CN220580578U - Various steel sheet wallboard installation cage of steel construction factory building - Google Patents

Various steel sheet wallboard installation cage of steel construction factory building Download PDF

Info

Publication number
CN220580578U
CN220580578U CN202321885311.1U CN202321885311U CN220580578U CN 220580578 U CN220580578 U CN 220580578U CN 202321885311 U CN202321885311 U CN 202321885311U CN 220580578 U CN220580578 U CN 220580578U
Authority
CN
China
Prior art keywords
factory building
cage
supporting beam
steel structure
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321885311.1U
Other languages
Chinese (zh)
Inventor
孙磊
张扬
赵旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN202321885311.1U priority Critical patent/CN220580578U/en
Application granted granted Critical
Publication of CN220580578U publication Critical patent/CN220580578U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a steel structure factory building color steel plate wallboard mounting suspension cage which comprises a bottom plate, wherein upright posts are arranged at four corners of the bottom plate, the upright posts are connected through cross bars to form a frame structure with three surrounding surfaces with one surface being open, diagonal bars are connected between upper and lower adjacent cross bars, a supporting beam is connected to the top of each adjacent upright post, a roller is arranged on the supporting beam at the top of the opening side of the frame, the roller can horizontally slide along a transverse track on the steel structure factory building, the top of the supporting beam is connected with lifting lugs, hooks are connected to the upright posts at the opening side of the frame at intervals, the hooks are connected with positioning holes on purlines of the steel structure factory building in a hanging mode, pedals are arranged in the frame at intervals from top to bottom, and the pedals are far away from the opening side of the frame. The distance is arranged between the upper pedal and the lower pedal and the opening side, so that the strip color steel plate can be integrally placed in the suspension cage, and the strip color steel plate can be integrally installed. The rollers on the supporting beam play a role in guiding the transverse moving cage, so that the repeated positioning during shifting is avoided.

Description

Various steel sheet wallboard installation cage of steel construction factory building
Technical Field
The utility model relates to steel structure factory building construction equipment, in particular to a steel structure factory building color steel plate wallboard mounting hanging cage.
Background
The side wall board of the enclosure structure of the steel structure factory building adopts color steel plates, in the wall board installation process, ground staff is adopted to lift the color steel plates to a preset position block by using a winch or a hand-pulled pulley, and then the installer stands on the purline in groups and nailing is carried out from the side surface, so that the color steel plates are fixed on the purline. The installer can only operate by one hand when beating the board from the side, is difficult to exert a force and is easy to be tired, thereby also influencing the construction efficiency.
When the existing installation hanging basket is constructed, only small steel color plates can be installed, and long color plates exceeding 3 meters cannot be integrally installed. The construction period requirement cannot be met. Therefore, there is a need to develop a new construction tool.
Disclosure of Invention
The utility model aims to solve the technical problem of providing a steel structure factory building color steel plate wallboard mounting suspension cage, which solves the problem that the existing equipment cannot integrally mount a long color steel plate.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a various steel sheet wallboard installation cage of steel construction factory building, which comprises a base plate, be equipped with the stand on the four corners of bottom plate, connect through the horizontal pole between the stand, form trilateral one side open-ended framework structure of encircleing, connect the diagonal bar between the upper and lower adjacent horizontal pole, connect a supporting beam at the top between adjacent stand, be equipped with the gyro wheel on the supporting beam at the open side top of framework, the gyro wheel can be followed the horizontal track horizontal slip on the steel construction factory building, the lug is connected at the top of supporting beam, the spacing connection couple on the stand of framework open side, the locating hole articulates on the purlin of couple and steel construction factory building, be equipped with the footboard from last interval down in the framework, the open side of framework is kept away from to the footboard.
The hook comprises an iron chain and a hook body which are connected with each other, and the iron chain is fixedly connected with the upright post.
The positioning holes are preset on the purlines at intervals.
The lifting lug is consistent with the upright post in position.
The pedal is connected between the cross bars in the frame body.
The distance between the pedal and the opening side of the frame body is more than 40mm.
The distance between the upper pedal and the lower pedal exceeds 2m.
Compared with the prior art, the utility model has the beneficial effects that:
the distance is arranged between the upper pedal and the lower pedal and the opening side, so that the strip color steel plate can be integrally placed in the suspension cage, and the strip color steel plate can be integrally installed. Meanwhile, the pedal is convenient for constructors to install. The rollers on the supporting beam play a role in guiding the transverse moving cage, so that the repeated positioning during shifting is avoided. And the construction efficiency is improved.
Drawings
Fig. 1 is a schematic structural view of the present utility model.
FIG. 2 is a schematic view of a portion of the present utility model.
Fig. 3 is a schematic diagram of the connection of the rollers.
Fig. 4 is a schematic view of a hanger.
Fig. 5 is a schematic view of a purlin.
In the figure: a bottom plate 1, upright posts 2, a cross bar 3, diagonal bars 4, a supporting beam 5, idler wheels 6, a transverse rail 7 lifting lug 8, hanging hook 9, purlin 10, locating hole 11, footboard 12, iron chain 12.1, coupler body 12.2.
Detailed Description
In the description of the present utility model, it should be understood that the terms "first," "second," and the like are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or number of technical features indicated. Thus, a feature defining "a first", "a second", etc. may explicitly or implicitly include one or more such feature. In the description of the present utility model, unless otherwise indicated, the meaning of "plurality" is two or more.
In the description of the present utility model, it should be noted that, unless explicitly specified and limited otherwise, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be either fixedly connected, detachably connected, or integrally connected, for example; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art in a specific case.
1-5, a steel construction factory building various steel sheet wallboard installation cage, including bottom plate 1, be equipped with stand 2 on the four corners of bottom plate 1, connect through horizontal pole 3 between the stand 2, form trilateral one side open-ended framework structure that surrounds, connect down diagonal rod 4 between the adjacent horizontal pole 3, connect supporting beam 5 at the top between the adjacent stand 2, be equipped with gyro wheel 6 on supporting beam 5 at the open side top of framework, gyro wheel 6 can follow the horizontal slip of transverse track 7 on the steel construction factory building, lug 8 is connected at the top of supporting beam 5, the couple 9 is connected to the interval on stand 2 at the framework open side, couple 9 articulates with locating hole 11 on the purlin 10 of steel construction factory building, be equipped with footboard 12 from top to bottom interval in the framework, the open side of framework is kept away from to footboard 12.
The hook 9 comprises an iron chain 12.1 and a hook body 12.2 which are connected with each other, and the iron chain 12.1 is fixedly connected with the upright post 2.
The positioning holes 11 are preset on the purlines 10 at intervals.
The lifting lug 8 is consistent with the upright post 2 in position.
The pedal 12 is connected between the cross bars 3 in the frame body.
The distance between the pedal 12 and the opening side of the frame body exceeds 40mm.
The distance between the upper and lower adjacent pedals 12 exceeds 2m.
During installation construction, the automobile crane is located wallboard mounting point oblique below, connects wire rope on the lug of cage, lifts by crane the cage, sets up two haulage ropes in the bottom of cage, controls the haulage rope by two cooperatives of below respectively to guarantee to lift by crane the in-process cage can be stable.
After the hanging cage is in place, the hanging cage is connected with the vacancy hole of the purline by using the hook, so that the hanging cage is always stable in the construction process, constructors enter the hanging cage one by one, safety protection is well achieved, long color steel plates shorter than the hanging cage are sent into the hanging cage from the upper part of the hanging cage, and the constructors fix the color steel plates on the purline by using self-tapping screws. After the station construction is completed, constructors leave the suspension cage, lift the suspension cage by using an automobile, loosen the hook, transversely move the suspension cage, fix the suspension cage at the next station and continue construction.
In order to make the purposes, technical schemes and technical effects of the utility model clearer, the technical schemes in the embodiments of the utility model are clearly and completely described. The embodiments described below are only some, but not all, embodiments of the utility model. All other embodiments, which can be made by those skilled in the art without the benefit of the teachings of this utility model, are intended to be within the scope of the utility model.
Examples
The utility model provides a various steel sheet wallboard installation cage of steel construction factory building, including bottom plate 1, bottom plate 1 size is 1 meter x1 meter, be equipped with stand 2 on the four corners of bottom plate 1, connect through horizontal pole 3 between the stand 2, form trilateral one side surrounding open-ended framework structure, connect down between the adjacent horizontal pole 3 down diagonal pole 4, connect supporting beam 5 at the top between the adjacent stand 2, be equipped with gyro wheel 6 on supporting beam 5 at the open side top of framework, gyro wheel 6 can follow the horizontal track 7 horizontal slip on the steel construction factory building, lug 8 is connected at supporting beam 5's top, lug 8 is unanimous with stand 2's position.
The upright post 2 at the opening side of the frame body is connected with hooks 9 at intervals, each hook 9 comprises an iron chain 12.1 and a hook body 12.2 which are connected with each other, and the iron chain 12.1 is fixedly connected with the upright post 2. The hooks 9 are hung with positioning holes 11 on purlines 10 of the steel structure factory building, and the positioning holes 11 are preset on the purlines 10 at intervals.
The steps 12 are provided in the frame at intervals from top to bottom, and the steps 12 are away from the opening side of the frame. The pedals 12 are connected between the cross bars 3 in the frame. The distance between the pedal 12 and the opening side of the frame is 45mm. The distance between the upper and lower adjacent steps 12 is 2.3m.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a various steel sheet wallboard installation cage of steel construction factory building, comprising a base plate, be equipped with the stand on the four corners of bottom plate, a serial communication port, connect through the horizontal pole between the stand, form trilateral one side open-ended framework structure of enclosing, connect the down-rod between the adjacent horizontal pole, connect a supporting beam at the top between adjacent stand, be equipped with the gyro wheel on the supporting beam at the open side top of framework, the gyro wheel can follow the horizontal track horizontal slip on the steel construction factory building, the lug is connected at the top of supporting beam, the couple is connected to the interval on the stand of framework open side, the locating hole on the purlin of couple and steel construction factory building articulates, be equipped with the footboard from last interval down in the framework, the open side of framework is kept away from to the footboard.
2. The steel structure factory building color plate wallboard installation cage of claim 1, wherein the hook comprises an iron chain and a hook body which are connected with each other, and the iron chain is fixedly connected with the upright post.
3. The steel structure plant color plate wallboard mounting suspension cage of claim 1, wherein the positioning holes are spaced and preset on the purline.
4. The steel structure plant color plate wallboard mounting suspension cage of claim 1, wherein the lifting lugs are consistent with the upright posts.
5. The steel structure plant color plate wallboard mounting suspension cage of claim 1, wherein the pedals are connected between the cross bars in the frame.
6. The steel structure plant color plate wallboard mounting suspension cage of claim 1, wherein the distance between the pedal and the opening side of the frame body is more than 40mm.
7. The steel structure plant color plate wallboard mounting suspension cage of claim 1, wherein the distance between the upper and lower adjacent pedals exceeds 2m.
CN202321885311.1U 2023-07-18 2023-07-18 Various steel sheet wallboard installation cage of steel construction factory building Active CN220580578U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321885311.1U CN220580578U (en) 2023-07-18 2023-07-18 Various steel sheet wallboard installation cage of steel construction factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321885311.1U CN220580578U (en) 2023-07-18 2023-07-18 Various steel sheet wallboard installation cage of steel construction factory building

Publications (1)

Publication Number Publication Date
CN220580578U true CN220580578U (en) 2024-03-12

Family

ID=90109727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321885311.1U Active CN220580578U (en) 2023-07-18 2023-07-18 Various steel sheet wallboard installation cage of steel construction factory building

Country Status (1)

Country Link
CN (1) CN220580578U (en)

Similar Documents

Publication Publication Date Title
CN201268937Y (en) Double-layer hanging cradle for working aloft
CN216446535U (en) Construction structure of overhead vestibule bottom furred ceiling of superelevation layer
CN215756279U (en) Lifting platform for road and bridge construction
CN220580578U (en) Various steel sheet wallboard installation cage of steel construction factory building
CN212356271U (en) Super thick cell board hoist and mount track device
CN202324662U (en) Installation device for foam cement composites
CN112523112A (en) Method for dismantling overhead suspension casting hanging basket
CN116905836A (en) Steel structure factory building color steel plate wallboard mounting suspension cage and use method
CN215755931U (en) Large transformer hoisting equipment in factory building
CN215326581U (en) Small steel frame winch for hoisting curtain wall stone
CN210286503U (en) Special four-beam casting crane for steel mill
CN201347719Y (en) Telescopic safety ladder
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN202185976U (en) Prestressed stretching-drawing working bracket for prefabricated beam slab
CN221216935U (en) Assembled curtain wall unit body lifting device for super high-rise building reconstruction
CN107700854B (en) Steel plate wall sliding installation device and installation method for super high-rise core tube
CN221607600U (en) Portal frame for hoisting cable saddle
CN2133627Y (en) Lifted scaffold using on bums and holes position of high-building
CN212984292U (en) Structure platform unit body articulates structure
CN211733664U (en) Hoisting support
CN221799114U (en) Construction hanging basket
CN113027146B (en) Method for lifting and hoisting outer wall stone
CN219710932U (en) Movable hanging basket device
CN221343693U (en) Curtain wall profile installation hanging system
CN217708579U (en) Hoisting travelling crane roller carrier installation fixing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant