Building climbing frame for building Download PDFInfo
- Publication number
- CN220889352U CN220889352U CN202322621849.8U CN202322621849U CN220889352U CN 220889352 U CN220889352 U CN 220889352U CN 202322621849 U CN202322621849 U CN 202322621849U CN 220889352 U CN220889352 U CN 220889352U
- Authority
- CN
- China
- Prior art keywords
- building
- wall
- climbing frame
- waistband
- spout
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000009194 climbing Effects 0.000 title claims abstract description 31
- 238000000034 method Methods 0.000 abstract description 7
- 238000010276 construction Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000013013 elastic material Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model discloses a building climbing frame for a building, which comprises a safety belt, two upright posts and a plurality of cross bars, wherein two ends of the cross bars are respectively connected with the two upright posts, the front wall of the upright post on the left side is provided with a chute, a sliding block is arranged in the chute in a sliding way, cavities are formed in the cross bars on the lower side of the cross bars on the top, the left ends of the limiting blocks penetrate through the left walls of the cavities and the right walls of the chute to enter the chute, springs are connected between the right walls of the limiting blocks and the left walls of the cavities, a stepping rod is arranged above the cross bars, the bottom wall of the stepping rod is connected with a driving plate, the driving plate penetrates through the top wall of the cavity, the top wall of the limiting blocks is provided with a groove, the bottom wall of the driving plate is contacted with the right wall of the groove, the safety belt comprises a waistband and leg bands, the waistband can be bound on the waist of a human body, the leg bands can be bound on the left leg parts of the human body, connecting ropes are connected between the waistband and the leg bands through connecting pieces; this structure can promote the protection performance of staff's climbing in-process, prevents that the staff from falling from the eminence.
Description
Technical Field
The utility model relates to the technical field of building apparatuses, in particular to a building climbing frame for a building.
Background
The building construction refers to production activities in the engineering construction implementation stage, and is the construction process of various buildings. The building climbs the frame and is the instrument that the staff is used for climbing the building, through installing climbing the frame and use in the outside side of building, after climbing the frame installation and accomplishing, the staff climbs the high-rise building through climbing the frame, and current building climbs the frame and generally does not have safety protection measure, and constructor is in the climbing in-process, and in case the focus is unstable, falls down from the eminence after falling down, can cause huge damage.
Disclosure of utility model
Aiming at the defects in the prior art, the utility model provides the building climbing frame for the building, which can improve the protection performance of workers in the climbing process and prevent the workers from falling from high positions.
The utility model provides a frame is climbed to building for building, includes safety belt, two stands and many crossbars, and many crossbars longitudinal distribution, the crossbeam both ends are connected with two stands respectively, and open the left stand antetheca has the spout, and the slip is provided with the slider in the spout, all is provided with the cavity in the horizontal pole of top horizontal pole downside, and the stopper left end passes cavity left wall and spout right wall and get into in the spout, is connected with the spring between stopper right wall and the cavity left wall, and the horizontal pole top has the pedal pole, pedal pole diapire connection drive plate, the drive plate passes the cavity roof, and open flutedly on the roof of stopper, the right wall of recess is followed the whole downward sloping in the direction of right side orientation left side, the diapire and the recess right wall contact of drive plate, the safety belt includes waistband and leg area, the waistband can be bound at human waist, the leg area can be bound in human left leg portion, is connected with the connecting rope between waistband and the leg area, is connected through the connecting piece between leg area and the slider.
Preferably, two ends of the treading rod are respectively contacted with the two upright posts.
Preferably, the height of the upright is 10m-20m.
Preferably, the number of the cross bars is 20-30.
Preferably, the side wall of the upright post on the right side is provided with a plurality of first sliding grooves, first sliding blocks are arranged in the first sliding grooves in a sliding mode, the treading rods are connected with the first sliding blocks, and the treading rods correspond to the first sliding blocks one by one.
Preferably, the top wall of the stepping rod is connected with a first spring, and the top end of the first spring is connected with the bottom wall of the last cross rod.
Preferably, each pedal rod is connected with two first springs, and the two first springs are respectively positioned at the left part and the right part of the pedal rod.
Preferably, the plurality of crossbars are longitudinally and evenly distributed.
The beneficial effects of the utility model are as follows: through the cooperation of each subassembly in this technical scheme, during the use, bind the waistband at human waist, bind the leg area at human left leg portion, when upwards climbing, climbing personnel right leg upwards lifts, step on the pedal pole of last horizontal pole top, pedal pole downward movement this moment, drive plate downward movement, drive plate downward movement drive stopper right side motion, the stopper left end leaves the spout, the stopper can not block the slider this moment, climbing personnel left leg upwards lifts and steps on the pedal pole of last horizontal pole top, slider motion is to the horizontal pole top of trampling this moment, stopper on the downside horizontal pole returns promptly, in case climbing personnel focus is unstable like this, the stopper of downside blocks the slider, the position of safety belt can not drop, protect the staff, this structure can promote the protectiveness of staff's climbing in-process like this, prevent that the staff from falling from the eminence.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. Like elements or portions are generally identified by like reference numerals throughout the several figures. In the drawings, elements or portions thereof are not necessarily drawn to scale.
FIG. 1 is a front view of the present utility model;
FIG. 2 is a schematic view showing the sectional structure of the position A in FIG. 1 according to the present utility model;
Fig. 3 is a front view of the seat belt of the present utility model.
In the attached drawings, the device comprises a 1-upright post, a 2-cross rod, a 3-sliding groove, a 4-sliding block, a 5-cavity, a 6-limiting block, a 7-stepping rod, an 8-driving plate, a 9-groove, a 10-spring, an 11-waistband, a 12-leg strap, a 13-connecting rope, a 14-connecting piece, a 15-first sliding groove, a 16-first sliding block and a 17-first spring.
Detailed Description
Embodiments of the technical scheme of the present utility model will be described in detail below with reference to the accompanying drawings. The following examples are only for more clearly illustrating the technical aspects of the present utility model, and thus are merely examples, and are not intended to limit the scope of the present utility model.
It is noted that unless otherwise indicated, technical or scientific terms used herein should be given the ordinary meaning as understood by one of ordinary skill in the art to which this utility model belongs.
Example 1
As shown in fig. 1-3, in this embodiment, a building climbing frame for building is provided, including a safety belt, two upright posts 1 and a plurality of cross bars 2, a plurality of cross bars 2 are longitudinally distributed, two ends of each cross bar 2 are respectively connected with two upright posts 1, the front wall of each upright post 1 on the left side is opened with a chute 3, a sliding block 4 is arranged in the chute 3 in a sliding manner, cavities 5 are all arranged in the cross bars 2 on the lower side of each top cross bar 2, the left end of each limiting block 6 passes through the left wall of each cavity 5 and the right wall of each chute 3, a spring 10 is connected between the right wall of each limiting block 6 and the left wall of each cavity 5, a pedal rod 7 is arranged above each cross bar 2, a bottom wall of each pedal rod 7 is connected with a driving plate 8, each driving plate 8 passes through the top wall of each cavity 5, the top wall of each limiting block 6 is opened with a groove 9, the right wall of each groove 9 is integrally inclined downwards in the direction from the right side to the left side, each safety belt comprises a waistband 11 and a leg belt 12, each waistband 11 can be bound on the waist of a human body, each leg belt 12 can be bound on the waist, each waistband 12 can be bound on the waist of the human body, and each leg belt 12 can be connected with a leg belt 12 through a connecting rope 14, and a leg belt 14.
Through the cooperation of each subassembly in this embodiment, during the use, bind waistband 11 at human waist, bind leg area 12 at human left leg portion, the height and the slider 4 basic unanimity of leg area 12 this moment, when upwards climbing, climbing personnel right side leg upwards lifts, step on the trampling pole 7 of last horizontal pole 2 top, trample pole 7 down motion this moment, drive corresponding drive plate 8 down motion drive stopper 6 right side motion, stopper 6 left end leaves spout 3, this stopper 6 can not block slider 4 this moment, climbing personnel left side leg upwards lifts tramples on trampling pole 7 of last horizontal pole 2 top, slider 4 moves to the horizontal pole 2 top that tramples this moment, stopper 6 in the downside horizontal pole 2 returns promptly, in case climbing personnel focus unstably falls down like this, stopper 6 of downside blocks slider 4, the position of safety belt can not drop, the safety belt protects staff, the protection performance of this structure in-process can promote staff's climbing, prevent that staff from falling from the eminence.
In this embodiment, the connecting member 14 is an elastic connecting member, such as an elastic material rod, and can be deformed moderately to supply the requirement of leg movement, and meanwhile, the slider 4 can be driven to move upwards in the process of lifting the left leg upwards.
In this embodiment, two ends of the pedal rod 7 are respectively contacted with the two upright posts 1.
The height of the upright 1 in this embodiment is 10m-20m.
In this embodiment, the number of the cross bars 2 is 20-30.
In this embodiment, the side wall of the upright post 1 on the right side is provided with a plurality of first sliding grooves 15, a first sliding block 16 is slidably arranged in the first sliding grooves 15, the treading rods 7 are connected with the first sliding blocks 16, and the treading rods 7 are in one-to-one correspondence with the first sliding blocks 16. In this embodiment, a first sliding groove 15 is provided, a first sliding block 16 is provided in the first sliding groove 15, and the treading rod 7 is connected with the first sliding block 16, so as to ensure the stability of the up-and-down movement of the treading rod 7.
In this embodiment, the top wall of the pedal rod 7 is connected with a first spring 17, and the top end of the first spring 17 is connected with the bottom wall of the previous cross rod 2. In this embodiment, a first spring 17 is connected between the pedal rod 7 and the bottom wall of the previous cross rod 2, so that the pedal rod 7 returns after the foot leaves the pedal rod 7.
In this embodiment, two first springs 17 are connected to each pedal lever 7, and the two first springs 17 are respectively located at the left and right parts of the pedal lever 7. In this embodiment, two first springs 17 are connected to the pedal rod 7, and the two first springs 17 can further ensure the stability of the return of the pedal rod 7.
In this embodiment, the plurality of cross bars 2 are uniformly distributed longitudinally.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present utility model, and not for limiting the same; although the utility model has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit of the utility model, and are intended to be included within the scope of the appended claims and description.
Claims (8)
1. The utility model provides a building climbing frame for building, a serial communication port, including the safety belt, two stand (1) and many horizontal poles (2), many horizontal poles (2) longitudinal distribution, horizontal pole (2) both ends are connected with two stand (1) respectively, open on the front wall of left stand (1) has spout (3), slide in spout (3) is provided with slider (4), all be provided with cavity (5) in horizontal pole (2) of top horizontal pole (2) downside, stopper (6) left end is passed cavity (5) left wall and spout (3) right wall and is got into in spout (3), be connected with spring (10) between stopper (6) right wall and cavity (5) left wall, horizontal pole (2) top has pedal lever (7), pedal lever (7) diapire connection drive plate (8), drive plate (8) are passed cavity (5) roof, the roof of stopper (6) is opened flutedly (9), the right wall of recess (9) is whole downward sloping from the direction on the right side direction of the left side, the diapire and recess (8) right side wall and recess (9) get into spout (3), be connected with waistband (12) between the left side wall and waistband, waistband portion can be in waistband portion (11) can be bound to waistband portion, waistband portion (12) can be bound to human body, a connecting rope (13) is connected between the waistband (11) and the leg bands (12), and the leg bands (12) are connected with the sliding blocks (4) through connecting pieces (14).
2. Building climbing frame according to claim 1, characterized in that the two ends of the pedal rod (7) are respectively contacted with the two upright posts (1).
3. A building climbing frame according to claim 1, characterized in that the height of the upright (1) is 10m-20m.
4. The building climbing frame for building according to claim 1, wherein the number of the cross bars (2) is 20-30.
5. The building climbing frame for building according to claim 1, wherein a plurality of first sliding grooves (15) are formed in the side wall of the upright post (1) on the right side, first sliding blocks (16) are arranged in the first sliding grooves (15) in a sliding mode, the treading rods (7) are connected with the first sliding blocks (16), and the treading rods (7) are in one-to-one correspondence with the first sliding blocks (16).
6. The building climbing frame for building according to claim 1, wherein the top wall of the pedal rod (7) is connected with a first spring (17), and the top end of the first spring (17) is connected with the bottom wall of the previous cross rod (2).
7. The building climbing frame for building according to claim 6, wherein two first springs (17) are connected to each pedal rod (7), and the two first springs (17) are respectively located at the left part and the right part of the pedal rod (7).
8. A building climbing frame according to claim 1, characterized in that the plurality of crossbars (2) are uniformly distributed longitudinally.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322621849.8U CN220889352U (en) | 2023-09-26 | 2023-09-26 | Building climbing frame for building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322621849.8U CN220889352U (en) | 2023-09-26 | 2023-09-26 | Building climbing frame for building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220889352U true CN220889352U (en) | 2024-05-03 |
Family
ID=90871337
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322621849.8U Active CN220889352U (en) | 2023-09-26 | 2023-09-26 | Building climbing frame for building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220889352U (en) |
-
2023
- 2023-09-26 CN CN202322621849.8U patent/CN220889352U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN220889352U (en) | Building climbing frame for building | |
CN205513556U (en) | Movable substation overhauls insulating height bench | |
CN202892814U (en) | Alternate vertical climbing device | |
CN102780175A (en) | Portable seat for telegraph pole climbing work | |
CN205531255U (en) | Construction scaffold | |
CN208633574U (en) | It is a kind of with preventing people from falling the safety net of effect | |
CN109364440A (en) | A kind of Electrician Operation step ladder | |
CN207654634U (en) | A kind of Skidproof climbers for climbing electric pole | |
CN213942019U (en) | Adjustable exerciser | |
CN206957566U (en) | A kind of combined type steps on bar repairing Anti-slipping ladder | |
CN216740630U (en) | Automatic descending connecting rod | |
CN215136396U (en) | Aerobics exercises training equipment | |
CN208193271U (en) | Its rail parallel bar training system | |
CN108525224B (en) | Parent-child interaction outdoor ball pushing and falling device | |
CN210355816U (en) | Multifunctional outdoor exercise fitness equipment | |
CN208405936U (en) | A kind of parent-child interaction open air election falling device | |
CN209113275U (en) | A kind of promotion Cargo Lift anti-falling safety device | |
CN110707595B (en) | Safety method for lightning arrester line to enter equipotential in live state | |
CN203139606U (en) | Electric bungee jumping bed | |
CN219136292U (en) | Lifting support for pruning fruit tree branches | |
CN206924352U (en) | Step on bar safety aid | |
CN219896957U (en) | Pier column climbing tool for bridge construction | |
CN219481369U (en) | Electric power safety device that ascends a height | |
CN110700611A (en) | Anti-falling net for power transmission construction | |
CN112546540B (en) | Chest expander for body-building exercise based on resistance increasing of electromagnetic principle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |