CN220599141U - Novel lower hoisting point component - Google Patents

Novel lower hoisting point component Download PDF

Info

Publication number
CN220599141U
CN220599141U CN202322116887.8U CN202322116887U CN220599141U CN 220599141 U CN220599141 U CN 220599141U CN 202322116887 U CN202322116887 U CN 202322116887U CN 220599141 U CN220599141 U CN 220599141U
Authority
CN
China
Prior art keywords
hanging
steel groove
holes
connecting steel
novel lower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322116887.8U
Other languages
Chinese (zh)
Inventor
高渭泉
彭辉
吴红梁
谢延义
付勇涛
童超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangmen Zhite New Material Technology Co ltd
Original Assignee
Jiangmen Zhite New Material Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangmen Zhite New Material Technology Co ltd filed Critical Jiangmen Zhite New Material Technology Co ltd
Priority to CN202322116887.8U priority Critical patent/CN220599141U/en
Application granted granted Critical
Publication of CN220599141U publication Critical patent/CN220599141U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to a novel lower hanging point component, which comprises a lower hanging point main frame, a hanging seat and a hanging tool, wherein the lower hanging point main frame comprises a first connecting steel groove and a second connecting steel groove which are fixedly connected through a first group of bolts and nuts, the lower hanging point main frame is fixedly connected with the hanging seat through a second group of bolts and nuts, one end of the hanging tool is connected with the hanging seat, and the other end of the hanging tool can be connected with an electric hoist hook; the lower hanging point components are connected and fixed by adopting bolts and nuts, so that the welding workload and the polishing workload are reduced, and the problem that the installation of a single component is difficult and the components are matched by multiple persons due to heavy weight on site can be effectively solved.

Description

Novel lower hoisting point component
Technical Field
The utility model relates to the technical field of building construction components, in particular to a novel lower lifting point component.
Background
The climbing frame gradually replaces the traditional overhanging scaffold because of the characteristics of high safety coefficient, steel saving and low labor cost, and becomes the most commonly used safety equipment in high-rise building construction; and the electric hoist is connected to the climbing frame body through the upper hanging point and the lower hanging point.
In the prior art, the lower lifting point through groove is formed by welding channel steel, rectangular pipes and angle steel and iron plates, so that the processing difficulty is high, the processing process is complex, and the lower lifting point finished product is single in weight, so that the on-site installation and the on-site detachment are inconvenient.
Disclosure of Invention
The present utility model aims to solve at least one of the problems of the related art to a certain extent, and therefore, the present utility model proposes a novel drop point member.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
the utility model provides a novel lower hoisting point component, is including lower hoisting point body frame, hanging seat and hanger, wherein, lower hoisting point body frame is including carrying out fixed connection's first connection steel tank and second connection steel tank through first set of bolt and nut, lower hoisting point body frame carries out fixed connection through second set of bolt and nut and hanging seat, hanger one end is connected with hanging seat, and the other end can be connected with electric block couple.
In some embodiments, the leg portions of the first connecting steel groove and the second connecting steel groove are provided with a plurality of first through holes, and the first group of bolts and nuts are arranged in the first through holes to connect the first connecting steel groove and the second connecting steel groove.
In some embodiments, a plurality of second through holes are formed in the middle of the waist positions of the first connecting steel groove and the second connecting steel groove, and the second group of bolts and nuts are arranged in the second through holes and used for connecting the first connecting steel groove, the second connecting steel groove and the hanging seat.
In some embodiments, the hanging seat comprises a connecting bottom plate, two hanging plates arranged on the front side of the connecting bottom plate at intervals left and right, and a limiting plate arranged between the two hanging plates at intervals up and down, wherein the connecting bottom plate, the hanging plates and the limiting plate are all fixed through welding connection, a connecting column is connected at the upper ends of the two hanging plates, and the hanging tool is arranged on the connecting column.
In some embodiments, a reinforcing plate is welded on the connection base plate and outside the two hanger plates.
In some embodiments, the connecting posts are bolt posts, connecting through holes correspondingly penetrate through the upper ends of the two hanging plates, through holes are formed in the hanging tool, and the bolt posts penetrate through the two connecting through holes and the through holes and are connected with nuts in a threaded mode.
In some embodiments, the hanging tool is provided with a hook hole for hanging the electric hoist hook.
In some embodiments, the hook aperture is an oval shaped structure.
Compared with the prior art, the utility model has the beneficial effects that: the lower hanging point components are connected and fixed by adopting bolts and nuts, so that the welding workload and the polishing workload are reduced, and the problem that the installation of a single component is difficult and the components are matched by multiple persons due to heavy weight on site can be effectively solved.
Drawings
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a second perspective view of the present utility model;
FIG. 3 is a schematic front view of the present utility model;
fig. 4 is an exploded view of the hanger and the hanging tool of the present utility model.
Detailed Description
The following detailed description provides many different embodiments, or examples, for implementing the utility model. Of course, these are merely embodiments or examples and are not intended to be limiting. In addition, repeated reference numerals, such as repeated numbers and/or letters, may be used in various embodiments. These repetition are for the purpose of simplicity and clarity in describing the utility model and do not in itself dictate a particular relationship between the various embodiments and/or configurations discussed.
The utility model is further described by the following drawings and detailed description: the novel lower lifting point component shown in fig. 1-4 comprises a lower lifting point main frame 10, a hanging seat 3 and a hanging tool 4, wherein the lower lifting point main frame 10 comprises a first connecting steel groove 1 and a second connecting steel groove 2 which are fixedly connected through a first group of bolts and nuts 5, the lower lifting point main frame 10 is fixedly connected with the hanging seat 3 through a second group of bolts and nuts 6, one end of the hanging tool 4 is connected with the hanging seat 3, and the other end of the hanging tool can be connected with an electric hoist hook.
The first connecting steel groove 1 and the second connecting steel groove 2 are connected through the first group of bolts and nuts 5, so that a lower hanging point main frame 10 is formed, and the lower hanging point main frame 10 can be connected with a guide rail and a vertical rod to form a complete stressed structure; in addition, the lower hanging point main frame 10 is fixedly connected with the hanging seat 3 through a second group of bolts and nuts 6; therefore, the lower hanging point component is connected and fixed by adopting the bolts and the nuts, the welding workload and the polishing workload are reduced, and the problem that the installation of a single component is difficult and the installation of multiple people is required due to heavy weight on site can be effectively solved.
In the utility model, the leg parts of the first connecting steel groove 1 and the second connecting steel groove 2 are respectively provided with a plurality of first through holes, the first group of bolt and nuts 5 are arranged in the first through holes and used for connecting the first connecting steel groove 1 with the second connecting steel groove 2, and when the connecting steel groove is installed, the connecting steel groove is connected with the nuts after penetrating through the first through holes through bolts, so that the connecting steel groove is simple in structure and convenient to install.
Further, a plurality of second through holes are formed in the middle of the waist positions of the first connecting steel groove 1 and the second connecting steel groove 2, and the second group of bolts and nuts 6 are arranged in the second through holes and used for connecting the first connecting steel groove 1, the second connecting steel groove 2 and the hanging seat 3; simple structure, simple to operate.
Referring to fig. 3 and 4, the hanging seat 3 includes a connection base 41, two hanging plates 42 disposed at left and right intervals on the front side of the connection base 41, and a limiting plate 43 disposed between the two hanging plates 42 at upper and lower intervals, where the connection base 41, the hanging plates 42 and the limiting plate 43 are all fixed by welding connection, a connection column 44 is connected to the upper ends of the two hanging plates 42, and the hanging tool 4 is disposed on the connection column 44.
In order to further enhance the strength of the hanger 3, a reinforcing plate 51 is welded to the connection base plate 41 at the outer sides of the hanging plates 42.
Further, the connecting post 44 is a bolt post 61, a connecting through hole 62 is correspondingly formed at the upper ends of the two hanging plates 42, a through hole 64 is formed on the hanger 4, and the bolt post 61 is threaded with a nut 63 after passing through the two connecting through holes 62 and the through hole 64.
When the hanger 4 is mounted, the hanger 4 is placed between the two hanger plates 42, and the bolt post 61 is threaded through the connecting through hole 62 and the through hole 64 and then is screwed with the nut 63.
Referring to fig. 1 and 4, the hanging tool 4 is provided with a hook hole 71 for hooking the electric hoist hook.
Further, the hook hole 71 has an oval shape structure, thereby facilitating the hanging of the hook of the electric hoist.
While the basic principles and main features of the present utility model and advantages thereof have been shown and described with reference to the drawings and the foregoing description, it will be understood by those skilled in the art that the present utility model is not limited to the foregoing embodiments, but is described in the foregoing embodiments and description merely illustrative of the principles of the utility model, and various changes and modifications can be made therein without departing from the spirit and scope of the utility model as defined in the appended claims. The scope of the utility model is defined by the appended claims and equivalents thereof.

Claims (8)

1. A novel lower hoisting point component which is characterized in that: including down hoisting point body frame (10), hanging seat (3) and hanger (4), wherein, down hoisting point body frame (10) is including carrying out fixed connection's first connection steel groove (1) and second connection steel groove (2) through first set of bolt nut (5), down hoisting point body frame (10) carries out fixed connection through second set of bolt nut (6) and hanging seat (3), hanger (4) one end is connected with hanging seat (3), and the other end can be connected with electric block couple.
2. A novel lower suspension point member according to claim 1, wherein: the leg parts of the first connecting steel groove (1) and the second connecting steel groove (2) are provided with a plurality of first through holes, and a first group of bolt nuts (5) are arranged in the first through holes and used for connecting the first connecting steel groove (1) with the second connecting steel groove (2).
3. A novel lower suspension point member according to claim 1, wherein: a plurality of second through holes are formed in the middle of the waist positions of the first connecting steel groove (1) and the second connecting steel groove (2), and the second group of bolts and nuts (6) are arranged in the second through holes and used for connecting the first connecting steel groove (1), the second connecting steel groove (2) and the hanging seat (3).
4. A novel lower suspension point member according to claim 1, wherein: the hanging seat (3) comprises a connecting bottom plate (41), two hanging plates (42) arranged on the front side of the connecting bottom plate (41) at intervals left and right, and a limiting plate (43) arranged between the two hanging plates (42) at intervals up and down, wherein the connecting bottom plate (41), the hanging plates (42) and the limiting plate (43) are all fixed through welding connection, connecting columns (44) are connected at the upper ends of the two hanging plates (42), and the hanging tool (4) is arranged on the connecting columns (44).
5. The novel lower suspension point member according to claim 4, wherein: a reinforcing plate (51) is welded on the connecting bottom plate (41) and positioned outside the two hanging plates (42).
6. The novel lower suspension point member according to claim 4, wherein: the connecting posts (44) are bolt posts (61), connecting through holes (62) correspondingly penetrate through the upper ends of the two hanging plates (42), through holes (64) are formed in the hanging tool (4), and the bolt posts (61) penetrate through the two connecting through holes (62) and the through holes (64) and are in threaded connection with nuts (63).
7. A novel lower suspension point member according to claim 1, wherein: the hanging tool (4) is provided with a hook hole (71) for hanging the electric hoist hook.
8. The novel lower suspension point member according to claim 7, wherein: the hook hole (71) has an oval shape.
CN202322116887.8U 2023-08-07 2023-08-07 Novel lower hoisting point component Active CN220599141U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322116887.8U CN220599141U (en) 2023-08-07 2023-08-07 Novel lower hoisting point component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322116887.8U CN220599141U (en) 2023-08-07 2023-08-07 Novel lower hoisting point component

Publications (1)

Publication Number Publication Date
CN220599141U true CN220599141U (en) 2024-03-15

Family

ID=90166947

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322116887.8U Active CN220599141U (en) 2023-08-07 2023-08-07 Novel lower hoisting point component

Country Status (1)

Country Link
CN (1) CN220599141U (en)

Similar Documents

Publication Publication Date Title
CN220599141U (en) Novel lower hoisting point component
CN217975496U (en) Construction elevator well protective structure is built to building room
CN213449395U (en) General stable scaffold frame of gate-type
CN216196494U (en) Climb a bracing piece and climb frame
CN212450250U (en) Special lifting appliance for outdoor construction of transformer substation
CN212562432U (en) Connecting device of automatic lifting scaffold
CN204552051U (en) The cradle structure of high-altitude crossbeam soffit monitoring point layout
CN219011498U (en) Connecting device of steel structure node
CN219259298U (en) Hanging bracket clamp for surface treatment of steel template
CN220502518U (en) Tower crane platform convenient to disassemble and assemble
CN220578699U (en) Hoisting lengthening device for vertical member
CN216952032U (en) Clamping device for anti-seismic support hanger
CN220467308U (en) Building panel beating lifts by crane anchor clamps
CN212295594U (en) Lower hoisting point truss structure of climbing frame
CN211998498U (en) Movable general quick-mounting hoist buffer
CN217518280U (en) Large-span steel beam installation hoisting system
CN217840301U (en) Support-free assembled type elevator shaft concrete member
CN215858987U (en) Attached lifting scaffold with wall-attached support lengthening device
CN213834248U (en) Adjustable steel beam connecting plate mounting frame body
CN218714989U (en) Scaffold for construction industry
CN217536705U (en) Balanced strutting arrangement of bent cap construction
CN210505352U (en) A machines and tools for construction of LOFT steel construction
CN210483233U (en) Transformer substation high-voltage distribution room safety fence hanger
CN216664904U (en) Building engineering is with diversified scaffold
CN211393619U (en) Mixer maintenance gantry crane for lithium battery cathode coating material