CN2520346Y CN 01201102 CN01201102U CN2520346Y CN 2520346 Y CN2520346 Y CN 2520346Y CN 01201102 CN01201102 CN 01201102 CN 01201102 U CN01201102 U CN 01201102U CN 2520346 Y CN2520346 Y CN 2520346Y
Authority
CN
China
Prior art keywords
grouting
slurry
basic unit
construction equipment
reinforcing construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 01201102
Other languages
Chinese (zh)
Inventor
陈文玮
曹峰
吕广荣
王杰
杨金钟
赵宝春
李正全
肖专文
鲁晓华
吴聚元
杨长岭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd
Original Assignee
BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd filed Critical BEIJING UNIV CONSTRUCTION SUBWAY AND FOUNDATION MUNICIPAL ENGINEERING Co Ltd
Priority to CN 01201102 priority Critical patent/CN2520346Y/en
Application granted granted Critical
Publication of CN2520346Y publication Critical patent/CN2520346Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

A mud injecting and strengthening construction equipment for a basal layer of an airfield runway comprises a truck-type mixer portion, a stuff tank, a bailer, and a generator, wherein the bailer is connected with a mud dividing device, the mud dividing device is provided with at least two mud injecting outlets which are connected with mud delivering tubes via a flow sensor and a switch, the mud dividing device is connected with a truck-type testing, analyzing and processing system for mud injecting parameters, the mud delivering tubes are connected with mud injecting tubes, compressing and sealing devices are arranged on the periphery. The utility model works fast, no trace is left, and the laying up cost is reduced, and is applicable for a large-area square and a large-area basal layer of cobble and sandstone.

Description

Airfield runway basic unit grouting and reinforcing construction equipment
The utility model relates to a kind of foundation stabilization construction equipment.
After the use of airfield runway through many years, the road face occurs damaged, and the phenomenon of coming to nothing appears in the sand pebble layer of basic unit and surface layer part, need carry out runway strengthening, to guarantee aircraft flight safety.Existing foundation grouting reinforcement process equipment takes up an area of big, dismounting inconvenience, and the construction period is long, is not suitable for airfield runway and uses, and needs placing of material place, and power supply, water supply all need backguy to take over, the not only normal navigation of influence, and can move to aircraft and bring potential safety hazard.Existing basic unit grouting and reinforcing construction equipment does not have branch slurry device, no vehicular, seal around the grouting tube bad, spillage easily, the job site face that paves is big, mechanization degree is not high, does not regain round the clock.Reinforce an airfield runway and suspend usually and need about 15 days, if per day navigation amount was 450 sortie/days, will cause suspends loses about 5.4 hundred million yuans.
The purpose of this utility model provides a kind of airfield runway basic unit grouting and reinforcing construction equipment, improves mechanization degree, and equipment construction flexible for installation, rapid reduces the economic loss of suspending.
The technical solution of the utility model:
Airfield runway basic unit grouting and reinforcing construction equipment comprises and stirs slurry equipment, circulating tank, slush pump, grouting tube, generator, it is characterized in that: stirring slurry equipment, circulating tank, slush pump, generator is vehicular, wherein slush pump links to each other with a minute slurry device, divide the slurry device that at least two slip casting outlets are arranged, be connected with sending the slurry pipe with switch through flow transmitter, send the slurry pipe to connect grouting tube, pressed sealing device is arranged on every side.
The slip casting exit of above-mentioned branch slurry device is provided with pressure meter and safety relief valve.
Above-mentioned branch slurry device connects the vehicular grouting parameter and gathers automatically and analysis process system.
Above-mentioned pressed sealing device comprises and is with plug and plug packing ring around the grouting tube, on O-ring seal and 2 on ground compress pedestal, its middle part perforation is provided with the positioning bolt that inserts ground.
Above-mentioned positioning bolt and compress and be lined with the balance cushion block between the pedestal.
On the above-mentioned positioning bolt crank of stepping up is arranged.
Advantage of the present utility model: this technology makes and to carry on construction work at night, the navigation on daytime becomes possibility, and construction and is not stayed any vestige flexibly, rapidly, reduces the economic loss of suspending, and has guaranteed that the airport normally opens the navigation or air flight.Be applicable to Large Square, large tracts of land sandy gravel basic unit terrace.
Below in conjunction with drawings and Examples the present invention is further described:
Fig. 1 is that schematic diagram is arranged in the job site of using this equipment;
Fig. 2 is the structural representation of airfield runway basic unit grouting and reinforcing construction equipment;
Fig. 3 is the structural representation of pressed sealing device in the airfield runway basic unit grouting and reinforcing construction equipment;
Fig. 4 divides the slurry device and send slurry pipe connection diagram in the airfield runway of the present invention basic unit grouting and reinforcing construction equipment.
Embodiment is an example with the airfield runway basic unit grouting and reinforcing construction in the Capital Airport as shown in Figure 1, construction sequence:
(1). cloth hole, slip casting diffusion radius 1-3 rice, every plate 5 holes;
(2). boring, earlier with core-drill(ing) machine boring, submersible creeps into 10~15cm, withdraw from drilling rod and take out core, simultaneously with instrument during operation trickling ground and hole in water clean out.Be drilled into below the panel with the air pressure gun operation afterwards, should verify following cable of pavement slab and pipeline situation before the pore-forming;
(3). clear hole, with the clear hole of device, clear hole, clear hole device is connected with air compressor machine, with spare and the residue in the high pressure draught purge hole, for avoiding the hole of collapsing;
(4). grouting equipment is installed, slurries are after stirring, send in the branch slurry device through slush pump pressure, divide the slurry device to be divided into five slip casting outlets, slurries all will pass through the flow directions such as flow transmitter, valve switch and send in the slurry pipe, send the slurry pipe to connect grouting tube, are respectively equipped with pressure meter and safety relief valve simultaneously near the slip casting outlet, with convenient slurries pressure is monitored at any time, guarantee construction and device security.Slurries are when flowing through flow transmitter, the inductor of flow transmitter is to the mobile generation induction of slurries, and it is changed into the mainboard that the signal of telecommunication transfers to corresponding flow meter, mainboard transfers to display screen after handling through data, display screen shows corresponding instantaneous velocity and the flow that send in the slurry pipe, also transfer to Acquisition Instrument through the mainboard data processed simultaneously, after Acquisition Instrument reads data, editor, be stored in the IC-card, card reader reads data again and enters the private database of computer from IC-card, editor's arrangement back is printed and bound into book form.
(5). the slip casting pressed sealing device is installed, pressure meter and flowmeter;
After hole depth adheres to specification, can insert grouting tube, seal plug-hole,, pressed sealing device is installed then in plugging device loam cake one annular iron plate with plugging device.Slurries must be with the grouting tube sealing and fixing in injected hole before injection, and cover top cement plug packing ring in grouting tube puts O-ring seal afterwards earlier, overlaps top cement plug again, inserts in the injected hole then.One location bolt is set at the position of the about 200mm of distance injected hole, to compress base sleeve then behind positioning bolt, the horizontal base head is buckled on the plug packing ring, the balance cushion block is pressed on one's body the pedestal by positioning bolt, step up crank and positioning bolt and be pressed on the balance cushion block, screw crank, just be pressed on the plug packing ring by the horizontal base head by screwed connection, plug is contacted, to reach enough slips casing by pressure with the sealing of slip casting aperture.
(6). slip casting.Allowing under the pressure of slip casting that adopt the mode of flow-control to give slip casting, grouting mode is a cycling element with every panel, every cycling element is by the slip casting simultaneously of 5 holes, and slip casting is operation from bottom to top, at twice slip casting, insert floral tube slip casting for the first time earlier, for the second time slip casting once more behind the tube drawing 5-10cm.Twice slip casting is not less than 5-10 minute blanking time.Make slurries filling widely in the hole or space of rubble and aggregate chips basic unit, and continue, produce a desired effect with gelling.In the time of slip casting, utilize special flow Acquisition Instrument reading, write down each hole grouting amount of every block of plate and printing.Every plate slip casting time should be controlled according to grouting pressure, pavement slab lifting amount and the excessive slurry situation of plate seam, and when grouting pressure remained on certain numerical value, grouting amount no longer increased, and can stop slip casting.For avoiding slurries to run off, grouting sequence should be during construction: earlier runway centerline outside pavement slab is carried out slip casting, seal both sides, do not exosmose in the time of can guaranteeing the slip casting of runway middle part like this, help the extruding of slurries and closely knit, and then middle part slip casting.
Injection slurry be the straight cement slurries and antifreeze morning strong composite water-reducing agent, water/binder ratio is 0.8.Grouting pressure is not more than 2.5MPa, when pressure surpasses, stop 5-10 minute after, continue slip casting.
(7). the shutoff injected hole.After grouting with plunger finishes, should in time give the sealing of hole operation, promptly cram boring to the aperture with super-early strength cement 525R, aperture palpus levelling is for preventing the frost heave in winter, than the low 3-5mm of original ground.
(8). the cleaning of road face.In the time of panel slip casting, foreign material such as rubble that will go out cement core, clear Kong Qing and aggregate chips, excessive cement grout thoroughly clean, and the preceding road face that guarantees to accomplish to hand over to the next shift does not stay more any hidden danger that jeopardizes aircraft flight.In the grouting and reinforcing construction of Capital Airport airfield runway basic unit, normally open the navigation or air flight daytime, the construction of marching into the arena night.Compare about 2.36 hundred million yuan of minimizing economic loss with the construction of suspending fully.
A complete set of construction equipment all is automobile-carried formula, comprises boring a complete set of equipment and slip casting a complete set of equipment.The boring a complete set of equipment mainly comprises core-drill(ing) machine, air pressure gun, portable electric hammer, clear hole device, pneumatics locomotive 1, generating locomotive 2, water tender 3 and lighting etc.The slip casting a complete set of equipment mainly comprises airfield runway basic unit grouting and reinforcing construction equipment, grouting parameter test and analysis process system test carriage 4, cleaning equipment, settlement observation instrument automatically.
The utility model airfield runway basic unit grouting and reinforcing construction equipment as shown in Figure 2, comprises and stirs slurry car 5, circulating tank 6, slush pump 7, grouting vehicle 8, generating locomotive 9.As shown in Figure 4, the branch slurry device 10 on slush pump 7 and the grouting vehicle 8 links to each other, divides slurry device 10 that at least two slip castings outlets 11 are arranged, and is connected with sending slurry pipe 14 with switch 13 through flow transmitter 12, and the slip casting that branch is starched device 10 exports 11 places and is provided with pressure meter 16 and safety relief valve 17.Dividing the slurry device to test automatically with the vehicular grouting parameter links to each other with analysis process system 4.Send slurry pipe 14 to connect grouting tube 15, pressed sealing device is arranged, as shown in Figure 3 on every side by connecting bolt 24.
Pressed sealing device is to be with plug 18, plug packing ring 19 and O-ring seal 25 around grouting tube 15, on O- ring seal 25 and 2 on ground compress pedestal 20, its middle part perforation is provided with the positioning bolt 21 that inserts ground.Positioning bolt 21 and compress and be lined with balance cushion block 22 between the pedestal 20.The crank of stepping up 23 is arranged on the positioning bolt 21.Grouting tube stretches in the graded sand boulder bed 27 through concrete cushion 26, carries out slip casting near cushion lime 28.

Claims (6)

1, a kind of airfield runway basic unit grouting and reinforcing construction equipment, comprise and stir slurry part, circulating tank, slush pump, send slurry to manage and generator, it is characterized in that: stir slurry part, circulating tank, slush pump, generator is a vehicular, wherein slush pump links to each other with a minute slurry device, divide the slurry device that at least two slip casting outlets are arranged, be connected with sending the slurry pipe with switch through flow transmitter, send the slurry pipe to connect grouting tube, pressed sealing device is arranged on every side.
2, airfield runway according to claim 1 basic unit grouting and reinforcing construction equipment is characterized in that: the slip casting exit of described branch slurry device is provided with pressure meter and safety relief valve.
3, airfield runway according to claim 1 basic unit grouting and reinforcing construction equipment is characterized in that: described branch slurry device connects test of vehicular grouting parameter and analysis process system.
4, airfield runway according to claim 1 basic unit grouting and reinforcing construction equipment, it is characterized in that: described pressed sealing device comprises plug, plug packing ring and the O-ring seal that is with around the grouting tube, on O-ring seal and 2 on ground compress pedestal, its middle part perforation is provided with the positioning bolt that inserts ground.
5, airfield runway according to claim 1 basic unit grouting and reinforcing construction equipment is characterized in that: described positioning bolt and compress and be lined with the balance cushion block between the pedestal.
6, airfield runway according to claim 1 basic unit grouting and reinforcing construction equipment is characterized in that: on the described positioning bolt crank of stepping up is arranged.
CN 01201102 2001-01-12 2001-01-12 Base course grouting reinforcing construction apparatus for airport runway Expired - Lifetime CN2520346Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 01201102 CN2520346Y (en) 2001-01-12 2001-01-12 Base course grouting reinforcing construction apparatus for airport runway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 01201102 CN2520346Y (en) 2001-01-12 2001-01-12 Base course grouting reinforcing construction apparatus for airport runway

Publications (1)

Publication Number Publication Date
CN2520346Y true CN2520346Y (en) 2002-11-13

Family

ID=33623233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 01201102 Expired - Lifetime CN2520346Y (en) 2001-01-12 2001-01-12 Base course grouting reinforcing construction apparatus for airport runway

Country Status (1)

Country Link
CN (1) CN2520346Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606179A (en) * 2012-04-18 2012-07-25 中铁十三局集团第一工程有限公司 Grouted slurry separation machine
CN103205962A (en) * 2013-04-27 2013-07-17 杨众 Grouting lifting method of subsided terrace
CN103334371A (en) * 2013-07-05 2013-10-02 中南大学 Roadbed subsidence grouting treatment structure and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606179A (en) * 2012-04-18 2012-07-25 中铁十三局集团第一工程有限公司 Grouted slurry separation machine
CN103205962A (en) * 2013-04-27 2013-07-17 杨众 Grouting lifting method of subsided terrace
CN103334371A (en) * 2013-07-05 2013-10-02 中南大学 Roadbed subsidence grouting treatment structure and construction method thereof

Similar Documents

Publication Publication Date Title
Henn Practical guide to grouting of underground structures
CN109972609A (en) A kind of railway traffic engineering construction method of underground continuous wall
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN102061938A (en) Filling process for recovering coal pillars by filling goaf with paste
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
CN101806059A (en) Drilling, grouting and sand-throwing process of ground surface of mined-out region under highway
CN1126841C (en) Technological equipment for airprot runway foundation cement mortar filling consolidation
CN111810180B (en) Construction method for ultra-large-diameter earth pressure balance jacking pipe to penetrate through expressway
CN108487297A (en) The construction method that bracing members are set up in a kind of half lid excavation construction of subway station
CN2520346Y (en) Base course grouting reinforcing construction apparatus for airport runway
JP3418069B2 (en) Injection method and injection equipment
CN101275393A (en) Method for controlling running sand in underground engineering and grouting system therefor
CN113756825A (en) Mechanical method connecting channel construction method utilizing pipe jacking technology
CN203213115U (en) Trailer type high polymer grouting system
CN114397233A (en) Three-dimensional simulation test method for directional drilling grouting
KR940002457B1 (en) Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall
CN205115266U (en) Harbour deposited silt solidification ratio experimental apparatus
Kaneshiro et al. Controlled Low Strength Material for Pipeline Backfill— Specifications, Case Histories and Lessons Learned
CN109826176B (en) Pipe trench engineering construction process for coastal special silt geology
CN107893659A (en) A kind of shaft excavation construction method for charging of being unearthed by underground
CN113931647A (en) Construction method for shield underpass railway line in sandy cobble stratum
Garshol Pre-excavation grouting in tunneling
CN216771351U (en) Three-dimensional grouting simulation test system based on flowing water flow field
JPH08296205A (en) Method for filling underground cavity
CN114910282B (en) High-water-pressure shield tunnel wall back grouting and duct piece floating model test device and method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
C20 Patent right or utility model deemed to be abandoned or is abandoned