CN220645489U - Assembled temporary construction encloses fender structure - Google Patents

Assembled temporary construction encloses fender structure Download PDF

Info

Publication number
CN220645489U
CN220645489U CN202322185880.1U CN202322185880U CN220645489U CN 220645489 U CN220645489 U CN 220645489U CN 202322185880 U CN202322185880 U CN 202322185880U CN 220645489 U CN220645489 U CN 220645489U
Authority
CN
China
Prior art keywords
concrete base
precast concrete
rod
upright post
temporary construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322185880.1U
Other languages
Chinese (zh)
Inventor
王晓东
李子文
郭金昂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Xinjian Architectural Design Co ltd
Original Assignee
Shanghai Xinjian Architectural Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Xinjian Architectural Design Co ltd filed Critical Shanghai Xinjian Architectural Design Co ltd
Priority to CN202322185880.1U priority Critical patent/CN220645489U/en
Application granted granted Critical
Publication of CN220645489U publication Critical patent/CN220645489U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fencing (AREA)

Abstract

The utility model discloses an assembled temporary construction enclosure structure, which relates to the technical field of construction enclosure structures and comprises a precast concrete base, wherein an upright post is movably inserted at the top of the precast concrete base, enclosure plates are detachably arranged on two sides of the upright post, a square rod which is matched and inserted at the bottom end of the upright post is movably arranged in the precast concrete base, a limiting ring is movably arranged in the precast concrete base, a pin rod is fixedly arranged in the limiting ring, the bottom end of the pin rod is matched and inserted in a square hole formed in the top of the square rod, and a first lifting lug positioned outside the precast concrete base is fixedly arranged at the top end of the pin rod. According to the utility model, the prefabricated concrete base and the upright post can be firmly connected through the insertion connection of the square rod and the pin rod, compared with a cement solidification installation mode, the prefabricated concrete base or the upright post is more rapid, and only needs to be detached and replaced independently after being damaged, so that the whole formed by the prefabricated concrete base and the upright post is not required to be replaced, and the maintenance cost is reduced.

Description

Assembled temporary construction encloses fender structure
Technical Field
The utility model relates to the technical field of construction enclosure structures, in particular to an assembled temporary construction enclosure structure.
Background
The temporary construction fence is a facility which enables a construction site to be a relatively closed isolation space in order to isolate the construction site from the external environment temporarily.
An assembled temporary construction fence structure relates to the technical field of construction fence structures, and aims to solve the problems that an existing fence foundation needs to be cast in situ, a truss column is complex in design, materials are wasted and construction is complicated. The short column is arranged at the upper end of the precast concrete base, the short column and the precast concrete base are integrally formed, a slot is formed in the short column, and the slot and the short column are integrally formed; the precast concrete stand column is arranged at the upper end of the short column, and the lower end of the precast concrete stand column extends to the inside of the slot; the embedded wall purline connecting plate is arranged on the front end face and the rear end face of the precast concrete stand column, twelve embedded wall purline connecting plates are arranged, and the lower end of the precast concrete stand column is fixedly connected with the slots in the short columns through the mortar binding layer.
With respect to the above-mentioned document, the inventor considers that it connects the precast concrete base and the precast concrete stand by the set cement, and once the precast concrete base or the precast concrete stand is damaged, the whole of the precast concrete base and the precast concrete stand needs to be replaced, which increases the maintenance cost, and thus needs to be improved.
Disclosure of Invention
Aiming at the defects existing in the prior art, the utility model provides an assembled temporary construction enclosure structure, which has the following specific technical scheme:
the utility model provides an assembly type temporary construction encloses fender structure, includes precast concrete base, precast concrete base top activity is pegged graft there is the stand, the equal dismantled and assembled enclose baffle in stand both sides, the activity is equipped with the cooperation in the precast concrete base and is pegged graft the square pole of stand bottom, precast concrete base internalization is equipped with the spacing ring, the fixed pin pole that is equipped with in the spacing ring, the cooperation of pin pole bottom is pegged graft in the square hole of square pole top seting up, the pin pole top is fixed with the outside first lug of being located precast concrete base.
Through adopting above-mentioned technical scheme, through the grafting of square pole and round pin pole, can carry out firm connection to precast concrete base and stand.
Optionally, a slot is formed in the center of the top of the precast concrete base, and the bottom end of the upright post is inserted into the slot in a matched manner.
Through adopting above-mentioned technical scheme, precast concrete accessible slot supports and spacing the stand.
Optionally, the fixed inserted bar that is equipped with evenly distributed in stand both sides, evenly distributed's jack has been seted up to the surrounding board both sides, the inserted bar cooperation is pegged graft in the jack, a plurality of the stand with a plurality of surrounding board staggered distribution.
Through adopting above-mentioned technical scheme, after the inserted bar pegged graft corresponding jack, can connect between stand and the surrounding baffle.
Optionally, a notch is formed in the top of one end of the square rod, and the notch of the square rod is located outside the precast concrete base.
By adopting the technical scheme, people can pull the opposite rod through the notch.
Optionally, a limit groove is formed in the precast concrete base, and the limit ring is slidably arranged in the limit groove in a matched mode.
Through adopting above-mentioned technical scheme, precast concrete base accessible spacing groove supports and spacing the spacing ring.
Optionally, the precast concrete base is kept away from the fixed dead lever that is equipped with in one side top of first lug, the sum of the height dimension of dead lever and the thickness dimension of spacing ring equals the degree of depth dimension of spacing groove, the dead lever top is fixed and is equipped with the second lug.
Through adopting above-mentioned technical scheme, can highly flush with the second lug after first lug is pulled up.
Optionally, the screw thread in stand top center department is equipped with the threaded rod, the fixed mounting panel that is equipped with in threaded rod top.
Through adopting above-mentioned technical scheme, through the connection of screw rod, can go up and down after making the mounting panel rotatory.
In summary, the present utility model includes at least one of the following beneficial effects:
1. through the grafting of square pole and round pin pole, can carry out firm connection to precast concrete base and stand, after people pulling first lug, plug square pole and plug stand, alright carry out quick assembly disassembly between precast concrete base and the stand, compare the mounting means that cement set more quick, improved people to enclosing the installation rate who keeps off the structure, and precast concrete base or stand damage after, only need to dismantle alone and change, need not to change the whole that precast concrete base and stand are constituteed, reduced cost of maintenance.
2. Through the connection of screw rod, can go up and down after making the mounting panel rotatory, the mounting panel after conveniently rising sprays behind mechanisms such as illumination, sprays and the illumination to the surrounding area is farther, and precast concrete base, parts such as stand and surrounding baffle can carry out quick assembly to can use repeatedly, be fit for promoting in a large number.
Drawings
FIG. 1 is a schematic view of the overall structure of the present utility model;
FIG. 2 is a diagram of the internal connections of the posts and the skirt of the present utility model;
FIG. 3 is a side cross-sectional view of the overall structure of the present utility model;
fig. 4 is an enlarged view of the structure a of fig. 3 in accordance with the present utility model.
Reference numerals illustrate: 1. prefabricating a concrete base; 11. a slot; 12. a limit groove; 13. a limiting ring; 14. a pin rod; 15. a first lifting lug; 16. a fixed rod; 17. the second lifting lug; 2. a column; 21. a threaded rod; 22. a mounting plate; 23. a rod; 3. a surrounding baffle; 31. a jack; 4. square rods; 41. and (5) a notch.
Detailed Description
The utility model is described in further detail below with reference to fig. 1-4.
Referring to fig. 1-4, the embodiment of the utility model discloses an assembled temporary construction enclosure structure, which comprises a precast concrete base 1, wherein an upright post 2 is movably inserted at the top of the precast concrete base 1, a slot 11 is formed in the center of the top of the precast concrete base 1, the bottom end of the upright post 2 is matched and inserted in the slot 11, the precast concrete base 1 can support and limit the upright post 2 through the slot 11, the upright post 2 can be inserted and pulled out on the precast concrete base 1, and the precast concrete base 1 can be installed on the ground in a cement or bolt fixing mode and the like.
Referring to fig. 1-2, the surrounding baffle plates 3 are all dismantled and assembled on two sides of the upright post 2, the inserted bars 23 which are uniformly distributed are fixedly arranged on two sides of the upright post 2, the jacks 31 which are uniformly distributed are formed on two sides of the surrounding baffle plates 3, the inserted bars 23 are matched and inserted in the jacks 31, the inserted bars 23 are inserted in the corresponding jacks 31, the upright post 2 and the surrounding baffle plates 3 can be connected, the upright posts 2 are arranged on two sides of the surrounding baffle plates 3, a plurality of upright posts 2 and a plurality of surrounding baffle plates 3 are distributed in a staggered manner, and a plurality of surrounding baffle plates 3 and a plurality of upright posts 2 which are distributed in a staggered manner form a surrounding baffle part of the surrounding baffle structure.
Referring to fig. 3-4, a square rod 4 which is inserted in the bottom end of the upright post 2 in a matched manner is movably arranged in the precast concrete base 1, a notch 41 is formed in the top of one end of the square rod 4, the notch 41 of the square rod 4 is positioned outside the precast concrete base 1, people can pull the square rod 4 through the notch 41, and the square rod 4 is conveniently inserted between the precast concrete base 1 and the upright post 2 to connect and fix the precast concrete base 1 and the upright post 2.
Referring to fig. 3-4, a limiting ring 13 is movably arranged in the precast concrete base 1, a limiting groove 12 is formed in the precast concrete base 1, the limiting ring 13 is slidably arranged in the adaptive limiting groove 12, and the precast concrete base 1 can support and limit the limiting ring 13 through the limiting groove 12.
Referring to fig. 3-4, the limiting ring 13 is internally and fixedly provided with the pin rod 14, the bottom end of the pin rod 14 is matched and inserted into a square hole formed in the top of the square rod 4, and after the pin rod 14 is inserted into the square rod 4, the square rod 4 inserted into the precast concrete base 1 and the upright post 2 can be fixed, so that the square rod 4 is prevented from sliding off from the precast concrete base 1 and the upright post 2 under the influence of external environment.
Referring to fig. 3-4, the top end of the pin rod 14 is fixedly provided with a first lifting lug 15 positioned outside the precast concrete base 1, people can pull the pin rod 14 through the first lifting lug 15, and the first lifting lug 15 can be connected with the precast concrete base 1 through the limiting ring 13, so that people can conveniently hang one side of the precast concrete base 1 by utilizing the first lifting lug 15.
Referring to fig. 3 to 4, a fixing rod 16 is fixedly arranged at the top of one side of the precast concrete base 1, which is far away from the first lifting lug 15, a second lifting lug 17 is fixedly arranged at the top end of the fixing rod 16, the fixing rod 16 can connect the precast concrete base 1 and the second lifting lug 17, the first lifting lug 15 is arranged in a construction area, the second lifting lug 17 is arranged outside the construction area, and people outside the construction area are prevented from stealing and dismantling the enclosure structure by pulling the first lifting lug 15 and the square rod 4.
Referring to fig. 3 to 4, the sum of the height dimension of the fixing rod 16 and the thickness dimension of the limit ring 13 is equal to the depth dimension of the limit groove 12, so that when the first lifting lug 15 is pulled up, the fixing rod can be flush with the second lifting lug 17 in height, and people can conveniently use the flush first lifting lug 15 and second lifting lug 17 to carry out hanging transportation on the precast concrete base 1.
Referring to fig. 1-2, a threaded rod 21 is screwed at the center of the top of the upright post 2, a mounting plate 22 is fixedly arranged at the top end of the threaded rod 21, the threaded rod 21 can connect the upright post 2 with the mounting plate 22, after the mounting plate 22 rotates, under the threaded connection of the threaded rod 21 and the upright post 2, the mounting plate 22 can rotate while lifting, after the mounting plate 22 lifts, spraying, lighting and other mechanisms can be installed, and the spraying, lighting and other mechanisms are in the prior art and are not repeated herein.
The implementation principle of the assembly type temporary construction enclosure structure provided by the embodiment of the utility model is as follows:
during installation, the bottom end of the upright post 2 is inserted into the slot 11 to initially connect the precast concrete base 1 and the upright post 2, then the first lifting lug 15 is pulled up to enable components such as the pin rod 14 to rise, the square rod 4 is inserted into the precast concrete base 1 and the upright post 2 to connect and fix the precast concrete base 1 and the upright post 2 again, then the first lifting lug 15 is placed down, at the moment, the pin rod 14 is inserted into the square rod 4 under the gravity, and the stability of the precast concrete base 1 and the upright post 2 after installation and fixation is improved.
Then, the enclosure plates 3 and the upright posts 2 can be assembled and connected in a mode of inserting the inserting rods 23 into the inserting holes 31, and the assembled temporary construction enclosure structure is formed after the plurality of enclosure plates 3 and the plurality of upright posts 2 which are distributed in a staggered mode are matched with the precast concrete base 1.
The above embodiments are not intended to limit the scope of the present utility model, so: all equivalent changes in structure, shape and principle of the utility model should be covered in the scope of protection of the utility model.

Claims (8)

1. The utility model provides a keep off structure is enclosed in temporary construction of assembled, includes precast concrete base (1), its characterized in that: precast concrete base (1) top activity is pegged graft has stand (2), stand (2) both sides all dismantled and assembled have surrounding shield (3), the activity is equipped with in precast concrete base (1) the cooperation is pegged graft square pole (4) of stand (2) bottom, precast concrete base (1) internalization is equipped with spacing ring (13), spacing ring (13) internal fixation is equipped with round pin pole (14), round pin pole (14) bottom cooperation is pegged graft in the square hole of seting up at square pole (4) top, round pin pole (14) top is fixed be equipped with first lug (15) that are located precast concrete base (1) outside.
2. The assembled temporary construction fence structure according to claim 1, wherein: a slot (11) is formed in the center of the top of the precast concrete base (1), and the bottom end of the upright post (2) is inserted into the slot (11) in a matched mode.
3. The assembled temporary construction fence structure according to claim 1, wherein: the utility model discloses a fence, including stand (2), surrounding baffle (3), stand (2) both sides are fixed be equipped with evenly distributed's inserted bar (23), evenly distributed's jack (31) have been seted up to surrounding baffle (3) both sides, inserted bar (23) cooperation is pegged graft in jack (31), a plurality of stand (2) and a plurality of surrounding baffle (3) are crisscross to be distributed.
4. The assembled temporary construction fence structure according to claim 1, wherein: a notch (41) is formed in the top of one end of the square rod (4), and the notch (41) of the square rod (4) is located outside the precast concrete base (1).
5. The assembled temporary construction fence structure according to claim 1, wherein: a limit groove (12) is formed in the precast concrete base (1), and the limit ring (13) is slidably arranged in the limit groove (12) in a matched mode.
6. The assembled temporary construction fence structure according to claim 5, wherein: a fixing rod (16) is fixedly arranged at the top of one side, far away from the first lifting lug (15), of the precast concrete base (1), and the sum of the height dimension of the fixing rod (16) and the thickness dimension of the limiting ring (13) is equal to the depth dimension of the limiting groove (12).
7. The assembled temporary construction fence structure according to claim 6, wherein: the top end of the fixed rod (16) is fixedly provided with a second lifting lug (17).
8. The assembled temporary construction fence structure according to claim 1, wherein: the center of the top of the upright post (2) is provided with a threaded rod (21) in a threaded manner, and the top end of the threaded rod (21) is fixedly provided with a mounting plate (22).
CN202322185880.1U 2023-08-14 2023-08-14 Assembled temporary construction encloses fender structure Active CN220645489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322185880.1U CN220645489U (en) 2023-08-14 2023-08-14 Assembled temporary construction encloses fender structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322185880.1U CN220645489U (en) 2023-08-14 2023-08-14 Assembled temporary construction encloses fender structure

Publications (1)

Publication Number Publication Date
CN220645489U true CN220645489U (en) 2024-03-22

Family

ID=90263310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322185880.1U Active CN220645489U (en) 2023-08-14 2023-08-14 Assembled temporary construction encloses fender structure

Country Status (1)

Country Link
CN (1) CN220645489U (en)

Similar Documents

Publication Publication Date Title
US5819487A (en) Prestressed concrete poles with internal bolting and leveling structures
KR100945561B1 (en) Method and apparatus for constructing pole of tower-type facilities
CN210507456U (en) Standardized lower pedestrian crossing of hanging down of deep basal pit can have enough to meet need
CN220645489U (en) Assembled temporary construction encloses fender structure
RU2346124C1 (en) Method for manufacture of columns
CN218234542U (en) Cement storage storehouse of steel construction
KR101077971B1 (en) Elementary Block for Supporting of Steel Pipe
CN216043088U (en) Municipal works construction bounding wall
CN111749384B (en) Steel structure roof structure of tower and construction method thereof
CN213509950U (en) Prefabricated perspective enclosure wall capable of being assembled and disassembled
CN108252569B (en) Rapid combined enclosure and construction method
CN214614158U (en) Assembled building foundation
CN215889588U (en) District enclosure structure
CN220704773U (en) Embedded part for steel structure of large-span factory building
CN219992883U (en) Novel steel structure column
CN219138584U (en) Building construction encloses fender
CN220100915U (en) Rural fence retaining wall
CN219672337U (en) Assembled construction encloses fender
CN216781769U (en) A strorage device for prefabricated stand of assembled bridge
CN215905762U (en) Combined tower body and base structure thereof
CN216811236U (en) Civil engineering construction is with detachable fender structure that encloses
CN213683497U (en) Security fence for building construction management
CN220100164U (en) Combined steel structure corridor
CN214117757U (en) Square steel structure assembled encloses fender
CN218759211U (en) Prefabricated enclosure wall stake of modularization

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant