China
Prior art keywords
fixed
wall
mount
spout
slider
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920887280.0U
Other languages
Chinese (zh)
Inventor
李斌
张龙洋
陈小飞
李煜麟
邓智毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201920887280.0U priority Critical patent/CN210316437U/en
Application granted granted Critical
Publication of CN210316437U publication Critical patent/CN210316437U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses an aerial vestibule erection equipment of multi-functional large-span, which comprises a base, base top outer wall both sides edge is fixed with the mount, and mount top outer wall both sides all are fixed with the stand, and the spout has all been opened to two stand one sides russia, the joint that all slides in the spout has the slider, and two slider one side outer wall are fixed with same lifting plate, the mount bottom is fixed with two motors, and motor output shaft passes the mount and is fixed with the screw rod, the screw rod is pegged graft in the spout, and the screw rod runs through the slider and forms screw-thread fit. The utility model discloses can conveniently carry out the lifting work to the material, also can go up and down to the installer in addition, make things convenient for staff's aerial work installation work, can also carry out spacing work when the device is placed, improve the stability of device, prevent that the lifting plate material from taking place the phenomenon that drops at the lifting work, increase the security of device.

Description

Multi-functional large-span air corridor erection equipment
Technical Field
The utility model relates to an aerial vestibule erection equipment technical field especially relates to an aerial vestibule erection equipment of multi-functional large-span.
Background
Along with the continuous improvement of building functions and the increasing abundance of building shapes, a plurality of architects like to connect adjacent building units to form a fashionable and inspirational air corridor, particularly in large-scale buildings such as trade centers, schools, hospitals and sports buildings, the air corridor often becomes a pen-point, plays a role in guiding traffic, can be used as a viewing platform and the like, and simultaneously, the corridor itself also becomes a landscape of the building.
Need use some lifting means to conveniently install in the aerial vestibule construction work of large-span, and present promotion erection equipment exists some not enoughly in the use, for example, the device structure is too complicated, carries out the little usefulness of big material a bit to the less material of some volumes when going up and down the work, can not satisfy the user demand.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a multifunctional large-span air corridor installation device.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an aerial vestibule erection equipment of multi-functional large-span, includes the base, base top outer wall both sides edge is fixed with the mount, and mount top outer wall both sides all are fixed with the stand, and the spout has all been opened to two stand one side outer walls, equal slip joint has the slider in the spout, and two slider one side outer walls are fixed with same lifting plate, the mount bottom is fixed with two motors, and motor output shaft passes the mount and is fixed with the screw rod, the screw rod is pegged graft in the spout, and the screw rod runs through the slider and forms screw-thread fit.
Furthermore, a plurality of cross rods and X frames are fixed between the two upright posts.
Further, the equal fixed connection piece of mount both sides outer wall, and connecting block bottom outer wall all is fixed with the telescopic link, and the extension rod bottom mounting of telescopic link grabs the floor.
Furthermore, a plurality of ground grabbing teeth are fixed at the bottom of the ground grabbing plate.
Furthermore, four corners of the outer wall of the bottom of the base are respectively fixed with a movable wheel.
Furthermore, a thread groove is formed in one side of the outer wall of the top of the lifting plate, a sleeve is inserted into the thread groove in an inserting mode, a loop bar is inserted into the sleeve, the bottom end of the loop bar and the inner wall of the bottom of the sleeve are fixedly provided with the same spring, and a fixed block is fixedly arranged at the top end of the loop bar.
The utility model has the advantages that:
1. the lifting plate can be driven by the motor and the screw rod to lift through the arrangement of the two sliding blocks, so that the lifting work of materials can be facilitated, and in addition, the lifting can be performed on an installer, so that the high-altitude operation installation work of the worker is facilitated;
2. the connecting force between the two stand columns can be increased through the arrangement of the X frame and the cross rod, the structural support strength between the two stand columns is improved, and the lifting stability of the device is improved;
3. the setting through the telescopic link can drive and grab floor downstream until with the opposite laminating for the device carries out spacing work when placing, improves the stability of device, prevents that the lifting plate material from taking place the phenomenon of dropping at the lift during operation, increases the security of device.
Drawings
Fig. 1 is a schematic view of a main view structure of an embodiment 1 of the multifunctional large-span air corridor installation equipment provided by the present invention;
fig. 2 is a schematic view of a main view structure of an embodiment 2 of the multifunctional large-span air corridor installation device provided by the present invention;
fig. 3 is the utility model provides a multi-functional large-span aerial vestibule erection equipment's embodiment 2 local half cuts open spatial structure sketch map.
In the figure: the device comprises a base 1, a fixing frame 2, a motor 3, a column 4, a sliding groove 5, a screw 6, a lifting plate 7, a sliding block 8, a cross rod 9, a frame 10X, a connecting block 11, a telescopic rod 12, a floor grabbing plate 13, a sleeve 14, a loop bar 15, a fixed block 16 and a spring 17.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are exemplary only for the purpose of explaining the present patent and are not to be construed as limiting the present patent.
Example 1
Referring to fig. 1, a multi-functional large-span air vestibule erection equipment, including base 1, 1 top outer wall both sides edge of base is fixed with mount 2, and 2 top outer wall both sides of mount all are fixed with stand 4, spout 5 has all been opened to two 4 outer walls of stand one side, equal slip joint has slider 8 in the spout 5, and two 8 outer walls of slider one side are fixed with same lifting plate 7, 2 bottoms of mount are fixed with two motors 3, and the motor 3 output shaft passes mount 2 and is fixed with screw rod 6, screw rod 6 is pegged graft in spout 5, and screw rod 6 runs through slider 8 and forms screw-thread fit.
Wherein, a plurality of cross bars 9 and X frames 10 are fixed between the two upright posts 4.
Wherein, 2 both sides outer walls of mount 11 all fixed connection blocks, and 11 bottom outer walls of connecting block all are fixed with telescopic link 12, and the extension rod bottom mounting of telescopic link 12 has grabs floor 13.
Wherein, a plurality of ground grabbing teeth are fixed at the bottom of the ground grabbing plate 13.
Wherein, four corners of the outer wall of the bottom of the base 1 are all fixed with moving wheels.
The working principle of the embodiment is as follows: two sliders 8 can drive lifting plate 7 under the drive of motor 3 and screw rod 6 and carry out the lifting work, and then can conveniently carry out the lifting work to the material, in addition also can go up and down to the installer, make things convenient for staff's aerial work installation work, X frame 10 and horizontal pole 9 can increase the connection dynamics between two stands 4, improve the structure support intensity between two stands 4, improve device lifting work's stability, the setting of telescopic link 12 can drive grabs floor 13 downstream until with the opposite laminating, make the device carry out spacing work when placing, improve device's stability, prevent that lifting plate 7 material from taking place the phenomenon that drops when lifting work, increase device's security.
Example 2
Referring to fig. 2 and 3, the multifunctional large-span air corridor installation equipment of the present embodiment is different from embodiment 1 in that a thread groove is further formed in one side of the outer wall of the top of a lifting plate 7, a sleeve 14 is inserted in the thread groove, a loop bar 15 is inserted in the sleeve 14, the same spring 17 is fixed to the bottom end of the loop bar 15 and the inner wall of the bottom of the sleeve 14, and a fixing block 16 is fixed to the top end of the loop bar 15.
The working principle of the embodiment is as follows: when lifting plate 7 upwards moved, fixed block 16 compressed spring 17 when contacting aerial vestibule top bearing structure, utilized spring 17 reaction force to support bearing structure, made things convenient for the individual to carry out bearing structure's installation work.
In the description of this patent, it is to be understood that the terms "coaxial," "bottom," "one end," "top," "middle," "other end," "upper," "one side," "top," "inner," "front," "center," "two ends," and the like are used in the orientations and positional relationships indicated in the drawings for convenience in describing the patent and for simplicity in description, and are not intended to indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the patent.
In this patent, unless expressly stated or limited otherwise, the terms "mounted," "disposed," "connected," "secured," "screwed" and the like are to be construed broadly and can, for example, be fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate, or they may be connected internally or in an interactive relationship with each other, and unless otherwise specifically limited, the specific meaning of the above terms in this patent will be understood by those skilled in the art according to the specific circumstances.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a multi-functional large-span air vestibule erection equipment, includes base (1), its characterized in that, base (1) top outer wall both sides edge is fixed with mount (2), and mount (2) top outer wall both sides all are fixed with stand (4), and spout (5) have all been opened to two stand (4) one side outer walls, equal slip joint has slider (8) in spout (5), and two slider (8) one side outer wall are fixed with same lifting plate (7), mount (2) bottom is fixed with two motor (3), and motor (3) output shaft passes mount (2) and is fixed with screw rod (6), screw rod (6) are pegged graft in spout (5), and screw rod (6) run through slider (8) and form screw-thread fit.
2. Multifunctional large-span air corridor installation equipment according to claim 1, characterized in that between two said uprights (4) are fixed a number of cross bars (9) and X-frames (10).
3. The multifunctional large-span air corridor installation equipment according to claim 1, wherein the outer walls of two sides of the fixed frame (2) are both fixed with a connecting block (11), the outer walls of the bottom of the connecting block (11) are both fixed with a telescopic rod (12), and the bottom end of the telescopic rod (12) is fixed with a floor (13).
4. Multifunctional large-span air corridor installation equipment according to claim 3, characterized in that a number of ground gripping teeth are fixed to the bottom of the ground gripping plate (13).
5. Multifunctional large-span air corridor installation equipment according to any of the claims 1-4, characterized in that the base (1) has moving wheels fixed at four corners of the bottom outer wall.
6. The multifunctional large-span air corridor installation equipment as claimed in claim 1, wherein one side of the outer wall of the top of the lifting plate (7) is further provided with a threaded groove, a sleeve (14) is inserted in the threaded groove in a threaded manner, a loop bar (15) is inserted in the sleeve (14), the same spring (17) is fixed at the bottom end of the loop bar (15) and the inner wall of the bottom of the sleeve (14), and a fixed block (16) is fixed at the top end of the loop bar (15).
CN201920887280.0U 2019-06-13 2019-06-13 Multi-functional large-span air corridor erection equipment Active CN210316437U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920887280.0U CN210316437U (en) 2019-06-13 2019-06-13 Multi-functional large-span air corridor erection equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920887280.0U CN210316437U (en) 2019-06-13 2019-06-13 Multi-functional large-span air corridor erection equipment

Publications (1)

Publication Number Publication Date
CN210316437U true CN210316437U (en) 2020-04-14

Family

ID=70143673

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920887280.0U Active CN210316437U (en) 2019-06-13 2019-06-13 Multi-functional large-span air corridor erection equipment

Country Status (1)

Country Link
CN (1) CN210316437U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115306132A (en) * 2022-08-26 2022-11-08 河南源泰建筑有限公司 Building construction platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115306132A (en) * 2022-08-26 2022-11-08 河南源泰建筑有限公司 Building construction platform
CN115306132B (en) * 2022-08-26 2024-05-14 广东尚华建筑工程有限公司 Building construction platform

Similar Documents

Publication Publication Date Title
CN210105345U (en) Large-scale steel structure mounting equipment
CN210316437U (en) Multi-functional large-span air corridor erection equipment
CN210563490U (en) Plate clamping device
CN110606338B (en) Building space express delivery carrying robot
CN214302803U (en) Adjustable construction hanging basket for constructional engineering
CN210480787U (en) Mining machinery supporting platform
CN201411783Y (en) Box type combined house with convenient disassembly and assembly
CN110899391A (en) Steel pipe aligning device is used in construction scaffolding processing
CN212689494U (en) Construction platform for building construction
CN212773634U (en) Adjustable building supporting device
CN210659199U (en) Attached detachable multifunctional aerial work platform
CN110700604B (en) Assembly type laminated slab mounting trolley and using method thereof
CN209024158U (en) A kind of suspension type high altitude operation platform device with vacuum chuck
CN208702127U (en) A kind of large-span steel construction scaffold integral slide device
CN213626807U (en) Support for civil engineering construction
CN218990858U (en) Portable hanging flower basket device
CN111519935A (en) Temporary support device for prefabricated staircase and application construction method thereof
CN213950475U (en) Lifting machine for constructional engineering
CN220580456U (en) Safety device for building construction
CN210389229U (en) Glass display carries manipulator
CN210013140U (en) Fixed scaffold for bridge maintenance
CN219587331U (en) Stable strong splicing fixed prefabricated component
CN218467044U (en) Construction is with portable equipment of ascending a height based on building engineering
CN215167801U (en) Scaffold for industrial and civil buildings
CN215974761U (en) Be used for small-size aluminium alloy frame concatenation auxiliary device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant