CN220664627U - Prefabricated cavity post hoist and mount component - Google Patents

Prefabricated cavity post hoist and mount component Download PDF

Info

Publication number
CN220664627U
CN220664627U CN202322405328.9U CN202322405328U CN220664627U CN 220664627 U CN220664627 U CN 220664627U CN 202322405328 U CN202322405328 U CN 202322405328U CN 220664627 U CN220664627 U CN 220664627U
Authority
CN
China
Prior art keywords
column
lifting
prefabricated
hanging beam
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322405328.9U
Other languages
Chinese (zh)
Inventor
孙春娥
孟丽娟
周进
宗路超
王杰
夏晋霞
谢建成
方健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202322405328.9U priority Critical patent/CN220664627U/en
Application granted granted Critical
Publication of CN220664627U publication Critical patent/CN220664627U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of building equipment, and discloses a prefabricated cavity column hoisting member, which comprises a hoisting beam, a hoisting beam and a hoisting beam, wherein the hoisting beam is arranged at the bottom of a cavity column; the column top tool is arranged at the top of the cavity column; the utility model provides a prefabricated cavity column hoisting member, which is characterized in that one end of the iron chain is fixedly arranged at the top of a hanging beam, the other end of the iron chain is observed and connected inside a column top tool, lifting lugs are welded at the left side and the right side of the upper surface of the hanging beam, lifting holes are formed in the two lifting lugs, reinforcing rings are welded at the outer walls of the left side and the right side of the hanging beam, and the two ends of each reinforcing ring are respectively welded with the outer walls of the two sides of the lifting lugs.

Description

Prefabricated cavity post hoist and mount component
Technical Field
The utility model belongs to the technical field of building equipment, and particularly relates to a prefabricated cavity column hoisting member.
Background
The prefabricated building has better development by virtue of the advantages of the prefabricated building, the current more cities put forward the assembly rate requirement on the newly built building, and the prefabricated components are improved to meet the increasingly changing market demands and the current social environment so as to lighten the dead weight of the prefabricated components to meet the complicated and diversified construction environments, and the installation and the use of the prefabricated columns are influenced by the fact that the dead weight of the existing prefabricated columns in the market is heavier in a large-span frame structure due to the large size, the high height and other reasons of the columns, so that the prefabricated cavity columns are derived.
The prefabricated cavity column in the prior art is generally hoisted through a hoisting ring embedded at the upper end of the prefabricated cavity column, but the prefabricated cavity column is large in self weight and long in length, the center of the prefabricated cavity column is high in the hoisting process of the prefabricated cavity column, the gravity center offset is large, the conventional prefabricated component hoisting facility cannot meet the requirements, and in order to solve the problems, the prefabricated cavity column hoisting component is provided.
Disclosure of Invention
The utility model aims at: in order to improve the hoisting stability of the cavity column.
The technical scheme adopted by the utility model is as follows: a prefabricated cavity column lifting member comprising:
the hanging beam is arranged at the bottom of the cavity column;
the column top tool is arranged at the top of the cavity column;
and one end of the iron chain is fixedly arranged at the top of the hanging beam, and the other end of the iron chain is connected inside the column top tool in an observation manner.
Through the technical scheme, after the preparation of the hoisting member and the equipment is completed, the column top tool is arranged on the column top in the middle, the hanging beam is arranged on the column bottom in the middle, the fact that the column top tool and the column bottom hanging beam are on the same vertical plane is guaranteed, the lower end of the iron chain is fixedly connected to the hanging beam, the upper end of the iron chain passes through the column top tool to be fixed to the crane, and then the crane machinery is used for maintaining the cavity column to stably carry out mechanical connection operation of cavity column steel bar connection until the cavity column steel bar connection is completed.
In a preferred embodiment, the hanging beam is 100mm x 1100mm solid steel column.
Through the technical scheme, the solid steel column is adopted to improve the integral strength of the hanging beam, and the hanging beam is prevented from being broken in the hanging process.
In a preferred embodiment, the post-top tooling is welded into hollow rectangular tubes by 100mm x 11100mm x 12mm steel strips.
In a preferred embodiment, lifting lugs are welded on the left side and the right side of the upper surface of the lifting beam, and lifting holes are formed in the two lifting lugs.
Through above-mentioned technical scheme, be connected hanging beam and iron chain through the lifting hole.
In a preferred embodiment, the outer walls of the left side and the right side of the hanging beam are welded with reinforcing rings, and two ends of each reinforcing ring are respectively welded with the outer walls of the two sides of the lifting lug.
Through above-mentioned technical scheme, through setting up the intensity that the strengthening ring improved between lug and the hanging beam.
In a preferred embodiment, the left side and the right side of the column top tool are provided with connecting holes.
In a preferred embodiment, a snap ring is fixedly arranged at the lower end of the iron chain.
In summary, due to the adoption of the technical scheme, the beneficial effects of the utility model are as follows: the utility model provides a prefabricated cavity column hoisting member, which aims to improve the hoisting stability of a cavity column.
The hoisting member can meet the safety of hoisting operation on one hand and can carry out line production in the hoisting operation construction process on the other hand in the hoisting operation hoisting process, has fewer requirements on labor, is convenient to operate, can effectively improve the hoisting work efficiency, ensures the construction period and simultaneously responds to the safety development concept of building construction.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of a hanging beam according to the present utility model;
FIG. 3 is a schematic structural view of a column top tooling according to the present utility model;
fig. 4 is a state diagram of the hollow column of the present utility model when it is lifted.
The marks in the figure: 1-hanging beams; 2-column top tooling; 3-iron chain; 4-lifting lugs; 5-lifting holes; 6-reinforcing rings; 7-connecting holes.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present utility model more apparent, the technical solutions in the embodiments of the present utility model will be clearly and completely described in the following in conjunction with the embodiments of the present utility model, and it is apparent that the described embodiments are some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
A prefabricated cavity column lifting member according to an embodiment of the present utility model will be described in detail with reference to fig. 1 to 4.
Examples:
a prefabricated cavity column lifting member comprising:
the hanging beam 1, hanging beam 1100mm is 100mm is 110mm solid steel column, and it sets up in cavity post bottom, adopts solid steel column to improve hanging beam's bulk strength, prevents that it from splitting at hoist and mount in-process, and roof column frock 2, roof column frock 2 pass through 100mm is 1100mm 12mm steel strap welded into hollow rectangular pipe, and it sets up at cavity post top, and connecting hole 7 has all been seted up to roof column frock 2 left and right sides.
Lifting lugs 4 are welded on the left side and the right side of the upper surface of the lifting beam 1, lifting holes 5 are formed in the two lifting lugs 4, the lifting beam 1 is connected with an iron chain 3 through the lifting holes 5, reinforcing rings 6 are welded on the outer walls of the left side and the right side of the lifting beam 1, two ends of each reinforcing ring 6 are welded with the outer walls of the two sides of each lifting lug 4 respectively, and the strength between the lifting lugs 4 and the lifting beam is improved by arranging the reinforcing rings 6.
The iron chain 3, iron chain 3 lower extreme fixed mounting has the snap ring, its one end fixed mounting is in roof beam 1 top, the other end is observed and is connected in the inside of roof beam frock 2, after hoist and mount component and equipment are prepared to accomplish, set up roof beam 2 at the roof beam in the middle first, set up roof beam 1 at the bottom of the post in the middle, guarantee roof beam frock 2 and the bottom of the post roof beam 1 on same perpendicular, 3 lower extreme fixed connection of iron chain is on roof beam 1, the upper end passes roof beam frock 2 and is fixed in on the hoist, then use hoist machinery to maintain the cavity post and stably carry out cavity post steel bar connection's mechanical connection operation, until cavity post steel bar connection is accomplished.
Working principle:
after the preparation of hoisting components and equipment is completed, the column top tool 2 is arranged on the column top in the middle, bolts on the clamping rings are loosened, the hanging beam 1 is arranged on the column bottom in the middle, the column top tool 2 and the column bottom hanging beam 1 are guaranteed to be on the same vertical plane, the bolts on the clamping rings are screwed, the cavity column is hoisted to a designated position, then a hoisting machine is used for maintaining the cavity column to stably carry out mechanical connection operation of cavity column steel bar connection until the cavity column steel bar connection is completed, after the cavity column steel bar connection is completed, bolts on the clamping rings on the hanging beam 1 are loosened, the hanging beam 1 is pulled out from a steel bar gap, the hanging beam 1, an iron chain 3 and the column top tool 2 are hoisted away from a high place by using a hoisting device, and the cavity column is circulated to the next cavity column construction position.
The above embodiments are only for illustrating the technical solution of the present utility model, and are not limiting; although the utility model has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit and scope of the technical solutions of the embodiments of the present utility model.

Claims (7)

1. A prefabricated cavity post hoist and mount component, its characterized in that: comprising the following steps:
the hanging beam (1) is arranged at the bottom of the cavity column;
the column top tool (2) is arranged at the top of the cavity column;
and one end of the iron chain (3) is fixedly arranged at the top of the hanging beam (1), and the other end of the iron chain is connected with the inside of the column top tool (2) in an observation manner.
2. A prefabricated hollow column lifting element according to claim 1, wherein: the hanging beam (1) is 100mm in 1100mm solid steel columns.
3. A prefabricated hollow column lifting element according to claim 1, wherein: the column top tool (2) is welded into a hollow rectangular pipe through 100mm 1100mm 12mm steel plate strips.
4. A prefabricated hollow column lifting element according to claim 1, wherein: lifting lugs (4) are welded on the left side and the right side of the upper surface of the lifting beam (1), and lifting holes (5) are formed in the two lifting lugs (4).
5. A prefabricated hollow column lifting element according to claim 1, wherein: reinforcing rings (6) are welded on the outer walls of the left side and the right side of the hanging beam (1), and two ends of each reinforcing ring (6) are welded with the outer walls of the two sides of the lifting lug (4) respectively.
6. A prefabricated hollow column lifting element according to claim 1, wherein: and connecting holes (7) are formed in the left side and the right side of the column top tool (2).
7. A prefabricated hollow column lifting element according to claim 1, wherein: the lower end of the iron chain (3) is fixedly provided with a clamping ring.
CN202322405328.9U 2023-09-05 2023-09-05 Prefabricated cavity post hoist and mount component Active CN220664627U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322405328.9U CN220664627U (en) 2023-09-05 2023-09-05 Prefabricated cavity post hoist and mount component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322405328.9U CN220664627U (en) 2023-09-05 2023-09-05 Prefabricated cavity post hoist and mount component

Publications (1)

Publication Number Publication Date
CN220664627U true CN220664627U (en) 2024-03-26

Family

ID=90340721

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322405328.9U Active CN220664627U (en) 2023-09-05 2023-09-05 Prefabricated cavity post hoist and mount component

Country Status (1)

Country Link
CN (1) CN220664627U (en)

Similar Documents

Publication Publication Date Title
CN201437639U (en) Integral type deformation joint steel moulding plate
CN113152873A (en) Heightening hanging basket system
CN211143305U (en) Steel structure building
CN112647719B (en) Modular hoisting method for embedded wall frame structure of steel structure factory building
CN220664627U (en) Prefabricated cavity post hoist and mount component
CN210619969U (en) Prefabricated staircase hoist and mount subassembly
CN212050135U (en) Hoisting carrying pole for hoisting prefabricated PC (polycarbonate) component
CN211313311U (en) Assembled concrete structure regularization stair protection platform
CN221191233U (en) Multifunctional hoisting connecting device
CN216196726U (en) Space truss lifting structure
CN214879479U (en) Boiler top beam
CN216810947U (en) Pier stud connects high light modularization equipment template under confined space
CN214885569U (en) Aluminum template lifting device
CN218619871U (en) Lifting appliance for integrally lifting large-span box girder side mold
CN217780496U (en) Hoisting tool for PC prefabricated part of prefabricated building
CN109505304A (en) A kind of permafrost soil area assembled type base for power transmission line iron tower prefab-form
CN216042530U (en) Heightening hanging basket system
CN219826097U (en) Novel steel mould of outer wall template and scaffold frame integration
CN201080697Y (en) Electric hoisting assembled type bridge frame
CN217921091U (en) Simple cantilever lifting device
CN211229118U (en) Assembled hidden beam floor system
CN215802774U (en) Environment-friendly energy-saving prefabricated reinforced concrete slab type stair
CN219279306U (en) Single-machine lifting ground wall-connected reinforcement cage device in narrow space
CN212531961U (en) Spacing formula opening beam hoist
CN216766231U (en) Upper and lower layer connection structure of light steel house

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant