CN214740094U - High-altitude falling object blocking fence for building construction - Google Patents
High-altitude falling object blocking fence for building construction Download PDFInfo
- Publication number
- CN214740094U CN214740094U CN202022514410.1U CN202022514410U CN214740094U CN 214740094 U CN214740094 U CN 214740094U CN 202022514410 U CN202022514410 U CN 202022514410U CN 214740094 U CN214740094 U CN 214740094U
- Authority
- CN
- China
- Prior art keywords
- net
- falling
- guardrail
- building construction
- falling object
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model belongs to the field of building construction, in particular to a high-altitude falling object blocking fence for building construction, which comprises a base, wherein a guardrail is arranged at the top of the base, vertical rods are arranged on two sides of the guardrail, and the vertical rods are connected with the guardrail through transverse plate pieces; a support table is mounted at the top of the vertical rod, an anti-falling net is placed at the top of the support table, and a limit column penetrates through the anti-falling net and the end face attached to the support table; the support plate on the wall frame is matched with the locking bolt and the support table on the vertical rod to be matched with the limiting column to install the anti-falling net, the anti-falling net shields the top of a high-risk area of the high-altitude falling object, and the hidden danger of body damage caused by the collision of the high-altitude falling object on workers in the high-risk area of the high-altitude falling object is reduced; prevent weighing down the net and be bilayer structure, go up the rack and be fretwork network structure with lower rack, and go up between the rack as connecting load structure through the connecting rod, promote the whole anti-falling object impact's of preventing weighing down the net performance.
Description
Technical Field
The utility model relates to a construction field, concretely relates to construction blocks rail with high altitude junk.
Background
The construction site refers to a construction site where construction activities such as house construction, civil engineering, equipment installation, and pipeline laying are performed in industrial and civil projects, and the construction site is approved to be occupied, and a site where safety production, civilized work, and construction are performed by human beings, including all regions where construction work can be performed on land, sea, and in the air. The project manager is responsible for the field management of the construction process, and the project manager establishes the management responsibility of the construction field and organizes and implements the management responsibility according to the project scale, the technical complexity and the specific situation of the construction field.
The prior art has the following problems:
the phenomenon that objects fall from high altitude exists in a building construction site, a constructor standing on the bottom wall surface has the hidden danger of being injured due to the collision of the objects falling from high altitude, and the problem that workers are injured due to the collision of the objects falling from high altitude is difficult to solve by wearing a safety helmet independently.
In order to solve the problems, the application provides a high-altitude falling object blocking fence for building construction.
SUMMERY OF THE UTILITY MODEL
Objects of the invention
For solving the technical problem who exists among the background art, the utility model provides a construction blocks rail with high altitude junk has the characteristics that prevent weighing down the net installation facility and high altitude junk blocks fast.
(II) technical scheme
In order to solve the technical problem, the utility model provides a high-altitude falling object blocking fence for building construction, which comprises a base, wherein a guardrail is arranged at the top of the base, vertical rods are arranged at two sides of the guardrail, and the vertical rods are connected with the guardrail through transverse plate pieces;
a support table is mounted at the top of the vertical rod, an anti-falling net is placed at the top of the support table, and a limit column penetrates through the anti-falling net and the end face attached to the support table;
the other end of the anti-falling net is clamped and fixed by a support plate and a locking bolt which are arranged on the wall surface.
Preferably, the bottom of the supporting plate is supported by a pillar, and the other end of the pillar is connected with a wall frame installed on the wall surface.
Preferably, the wall frame is of a triangular structure.
Preferably, prevent weighing down the net including last rack and the lower rack that the symmetry set up, go up the rack with connect through the connecting rod between the rack down.
Preferably, four corners of the anti-falling net are respectively fixed through the matching of the supporting tables with the same structure and the limiting columns and the matching of the supporting plates and the locking bolts.
Preferably, the guardrail bars are installed at intervals inside the guardrail.
The above technical scheme of the utility model has following profitable technological effect:
1. the supporting plate on the wall frame is matched with the locking bolt and the supporting table on the vertical rod to be matched with the limiting column to install the anti-falling net, the anti-falling net shields the top of a high-risk area of an overhead falling object, and the hidden danger that a worker is impacted by the overhead falling object to cause body damage in the high-risk area of the overhead falling object is reduced.
2. Prevent weighing down the net and be bilayer structure, go up the rack and be fretwork network structure with lower rack, and go up between the rack as connecting load structure through the connecting rod, promote the whole anti-falling object impact's of preventing weighing down the net performance.
Drawings
Fig. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic side view of the present invention;
FIG. 3 is an enlarged schematic view of the structure A of the present invention;
fig. 4 is a schematic view of the anti-falling net structure of the utility model.
Reference numerals:
1. a base; 2. a guardrail; 3. guard rails; 4. a cross plate member; 5. a vertical rod; 6. a support table; 7. the anti-falling net; 701. mounting a net rack; 702. a lower net rack; 703. a connecting rod; 8. a limiting column; 9. a wall frame; 10. a pillar; 11. a support plate; 12. and locking the bolt.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the description is intended to be illustrative only and is not intended to limit the scope of the present invention. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
As shown in fig. 1-4, the high-altitude falling object blocking fence for building construction provided by the utility model comprises a base 1, a guardrail 2 is installed on the top of the base 1, guardrail rods 3 are installed at intervals inside the guardrail 2, vertical rods 5 are arranged on two sides of the guardrail 2, and the vertical rods 5 are connected with the guardrail 2 through cross plates 4;
a supporting table 6 is installed at the top of the vertical rod 5, an anti-falling net 7 is placed at the top of the supporting table 6, a limiting column 8 penetrates through the attached end face of the anti-falling net 7 and the supporting table 6, and the other end of the anti-falling net 7 is clamped and fixed through a supporting plate 11 and a locking bolt 12 which are installed on the wall surface.
It should be noted that: four corners of the anti-falling net 7 are respectively fixed with a supporting plate 11 through two supporting tables 6 with the same structure matched with a limiting column 8 and a locking bolt 12; the connecting structure of the supporting table 6 and the limiting column 8 fixes two corners of the anti-falling net 7, and the rest two corners are fixed by the supporting plate 11 matched with the locking bolt 12 to quickly install the anti-falling net 7.
In this embodiment, set up base 1 in wall limit one side, install guardrail 2 on base 1, install montant 5 in 1 both sides of base, montant 5 and guardrail 2 carry out the separation to the high altitude weight region, prevent that outer person from missing the high altitude weight high risk area, install wall frame 9 on the wall, backup pad 11 on the wall frame 9 cooperates spacing post 8 of supporting bench 6 cooperation on locking bolt 12 and the montant 5 and installs preventing weighing down net 7, prevent weighing down net 7 and shelter from the top of high altitude weight high risk area, realize stopping of high altitude weight high risk area top and side, reduce the high altitude weight high risk area interior staff of high altitude weight and receive the high altitude weight striking hidden danger that physical damage appears.
As shown in fig. 3, the bottom of the supporting plate 11 is supported by a support column 10, and the other end of the support column 10 is connected to a wall frame 9 installed on a wall surface.
It should be noted that the wall frame 9 is a triangular structure; the wall frame 9 is directly installed on the wall surface, the wall frame 9 and the wall surface of the triangular structure are provided with two connection points, the installation stability is high, and the anti-falling net 7 is assisted to be installed.
In this embodiment, the supporting plate 11 is supported and installed by the pillars 10 on the wall frame 9, the corners of the anti-falling net 7 are placed on the supporting plate 11, the locking bolts 12 penetrate through the anti-falling net 7 and connect the supporting plate 11, clamping and installation of the anti-falling net 7 are realized, and single-side fixation of the anti-falling net 7 is realized.
As shown in FIG. 4, the anti-falling net 7 comprises an upper net rack 701 and a lower net rack 702 which are symmetrically arranged, and the upper net rack 701 and the lower net rack 702 are connected through a connecting rod 703.
In this embodiment, the anti-falling net 7 has a double-layer structure, the upper net rack 701 and the lower net rack 702 are both hollow net structures, and the upper net rack and the lower net rack are connected through the connecting rod 703 to form a force bearing structure, so that the overall anti-falling object impact performance of the anti-falling net 7 is improved.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundaries of the appended claims or the equivalents of such scope and boundaries.
Claims (6)
1. The high-altitude falling object blocking fence for building construction is characterized by comprising a base (1), wherein a guardrail (2) is installed at the top of the base (1), vertical rods (5) are arranged on two sides of the guardrail (2), and the vertical rods (5) are connected with the guardrail (2) through cross plate pieces (4);
a supporting table (6) is installed at the top of the vertical rod (5), an anti-falling net (7) is placed at the top of the supporting table (6), and a limiting column (8) penetrates through the attached end faces of the anti-falling net (7) and the supporting table (6);
the other end of the anti-falling net (7) is clamped and fixed through a support plate (11) and a locking bolt (12) which are arranged on the wall surface.
2. A high-altitude falling object blocking fence for building construction as claimed in claim 1, wherein the bottom of the supporting plate (11) is supported by a supporting column (10), and the other end of the supporting column (10) is connected with a wall frame (9) installed on the wall surface.
3. A high-drop barrier fence for building construction according to claim 2, characterized in that the wall frame (9) is of a triangular structure.
4. The high-altitude falling object blocking fence for building construction as claimed in claim 1, wherein the anti-falling net (7) comprises an upper net rack (701) and a lower net rack (702) which are symmetrically arranged, and the upper net rack (701) and the lower net rack (702) are connected through a connecting rod (703).
5. The high-altitude falling object blocking fence for building construction as claimed in claim 1, wherein four corners of the falling prevention net (7) are respectively fixed by two supporting tables (6) with the same structure matching with the limiting column (8) and the supporting plate (11) matching with the locking bolt (12).
6. A high-altitude falling object blocking fence for building construction according to claim 1, characterized in that a guardrail bar (3) is installed at the inner interval of the guardrail (2).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202022514410.1U CN214740094U (en) | 2020-11-03 | 2020-11-03 | High-altitude falling object blocking fence for building construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202022514410.1U CN214740094U (en) | 2020-11-03 | 2020-11-03 | High-altitude falling object blocking fence for building construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN214740094U true CN214740094U (en) | 2021-11-16 |
Family
ID=78574841
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202022514410.1U Expired - Fee Related CN214740094U (en) | 2020-11-03 | 2020-11-03 | High-altitude falling object blocking fence for building construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN214740094U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114856248A (en) * | 2022-06-07 | 2022-08-05 | 中建八局第三建设有限公司 | Corridor type safety channel applied to sloping type deep foundation pit and construction method |
-
2020
- 2020-11-03 CN CN202022514410.1U patent/CN214740094U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114856248A (en) * | 2022-06-07 | 2022-08-05 | 中建八局第三建设有限公司 | Corridor type safety channel applied to sloping type deep foundation pit and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206233562U (en) | The safety device of revealing all the details of hydraulic pressure lift form frame system | |
| CN108412187B (en) | A construction device and construction method for the outer frame structure of ultra-high conjoined towers | |
| CN107806237A (en) | A kind of high building hydraulic climbing protecting screen and its construction method | |
| CN110644800A (en) | Outer periphery of construction edge and using method thereof | |
| CN112267661B (en) | Climbing frame convenient to adjust for construction industry | |
| CN202272594U (en) | Mounting structure of protective fence at top of elevator car | |
| CN217518117U (en) | Novel unsettled cage platform | |
| CN213898056U (en) | Scaffold with prevent function of falling | |
| CN112431398B (en) | A protective frame and a safety protection device for high-altitude operations | |
| CN209891694U (en) | Building faces limit structure post construction protection frame | |
| CN220621173U (en) | Face limit protection device of assembled building | |
| CN221277184U (en) | Auxiliary installation operation platform | |
| CN203257118U (en) | Constructional engineering safety protection rebar protective shed | |
| CN207847037U (en) | A kind of high building hydraulic climbing protecting screen | |
| CN219808613U (en) | Safety device for classroom corridor | |
| CN205000691U (en) | Novel steel construction factory building that takes precautions against earthquakes | |
| CN222121071U (en) | Assembled building protection canopy | |
| CN216712761U (en) | Bridge pier column tie beam is pour construction and is used safe cat ladder from top to bottom | |
| CN223707193U (en) | Protective supporting structure for construction | |
| CN211256690U (en) | Pier column high-altitude operation fixed net type safety protection system | |
| CN211923615U (en) | Anti-falling safety device for building | |
| CN218117314U (en) | Safety protection device | |
| CN210918856U (en) | Cat ladder for construction | |
| CN212743306U (en) | Dry process kiln preheater overhauls cross operation safety device | |
| CN221095956U (en) | Outer facade protective structure of overhanging platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211116 |