CN221073640U - Support that high altitude construction constructor was prevented falling - Google Patents
Support that high altitude construction constructor was prevented falling Download PDFInfo
- Publication number
- CN221073640U CN221073640U CN202322406147.8U CN202322406147U CN221073640U CN 221073640 U CN221073640 U CN 221073640U CN 202322406147 U CN202322406147 U CN 202322406147U CN 221073640 U CN221073640 U CN 221073640U
- Authority
- CN
- China
- Prior art keywords
- connecting rod
- support frame
- rods
- support
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 12
- 230000003014 reinforcing effect Effects 0.000 claims description 8
- 238000005452 bending Methods 0.000 claims description 3
- 230000009194 climbing Effects 0.000 abstract description 3
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 239000003351 stiffener Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000000523 sample Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model discloses an anti-falling bracket for an overhead operation constructor, which comprises an upper supporting platform, wherein the upper supporting platform comprises 2 supporting rods with front ends connected, the tail ends of the 2 supporting rods are provided with a first vertical downward connecting rod, the lower ends of the connecting parts of the 2 supporting rods are connected with a first supporting frame, the rear ends of the 2 supporting rods are connected with a second supporting frame, the second supporting frame is connected with the bottom of the first supporting frame, and a plurality of connecting cross rods are arranged between the 2 supporting rods; the climbing device can be used for constructors to climb up and down, and can be used for multiple times; simple structure, durable, be convenient for operation, with low costs, convenient personnel high altitude construction point operation has improved the operating efficiency after the use.
Description
Technical Field
The utility model relates to the field of safety equipment for overhead operation, in particular to a falling-preventing bracket for an overhead operation constructor.
Background
In the field construction process, because vertical structures such as vertical wall, post, pier stud are high, when carrying out the reinforcement more than 2 meters, constructor appears for convenient operation: 1. the construction operators cannot perform up-and-down operation, so that the operators perform up-and-down operation by stepping on the bound steel bars, and the finished products after construction are damaged; 2. the direct connection station carries out steel bar binding operation on the steel bar framework, so that the potential safety hazard is great; 3. the scaffold is not firm in erection, the scaffold plates on the working surface are not firm in laying, and a probe plate appears, so that the potential safety hazard is great; 4. when the construction is completed in the construction replacement place, the original built frame needs to be removed, and then the frame is built again in a new working position, so that the labor and the work efficiency are wasted; the construction phenomenon is easy to cause serious potential safety hazard and damage to finished products.
Disclosure of utility model
In order to solve the problems, the utility model adopts the following technical scheme.
The utility model provides a support that high altitude construction constructor was prevented falling, includes upper portion supporting platform, and upper portion supporting platform includes the bracing piece that 2 front ends link to each other, and the end of 2 bracing pieces is equipped with vertical decurrent connecting rod one, and the lower extreme of 2 bracing piece junctions is connected with support frame one, and the rear end and the support frame two of 2 bracing pieces are connected, and support frame two is connected with the bottom of support frame one, is equipped with a plurality of connection horizontal pole between 2 bracing pieces.
Further, upper portion supporting platform still is equipped with 2 stiffener, and the stiffener is the structure of bending, and the stiffener is installed in the inboard of bracing piece and connecting rod one.
Further, the first support frame comprises a second connecting rod which is obliquely arranged and a third connecting rod which is vertically arranged, and the second connecting rod is connected with the supporting rod and the third connecting rod.
Further, the support frame II comprises a connecting rod IV which is horizontally arranged, the connecting rod IV is connected with the upper end of the support rod, the two ends of the support rod IV are respectively connected with a connecting rod V which is inclined downwards, the tail end of the connecting rod V is connected with a connecting rod VI which is vertical downwards, and 2 connecting rods VI are welded with the connecting rod III.
Advantageous effects
Compared with the prior art, the utility model has the advantages that:
The operator stands on the bracket to perform safe operation, so that the operation safety risk of the operator can be greatly reduced; the climbing device can be used for constructors to climb up and down, and can be used for multiple times; simple structure, durable, be convenient for operation, with low costs, convenient personnel high altitude construction point operation has improved the operating efficiency after the use.
Drawings
FIG. 1 is a schematic diagram of the present utility model.
Fig. 2 is a schematic view of another view of the present utility model.
Fig. 3 is a top view of the present utility model.
Detailed Description
The present utility model will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present utility model more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the utility model.
As shown in the figure, the utility model discloses a falling-preventing bracket for an overhead operation constructor, which comprises an upper supporting platform 1, wherein the upper supporting platform 1 comprises 2 supporting rods 2 with front ends connected, and the included angle of the 2 supporting rods 2 is 22 degrees. The end of the 2 support rods 2 is provided with a vertical downward connecting rod I3, the lower end of the joint of the 2 support rods 2 is connected with a support frame I4, the rear end of the 2 support rods 2 is connected with a support frame II 5, the support frame II 5 is connected with the bottom of the support frame I4, and a plurality of connecting cross bars 6 are arranged between the 2 support rods 2. The connecting cross bar 6 is convenient for the operator to stand. The operator can step on the first support frame 4 and the second support frame 5 and climb onto the upper support platform 1. Work is performed on the upper support platform 1. The length of the welding seam between the first support frame 4, the second support frame 5 and the upper support platform 1 is 9mm.
The utility model can be used in superposition, e.g
The first step: hanging a bracket on the steel bar net sheet with the bound lower part, and climbing the personnel upwards;
And a second step of: after the operator stands on the bracket, a second bracket is hung on the upper part;
and a third step of: the operator goes up to the second bracket;
Fourth step: after the worker stands on the second bracket, the first bracket below the worker is taken off;
Fifth step: the first stand is suspended … … further upward in sequence up to the working level.
In an embodiment of the present utility model, the upper supporting platform 1 is further provided with 2 reinforcing rods 7, the reinforcing rods 7 are of a bending structure, and the reinforcing rods 7 are installed inside the supporting rods 2 and the first connecting rod 3. The reinforcing rod 7 plays a reinforcing role. The reinforcing rod 7 and the first connecting rod 3 are hung on the reinforcing mesh.
In an embodiment of the present utility model, the first support frame 4 includes a second connecting rod 8 disposed obliquely and a third connecting rod 9 disposed vertically, and the second connecting rod 8 connects the support rod 2 and the third connecting rod 9.
In an embodiment of the utility model, the second support frame 5 comprises a fourth connecting rod 10 which is horizontally arranged, the fourth connecting rod 10 is connected with the upper end of the support rod 2, two ends of the fourth connecting rod 10 are respectively connected with a fifth connecting rod 11 which is inclined downwards, the tail end of the fifth connecting rod 11 is connected with a sixth connecting rod 12 which is vertical downwards, and the sixth connecting rods 12 are welded with the third connecting rod 9. The operator steps between the connecting rods six 12 and three 9 and climbs to the upper support platform 1. The included angle of the 2 connecting rods five 11 is 22 degrees.
The above description is only of the preferred embodiments of the present utility model; the scope of the utility model is not limited in this respect. Any person skilled in the art, within the technical scope of the present disclosure, may apply to the present utility model, and the technical solution and the improvement thereof are all covered by the protection scope of the present utility model.
Claims (4)
1. The utility model provides a support that high altitude construction constructor was prevented falling which characterized in that: including upper portion supporting platform, upper portion supporting platform includes the bracing piece that 2 front ends link to each other, and the end of 2 bracing pieces is equipped with vertical decurrent connecting rod one, and the lower extreme of 2 bracing piece junctions is connected with support frame one, and the rear end and the support frame two of 2 bracing pieces are connected, and support frame two is connected with the bottom of support frame one, is equipped with a plurality of connection horizontal pole between 2 bracing pieces.
2. The aerial work constructor fall protection bracket according to claim 1, wherein: the upper supporting platform is also provided with 2 reinforcing rods which are of a bending structure and are arranged on the inner sides of the first supporting rods and the first connecting rods.
3. The aerial work constructor fall protection bracket according to claim 1, wherein: the first support frame comprises a second connecting rod which is obliquely arranged and a third connecting rod which is vertically arranged, and the second connecting rod is connected with the supporting rod and the third connecting rod.
4. A fall arrest bracket for an overhead working personnel according to claim 3, wherein: the support frame II comprises a connecting rod IV which is horizontally arranged, the connecting rod IV is connected with the upper end of the support rod, the two ends of the support rod IV are respectively connected with a connecting rod V which is inclined downwards, the tail end of the connecting rod V is connected with a connecting rod V which is vertical downwards, and 2 connecting rods V are welded with the connecting rod V.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322406147.8U CN221073640U (en) | 2023-09-04 | 2023-09-04 | Support that high altitude construction constructor was prevented falling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322406147.8U CN221073640U (en) | 2023-09-04 | 2023-09-04 | Support that high altitude construction constructor was prevented falling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN221073640U true CN221073640U (en) | 2024-06-04 |
Family
ID=91273304
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322406147.8U Active CN221073640U (en) | 2023-09-04 | 2023-09-04 | Support that high altitude construction constructor was prevented falling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN221073640U (en) |
-
2023
- 2023-09-04 CN CN202322406147.8U patent/CN221073640U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212957538U (en) | Roof flower frame beam and outer wall decoration construction movable operation platform | |
CN221073640U (en) | Support that high altitude construction constructor was prevented falling | |
CN201793330U (en) | Gantry hanger frame device | |
CN107059641B (en) | Goods shelf type pier body outer scaffold | |
CN112573341B (en) | Column top hoisting mechanism and construction method thereof | |
CN213951973U (en) | Adjustable construction platform | |
CN211499681U (en) | Movable overhanging working frame | |
CN209040527U (en) | A kind of scaffold cradle structure | |
CN213802471U (en) | Guardrail is overhauld in construction elevator installation | |
CN212002185U (en) | Construction equipment is increased to landing leg behind hanging flower basket | |
CN113202280A (en) | Conversion bracket type steel structure for steel structure high-altitude construction and construction method thereof | |
CN215925721U (en) | Cantilever hanging rack for steel box girder | |
CN206581578U (en) | Double-layer basket constructing device for overhanging scaffold | |
CN211286560U (en) | Spherical node suspension adjustable operation platform | |
CN218912192U (en) | Clamp type operation platform suitable for box girder | |
CN211114704U (en) | Interim construction platform of tunnel maintenance | |
CN215484589U (en) | Scaffold board structure | |
CN212897458U (en) | Operation platform for self-made movable suspension operation | |
CN211114943U (en) | A high outer wall protector of security for construction | |
CN216913799U (en) | Simple and easy wire rope stores pylon of assemblization | |
CN203640245U (en) | Scaffold structure for building exterior wall construction | |
CN217439492U (en) | High-altitude overhanging movable operation platform | |
CN112411568B (en) | Foundation pit concrete support beam bottom form removal device and form removal method | |
CN217203935U (en) | Trash rack pier template hoisting device | |
CN212897484U (en) | High-altitude operation platform for constructional engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |