CN220789591U - Adjacent water operation removes hanging flower basket - Google Patents

Adjacent water operation removes hanging flower basket Download PDF

Info

Publication number
CN220789591U
CN220789591U CN202322149719.9U CN202322149719U CN220789591U CN 220789591 U CN220789591 U CN 220789591U CN 202322149719 U CN202322149719 U CN 202322149719U CN 220789591 U CN220789591 U CN 220789591U
Authority
CN
China
Prior art keywords
truss
crawling
platform
cantilever
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322149719.9U
Other languages
Chinese (zh)
Inventor
喻叶
杨琪
丁伦军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Yangtze Power Co Ltd
Original Assignee
China Yangtze Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Yangtze Power Co Ltd filed Critical China Yangtze Power Co Ltd
Priority to CN202322149719.9U priority Critical patent/CN220789591U/en
Application granted granted Critical
Publication of CN220789591U publication Critical patent/CN220789591U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

The utility model provides a movable hanging basket for adjacent water operation, which comprises a weight platform, a cantilever truss horizontally fixed at the top of the weight platform, a crawling truss vertically fixed at the movable end of the cantilever truss and a hanging basket horizontally fixed at the bottom end of the crawling truss. The utility model has the effect of improving the safety and efficiency of the maintenance of the dam body adjacent water wall lamp.

Description

Adjacent water operation removes hanging flower basket
Technical Field
The utility model relates to the technical field of dam maintenance equipment, in particular to a movable hanging basket for adjacent water operation.
Background
At present, more urban rendering illumination is installed, in order to achieve good light effect, part of lamps are installed on a dam body of a hydropower station, the positions belong to environments adjacent to water and at high altitude, and the construction and maintenance security risk level of equipment is high.
Disclosure of Invention
Aiming at the defects existing in the prior art, the utility model provides the adjacent water operation movable hanging basket which solves the problem that the adjacent water surface construction risk of the dam body is large in the prior art.
According to the embodiment of the utility model, the adjacent water operation mobile hanging basket comprises a weight platform, a cantilever truss horizontally fixed on the top of the weight platform, a crawling truss vertically fixed on the movable end of the cantilever truss and a hanging basket horizontally fixed on the bottom end of the crawling truss, wherein the bottom of the weight platform is provided with rollers, the distance between the bottom of the cantilever truss and the bottom of the weight platform is larger than the height of a dam body edge guardrail, and crawling ladders are equidistantly arranged on the side wall of the crawling truss from top to bottom.
Preferably, the roller is a unidirectional wheel, and the rotation axis of the unidirectional wheel is parallel to the cantilever truss.
Preferably, a serial connecting rod is vertically arranged in the weight platform, cement test blocks are connected in series on the serial connecting rod, and the cement test blocks are stacked on the bottom plate of the weight platform.
Preferably, the connecting end of the cantilever truss and the weight platform is in a trapezoid structure, the thinner part of the trapezoid structure is positioned at the end part, and the thicker part is connected with the cantilever truss body.
Preferably, a gap for an operator to stand is arranged between the weight platform and the crawling truss.
Preferably, a gap is arranged between the ladder stand at the top and the top of the crawling truss.
Compared with the prior art, the utility model has the following beneficial effects:
support cantilever truss, truss and hanging flower basket of crawling through the ballast platform for the hanging flower basket is located the outside of dam body, and operating personnel gets into inside the hanging flower basket through the truss of crawling, drives the hanging flower basket through the ballast platform and removes along the dam body side, and operating personnel maintains the construction to the lamps and lanterns on the adjacent water wall of dam body in the in-process that removes along with the ballast platform, has improved the security and the efficiency of construction.
Drawings
Fig. 1 is a front view of an embodiment of the present utility model.
Fig. 2 is a front view of a basket according to an embodiment of the present utility model.
In the above figures: 1. a weight platform; 2. cantilever truss; 3. crawling truss; 4. a hanging basket; 5. a unidirectional wheel; 6. balancing weight; 7. and (5) climbing a ladder.
Detailed Description
The technical scheme of the utility model is further described below with reference to the accompanying drawings and examples.
1-2, to improve the safety and efficiency of maintenance construction of lamps on adjacent water walls of dam bodies. The utility model provides a movable hanging basket for adjacent water operation, which comprises a weight platform 1, a cantilever truss 2 horizontally fixed on the top of the weight platform 1, a crawling truss 3 vertically fixed on the movable end of the cantilever truss 2 and a hanging basket 4 horizontally fixed on the bottom end of the crawling truss 3, wherein rollers are arranged at the bottom of the weight platform 1, the distance between the bottom of the cantilever truss 2 and the bottom of the weight platform 1 is larger than the height of a dam body edge guardrail, and crawling ladders 7 are equidistantly arranged on the side wall of the crawling truss 3 from top to bottom.
The cantilever truss 2, the crawling truss 3 and the hanging basket 4 are supported through the ballast platform 1, the ballast platform 1 is located at the edge of a dam body and close to the adjacent water wall of the dam body, an operator carries tools required for maintenance into the hanging basket 4 through the crawling truss 3, the hanging basket 4 is driven to move along the dam body by pushing the ballast platform 1, the operator reaches the position required to be maintained, and maintenance construction of the lamp on the adjacent water wall of the dam body is carried out. The cantilever truss 2 and the crawling truss 3 are steel structure trusses, and reinforced steel rods are obliquely arranged in the cantilever trusses and the crawling trusses. When the crawling truss 3 is built, the length of the crawling truss 3 is set according to the height of the dam body adjacent to the lamp on the water wall, so that an operator can just face the lamp when standing in the hanging basket 4.
As shown in fig. 1, in order to improve the stability of the movement of the ballast platform 1. The idler wheels are unidirectional wheels 5, and the rotation shafts of the unidirectional wheels 5 are parallel to the cantilever truss 2. The rotation installing support of unidirectional wheel 5 fixed mounting is in the bottom of ballast platform 1, can't rotate freely in vertical direction, can only follow the direction removal of dam body for hanging flower basket 4 keeps the equidistance with the adjacent water wall of dam body in the in-process of following the movement of ballast platform 1.
As shown in fig. 1, to improve the stability of the mobile basket. The inside of the weight platform 1 is vertically provided with a serial connecting rod, the serial connecting rod is connected with a cement test block in series, and the cement test block is stacked on the bottom plate of the weight platform 1. The cement test blocks are used as the balancing weights 6, and the number of the cement test blocks to be placed is selected according to the total weight of the cantilever truss 2, the crawling truss 3, the hanging basket 4 and operators, so that the balance weight on the weight platform 1 can meet the requirements. The number of cement test blocks can be increased or decreased, so that the weight of the weight platform 1 can be reduced while the stability of a movable hanging basket is met, and an operator can conveniently push the weight platform 1 to move.
As shown in fig. 1, in order to ensure the strength of the connection end of the cantilever truss 2 and the weight platform 1. The connecting end of the cantilever truss 2 and the weight platform 1 is of a trapezoid structure, the thinner part of the trapezoid structure is positioned at the end part, and the thicker part is connected with the cantilever truss 2 body. The connecting end of the cantilever truss 2 and the weight platform 1 is in a trapezoid structure, and compared with the connection of a rectangular structure, the inclined arm in the trapezoid structure can avoid deformation of the connecting end.
As shown in fig. 1, to facilitate the operator's access to the crawling truss 3. A gap for an operator to stand is arranged between the weight platform 1 and the crawling truss 3. The dam body edge of the dam is provided with guardrails, the crawling truss 3 and the weighting platform 1 are respectively located on two sides of the guardrails, operators need to enter the crawling truss 3 first and then enter the hanging basket 4, and therefore gaps are formed between the weighting platform 1 and the crawling truss 3, so that the operators can conveniently enter the crawling truss 3.
As shown in fig. 1. A gap is arranged between the crawling ladder 7 positioned at the top and the top of the crawling truss 3. Before entering the crawling truss 3, operators need to cross the guardrails of the dam body, if the crawling ladder 7 is arranged at the top of the crawling truss 3, the operators are difficult to enter the crawling truss 3 from the gap between the adjacent crawling ladders 7.

Claims (6)

1. The utility model provides a water adjacent operation removes hanging flower basket which characterized in that: including ballast platform (1), cantilever truss (2) that the level is fixed in the top of ballast platform (1), vertically be fixed in the truss (3) of crawling of cantilever truss (2) expansion end and the horizontal hanging flower basket (4) that are fixed in the truss (3) bottom of crawling, the bottom of ballast platform (1) is provided with the gyro wheel, the interval of cantilever truss (2) bottom and ballast platform (1) bottom is greater than the height of dam body edge guardrail, the ladder (7) have been arranged from last to lower equidistance to the truss (3) lateral wall of crawling.
2. A water-adjacent operation mobile basket as claimed in claim 1, wherein: the idler wheels are unidirectional wheels (5), and the rotating shafts of the unidirectional wheels (5) are parallel to the cantilever truss (2).
3. A water-adjacent operation mobile basket as claimed in claim 1, wherein: the device is characterized in that a serial connecting rod is vertically arranged in the weight pressing platform (1), cement test blocks are connected in series on the serial connecting rod, and the cement test blocks are stacked on a bottom plate of the weight pressing platform (1).
4. A water-adjacent operation mobile basket as claimed in claim 1, wherein: the connecting end of the cantilever truss (2) and the weight platform (1) is of a trapezoid structure, the thinner part of the trapezoid structure is positioned at the end part, and the thicker part is connected with the cantilever truss (2) body.
5. A water-adjacent operation mobile basket as claimed in claim 1, wherein: a gap for an operator to stand is arranged between the weight platform (1) and the crawling truss (3).
6. An adjacent water work mobile basket according to claim 5 wherein: a gap is arranged between the crawling ladder (7) positioned at the top and the top of the crawling truss (3).
CN202322149719.9U 2023-08-10 2023-08-10 Adjacent water operation removes hanging flower basket Active CN220789591U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322149719.9U CN220789591U (en) 2023-08-10 2023-08-10 Adjacent water operation removes hanging flower basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322149719.9U CN220789591U (en) 2023-08-10 2023-08-10 Adjacent water operation removes hanging flower basket

Publications (1)

Publication Number Publication Date
CN220789591U true CN220789591U (en) 2024-04-16

Family

ID=90658247

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322149719.9U Active CN220789591U (en) 2023-08-10 2023-08-10 Adjacent water operation removes hanging flower basket

Country Status (1)

Country Link
CN (1) CN220789591U (en)

Similar Documents

Publication Publication Date Title
WO2021120687A1 (en) Method for entire removal of space truss and assistive support mechanism
CN220789591U (en) Adjacent water operation removes hanging flower basket
CN109879179B (en) Assembled steel construction tower crane platform
CN111058609A (en) Construction and protection integrated portable operation platform and method
CN212771963U (en) Movable suspension operation platform
CN111305433B (en) Construction structure and construction method of roof steel structure platform inclined glass curtain wall
WO2021036323A1 (en) Hydraulic lifting underground ring main unit system having stroke-controlled guide rail and control method
CN209228015U (en) A kind of construction of lift well steel platform
CN112942846A (en) Glass daylighting roof suspended steel structure rod sliding, transporting and hoisting construction method
CN208718336U (en) A kind of top pipe network construction lifting platform
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN213391144U (en) Internal top and external climbing type formwork construction platform for construction of super high-rise building
CN219060835U (en) Self-elevating lighting well operation platform device
CN214701974U (en) Chimney blasting is demolishd and is pushed down device with single action
CN219431305U (en) Construction frame
CN214192360U (en) Tower crane with automatic dismounting function
CN213626768U (en) High-stability protection device for high-rise building construction
CN220003061U (en) Attachable sliding type working frame for large thickener
CN214831972U (en) Portable bridge suspended member steel formwork mounting machine
CN215208318U (en) Maintenance device for wind power equipment
CN218952007U (en) Horizontal movement hanging basket device for installing upper pipe box of bridge guardrail
CN220417196U (en) Searchlight lamp bracket arranged at top of deep foundation pit
CN218815075U (en) Construction moving platform
CN213417599U (en) Suspension construction device for box girder