CN221277184U - Auxiliary installation operation platform - Google Patents

Auxiliary installation operation platform Download PDF

Info

Publication number
CN221277184U
CN221277184U CN202323190998.XU CN202323190998U CN221277184U CN 221277184 U CN221277184 U CN 221277184U CN 202323190998 U CN202323190998 U CN 202323190998U CN 221277184 U CN221277184 U CN 221277184U
Authority
CN
China
Prior art keywords
scaffold
auxiliary installation
wall
auxiliary
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323190998.XU
Other languages
Chinese (zh)
Inventor
魏焰
胡学龙
李军
汪斌
刘杰
袁宇
薛连
何群秀
王前华
宗振邦
马伍希
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd, Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Application granted granted Critical
Publication of CN221277184U publication Critical patent/CN221277184U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an auxiliary installation operation platform, which relates to the technical field of installation platforms and comprises a stressed scaffold, an auxiliary installation platform arranged above the stressed scaffold, a wall connecting assembly arranged on the side wall of the stressed scaffold, and a safety protection assembly arranged on one side of the auxiliary installation platform, wherein the safety protection assembly is arranged on one side far away from a wall body, the part of the auxiliary installation platform extends out of the stressed scaffold to form an overhanging part, and a steel pipe diagonal bracing piece for auxiliary support is arranged between the overhanging part of the auxiliary installation platform and the stressed scaffold; the utility model has reasonable design, and solves the problem that the auxiliary mounting platform exceeds the overhanging part of the stressed scaffold by adding the steel pipe diagonal bracing piece and the safety protection component to the stressed scaffold.

Description

Auxiliary installation operation platform
Technical Field
The utility model relates to the technical field of installation platforms, in particular to the technical field of auxiliary installation operation platforms.
Background
The aerial work operation platform is an aerial work product for equipment installation, overhaul and the like used in various industries. The common operation platform comprises a movable operation platform and an overhanging type steel platform. The allowable load value should be marked significantly on the operating platform. The total weight of personnel and materials on the operation platform is strictly forbidden to exceed the designed allowable load. The prior patent discloses the following technology:
Patent publication CN110644757a, entitled "an operation platform device", discloses the following: an operation platform device. The operation platform device comprises a first steel piece, a second steel piece and a supporting component; the number of the first steel pieces is two, and the two first steel pieces are arranged in parallel; the number of the second steel pieces is multiple, the second steel pieces are connected with the two first steel pieces, and the second steel pieces are arranged at intervals; welding the second steel piece and the first steel piece; the support assembly comprises a first support piece and a second support piece, wherein the number of the first support pieces is two, and one end of the first support piece is detachably and vertically connected with one end of the first steel piece; the number of the second supporting pieces is two, and two ends of the second supporting pieces are detachably connected with the other end of the first steel piece and the other end of the first supporting piece respectively; the first supporting pieces, the first steel pieces and the second supporting pieces are in one-to-one correspondence. The operation platform device can avoid reserving a large number of holes on the shear wall, is convenient and safe to use and convenient to operate.
The overhanging part of the operation platform has the stress problem that the stress is uneven, the stability is poor and the load can not be well transferred.
Disclosure of utility model
The utility model aims at: the utility model provides an auxiliary installation operation platform for solving the technical problems of uneven stress and poor stability of an overhanging type steel platform.
The utility model adopts the following technical scheme for realizing the purposes:
The utility model provides an auxiliary installation operation platform which comprises a stressed scaffold, an auxiliary installation platform arranged above the stressed scaffold, a wall connecting assembly arranged on the side wall of the stressed scaffold, and a safety protection assembly arranged on one side of the auxiliary installation platform, wherein the safety protection assembly is arranged on one side far away from a wall body, the part of the auxiliary installation platform extends out of the stressed scaffold to form an overhanging part, and a steel pipe diagonal bracing piece for auxiliary support is arranged between the overhanging part of the auxiliary installation platform and the stressed scaffold.
In one embodiment, the stressed scaffold is a double-row steel pipe landing frame or an overhanging frame.
In one embodiment, the double-row steel pipe floor frame comprises two groups of scaffold upright rods and a plurality of scaffold cross bars used for connecting the two groups of scaffold upright rods, and connecting fasteners are arranged at the joints of the scaffold cross bars and the corresponding scaffold upright rods.
Specifically, the stressed scaffold is a double-row steel pipe floor frame (or an overhanging frame), and the scaffold upright posts and the scaffold cross bars are mutually connected through connecting fasteners to form the stressed scaffold. The scaffold upright rod has the function of transmitting the upper load to the ground, and the scaffold cross rod has the function of connecting the scaffold upright rods together to bear force together.
In one embodiment, two ends of the steel pipe diagonal bracing piece are respectively locked on the auxiliary mounting platform and the stressed scaffold through connecting pieces.
Specifically, the steel pipe diagonal bracing pieces are respectively connected with the scaffold upright posts and the scaffold cross bars through connecting pieces, the tops of the two groups of scaffold upright posts mainly bear the load of the auxiliary mounting platform at the non-overhanging part, the steel pipe diagonal bracing pieces mainly bear the load of the auxiliary mounting platform at the overhanging part, and the load born by the steel pipe diagonal bracing pieces is finally transmitted to the stressed scaffold.
In one embodiment, the wall-connecting assembly includes a wall-connecting scaffold tube connected to a wall.
Specifically, the wall connecting piece scaffold tube is connected with the scaffold upright rod through the connecting piece, and the wall connecting component has the function of preventing the double-row steel tube floor frame (or cantilever frame) formed by connecting the scaffold upright rod and the scaffold cross rod from toppling over, playing a role of drawknot and bearing the load in the horizontal direction.
In one embodiment, a safety net bag component is arranged below the wall connecting scaffold pipe, and two ends of the safety net bag component are respectively connected to the side wall and the wall of the double-row steel pipe landing frame.
In particular, the safety net assembly is also intended to prevent tools or building materials from falling aloft.
In one embodiment, the safety shield assembly includes a shield rail disposed on the overhanging portion of the auxiliary mounting platform.
Specifically, the guard rail is used for preventing an operator from falling off from a high altitude by a person or a tool when the operator works on the auxiliary mounting platform, so that a safety protection effect is achieved.
In one embodiment, the guard rail has a height of at least 1.5m.
In one embodiment, the guard rail is provided with a dense mesh safety net, and the dense mesh safety net is mounted on the guard rail in a hanging manner.
Specifically, the function of the dense mesh safety net is to further prevent an operator from falling off from the high altitude of a person or a tool when working on the auxiliary mounting platform on the basis of the protective railing, and the dense mesh safety net and the protective railing together play a double safety protection role.
In one embodiment, the auxiliary mounting platform is horizontally disposed.
Specifically, the auxiliary mounting platform is used as an operation platform, the load of the auxiliary mounting platform of the overhanging part is transferred to the steel pipe diagonal bracing piece, and the load of the auxiliary mounting platform of the non-overhanging part is transferred to the two groups of scaffold upright rods.
Working principle:
Firstly, two groups of scaffold upright poles are installed, a scaffold cross bar is installed on the two groups of scaffold upright poles by using connecting fasteners to form a double-row steel pipe floor frame (or cantilever frame), a wall connecting piece scaffold pipe is installed by using connecting pieces, a safety net bag assembly is installed, a steel pipe diagonal bracing is installed by using the connecting pieces, an auxiliary installation platform is installed by using the connecting pieces, a protection railing is installed by using the connecting pieces, and a dense safety net is installed on the protection railing to complete the assembly of the whole device.
The beneficial effects of the utility model are as follows:
1. The utility model has reasonable design, and solves the problem that the auxiliary mounting platform exceeds the overhanging part of the stressed scaffold by adding the steel pipe diagonal bracing piece and the safety protection component to the stressed scaffold.
2. The auxiliary mounting platform is used as an operation platform, the load of the auxiliary mounting platform of the overhanging part is transmitted to the steel pipe diagonal bracing piece, and the load of the auxiliary mounting platform of the non-overhanging part is transmitted to the two groups of scaffold upright rods.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
Reference numerals: the scaffold comprises a 1-scaffold upright rod, a 2-scaffold cross rod, a 3-steel pipe diagonal bracing piece, a 4-connection fastener, a 5-wall-connecting piece scaffold pipe, a 6-safety protection component, a 7-auxiliary mounting platform, an 8-protection railing and a 9-dense safety net.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present utility model more apparent, the technical solutions of the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model, and it is apparent that the described embodiments are some embodiments of the present utility model, but not all embodiments of the present utility model. The components of the embodiments of the present utility model generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the utility model, as presented in the figures, is not intended to limit the scope of the utility model, as claimed, but is merely representative of selected embodiments of the utility model. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
It should be noted that: like reference numerals and letters denote like items in the following figures, and thus once an item is defined in one figure, no further definition or explanation thereof is necessary in the following figures. Furthermore, the terms "first," "second," and the like, are used merely to distinguish between descriptions and should not be construed as indicating or implying relative importance.
In describing embodiments of the present utility model, it should be noted that the directions or positional relationships indicated by the terms "inner", "outer", "upper", etc. are directions or positional relationships based on those shown in the drawings, or those that are conventionally put in place when the inventive product is used, are merely for convenience of description and simplification of description, and are not indicative or implying that the apparatus or element in question must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as limiting the present utility model.
Example 1
As shown in fig. 1, this embodiment provides an auxiliary installation operation platform, including the atress scaffold frame, the auxiliary installation platform 7 of setting in atress scaffold frame top, set up even wall subassembly on the atress scaffold frame lateral wall, and establish the safety protection subassembly 6 in auxiliary installation platform 7 one side, safety protection subassembly 6 sets up in keeping away from wall body one side, auxiliary installation platform 7 part extends the atress scaffold frame and forms the part of encorbelmenting, be provided with the steel pipe diagonal bracing piece 3 that is used for auxiliary stay between the part of encorbelmenting of auxiliary installation platform 7 and the atress scaffold frame.
Example 2
As shown in fig. 1, this embodiment provides an auxiliary installation operation platform, including the atress scaffold frame, the auxiliary installation platform 7 of setting in atress scaffold frame top, set up even wall subassembly on the atress scaffold frame lateral wall, and establish the safety protection subassembly 6 in auxiliary installation platform 7 one side, safety protection subassembly 6 sets up in keeping away from wall body one side, auxiliary installation platform 7 part extends the atress scaffold frame and forms the part of encorbelmenting, be provided with the steel pipe diagonal bracing piece 3 that is used for auxiliary stay between the part of encorbelmenting of auxiliary installation platform 7 and the atress scaffold frame.
The stressed scaffold is a double-row steel pipe floor frame or an overhanging frame.
Example 3
As shown in fig. 1, this embodiment provides an auxiliary installation operation platform, including the atress scaffold frame, the auxiliary installation platform 7 of setting in atress scaffold frame top, set up even wall subassembly on the atress scaffold frame lateral wall, and establish the safety protection subassembly 6 in auxiliary installation platform 7 one side, safety protection subassembly 6 sets up in keeping away from wall body one side, auxiliary installation platform 7 part extends the atress scaffold frame and forms the part of encorbelmenting, be provided with the steel pipe diagonal bracing piece 3 that is used for auxiliary stay between the part of encorbelmenting of auxiliary installation platform 7 and the atress scaffold frame.
The stressed scaffold is a double-row steel pipe floor frame.
The double-row steel pipe floor frame comprises two groups of scaffold upright posts 1 and a plurality of scaffold cross bars 2 used for connecting the two groups of scaffold upright posts 1, wherein connecting fasteners 4 are arranged at the joints of the scaffold cross bars 2 and the corresponding scaffold upright posts 1.
Specifically, the stressed scaffold is a double-row steel pipe floor frame (or an overhanging frame), and the scaffold upright 1 and the scaffold cross bar 2 are connected with each other through the connecting fastener 4 to form the stressed scaffold. The scaffold upright 1 is used for transmitting an upper load to the ground, and the scaffold cross bar 2 is used for connecting the scaffold upright 1 together to bear force together.
Example 4
As shown in fig. 1, this embodiment provides an auxiliary installation operation platform, including the atress scaffold frame, the auxiliary installation platform 7 of setting in atress scaffold frame top, set up even wall subassembly on the atress scaffold frame lateral wall, and establish the safety protection subassembly 6 in auxiliary installation platform 7 one side, safety protection subassembly 6 sets up in keeping away from wall body one side, auxiliary installation platform 7 part extends the atress scaffold frame and forms the part of encorbelmenting, be provided with the steel pipe diagonal bracing piece 3 that is used for auxiliary stay between the part of encorbelmenting of auxiliary installation platform 7 and the atress scaffold frame.
The stressed scaffold is a double-row steel pipe floor frame.
The double-row steel pipe floor frame comprises two groups of scaffold upright posts 1 and a plurality of scaffold cross bars 2 used for connecting the two groups of scaffold upright posts 1, wherein connecting fasteners 4 are arranged at the joints of the scaffold cross bars 2 and the corresponding scaffold upright posts 1.
Specifically, the stressed scaffold is a double-row steel pipe floor frame (or an overhanging frame), and the scaffold upright 1 and the scaffold cross bar 2 are connected with each other through the connecting fastener 4 to form the stressed scaffold. The scaffold upright 1 is used for transmitting an upper load to the ground, and the scaffold cross bar 2 is used for connecting the scaffold upright 1 together to bear force together.
Two ends of the steel pipe diagonal bracing piece 3 are respectively locked on the auxiliary mounting platform 7 and the stressed scaffold through connecting pieces.
Specifically, the steel pipe diagonal bracing pieces 3 are respectively connected with the scaffold upright 1 and the scaffold cross bars 2 through connecting pieces, the tops of the two groups of scaffold upright 1 mainly bear the load of the auxiliary installation platform 7 at the non-overhanging part, the steel pipe diagonal bracing pieces 3 mainly bear the load of the auxiliary installation platform 7 at the overhanging part, and the load born by the steel pipe diagonal bracing pieces 3 is finally transmitted to the stressed scaffold.
The wall connection assembly comprises a wall connection scaffold tube 5 connected with the wall.
Specifically, the wall connecting piece scaffold tube 5 is connected with the scaffold upright 1 through a connecting piece, and the wall connecting component has the function of preventing the double-row steel tube floor frame (or cantilever frame) formed by connecting the scaffold upright 1 and the scaffold cross bar 2 from toppling over, and has the function of drawknot and bearing the load in the horizontal direction.
Example 5
This embodiment is further optimized based on any one of embodiments 1 to 4, specifically:
The safety net bag component is arranged below the wall connecting piece scaffold tube 5, and two ends of the safety net bag component are respectively connected to the side wall of the double-row steel tube floor frame and the wall body.
In particular, the safety net assembly is also intended to prevent tools or building materials from falling aloft.
The safety assembly 6 comprises a guard rail 8 arranged on the overhanging portion of the auxiliary mounting platform 7.
Specifically, the guard rail 8 is used for preventing an operator from falling off from the high altitude of a person or a tool used for assisting the operator to work on the mounting platform 7, and plays a role in safety protection.
The height of the guard rail 8 is at least 1.5m.
The guard rail 8 is provided with a dense mesh safety net 9, and the dense mesh safety net 9 is arranged on the guard rail 8 in a hanging mode.
Specifically, the function of the dense mesh safety net 9 is to further prevent an operator from falling off from the high altitude of a person or a tool used when working on the auxiliary mounting platform 7 on the basis of the protective rail 8, and the dense mesh safety net and the protective rail 8 together play a double safety protection role.
Example 6
This embodiment is further optimized based on any one of embodiments 1 to 5, specifically:
the auxiliary installation platform 7 is horizontally arranged.
Specifically, the auxiliary mounting platform 7 is used as an operation platform, the load of the auxiliary mounting platform 7 of the overhanging part is transmitted to the steel pipe diagonal bracing member 3, and the load of the auxiliary mounting platform 7 of the non-overhanging part is transmitted to the two groups of scaffold uprights 1.
Working principle:
Firstly, two groups of scaffold upright posts 1 are installed, a scaffold cross bar 2 is installed on the two groups of scaffold upright posts 1 by using a connecting fastener 4 to form a double-row steel pipe floor frame (or cantilever frame), a wall connecting piece scaffold pipe 5 is installed by using a connecting piece, a safety net bag component is installed, a steel pipe diagonal bracing is installed by using the connecting piece, an auxiliary installation platform 7 is installed by using the connecting piece, a protective railing 8 is installed by using the connecting piece, and a dense safety net 9 is installed on the protective railing 8 to complete the assembly of the whole device.

Claims (10)

1. The utility model provides an auxiliary installation operation platform, its characterized in that is in including atress scaffold frame, setting auxiliary installation platform (7) of atress scaffold frame top, set up even wall subassembly on the atress scaffold frame lateral wall and establish safety protection subassembly (6) of auxiliary installation platform (7) one side, safety protection subassembly (6) set up in keeping away from wall body one side, auxiliary installation platform (7) part extends the atress scaffold frame forms the part of encorbelmenting, the part of encorbelmenting of auxiliary installation platform (7) with be provided with between the atress scaffold frame steel pipe diagonal bracing piece (3) that are used for auxiliary stay.
2. The auxiliary installation operation platform according to claim 1, wherein the stressed scaffolding is a double-row steel pipe landing or overhanging frame.
3. An auxiliary installation operating platform according to claim 2, characterized in that the double-row steel pipe landing frame comprises two groups of scaffold uprights (1) arranged side by side and a plurality of scaffold crossbars (2) for connecting the two groups of scaffold uprights (1), and connecting fasteners (4) are arranged at the joints of the scaffold crossbars (2) and the corresponding scaffold uprights (1).
4. An auxiliary installation operation platform according to claim 3, wherein two ends of the steel pipe diagonal bracing member (3) are respectively locked on the auxiliary installation platform (7) and the stressed scaffold through connecting members.
5. An auxiliary installation and operation platform according to claim 4, wherein the wall-connection assembly comprises a wall-connection scaffold tube (5) connected to the wall.
6. The auxiliary installation operation platform according to claim 5, wherein a safety net bag assembly is arranged below the wall connecting scaffold tube (5), and two ends of the safety net bag assembly are respectively connected to the side wall and the wall of the double-row steel tube landing frame.
7. An auxiliary installation and operation platform according to claim 4, characterized in that the safety protection assembly (6) comprises a protection railing (8) arranged on the overhanging portion of the auxiliary installation platform (7).
8. An auxiliary installation operating platform according to claim 7, characterized in that the height of the guard rail (8) is at least 1.5m.
9. An auxiliary installation and operation platform according to claim 7, characterized in that the guard rail (8) is provided with a dense mesh safety net (9), and the dense mesh safety net (9) is installed on the guard rail (8) in a hanging manner.
10. An auxiliary installation and operation platform according to claim 1, characterized in that the auxiliary installation platform (7) is arranged horizontally.
CN202323190998.XU 2023-11-24 Auxiliary installation operation platform Active CN221277184U (en)

Publications (1)

Publication Number Publication Date
CN221277184U true CN221277184U (en) 2024-07-05

Family

ID=

Similar Documents

Publication Publication Date Title
CN205822747U (en) Architectural engineering scaffold
CN221277184U (en) Auxiliary installation operation platform
CN104278830A (en) Integrated combined scaffold
CN112267661A (en) Climbing frame convenient to adjust for construction industry
CN211775603U (en) Combined type step construction platform
CN214740094U (en) High-altitude falling object blocking fence for building construction
CN213951973U (en) Adjustable construction platform
CN211998568U (en) Standard knot and tower crane
CN212716012U (en) Elevator well head protector
CN204212388U (en) Monolithic combined scaffold
CN210177931U (en) Scaffold for building construction
CN212269280U (en) Standard knot for tower crane and tower crane
CN110965750A (en) Liftable full hall scaffold
CN215167877U (en) Safety hanging basket for cleaning outer wall
CN215760282U (en) High altitude construction scaffold with lift platform
CN215484490U (en) Telescopic scaffold
CN110629997A (en) Integrated form climbs frame
CN217379718U (en) Prefabricated stairwell operation protection platform
CN213898056U (en) Scaffold with prevent function of falling
CN114908958B (en) Climbing frame attaching method
CN218842867U (en) Movable bridge arch rib support frame
CN220319104U (en) Scaffold connecting assembly and scaffold
CN218952746U (en) Scaffold frame
CN219604807U (en) Assembled turnover wallboard installation operation frame
CN216766685U (en) Overhanging type mobile operation platform and system

Legal Events

Date Code Title Description
GR01 Patent grant