CN220814795U - Building construction frame - Google Patents

Building construction frame Download PDF

Info

Publication number
CN220814795U
CN220814795U CN202322354628.9U CN202322354628U CN220814795U CN 220814795 U CN220814795 U CN 220814795U CN 202322354628 U CN202322354628 U CN 202322354628U CN 220814795 U CN220814795 U CN 220814795U
Authority
CN
China
Prior art keywords
frame
fixed
balladeur train
fixed mounting
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322354628.9U
Other languages
Chinese (zh)
Inventor
陈柯帆
郑国辉
祝倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Art Vocational University
Original Assignee
Chengdu Art Vocational University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Art Vocational University filed Critical Chengdu Art Vocational University
Priority to CN202322354628.9U priority Critical patent/CN220814795U/en
Application granted granted Critical
Publication of CN220814795U publication Critical patent/CN220814795U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a building construction frame, which relates to the technical field of construction frames and comprises a construction frame top plate, wherein a protection frame is fixedly arranged at the upper end of the construction frame top plate, a frame door is arranged at an opening at the right end of the protection frame, a lifting mechanism is arranged at the front side of the upper end of the protection frame, a sliding rod is fixedly arranged at the rear side of the upper end of the protection frame, a sliding frame is slidingly connected with the outer side of the sliding rod, a fixing mechanism is arranged on the back surface of the sliding frame, clamping grooves are formed in the back surface of the sliding rod at equal intervals, and the sliding frame is connected with one of the clamping grooves at the outer side of the sliding rod in a clamping mode through the fixing mechanism. According to the utility model, by adopting the structure, the wind-up roller is arranged at the square hole at the upper end of the bracket, the wind-up roller is driven by the output end of the driving motor to wind up the steel wire, and the lifting hook at the lower end of the steel wire is utilized to conveniently transport construction materials, so that manual climbing up and down conveying materials are not needed, building construction is convenient, and the practicability is greatly enhanced.

Description

Building construction frame
Technical Field
The utility model belongs to the technical field of construction frames, and particularly relates to a building construction frame.
Background
The building construction frame refers to various supports which are erected for workers to operate and solve the problem of vertical and horizontal transportation on a construction site, and the general term of the building world refers to places which cannot be directly constructed and are used on an outer wall, an interior decoration or a high storey height on the construction site, and plays an important role in the construction field mainly for constructors to operate up and down or peripheral safety net enclosure and high-altitude installation members.
Patent bulletin number CN218933777U searched by Chinese patent network, a building construction frame relates to construction frame technical field. The climbing device comprises a supporting mechanism, a top mechanism and a climbing mechanism, wherein the top mechanism comprises a top plate, the climbing mechanism comprises a ladder rotating on one side of the bottom end of the top plate, the climbing mechanism rotates on one side of the bottom end of the supporting mechanism, the top end of the supporting mechanism is provided with the top mechanism, the bottom end of the top plate is provided with two supporting frames in a relative rotation mode, and the supporting mechanism comprises a fixed frame, and one end of the fixed frame is provided with a weight box. At present, the work frame among the prior art can realize the function of making things convenient for the staff to scramble through the climbing mechanism in the outside in the use, however the roof department of work frame is because lack the structure of making things convenient for the construction, for example, the staff need bow in the work process take the instrument or climb down through the manual work and carry construction article etc..
Disclosure of utility model
In view of the problems mentioned in the background art, it is an object of the present utility model to provide a construction frame to solve the problems mentioned in the background art above.
The technical aim of the utility model is realized by the following technical scheme:
The utility model provides a building construction frame, includes the scaffold roof, the upper end fixed mounting of scaffold roof has the protection frame, the frame door is installed to the opening part of protection frame right-hand member, hoist mechanism is installed to the upper end front side of protection frame, the upper end rear side fixed mounting of protection frame has the slide bar, the outside sliding connection of slide bar has the balladeur train, the back-mounted of balladeur train has fixed establishment, the back equidistance of slide bar leaves and is equipped with the draw-in groove, the balladeur train passes through one of them draw-in groove joint in fixed establishment and the slide bar outside and connects, the back of balladeur train is equipped with placement machine.
Further, as the preferred technical scheme, hoist mechanism includes the support, support fixed mounting is in the upper end of protection frame, square hole has all been seted up to the upper and lower both ends of support symmetry, the inboard rotation in square hole of support upper end is connected with the wind-up roll, one side fixed mounting of support has driving motor, the roller one end rotation of wind-up roll runs through the square hole pore wall of support upper end and driving motor's output fixed mounting, the outside round joint of wind-up roll is connected with the steel wire, the lower extreme fixed mounting of steel wire has the lifting hook.
Further, as the preferable technical scheme, the lower extreme fixedly connected with support arm of support, the back fixed mounting of support arm has same fixed block, the slot has been seted up to the lower extreme of fixed block, the lower extreme of fixed block passes through slot and protection frame grafting connection, the fixed block passes through screw and protection frame fixed mounting.
Further, as the preferable technical scheme, the back of balladeur train has seted up first rectangular hole, fixed establishment installs the inboard at first rectangular hole, the second rectangular hole has been seted up in the outside of balladeur train, the balladeur train passes through the spacing slip cap of second rectangular hole and establishes in the outside of slide bar, placement machine constructs the back at the balladeur train.
Further, as the preferred technical scheme, fixed establishment includes the fixed shell, fixed shell fixed mounting is inboard at first rectangular hole, the inboard sliding connection of fixed shell has the board that moves, one side fixed mounting who moves the board has the draw-in lever, one end that the board was kept away from to the draw-in lever slides and runs through the shell wall of fixed shell and one of them draw-in groove joint in the slide bar outside is connected, one side fixed mounting who moves the board and keep away from the draw-in lever has the spring, one end and the inner wall fixed mounting of fixed shell that move the board are kept away from to the spring, one side fixed mounting who moves the board and be close to the spring has the pull rod, one end of pull rod slides and runs through the shell wall fixedly connected with pull handle of fixed shell, the middle part of spring is run through to the one end of pull rod.
Further, as a preferable technical scheme, the inner side of the fixed shell is symmetrically provided with sliding grooves, the outer side of the moving plate is fixedly provided with sliding blocks, and the sliding blocks are in sliding connection with the sliding grooves.
Further, as the preferred technical scheme, placing the mechanism and including placing the box, place the positive lower extreme of box and rotate through hinge and balladeur train and be connected, the outside symmetry of placing the box rotates and is connected with the cardboard, the outside symmetry fixedly connected with card post of balladeur train, one side fixedly connected with stopper that the balladeur train was kept away from to the card post, the lower extreme recess and the card post joint of cardboard are connected.
In summary, the utility model has the following advantages:
Firstly, through installing the wind-up roll in the square hole department of support upper end, utilize driving motor output to drive the wind-up roll and roll up the steel wire, utilize the lifting hook of steel wire lower extreme, can conveniently transport construction material to need not the manual work to climb the transport material of climbing down, conveniently carry out construction, and then strengthen the practicality greatly;
Secondly, a pull rod connected with a pull handle pulls the moving plate, so that the moving plate compresses a spring in the fixed shell, meanwhile, a clamping rod connected with the moving plate is separated from a current clamping groove, then the sliding frame is moved to a designated position, and then the pull handle is loosened, so that the spring is reset to push the clamping rod connected with the moving plate to be clamped into the adjusted clamping groove, and the sliding frame can be conveniently adjusted and used according to the position of a construction wall surface;
thirdly, through rotating the installation on the balladeur train and placing the box, can be through rotating the draw-in groove card that the back utilized the lower extreme to go into the balladeur train left and right sides to have the draw-in groove card of stopper on placing a pair of pivoted cardboard on the box and go into on fixing can conveniently placing construction articles for use when needs use, has further made things convenient for the construction.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of the back structure of the protective frame of the present utility model;
FIG. 3 is an enlarged view of FIG. 2A in accordance with the present utility model;
Fig. 4 is a schematic structural view of the fixing mechanism of the present utility model.
Reference numerals: 1. the construction frame top plate, 2, a frame door, 3, a protection frame, 4, a lifting mechanism, 401, a winding roller, 402, a driving motor, 403, a lifting hook, 404, a square hole, 405, a steel wire, 406, a support, 7, a slot, 8, a fixed block, 9, a fixing mechanism, 901, a fixed shell, 902, a clamping rod, 903, a spring, 904, a moving plate, 905, a pull handle, 906, a pull rod, 10, a support arm, 11, a slide bar, 12, a sliding frame, 13, a clamping groove, 14, a first rectangular hole, 15, a second rectangular hole, 16, a placing mechanism, 161, a placing box, 162, a clamping column, 163, a clamping plate, 164, a limiting block, 17, a slide block, 18 and a slide groove.
Detailed Description
Example 1
Referring to fig. 1 to 4, the building construction frame according to the present embodiment includes a construction frame top plate 1, a protection frame 3 is fixedly mounted at the upper end of the construction frame top plate 1, a frame door 2 is mounted at the opening of the right end of the protection frame 3, a lifting mechanism 4 is mounted at the front side of the upper end of the protection frame 3, a sliding rod 11 is fixedly mounted at the rear side of the upper end of the protection frame 3, a sliding frame 12 is slidingly connected at the outer side of the sliding rod 11, a fixing mechanism 9 is mounted at the back of the sliding frame 12, clamping grooves 13 are formed at the back of the sliding rod 11 at equal intervals, the sliding frame 12 is connected with one of the clamping grooves 13 at the outer side of the sliding rod 11 in a clamping manner through the fixing mechanism 9, and a placing mechanism 16 is arranged at the back of the sliding frame 12; the back of the sliding frame 12 is provided with a first rectangular hole 14, the fixing mechanism 9 is arranged on the inner side of the first rectangular hole 14, the outer side of the sliding frame 12 is provided with a second rectangular hole 15, the sliding frame 12 is arranged on the outer side of the sliding rod 11 through a limiting sliding sleeve of the second rectangular hole 15, the placing mechanism 16 is arranged on the back of the sliding frame 12, the fixing mechanism 9 is arranged at the first rectangular hole 14 of the sliding frame 12, the sliding frame 12 can be conveniently fixed according to a clamping groove 13 at a corresponding adjusting position, and the sliding frame 12 can conveniently slide on the sliding rod 11 through the second rectangular hole 15 on the sliding frame 12; the top plate 1 of the construction frame is also provided with mounting holes, which are required to be mounted on a supporting part at the lower end of the construction frame, and the supporting part at the lower end of the construction frame is in the prior art, so that redundant description is not made here.
Example 2
Referring to fig. 1-2, on the basis of embodiment 1, in order to achieve the purpose of conveniently transporting construction articles, this embodiment has innovatively designed lifting mechanism 4, specifically, lifting mechanism 4 includes support 406, support 406 fixed mounting is in the upper end of protection frame 3, square hole 404 has all been seted up symmetrically at the upper and lower both ends of support 406, square hole 404 inboard rotation in support 406 upper end is connected with wind-up roll 401, one side fixed mounting of support 406 has driving motor 402, wind-up roll 401's roller one end rotates the square hole 404 pore wall that runs through support 406 upper end and driving motor 402's output fixed mounting, wind-up roll 401's outside round connection is connected with steel wire 405, steel wire 405's lower extreme fixed mounting has lifting hook 403, through installing wind-up roll 401 in support 406 upper end's square hole 404 department, utilize driving motor 402 output end to drive wind-up roll 401 to steel wire 405, utilize lifting hook 403 of steel wire 405 lower extreme, can conveniently transport construction materials, thereby the transport materials that need not to climb up and down manually, the convenience is constructed.
Referring to fig. 1-2, in order to achieve the purpose of facilitating the installation of the support 406, the lower end of the support 406 is fixedly connected with the support arm 10, the back of the support arm 10 is fixedly provided with the same fixing block 8, the lower end of the fixing block 8 is provided with the slot 7, the lower end of the fixing block 8 is connected with the protection frame 3 in a plugging manner through the slot 7, the fixing block 8 is fixedly installed with the protection frame 3 through a screw, the fixing frame with the slot 7 is installed at the upper end of the protection frame 3, and the fixing frame is fixedly connected with the support 406 through the support arm 10, so that the installation of the support 406 can be facilitated.
Example 3
Referring to fig. 1-4, in order to achieve the purpose of adjusting and placing a construction tool based on embodiment 1, the embodiment innovatively designs a placement mechanism 16 and an adjusting mechanism, specifically, a fixing mechanism 9 includes a fixing case 901, the fixing case 901 is fixedly mounted inside a first rectangular hole 14, a moving plate 904 is slidably connected to the inside of the fixing case 901, a clamping rod 902 is fixedly mounted on one side of the moving plate 904, one end of the clamping rod 902 away from the moving plate 904 is slidably connected through a case wall of the fixing case 901 and one of clamping grooves 13 on the outer side of a slide rod 11 in a clamping manner, a spring 903 is fixedly mounted on one side of the moving plate 904 away from the clamping rod 902, one end of the spring 903 away from the moving plate 904 is fixedly mounted on the inner wall of the fixing case 901, a pull rod 906 is fixedly arranged on one side of the moving plate 904, which is close to the spring 903, one end of the pull rod 906 penetrates through the shell wall of the fixed shell 901 in a sliding manner and is fixedly connected with a pull handle 905, one end of the pull rod 906 penetrates through the middle part of the spring 903, when the sliding frame 12 with the placement mechanism 16 needs to be adjusted and fixed, the moving plate 904 is pulled by the pull rod 906 connected with the pull handle 905, so that the spring 903 in the fixed shell 901 is compressed, meanwhile, the clamping rod 902 connected with the moving plate 904 is separated from the current clamping groove 13, then the sliding frame 12 is moved to a designated position, and then the pull handle 905 is released, so that the spring 903 is reset to push the clamping rod 902 connected with the moving plate 904 to be clamped into the adjusted clamping groove 13, and therefore, the sliding frame 12 can be adjusted and used conveniently according to the position of a construction wall surface; the placement machine 16 is including placing the box 161, place the positive lower extreme of box 161 and rotate through hinge and balladeur train 12 and be connected, the outside symmetry of placing the box 161 rotates and is connected with cardboard 163, the outside symmetry fixedly connected with card post 162 of balladeur train 12, one side fixedly connected with stopper 164 that the balladeur train 12 was kept away from to the card post 162, the lower extreme recess and the card post 162 joint of cardboard 163 are connected, through rotating the installation on balladeur train 12 and place the box 161, can be with placing the box 161 a pair of pivoted cardboard 163 through rotating the draw-in groove 13 card of back utilization lower extreme and going into the card post 162 that the balladeur train 12 left and right sides had stopper 164 on the fixed construction articles of can conveniently placing.
Referring to fig. 4, in order to achieve the purpose of facilitating the sliding of the moving plate 904 inside the fixed housing 901, in this embodiment, the inner side of the fixed housing 901 is symmetrically provided with sliding grooves 18, and the outer side of the moving plate 904 is fixedly provided with sliding blocks 17, and the sliding blocks 17 are in sliding connection with the sliding grooves 18.
The use principle and the advantages are that: during installation, firstly, install the scaffold roof 1 on the support body of scaffold, constructor passes through climbing structure on the support body, can conveniently step on the scaffold roof 1, through the protection frame 3 that has frame door 2, can protect constructor in the work progress, through installing wind-up roll 401 in the square hole 404 department of support 406 upper end, utilize driving motor 402 output to drive wind-up roll 401 and carry out the rolling to steel wire 405, utilize the lifting hook 403 of steel wire 405 lower extreme, can conveniently transport the construction material, need move board 904 through the pull rod 906 pulling of pull handle 905 connection when measuring or construction installation, make move board 904 to the spring 903 compression in the fixed casing 901, simultaneously move board 904 joint's clamping lever 902 and current draw-in groove 13 separation, then with the balladeur 12 remove appointed position department, then loosen the pull handle, make spring 903 reset promote the clamping lever 902 card that moves board 904 joint to adjust back 13 department can, through rotating on balladeur 12 and installing the box 161, need use when can rotate the box 161 and can rotate the stopper through the left and right side of the fixed support of the stopper 162 on the right side of the support frame 12.

Claims (7)

1. Building construction frame, including scaffold roof (1), its characterized in that: the utility model discloses a construction frame roof, including rack roof, slide bar (11), slide bar (12) are installed in the upper end fixed mounting of rack roof (1), protection frame (3), frame door (2) are installed to the opening part of protection frame (3) right-hand member, hoist mechanism (4) are installed to the upper end front side of protection frame (3), slide bar (11) are installed to the upper end rear side fixed mounting of protection frame (3), slide bar (11)'s outside sliding connection has balladeur train (12), back mounting of balladeur train (12) has fixed establishment (9), the back equidistance of slide bar (11) leaves and is equipped with draw-in groove (13), balladeur train (12) are connected through one of them draw-in groove (13) card in fixed establishment (9) and slide bar (11) outside, the back of balladeur train (12) is equipped with placing mechanism (16).
2. A building construction rack according to claim 1, wherein: lifting mechanism (4) are including support (406), support (406) fixed mounting is in the upper end of protection frame (3), square hole (404) have all been seted up to the upper and lower both ends of support (406) symmetry, square hole (404) inboard rotation of support (406) upper end is connected with wind-up roll (401), one side fixed mounting of support (406) has driving motor (402), the roller one end rotation of wind-up roll (401) runs through the square hole (404) pore wall of support (406) upper end and driving motor (402) output fixed mounting, the outside round joint of wind-up roll (401) is connected with wire (405), the lower extreme fixed mounting of wire (405) has lifting hook (403).
3. A building construction rack according to claim 2, wherein: the lower extreme fixedly connected with support arm (10) of support (406), the back fixed mounting of support arm (10) has same fixed block (8), slot (7) have been seted up to the lower extreme of fixed block (8), the lower extreme of fixed block (8) is through slot (7) and protection frame (3) grafting connection, fixed block (8) is through screw and protection frame (3) fixed mounting.
4. A building construction rack according to claim 1, wherein: the back of balladeur train (12) has seted up first rectangular hole (14), fixed establishment (9) install the inboard in first rectangular hole (14), second rectangular hole (15) have been seted up in the outside of balladeur train (12), balladeur train (12) are established in the outside of slide bar (11) through the spacing slip cap of second rectangular hole (15), place mechanism (16) and install the back at balladeur train (12).
5. A building construction rack according to claim 4 wherein: fixed establishment (9) are including fixed casing (901), fixed casing (901) fixed mounting is inboard at first rectangular hole (14), the inboard sliding connection of fixed casing (901) has to move board (904), one side fixed mounting who moves board (904) has draw-in lever (902), one end that moves board (904) is kept away from to draw-in lever (902) slides and runs through the shell wall of fixed casing (901) and one of them draw-in groove (13) card connection in slide bar (11) outside, one side fixed mounting that moves board (904) and keep away from draw-in lever (902) has spring (903), one end that moves board (904) and the inner wall fixed mounting of fixed casing (901) are kept away from to spring (903), one side fixed mounting that moves board (904) and be close to spring (903) has pull rod (906), one end that moves rod (906) slides and runs through the shell wall fixed connection of fixed casing (901) has pull handle (905), one end that moves rod (906) runs through the middle part of spring (903).
6. A building construction rack according to claim 5 wherein: the inner side of the fixed shell (901) is symmetrically provided with sliding grooves (18), the outer side of the moving plate (904) is fixedly provided with sliding blocks (17), and the sliding blocks (17) are in sliding connection with the sliding grooves (18).
7. A building construction rack according to claim 4 wherein: placement mechanism (16) are including placing box (161), place the front lower extreme of box (161) and rotate through hinge and balladeur train (12) and be connected, the outside symmetry of placing box (161) rotates and is connected with cardboard (163), the outside symmetry fixedly connected with card post (162) of balladeur train (12), one side fixedly connected with stopper (164) that balladeur train (12) were kept away from to card post (162), the lower extreme recess and the card post (162) joint of cardboard (163) are connected.
CN202322354628.9U 2023-08-30 2023-08-30 Building construction frame Active CN220814795U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322354628.9U CN220814795U (en) 2023-08-30 2023-08-30 Building construction frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322354628.9U CN220814795U (en) 2023-08-30 2023-08-30 Building construction frame

Publications (1)

Publication Number Publication Date
CN220814795U true CN220814795U (en) 2024-04-19

Family

ID=90672819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322354628.9U Active CN220814795U (en) 2023-08-30 2023-08-30 Building construction frame

Country Status (1)

Country Link
CN (1) CN220814795U (en)

Similar Documents

Publication Publication Date Title
CN112482788B (en) Auxiliary positioning device for installing composite wall board
CN209942205U (en) Construction hanging basket
CN220814795U (en) Building construction frame
CN113463930A (en) Indoor building decoration ceiling equipment and use method thereof
CN102628321A (en) Movable wallboard-mounting carriage
CN211666210U (en) Scaffold for building engineering
CN114150858A (en) Eminence construction auxiliary device for building engineering
CN210316437U (en) Multi-functional large-span air corridor erection equipment
CN216380487U (en) Telescopic scaffold suitable for indoor use
CN201232015Y (en) Flat-arm window type hoisting machine
CN220954557U (en) Suspension type anti-shaking construction platform for building outer wall construction
CN214462364U (en) Scaffold frame for fitment construction that can freely go up and down
CN218149691U (en) Anti-falling device for building curtain wall construction
CN217975310U (en) House building moving working frame
CN214618929U (en) Rotary telescopic suspension device for methane sensor at coal bunker opening
CN217924725U (en) Scaffold frame for whole easy dismounting municipal works
CN218091947U (en) Suspension type hanging basket
CN220787884U (en) Civil house construction material transportation frame
CN220645115U (en) Construction frame with multiple-aspect adjustment function
CN212174403U (en) 500kv live-line overhead working hoisting device with folding bed
CN215974711U (en) Well lid opening tool for underground operation
CN219760483U (en) Cable hanging structure for electromechanical installation
CN214117467U (en) Portable movable aluminum alloy climbing frame
CN215716360U (en) Curtain wall steel structure with telescopic function
CN218147835U (en) Simple and easy support of concrete crash barrier fitment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant