CN220999016U - Lifting equipment for building construction - Google Patents

Lifting equipment for building construction Download PDF

Info

Publication number
CN220999016U
CN220999016U CN202322760493.6U CN202322760493U CN220999016U CN 220999016 U CN220999016 U CN 220999016U CN 202322760493 U CN202322760493 U CN 202322760493U CN 220999016 U CN220999016 U CN 220999016U
Authority
CN
China
Prior art keywords
lifting
fixedly connected
motor
rod
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322760493.6U
Other languages
Chinese (zh)
Inventor
杨瀚
罗忠余
李祥
唐忠茂
朱备
李东旭
杨岸青
邓正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan No4 Construction Co ltd
Original Assignee
Sichuan No4 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan No4 Construction Co ltd filed Critical Sichuan No4 Construction Co ltd
Priority to CN202322760493.6U priority Critical patent/CN220999016U/en
Application granted granted Critical
Publication of CN220999016U publication Critical patent/CN220999016U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses lifting equipment for building construction, which comprises a lifting rod, wherein the bottom end of the lifting rod is fixedly connected with a mounting plate, the top of the mounting plate is fixedly connected with a driving mechanism, the outer side of the mounting plate is fixedly connected with a lifting frame, the inner side of the lifting frame is fixedly connected with a reinforcing component, the outer side of the lifting rod is fixedly connected with a motor plate, the top of the motor plate is fixedly connected with an adjusting motor, the driving end of the adjusting motor is fixedly connected with an adjusting gear, the top of the lifting rod is fixedly connected with a rotating flange, the top of the rotating flange is fixedly connected with a suspension arm main body, the inner side of the top of the suspension arm main body is provided with a sliding groove, and pulleys are movably connected in the sliding groove.

Description

Lifting equipment for building construction
Technical Field
The utility model relates to the technical field, in particular to hoisting equipment for building construction.
Background
The patent document with the prior art publication number of CN115893232B provides hoisting equipment and a hoisting method for building construction, relates to the technical field of hoisting or hoisting of construction building materials, and mainly comprises a frame and a hoisting mechanism, wherein the frame comprises a supporting part and a mounting part, and the mounting part is provided with a first supporting table and a second supporting table; the hoisting mechanism comprises a main hoisting assembly and an auxiliary hoisting assembly, and the main hoisting assembly and the auxiliary hoisting assembly are respectively arranged on the first supporting table and the second supporting table; a universal connecting piece is arranged between the main hoisting component and the auxiliary hoisting component, the universal connecting piece comprises a first end head and a second end head, the first end head is rotationally connected with the main hoisting component, and the second end head is in universal connection with the auxiliary hoisting component; the hoisting method is realized based on the hoisting equipment. According to the hoisting equipment and the hoisting method, the main hoisting assembly and the auxiliary hoisting assembly are arranged, and the relatively free adjusting space is reserved between the main hoisting assembly and the auxiliary hoisting assembly, so that the multi-point hoisting operation at different positions can be handled, and the stable hoisting requirements of increasingly complex and irregularly-shaped hoisted objects can be met.
However, the existing lifting equipment for building construction is low in safety, when the lifting equipment is used for lifting building materials from below a building to the building, as the boom rod of the lifting equipment is suspended outside the building, when the building materials are lifted to the building, workers are required to manually pull the boom rod to enable the boom rod to be positioned in the building, and when the boom rod is pulled, most of the body of the workers is suspended outside the building, so that the problem of operation safety accidents is easily caused when faults occur.
Disclosure of utility model
(One) solving the technical problems
The utility model provides lifting equipment for building construction, which aims to solve the problems in the background technology.
(II) technical scheme
In order to achieve the above purpose, the utility model is realized by the following technical scheme: the utility model provides a lifting device for construction, includes the lifter, the bottom fixedly connected with mounting panel of lifter, the top fixedly connected with actuating mechanism of mounting panel, the outside fixedly connected with lifting frame of mounting panel, the inboard fixedly connected with reinforcing assembly of lifting frame, the outside fixedly connected with motor plate of lifter, the top fixedly connected with accommodate motor of motor plate, accommodate motor's drive end fixedly connected with adjusting gear, the top fixedly connected with flange of lifter, flange's top fixedly connected with davit main part, the spout has been seted up to the top inboard of davit main part, swing joint has the pulley in the spout, the top fixedly connected with regulating spindle of davit main part, the top fixedly connected with drive gear of regulating spindle, the outside fixedly connected with davit pole of davit main part, the inboard swing joint of the one end of davit pole lifts by crane the pulley.
Further preferably, the driving mechanism comprises a motor frame, a lifting motor, a rope collecting tube and a lifting rope, wherein the motor frame is fixedly connected to the top of the mounting plate, the lifting motor is fixedly connected to the top of the motor frame, the rope collecting tube is fixedly connected to the driving end of the lifting motor, and the lifting rope is movably connected to the outer side of the rope collecting tube.
Further preferably, the lifting rope is movably connected with the pulley and the lifting pulley respectively, and one end of the lifting rope is movably connected with the mounting assembly.
Further preferably, the installation component includes go-between, hoist cable and lifting hook, go-between swing joint is in the one end of lifting rope, the outside swing joint of go-between has the hoist cable, the both ends swing joint of hoist cable has the lifting hook.
Further preferably, one side of the lifting frame is movably connected with an adjusting rod, and the top of the lifting frame is penetrated and movably connected with a bolt.
Further preferably, the reinforcing component comprises a reinforcing rod and a reinforcing support, wherein the reinforcing rod is fixedly connected to the inner side of the lifting frame, the reinforcing support is fixedly connected to the outer side of the reinforcing rod, and the reinforcing support is fixedly connected with the lifting rod through a bolt.
(III) beneficial effects
The utility model provides lifting equipment for building construction, which has the following beneficial effects:
(1) The lifting equipment for building construction is characterized in that through the lifting rod, the adjusting motor, the adjusting gear, the rotating flange, the lifting arm main body and the transmission gear, when the lifting equipment for building construction is used, a worker drives the lifting arm main body to lift by starting the lifting rod, so as to adjust the height of the lifting arm main body, after the lifting equipment is adjusted, the worker fixes building materials on a sling and fixes the building materials by using a hook, after the lifting equipment is fixed, the lifting motor is started, the lifting motor drives the rope collecting drum to rotate, and the rope collecting drum can wind up the lifting rope, the lifting rope will move up through the pulley and lift by crane the pulley to on carrying building material to building floor, then the staff starts accommodate motor, accommodate motor drives adjusting gear and rotates, and adjusting gear drives the davit main part through drive gear and will rotate through rotatory flange simultaneously, thereby adjust the davit pole to the building house in, this kind of structure sets up and has improved construction with lifting by crane equipment security, avoided the manual pulling of staff to hang the arm pole, appear the health unsettled outside the building house, thereby prevented the appearance of operation incident.
Drawings
FIG. 1 is a schematic view of the overall structure of the present utility model;
FIG. 2 is a schematic view of a part of the structure of the regulating motor of the present utility model;
FIG. 3 is a schematic view of a part of the construction of the hoist motor of the present utility model;
Fig. 4 is a schematic view of a partial structure of the sling according to the utility model.
In the figure: 1. an adjusting rod; 2. a lifting frame; 3. a plug pin; 4. a reinforcing rod; 5. reinforcing the support; 6. a mounting plate; 7. a motor frame; 8. lifting a motor; 801. a rope winding drum; 9. a hanging rope; 10. a connecting ring; 11. a sling; 12. a lifting hook; 13. a lifting rod; 14. a motor plate; 15. adjusting a motor; 16. an adjusting gear; 17. rotating the flange; 18. a boom body; 19. a chute; 20. an adjusting shaft; 21. a transmission gear; 22. a boom lever; 23. and (5) hoisting the pulley.
Detailed Description
The technical solutions of the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model, and it is apparent that the described embodiments are only some embodiments of the present utility model, but not all embodiments, and all other embodiments obtained by those skilled in the art without making creative efforts based on the embodiments of the present utility model are included in the protection scope of the present utility model.
Referring to fig. 1-4, the present utility model provides a technical solution: a lifting equipment for construction, including lifter 13, the bottom fixedly connected with mounting panel 6 of lifter 13, the top fixedly connected with actuating mechanism of mounting panel 6, the outside fixedly connected with lifting frame 2 of mounting panel 6, the inboard fixedly connected with reinforcing assembly of lifting frame 2, the outside fixedly connected with motor plate 14 of lifter 13, the top fixedly connected with accommodate motor 15 of motor plate 14, the drive end fixedly connected with adjusting gear 16 of accommodate motor 15, the top fixedly connected with flange 17 of lifter 13, the top fixedly connected with davit main part 18 of flange 17, spout 19 has been seted up to the top inboard of davit main part 18, swing joint pulley in the spout 19, the top fixedly connected with regulating spindle 20 of davit main part 18, the top fixedly connected with drive gear 21 of regulating spindle 20, the outside fixedly connected with davit pole 22 of davit main part 18, the inboard swing joint of one end of davit pole 22 has lifting pulley 23.
In this embodiment, specifically, actuating mechanism includes motor frame 7, lift by crane motor 8, receipts rope reel 801 and lifting rope 9, motor frame 7 fixed connection is at the top of mounting panel 6, the top fixedly connected with of motor frame 7 lifts by crane motor 8, lift by crane motor 8's drive end fixedly connected with receipts rope reel 801, the outside swing joint of receipts rope reel 801 has lifting rope 9, through starting lift by crane motor 8, lift by crane motor 8 drives receipts rope reel 801 rotation, receipts rope reel 801 will roll up lifting rope 9, lifting rope 9 will move through pulley and lifting pulley 23 and rise, thereby on carrying building material to the building floor.
In this embodiment, specifically, the lifting rope 9 is movably connected with the pulley and the lifting pulley 23 respectively, and one end of the lifting rope 9 is movably connected with the installation component, so that the lifting rope 9 is more flexible in the lifting process through the pulley and the lifting pulley 23.
In this embodiment, specifically, the installation component includes go-between 10, hoist cable 11 and lifting hook 12, and go-between 10 swing joint is in the one end of lifting rope 9, and the outside swing joint of go-between 10 has hoist cable 11, and the both ends swing joint of hoist cable 11 has lifting hook 12, through wrapping building material with hoist cable 11 and using lifting hook 12 to fix, can be with building material fixed mounting.
In this embodiment, specifically, one side of the lifting frame 2 is movably connected with an adjusting rod 1, the top of the lifting frame 2 is movably connected with a bolt 3 in a penetrating manner, the adjusting rod 1 is pulled out by pulling out the bolt 3, and when a certain length is pulled out, the bolt 3 is inserted into the lifting frame 2 and the adjusting rod 1, so that the weighting position space can be adjusted.
In this embodiment, specifically, the reinforcement subassembly includes stiffening rod 4 and reinforcing support 5, and stiffening rod 4 fixed connection is in the inboard of lifting frame 2, and the outside fixedly connected with of stiffening rod 4 consolidates support 5, and reinforcing support 5 passes through bolt and lifter 13 fixed connection, has played the reinforcement effect through stiffening rod 4 and reinforcing support 5, avoids lifter 13 to appear cracked problem.
Working principle: after the utility model is installed, firstly, the installation and fixation and safety protection of the utility model are checked, when the lifting equipment for building construction is used, a worker starts the lifting rod 13, the lifting rod 13 drives the lifting arm main body 18 to lift, so that the height of the lifting arm main body 18 is adjusted, after the lifting arm main body 18 is adjusted, the worker fixes building materials on the sling 11 and uses the lifting hook 12 to fix, after the lifting motor 8 is started, the lifting motor 8 drives the rope collecting drum 801 to rotate, the rope collecting drum 801 winds up the lifting rope 9, the lifting rope 9 moves upwards through the pulley and the lifting pulley 23, so that the building materials are conveyed to a building floor, then the worker starts the adjusting motor 15, the adjusting motor 15 drives the adjusting gear 16 to rotate, and meanwhile, the adjusting gear 16 drives the lifting arm main body 18 to rotate through the rotary flange 17, so that the lifting arm lever 22 is adjusted into a building house, so that the use process of the utility model is completed, and the utility model has simple structure and safe and convenient use.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. Lifting equipment for building construction, comprising a lifting rod (13), characterized in that: the lifting device comprises a lifting rod (13), wherein a mounting plate (6) is fixedly connected to the bottom end of the lifting rod (13), a driving mechanism is fixedly connected to the top of the mounting plate (6), a lifting frame (2) is fixedly connected to the outer side of the mounting plate (6), a reinforcing component is fixedly connected to the inner side of the lifting frame (2), a motor plate (14) is fixedly connected to the outer side of the lifting rod (13), an adjusting motor (15) is fixedly connected to the top of the motor plate (14), an adjusting gear (16) is fixedly connected to the driving end of the adjusting motor (15), a rotary flange (17) is fixedly connected to the top end of the lifting rod (13), a lifting arm main body (18) is fixedly connected to the inner side of the top end of the lifting arm main body (18), a sliding groove (19) is formed in the inner side of the top end of the lifting arm main body (18), a pulley is movably connected to the inner side of the sliding groove (19), an adjusting shaft (20) is fixedly connected to the top end of the adjusting shaft (20), a driving gear (21), a lifting arm rod (22) is fixedly connected to the outer side of the lifting arm main body (18), and a lifting pulley (23) is movably connected to the inner side of the lifting arm (22).
2. A hoisting device for use in building construction according to claim 1, characterized in that: the driving mechanism comprises a motor frame (7), a lifting motor (8), a rope collecting tube (801) and a lifting rope (9), wherein the motor frame (7) is fixedly connected to the top of the mounting plate (6), the lifting motor (8) is fixedly connected to the top of the motor frame (7), the rope collecting tube (801) is fixedly connected to the driving end of the lifting motor (8), and the lifting rope (9) is movably connected to the outer side of the rope collecting tube (801).
3. A hoisting device for use in building construction according to claim 2, characterized in that: the lifting rope (9) is movably connected with the pulley and the lifting pulley (23) respectively, and one end of the lifting rope (9) is movably connected with the mounting assembly.
4. A hoisting device for use in building construction according to claim 3, characterized in that: the installation component includes go-between (10), hoist cable (11) and lifting hook (12), go-between (10) swing joint is in the one end of lifting rope (9), the outside swing joint of go-between (10) has hoist cable (11), the both ends swing joint of hoist cable (11) has lifting hook (12).
5. A hoisting device for use in building construction according to claim 1, characterized in that: one side of the lifting frame (2) is movably connected with an adjusting rod (1), and the top of the lifting frame (2) is penetrated and movably connected with a bolt (3).
6. A hoisting device for use in building construction according to claim 3, characterized in that: the reinforcing component comprises a reinforcing rod (4) and a reinforcing support (5), wherein the reinforcing rod (4) is fixedly connected to the inner side of the lifting frame (2), the reinforcing support (5) is fixedly connected to the outer side of the reinforcing rod (4), and the reinforcing support (5) is fixedly connected with the lifting rod (13) through bolts.
CN202322760493.6U 2023-10-16 2023-10-16 Lifting equipment for building construction Active CN220999016U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322760493.6U CN220999016U (en) 2023-10-16 2023-10-16 Lifting equipment for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322760493.6U CN220999016U (en) 2023-10-16 2023-10-16 Lifting equipment for building construction

Publications (1)

Publication Number Publication Date
CN220999016U true CN220999016U (en) 2024-05-24

Family

ID=91115999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322760493.6U Active CN220999016U (en) 2023-10-16 2023-10-16 Lifting equipment for building construction

Country Status (1)

Country Link
CN (1) CN220999016U (en)

Similar Documents

Publication Publication Date Title
CN201971567U (en) Small-sized indoor sand hoister
CN218320259U (en) Auxiliary hoisting reinforcing device for wind power construction
CN111270861A (en) Curtain wall construction device
CN211850947U (en) Curtain wall construction device
CN109252733B (en) Attached self-climbing holding pole lifting system
CN220999016U (en) Lifting equipment for building construction
CN210366665U (en) Intelligent automatic unhooking device for marine crane
CN116374804A (en) Ton bag lifting hook
CN209583464U (en) A kind of movable arm tower crane pull rod
CN112299256A (en) Hoisting equipment with stable form hoisting device
CN218507351U (en) Hoisting mechanism for freight container
CN215479320U (en) High material hoisting device for construction of security
CN220283436U (en) Hoisting mechanism, wind power device thereof and full-automatic tower crane
JPH0124077Y2 (en)
CN219297012U (en) Self-jacking cable crane top portal frame
CN217439514U (en) Rail-mounted hanging basket for inward-inclined curtain wall
CN221396882U (en) Steel construction section bar hoist device
CN217838039U (en) A hoisting accessory is used in construction for transmission of electricity specialty
CN218058157U (en) Municipal administration sewer is hoisting apparatus for fence
CN216785468U (en) Hoisting equipment for construction of periphery of power transmission tower
CN212503707U (en) Maintenance crane of wind generating set
CN216512321U (en) Novel hanging beam structure for hoisting reinforcing steel bars
CN214611222U (en) Hoisting equipment among building engineering convenient to use
CN210854988U (en) Overweight protection device for crane hook
CN215797942U (en) Dedicated hoist of coiled material

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant