CN2538806Y - Double-blasting fast-smelting blast furnace - Google Patents
Double-blasting fast-smelting blast furnace Download PDFInfo
- Publication number
- CN2538806Y CN2538806Y CN 01279863 CN01279863U CN2538806Y CN 2538806 Y CN2538806 Y CN 2538806Y CN 01279863 CN01279863 CN 01279863 CN 01279863 U CN01279863 U CN 01279863U CN 2538806 Y CN2538806 Y CN 2538806Y
- Authority
- CN
- China
- Prior art keywords
- blast furnace
- refining
- double
- air
- furnace
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000003723 Smelting Methods 0.000 title claims description 9
- 238000005422 blasting Methods 0.000 title claims description 7
- 238000007670 refining Methods 0.000 claims abstract description 12
- 235000012054 meals Nutrition 0.000 claims description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract description 14
- 229910052742 iron Inorganic materials 0.000 abstract description 7
- 239000000571 coke Substances 0.000 abstract description 5
- 238000005516 engineering process Methods 0.000 abstract description 4
- 238000010438 heat treatment Methods 0.000 abstract description 4
- 239000003245 coal Substances 0.000 abstract description 3
- 239000003034 coal gas Substances 0.000 abstract description 3
- 230000000694 effects Effects 0.000 abstract description 3
- 238000002844 melting Methods 0.000 abstract description 3
- 230000008018 melting Effects 0.000 abstract description 3
- 229910000805 Pig iron Inorganic materials 0.000 abstract description 2
- 239000002817 coal dust Substances 0.000 abstract 1
- 238000002485 combustion reaction Methods 0.000 abstract 1
- 230000009286 beneficial effect Effects 0.000 description 3
- 238000010411 cooking Methods 0.000 description 3
- 239000000446 fuel Substances 0.000 description 3
- 230000029087 digestion Effects 0.000 description 2
- 239000012943 hotmelt Substances 0.000 description 2
- 229940098458 powder spray Drugs 0.000 description 2
- 239000002893 slag Substances 0.000 description 2
- 241001417490 Sillaginidae Species 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000009977 dual effect Effects 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 230000004927 fusion Effects 0.000 description 1
- 230000002496 gastric effect Effects 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 210000002784 stomach Anatomy 0.000 description 1
- 208000011580 syndromic disease Diseases 0.000 description 1
Images
Landscapes
- Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)
Abstract
The utility model relates to a double heating and fast refining blast furnace, which can settles the disadvantages of single heating, slow refining, low yield, high consumption and low benefit of the prior high furnaces. On the prior blast furnaces, the big circular air duct and the pipe branches of the air port are all arranged on a circumference plane, and the hot blast sent into the furnace is also centralized on the plan. Just when the charge goes to the filmy high temperature melting zone, the charge can be melted and then sink into the crucible. Refining iron with coke is the second combustion of coal, so the consumption is great and the firepower is not enough. With the added coal dust or coal gas, the effect of the prior blast furnaces is not ideal yet. The utility model is characterized in that: at the proper position above the present big circular air duct, another same big circular air duct and a plurality of pipe branches of the air port are added; a wind brake is arranged on the chief pipe connecting the air duct and the hot blast stove, so as to regulate the air volume and the temperature in the furnace. Adopting the double air ducts to refine pig iron, the utility model has the advantages of double heating, fast refining, high yield, low consumption and high profit. The efficacy of the prior technology is increased greatly.
Description
Affiliated technical field
The utility model relates to a kind of smelting new technology of existing blast furnace, can realize the Double-blasting fast-smelting blast furnace of fast refining, high yield, low consumption, high benefit.
Background technology
As everyone knows, existing blast furnace all is to adopt a big circular duct of circle and more piece arm to be communicated with the air port of furnace wall, and the wind conveying pipe of hotblast stove is communicated with big circular duct and hot blast cooked a meal into smelts operation in the stove.This single tube air supply mode follows so far and did not change.Found the state so far, especially "Patent Law" is since the execution on April 1 in 85 year, and former patent newspaper now be intellectual property newspaper, invent and authoritative newpapers and periodicals such as innovation, there is no to step on the change report of air supply line system of blast furnace both domestic and external.Its subject matter is: ore fusion slowly, grow, yield poorly, consume height, of poor benefits, the potentiality that can not give full play to blast furnace tap to tap time.
Summary of the invention
Technical problem to be solved: the key of blast-furnace smelting is: strong wind, high temperature, fine fodder.At present, the blast furnace of state-owned big-and-middle-sized iron and steel enterprise has generally all reached this requirement, and still, its effect is still not ideal enough, and the annual utilization coefficient is difficult to reach more than 1: 2.Its reason of opinion: the one, the refining of cooking a meal of single airduct air feed, its air port all on a planar circumferential line, cause furnace high-temperature melting range section shallow, and blast furnace is very high, hot blast is cooked a meal in the stove also mainly in this shallow-thin layer, and charge goes downwards to could be burnt here for liquid and sinks to cupola well; The 2nd, coke ironmaking is burning for the second time, and it is relatively poor that its heat is imitated function, especially lacks flame resistivity and reserve strength, more do not have robust flame to upper punch, the above crude fuel of pre-heating duct, and cupola well also can be suffered from cold sometimes, produces some faults.Generally speaking, the firepower deficiency, oligopepsia, output are not high.Therefore, blast furnace both domestic and external is all adding Coal powder spray or coal gas.At present ubiquitous be singly cook a meal, refining slowly, low yield, high consumption, poor benefit problem.
Solve the technical scheme that its technical problem adopts: the technical scheme that the utility model adopted is: under the prerequisite that does not change at the existing air supply line of blast furnace system and other each position, set up a new air supply line system identical with former pipeline, adopt the refining of cooking a meal of two airducts, the capacity of its stove stomach and digestion ability are comparable to be twice originally.The two-tube wind of cooking a meal is means, and refining high yield soon is purpose, realizes by blast furnace, so cry: Double-blasting fast-smelting blast furnace.Its technical characterictic is: the appropriate location (deciding according to the blast furnace size) on the big circular duct of the existing circle of blast furnace, newly establish identical therewith airduct and the air port arm of a circle, be fixed on the steel bracing frame on the outer cover of steel plate of blast furnace circumference, should there be the suitable gradient that dips down in its arm and air port, ore speed hot melt is separated, and wind power energy affects crude fuel descending, can prevent that the air port from stopping up and the hanging fault; Newly-increased air port of going up the circle airduct should enclosed down between the air port of airduct, the air port should be arranged in a crossed manner up and down, can not overlap, can form cook a meal refining zone of a hot blast that increases newly thus, the expansion section s of stove gastric capacity just, can not only keep the up and down hot blast rate in zone and the equilibrium of temperature, and can will go up the thermophilic digestion regional integration that infracommissure becomes the original twice speed heat of ratio, softening, semi-molten, running down, just can give full play to the potentiality of blast furnace; Newly-increased circular duct leads between the house steward of hotblast stove, and air lock should be installed, so that regulate hot blast rate and temperature in the stove.
Beneficial effect against existing technologies: the beneficial effects of the utility model are: many one times of the hot blast rate of supply blast furnace, the fast hot melt of crude fuel separate layer thicken one times, high temperature melting zone expand be twice, ore scorification speed is fast again, the temperature in the stove also can significantly improve, can reduce or avoid the obstruction in iron notch, slag notch, air port to damage fault, can give full play to the potentiality of blast furnace, reach two and cook a meal, the purpose of refining, high yield soon.Significantly technique effect will inevitably produce significant output value benefit.Can not only increase considerably pig iron output, and can reduce consumption, especially can reduce coke ratio, because of the burnt amount of iron output and consumption is inverse ratio, output is high more, and coke ratio is low more, not only can save a large amount of coke, and blast furnace need not add Coal powder spray or coal gas again, reach dual energy-conservation purpose.High yield, low consumption, high benefit are total beneficial effects.
Description of drawings
Fig. 1: the blast furnace front view, only painted cupola well, furnace bosh, three positions of shaft, furnace roof and this case are irrelevant, the Therefore, omited; Fig. 2; It is the vertical view of Fig. 1; Fig. 3: be the vertical cross-sectional of Fig. 1, promptly therefrom analyse and observe to the iron notch right side from the hotblast stove left side.Blast furnace is a round, and is identical all around, be built on the reinforced concrete seat, the Therefore, omited left and right side view and upward view.The label 1-11 of Fig. 2 and Fig. 3 is consistent with the label 1-11 of Fig. 1.
Fig. 1-1 is an iron notch; Fig. 1-2 is the cupola well position; Fig. 1-3 is a slag notch; Fig. 1-4 is the original big circular duct of blast furnace; Fig. 1-5 is the arm and the air port of original big circular duct; Fig. 1-6 is the furnace bosh position; The big circular duct of Fig. 1-7 for newly establishing; Fig. 1-8 is the arm and the air port of the big circular duct newly established; Fig. 1-9 is the shaft position; Fig. 1-10 is the house steward that original big circular duct is communicated with hotblast stove, and hot blast house steward thus leads to the big circular duct of Fig. 1-4, again in stove is cooked a meal in Fig. 1-5 arm and air port; The house steward that Fig. 1-11 is communicated with hotblast stove for the big circular duct newly established, hot blast is the big circular duct newly established towards Fig. 1-7 of house steward thus, again in stove is cooked a meal in Fig. 1-8 arm and air port.
Embodiment
1, with reference to existing big circular duct, carry out second big circular duct of circle and the air port arm in advance, there is the suitable gradient that dips down in its arm and air port.
2, calculate wind speed, the air quantity of existing blower fan in advance, can be enough? so that take measures;
Can 3, appearance air quantity, the wind-warm syndrome of many hotblast stoves reach requirement? also should carry out prediction work.
4, utilize the blast furnace overhaul chance, install the big circular duct of second circle.The igniting baker is finished in overhaul, treat that stove fire is vigorous after, progressively open the air lock that encloses airduct again, the Double-blasting fast-smelting blast furnace commencement of commercial operation.
5, state-owned iron and steel enterprise blast furnace is more, and the overhaul time is in turn arranged.Machinery, equipment leave the factor of assurance about 50% when design, above-mentioned 2,3 is for precautions averts perils.
Claims (1)
- A kind of Double-blasting fast-smelting blast furnace, be that a same air supply line system is set on the air supply line system of blast furnace, be fixed on the steel bracing frame on the outer cover of steel plate of blast furnace circumference, just be and be Double-blasting fast-smelting blast furnace, it is characterized in that: air supply line system that this kind blast furnace is many, manifest is that two pipelines are vertically overlapping, two airducts laterally arranged side by side are the cook a meal innovation blast furnace of refining of air feeds simultaneously, on enclose the arm of airduct and lead to into that should there be downward obliquity in the interior air port of stove, enclose up and down the air port of airduct should be arranged in a crossed manner can not be overlapping, the newly-increased big circular duct of circle of going up should be installed air lock towards between the house steward of hotblast stove.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 01279863 CN2538806Y (en) | 2001-12-28 | 2001-12-28 | Double-blasting fast-smelting blast furnace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 01279863 CN2538806Y (en) | 2001-12-28 | 2001-12-28 | Double-blasting fast-smelting blast furnace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2538806Y true CN2538806Y (en) | 2003-03-05 |
Family
ID=33683014
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 01279863 Expired - Fee Related CN2538806Y (en) | 2001-12-28 | 2001-12-28 | Double-blasting fast-smelting blast furnace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2538806Y (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106702054A (en) * | 2017-01-13 | 2017-05-24 | 张英华 | Improved iron-smelting blast furnace and production method for air outlet pipes and hollow grate |
CN109355449A (en) * | 2018-12-18 | 2019-02-19 | 康书信 | Blast furnace ironmaking equipment |
-
2001
- 2001-12-28 CN CN 01279863 patent/CN2538806Y/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106702054A (en) * | 2017-01-13 | 2017-05-24 | 张英华 | Improved iron-smelting blast furnace and production method for air outlet pipes and hollow grate |
CN109355449A (en) * | 2018-12-18 | 2019-02-19 | 康书信 | Blast furnace ironmaking equipment |
CN109355449B (en) * | 2018-12-18 | 2020-10-09 | 康书信 | Blast furnace ironmaking equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102778124A (en) | Secondary radial air-supplying device for direct reduction equipment of rotary kiln | |
CN201740068U (en) | Premixing type combustion energy-saving stove | |
CN201555446U (en) | Smelting rotary hearth furnace for directly reducing nickel | |
CN104805247B (en) | A kind of energy-conservation regulation and control method of blast funnace hot blast stove combustion fan | |
CN2538806Y (en) | Double-blasting fast-smelting blast furnace | |
CN201104092Y (en) | Built-in coal based sponge iron shaft furnace | |
CN104891831A (en) | Energy-saving environment-friendly active lime roasting shaft kiln | |
CN201497328U (en) | Novel resistance band expansion furnace for vitrified small balls | |
CN203364408U (en) | Direct-fired coal hot air furnace with built-in heat exchange mixing chamber in hearth box | |
CN208472137U (en) | A kind of low-grade Iron concentrate directly melts iron-smelting device | |
CN201581100U (en) | Efficient and energy-saving burner for top combustion stove | |
CN103278016A (en) | Method of pre-heating pre-loaded material by using waste heat of flue gas | |
CN210215414U (en) | Blast furnace coal powder injection and hot blast stove air/coal gas series preheating system | |
CN109022660B (en) | A kind of heating furnace heating high hydrogen content reducing gas | |
CN203159642U (en) | Air quantity regulation device of blast furnace | |
CN207231215U (en) | A kind of intelligent natural gas kiln with novel energy-conserving technology | |
CN201203356Y (en) | Energy-saving furnace-in-furnace | |
CN206037701U (en) | Living beings melt aluminium stove | |
CN203295520U (en) | Blast furnace and blast furnace and medium-frequency induction furnace integrated smelting system | |
CN201217652Y (en) | Coal gas burnt lime vertical kiln | |
CN203890377U (en) | Gas-based reduction shaft furnace device | |
CN108609872A (en) | The energy conservation and environmental protection limekiln of furnace temperature monitored by microcomputer | |
CN204714712U (en) | Energy-saving environment protection active lime roasting shaft kiln | |
CN202648371U (en) | External-heat, air-blowing and water-cooling cupola furnace with long furnace age | |
CN102795757B (en) | Method for applying low-heat value gas to combustion in melting furnace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee |
Owner name: NO. 12, BUILDING 10, DADUKOUYUEGUANG VILLAGE, CHON Free format text: FORMER NAME OR ADDRESS: NO. 59, BUILDING 73, DAYANYI VILLAGE, DADUKOU DISTRICT, CHONGQING CITY, 400080 |
|
CP03 | Change of name, title or address |
Patentee address after: 400084 Chongqing Dadukou village 10 Building No. 12 moonlight Patentee address before: 400080 Chongqing Dadukou District weir village 73 Building No. 59 |
|
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |