, so very high to the requirement of roaster in the catalyst.Mainly there is following problem in existing oil refining catalyst vertical roasting stove:
(1) main material of roaster is a stainless steel, and it is corrosion easily in high temperature and Korrosionsmedium, and directly pollutes the catalyst that roaster includes noble metal, thereby forms waste product, and economic loss is serious.This mainly is that the turning is many because the roaster overall structure is unreasonable, and the macro-corrosion exhaust emissions that generates in the roasting process is not smooth.Simultaneously, the stove inner exhaust gas enters feeding warehouse easily, forms low-temperature space at this, causes water recovery, combines the back with chlorion and produces " dew point " corrosion at the feeding warehouse inwall.And along with a large amount of tail gas is played a reversed role, when opening the big lid of feeding warehouse and feed intake, tail gas fills the air, and environment is abominable, is not easy to operation.
(2) corrosion is damaged easily in high temperature and Korrosionsmedium for the metal parts of roaster, and particularly as the tail gas egress filtering device of critical component, only be 10 days average service time.So not only make the roaster maintenance frequent, the maintenance cost height, and also idle cost is big.
(3) at high temperature elongation is very big for the charging pipe of roaster, and original structure has retrained its distortion, makes parts deformation such as tremie pipe and tail gas fairlead serious, has influenced the serviceability of roaster.
Summary of the invention
The purpose of this utility model is improved at shortcoming that exists in the background technology and problem, provide a kind of can long-period stable operation in harsh conditions such as high temperature, Korrosionsmedium, and pollute the vertical roasting stove of problems such as easy breakage of parts and high temperature deformation owing to corrode the material that causes in the time of can solving the catalyst roasting.
The technical scheme that realizes the utility model purpose is such: the utility model is incubated the body of heater of cartridge clip by band and is located at the hot-wind inlet of body of heater bottom, discharging opening and charging aperture are formed the roast system, be characterized in that a side of body of heater is provided with the feed system of band cooling air port, opposite side and upper of furnace body are provided with exhaust treatment system, described feed system is made up of feeding warehouse and feed pipe again, wherein the feed pipe that is connected by with body of heater is established in the bottom of feeding warehouse, described exhaust treatment system is made up of the gentle material separating device of tail gas filter, wherein tail gas filter is located at the top of body of heater, and the gas material separating device is located at a side of body of heater.
The utility model has been avoided the generation of waste product in the roasting process, has improved the quality of product.Former roaster product percent of pass is about 98%, and novel roaster product percent of pass reaches 100%.Calculate if handle 200 tons of noble metal catalysts per year, can avoid about 400 kilograms of waste product the whole year, amount to about 320,000 yuan of the amount of money.Avoid about 20,000 yuan of cost of waste disposal simultaneously; The utility model has also improved the life cycle of roaster, has guaranteed that it stablely covers with excellent operation.The average shut-down (breakdown) mainteance cycle of former roaster is 10 days, about 1.4 ten thousand yuan of each recondition expense, and down period is about 18 hours.The average time between overhauls(TBO) of novel roaster is 120 days, saves about 140,000 yuan of recondition expense, avoids down period about 180 hours.
Description of drawings
Accompanying drawing is the real structural representation of the utility model.
The specific embodiment
By accompanying drawing as can be known, the utility model is incubated the body of heater (11) of cartridge clip (12) by band and is located at the hot-wind inlet (13) of body of heater (11) bottom, discharging opening (14) and charging aperture are formed the roast system, be characterized in that a side of body of heater (11) is provided with the feed system of band cooling air port, opposite side and upper of furnace body are provided with exhaust treatment system, described feed system is made up of feeding warehouse (1) and feed pipe (15), wherein the bottom of feeding warehouse (1) is provided with the feed pipe (15) that is connected with body of heater (11), described exhaust treatment system is made up of the gentle material separating device of tail gas filter, wherein tail gas filter is located at the top of body of heater (11), and the gas material separating device is located at a side of body of heater (11).
The feed system of band cooling air port described in the utility model, wherein cooling air port is located on the feed pipe (15); Tail gas filter described in the utility model comprises upper sieve plate (6), following sieve plate (9), filler (7) and tail gas fairlead (2), wherein filler (7) is located at up and down between the sieve plate (6,9), tail gas fairlead (2) is located at the top of body of heater (11), and is connected with separator; Separator described in the utility model comprises exhaust emissions chimney (3), cyclone separator (4) and fine powder delivery pipe (5), wherein exhaust emissions chimney (3) is located at the top of cyclone separator (4), fine powder delivery pipe (5) is located at the bottom of cyclone separator (4), and a side of cyclone separator (4) is provided with the tail gas fairlead (2) that is connected with body of heater (11).Filler described in the utility model (7) is a non-metallic fillers.
Technological process of the present utility model is:
1, the feed system of forming roaster by feeding warehouse (1), feed pipe (15), cooling air port.The oil refining catalyst for the treatment of roasting is contained in the feeding warehouse (1) and carries out high-temperature roasting in feed pipe (15) enters body of heater (11).Owing to taked to introduce measures such as a certain amount of cooling air, the tail gas content in the feeding warehouse (1) of playing a reversed role from body of heater (11) is reduced greatly, thus the low-temperature dew point corrosion of having avoided feeding warehouse (1) to exist preferably.And improved operating environment well.
2, the roasting system of forming roaster by body of heater (11), insulation jacket (12), hot-wind inlet (13) and discharging opening (14) etc.The oil refining catalyst for the treatment of roasting is introduced the roasting that body of heater (11) begins catalyst with the high-temperature roasting hot blast from hot-wind inlet (14) after tremie pipe (16) is filled body of heater (11), and by temperature thermocouple sintering temperature is monitored.Catalyst enters next process through discharging opening (14) again through after the roasting of certain hour.
3, the exhaust treatment system of forming roaster by upper sieve plate (6), following sieve plate (9), non-metallic fillers (7), tail gas fairlead (2), cyclone separator (4), exhaust emissions chimney (3), fine powder delivery pipe (5) etc.Because upper sieve plate (6), following sieve plate (9), non-metallic fillers (7) and filler purge the tail gas filter and the vertical one of roaster body of heater (11) that line (8) is formed, not only reduced the exhaust resistance of roasting tail gas, and increased circulation area, a large amount of tail gas that produce in the roasting process can in time be discharged.And owing to adopt sieve plate, the novel filtering technique of non-metallic fillers has greatly improved the high temperature corrosion resistance of this filter, has prolonged its life cycle, has reduced down period.Adopt in the exhaust treatment system after the cyclone separator (4), can separate the fine powder in the tail gas effectively, reduce the emptying amount of fine powder, help environmental protection.
4, feeding warehouse (1) supports by feed bin and is connected with body of heater (11), cyclone separator (4) supports by cyclone separator and is connected with body of heater (11), and the upper outlet of cyclone separator (4) connects with the spigot-and-socket of exhaust emissions chimney (3) the employing activity of fixing.This structure fully can fully guarantee body of heater (11) freely extending at high temperature, has avoided the deformation of tail gas fairlead (2) and feed pipe (15).
Claims (5)
1, a kind of vertical roasting furnace, by being with body of heater (11) that is incubated cartridge clip (12) and the hot-wind inlet (13) that is located at body of heater (11) bottom, discharging opening (14) and charging aperture are formed the roast system, it is characterized in that a side of body of heater (11) is provided with the feed system of band cooling air port, opposite side and upper of furnace body are provided with exhaust treatment system, described feed system is made up of feeding warehouse (1) and feed pipe (15), wherein the bottom of feeding warehouse (1) is provided with the feed pipe (15) that is connected with body of heater (11), described exhaust treatment system is made up of the gentle material separating device of tail gas filter, wherein tail gas filter is located at the top of body of heater (11), and the gas material separating device is located at a side of body of heater (11).
2, vertical roasting furnace according to claim 1 is characterized in that the feed system of described band cooling air port, and wherein cooling air port is located on the feed pipe (15).
3, vertical roasting furnace according to claim 1, it is characterized in that described tail gas filter comprises upper sieve plate (6), following sieve plate (9), filler (7) and tail gas fairlead (2), wherein filler (7) is located at up and down between the sieve plate (6,9), tail gas fairlead (2) is located at the top of body of heater (11), and is connected with the gas material separating device.
4, vertical roasting furnace according to claim 1, it is characterized in that described gas material separating device comprises exhaust emissions chimney (3), cyclone separator (4) and fine powder delivery pipe (5), wherein exhaust emissions chimney (3) is located at the top of cyclone separator (4), fine powder delivery pipe (5) is located at the bottom of cyclone separator (4), and a side of cyclone separator (4) is provided with the tail gas fairlead (2) that is connected with body of heater (11).
5, vertical roasting furnace according to claim 3 is characterized in that described filler (7) is a non-metallic fillers.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200320124143 CN2670881Y (en) | 2003-12-26 | 2003-12-26 | Vertical sintering furnace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200320124143 CN2670881Y (en) | 2003-12-26 | 2003-12-26 | Vertical sintering furnace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2670881Y true CN2670881Y (en) | 2005-01-12 |
Family
ID=34476596
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200320124143 Expired - Lifetime CN2670881Y (en) | 2003-12-26 | 2003-12-26 | Vertical sintering furnace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2670881Y (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101261086B (en) * | 2007-09-11 | 2010-10-06 | 李朝侠 | Trihydrate alumina gas phase fluidization calcining furnace lining |
-
2003
- 2003-12-26 CN CN 200320124143 patent/CN2670881Y/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101261086B (en) * | 2007-09-11 | 2010-10-06 | 李朝侠 | Trihydrate alumina gas phase fluidization calcining furnace lining |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101074385B (en) | Waste-plastic continuous cracking process and cracker | |
CN101451173A (en) | Converter gas dry method pocket type purification and recovery process and system | |
CN101280201A (en) | Full cycle dry distillation process and system for producing shale oil from oil shale (coal) | |
CN2859431Y (en) | Intermittent combustion casting waste sand roasting furnace | |
CN2670881Y (en) | Vertical sintering furnace | |
CN207904180U (en) | The environmentally friendly recycling system of waste tire | |
CN100366765C (en) | Method and apparatus for calcining mineral materials difficult to be treated | |
CN201071356Y (en) | Continuous-cracking equipment for waste plastics | |
CN1810929A (en) | Coal gas-recovering economizing clean coking process | |
CN210473404U (en) | Multi-nozzle type ethylene coke cleaning and dust removing device | |
CN1856584A (en) | Method for collecting and treating reaction gases from a production plant for molten metal and dust-removing machine therefor | |
CN206325310U (en) | A kind of secondary aluminium waste gas purification apparatus | |
CN205838923U (en) | Tire fast pyrolysis systems | |
CN105087854B (en) | Converter high-temperature flue gas dry method dust and process waste heat staged reclaimer and method | |
CN101530710A (en) | Process and equipment for purifying flue gas in dry type for biomass electric power plant | |
CN108220520A (en) | A kind of apparatus and method using pyrolysis production reducing gas for shaft furnace | |
CN205921050U (en) | Processing system is smelted to lead plaster | |
CN107324287A (en) | A kind of high temperature steam desulfurization device | |
CN211626130U (en) | Device for drying material in storage bin by using low-temperature waste gas of industrial kiln | |
CN2793078Y (en) | Straw thermal cracking device | |
CN207789460U (en) | The environmentally friendly cracking system of waste tire recycling | |
CN2637499Y (en) | Equipment for extracting fuel oil from waste rubber, waste plastics and waste oil | |
CN211651175U (en) | Shaft furnace for semi-coke modification | |
CN201216907Y (en) | Flue gas filter of smelting-furnace | |
CN201342379Y (en) | Biomass electric power plant smoke gas dry type purification apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CX01 | Expiry of patent term |
Expiration termination date: 20131226 Granted publication date: 20050112 |