CN220502336U CN202322104287.XU CN202322104287U CN220502336U CN 220502336 U CN220502336 U CN 220502336U CN 202322104287 U CN202322104287 U CN 202322104287U CN 220502336 U CN220502336 U CN 220502336U
Authority
CN
China
Prior art keywords
rod
paying
steel wire
elevator installation
supporting frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322104287.XU
Other languages
Chinese (zh)
Inventor
杨再高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202322104287.XU priority Critical patent/CN220502336U/en
Application granted granted Critical
Publication of CN220502336U publication Critical patent/CN220502336U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to the field of elevator installation, in particular to an elevator installation paying-off device, which comprises a fixing mechanism, a paying-off mechanism, a guiding mechanism and a steel wire, wherein the fixing mechanism is arranged on the steel wire; the paying-off mechanism is positioned at the rear of the upper end of the fixing mechanism, the guiding mechanism is positioned at the front of the upper end of the fixing mechanism, and the steel wire is positioned in the middle of the paying-off mechanism; the guide mechanism comprises a supporting rod, a sliding block and a guide ring, wherein the sliding rod is fixedly assembled above the inner end of the supporting rod, the sliding block is movably arranged at the outer end of the sliding rod, and the guide ring is fixedly assembled at the lower end of the sliding block; through with slider movable mounting at the outer end of slide bar, make the slider in use can move according to the position of steel wire unwrapping wire, then the steel wire alternates from the inside of guide ring and cross, and the annular structure of guide ring is comparatively slick and sly, and the smoothness when making the steel wire unwrapping wire to have guide part when making the steel wire unwrapping wire, the setting of this structure makes the elevator be difficult for winding when the installation unwrapping wire, increases the convenience when steel wire rolling, unwrapping wire.

Description

Elevator installation pay-off
Technical Field
The utility model relates to the field of elevator installation, in particular to an elevator installation paying-off device.
Background
Through retrieval, chinese patent number is: CN219058087U discloses an elevator installation pay-off device, which comprises a supporting protection pay-off rack structure connected with a fixed seat, wherein the supporting protection pay-off rack structure is used for adjusting a supporting buffering protection fixing rack structure and a lifting protection movable rack structure, and a fixing shell is connected with the middle position of the lower part of the inner side of the fixed seat through bolts; the fastening seat is connected with the middle position of the lower part of the inner side of the fixed shell through bolts; the protection shaft is inlaid in the middle position of the upper part of the inner side of the fixing seat. In the scheme, the support plate, the pay-off shaft, the fastening rod, the primary winding wheel, the power line, the protection block, the connecting plate and the secondary winding wheel are arranged, so that the stability of paying-off of the power line is improved; the setting of adjusting support buffering protection mount structure is favorable to carrying out fixed protection to pay-off.
The beacon light bracket in the above patent has the following problems when in use:
1. the supporting protection pay-off rack structure in the patent is not provided with the guide structure during paying off, the wire harness wound on the winding rod is not fixed in one place, and the wire harness changes along with the change of the position during paying off, so that the wire harness is not easy to wind together and is difficult to maintain due to the fact that the guide structure is not arranged during winding and winding of the wire harness;
2. the fixing seat in the patent is not provided with the weighting block and the pulley, so that the equipment is inconvenient to move when in use, and when the weight of the lower end of the wire harness is heavier, the equipment is easy to weigh the head and the feet, and the equipment is easy to topple.
Disclosure of Invention
In order to make up the defects of the prior art, the utility model provides an elevator installation paying-off device which is used for solving the problem that a wire harness is easy to wind in elevator installation paying-off.
The technical scheme adopted for solving the technical problems is as follows: the utility model relates to an elevator installation paying-off device, which comprises a fixing mechanism, a paying-off mechanism, a guiding mechanism and a steel wire; the paying-off mechanism is positioned at the rear of the upper end of the fixing mechanism, the guiding mechanism is positioned at the front of the upper end of the fixing mechanism, and the steel wire is positioned in the middle of the paying-off mechanism;
the guide mechanism comprises a supporting rod, a sliding block and a guide ring, wherein the sliding rod is fixedly assembled above the inner end of the supporting rod, the sliding block is movably arranged at the outer end of the sliding rod, the guide ring is fixedly assembled at the lower end of the sliding block, the sliding block can move according to the paying-off position of a steel wire in use by movably mounting the sliding block at the outer end of the sliding rod, the steel wire is penetrated through the guide ring from the inner part of the guide ring, and the guide of the steel wire during paying-off is increased.
Preferably, the fixed establishment is including base, pulley, built-in groove, hoist and aggravate the piece, pulley fixed mounting is in the avris of base lower extreme, the inside of built-in groove fixed setting in the base lower extreme, hoist fixed mounting is in the left and right sides of built-in inslot end, aggravate the piece movable mounting in the inside of built-in groove and with the upper end fixed connection of hoist, make the device be convenient for remove through setting up the pulley, increase the convenience that the device was used in different positions.
Preferably, the paying-off mechanism comprises a supporting frame, an assembling frame, a motor, a first transmission rod, a driving gear, a driven gear and a second transmission rod, wherein the assembling frame is fixedly arranged on the left side of the outer end of the supporting frame, the motor is fixedly arranged at the upper end of the assembling frame, the first transmission rod is fixedly arranged at the inner end of the motor, the driving gear is fixedly arranged at the inner end of the first transmission rod and is fixedly connected with the supporting frame, the second transmission rod is fixedly arranged at the outer end of the supporting frame and is positioned above the driving gear, the second transmission rod is fixedly arranged at the inner end of the driven gear and penetrates into the supporting frame, the driving gear is driven by the driving motor to rotate during operation, and the driving gear and the driven gear are in meshed connection, so that the rotation and stop of the driven gear can be controlled, and the paying-off device is convenient to operate and manual control is avoided.
Preferably, the paying-off mechanism comprises a rotating shaft, a winding rod, an electric push rod, a limiting groove and a control panel, wherein the rotating shaft is fixedly assembled at the inner end of the supporting frame and connected with the second transmission rod, the winding rod is fixedly installed at the inner end of the rotating shaft, the electric push rod is fixedly installed at the inner end of the supporting frame and positioned at the upper side and the lower side of the rotating shaft, the limiting groove is fixedly arranged in the outer end of the winding rod, the control panel is fixedly installed above the outer end of the supporting frame, and the limiting groove is arranged, so that the electric push rod can be clamped into the limiting groove in the paying-off process, and the rotation of the winding rod is limited.
Preferably, the bracing piece fixed mounting is in the left and right sides at base upper end middle part, guide ring and copper wire looks adaptation, copper wire movable mounting is in the middle part of wire winding pole, and the annular structure of guide ring is comparatively slick and sly, the smoothness nature when increasing the copper wire unwrapping wire.
Preferably, the built-in groove is T type structure, the hoist is the symmetric distribution in the left and right sides of aggravating the piece lower extreme, through setting up the built-in groove to T type structure, is convenient for install the aggravating the piece of adaptation in, is difficult for breaking away from, and the setting of adding the pouring weight, in operation, the gravity of multiplicable device lower extreme avoids taking place to empty.
Preferably, the support frame fixed mounting is in the left and right sides at base upper end middle part and is located the place ahead of support frame, driving gear and driven gear are the meshing and connect, the wire winding pole is H type structure, electric putter's quantity is two, electric putter and spacing groove looks adaptation, the spacing groove equidistance distributes in the inside of wire winding pole outer end, through setting up the wire winding pole to H type structure, makes difficult follow both sides after the steel wire winding drop.
The utility model has the advantages that:
1. according to the elevator installation paying-off device, the sliding block is movably arranged at the outer end of the sliding rod, so that the sliding block can move according to the paying-off position of the steel wire in use, then the steel wire penetrates through the guide ring, the annular structure of the guide ring is smooth, the steel wire is smooth in paying-off, the steel wire is provided with the guide component in paying-off, and due to the arrangement of the structure, the elevator is not easy to wind in the process of installing and paying-off, and convenience in winding and paying-off of the steel wire is improved;
2. this elevator installation pay-off, through setting up built-in groove, be convenient for install the weighting piece of adaptation in, be difficult for breaking away from, and the setting of weighting piece, in operation, not only can increase the gravity of device lower extreme, avoid taking place to empty, can also be used to the removal of fixed pulley, the security when increasing the device and using.
Drawings
In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings that are required in the embodiments or the description of the prior art will be briefly described, it being obvious that the drawings in the following description are only some embodiments of the utility model, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic cross-sectional view of the present utility model;
FIG. 3 is an enlarged schematic view of the structure of FIG. 1A according to the present utility model;
fig. 4 is an enlarged view of fig. 2B according to the present utility model.
In the figure: 1. a fixing mechanism; 101. a base; 102. a pulley; 103. a built-in groove; 104. a crane; 105. weighting blocks; 2. a paying-off mechanism; 201. a support frame; 202. an assembly frame; 203. a motor; 204. a first transmission rod; 205. a drive gear; 206. a driven gear; 207. a second transmission rod; 208. a rotating shaft; 209. a winding rod; 210. an electric push rod; 211. a limit groove; 212. a control panel; 3. a guide mechanism; 301. a support rod; 302. a slide bar; 303. a slide block; 304. a guide ring; 4. steel wire.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 4, an elevator installation paying-off device comprises a fixing mechanism 1, a paying-off mechanism 2, a guiding mechanism 3 and a steel wire 4; the paying-off mechanism 2 is positioned at the rear of the upper end of the fixing mechanism 1, the guiding mechanism 3 is positioned at the front of the upper end of the fixing mechanism 1, and the steel wire 4 is positioned in the middle of the paying-off mechanism 2;
the guide mechanism 3 comprises a supporting rod 301, a sliding rod 302, a sliding block 303 and a guide ring 304, wherein the sliding rod 302 is fixedly assembled above the inner end of the supporting rod 301, the sliding block 303 is movably arranged at the outer end of the sliding rod 302, and the guide ring 304 is fixedly assembled at the lower end of the sliding block 303;
during operation, through with slider 303 movable mounting at the outer end of slide bar 302, make slider 303 in use can move according to the position of steel wire 4 unwrapping wire to pass steel wire 4 from the inside interlude of guide ring 304, the direction when increasing steel wire 4 unwrapping wire, the setting of this structure makes the elevator be difficult for winding when the installation unwrapping wire, increases convenience when steel wire 4 rolling, unwrapping wire.
Further, the fixing mechanism 1 comprises a base 101, a pulley 102, a built-in groove 103, a crane 104 and a weighting block 105, wherein the pulley 102 is fixedly arranged at the side of the lower end of the base 101, the built-in groove 103 is fixedly arranged in the lower end of the base 101, the crane 104 is fixedly arranged at the left and right sides of the inner end of the built-in groove 103, and the weighting block 105 is movably arranged in the built-in groove 103 and is fixedly connected with the upper end of the crane 104;
in operation, the pulley 102 is arranged to facilitate movement of the device, thereby increasing the convenience of the device in use at different positions.
Further, the paying-off mechanism 2 comprises a supporting frame 201, an assembling frame 202, a motor 203, a first transmission rod 204, a driving gear 205, a driven gear 206 and a second transmission rod 207, wherein the assembling frame 202 is fixedly arranged at the left side of the outer end of the supporting frame 201, the motor 203 is fixedly arranged at the upper end of the assembling frame 202, the first transmission rod 204 is fixedly arranged at the inner end of the motor 203, the driving gear 205 is fixedly arranged at the inner end of the first transmission rod 204 and fixedly connected with the supporting frame 201, the second transmission rod 207 is fixedly arranged at the outer end of the supporting frame 201 and is positioned above the driving gear 205, and the second transmission rod 207 is fixedly arranged at the inner end of the driven gear 206 and penetrates into the supporting frame 201;
during operation, the driving motor 203 rotates the driving gear 205, the driving gear 205 is meshed with the driven gear 206, and the rotation and stop of the driven gear 206 can be controlled, so that the device is convenient to operate during paying-off, manual control is avoided, and in the structure, the stability of the assembly frame 202 during assembly of the motor 203 is improved.
Further, the paying-off mechanism 2 comprises a rotating shaft 208, a winding rod 209, an electric push rod 210, a limiting groove 211 and a control panel 212, wherein the rotating shaft 208 is fixedly assembled at the inner end of the supporting frame 201 and is connected with the second transmission rod 207, the winding rod 209 is fixedly arranged at the inner end of the rotating shaft 208, the electric push rod 210 is fixedly arranged at the inner end of the supporting frame 201 and is positioned at the upper side and the lower side of the rotating shaft 208, the limiting groove 211 is fixedly arranged in the outer end of the winding rod 209, and the control panel 212 is fixedly arranged above the outer end of the supporting frame 201;
during operation, through setting up spacing groove 211, at the unwrapping wire in-process, accessible electric putter 210 card goes into the inside of spacing groove 211 to the rotation of restriction wire winding pole 209, in this structure, all have control panel 212 to control to the used part, from this the automaticity that further increases the device to use.
Further, the supporting rod 301 is fixedly installed on the left and right sides of the middle of the upper end of the base 101, the guide ring 304 is matched with the steel wire 4, and the steel wire 4 is movably installed in the middle of the winding rod 209;
in operation, the annular structure of the guide ring 304 is smooth, the smoothness of the steel wire 4 during paying-off is improved, and the supporting rod 301 is positioned at the front end of the supporting frame 201 and is relatively low in height, so that convenience of the steel wire 4 during paying-off is facilitated.
Further, the built-in groove 103 is of a T-shaped structure, and the cranes 104 are symmetrically distributed on the left side and the right side of the lower end of the weighting block 105;
during operation, through setting built-in groove 103 to T type structure, be convenient for install the heavy piece 105 of adaptation in, be difficult for breaking away from, and the setting of heavy piece 105, in operation, not only can increase the gravity of the device lower extreme, avoid taking place to empty, can also be used to the removal of fixed pulley 102, the security when increasing the device and using.
Further, the supporting frame 201 is fixedly installed on the left side and the right side of the middle of the upper end of the base 101 and is located in front of the supporting frame 201, the driving gear 205 and the driven gear 206 are in meshed connection, the winding rod 209 is of an H-shaped structure, the number of the electric push rods 210 is two, the electric push rods 210 are matched with the limit grooves 211, and the limit grooves 211 are distributed in the outer end of the winding rod 209 at equal intervals;
during operation, through setting up wire winding pole 209 to H type structure, be difficult for following both sides and drop after making steel wire 4 winding, and still with spacing groove 211 equidistance distribution in the inside of wire winding pole 209 outer end, then make wire winding pole 209 all fixable in a plurality of positions, convenience when increasing wire winding pole 209 location from this.
Working principle: the utility model relates to an elevator installation paying-off device, firstly, the device is moved to a required position through a pulley 102 during operation, a crane 104 is driven to lower a weighting block 105 and prop against the ground, the gravity of the lower end of the device is increased, tilting is avoided, the elevator installation paying-off device can be used for fixing the movement of the pulley 102, the safety of the elevator installation during use is improved, after the elevator installation is finished, a driving motor 203 is controlled by a control panel 212 to enable a driving gear 205 to rotate, the driving gear 205 is connected with a driven gear 206 in a meshed manner, the rotation and stop of the driven gear 206 can be controlled, the driven gear 206 drives a winding rod 209 through a second transmission rod 207 to control the paying-off condition of a steel wire 4, in addition, a sliding block 303 is movably arranged at the outer end of a sliding rod 302, the sliding block 303 can move according to the paying-off position of the steel wire 4 during paying-off in use, the guiding of a guide ring 304 is penetrated through the inside, the elevator installation is increased, the elevator installation is not easy to wind during paying-off of the steel wire 4, the elevator installation is convenient to wind the steel wire 4 during paying-off, the elevator installation is complemented with the components, the winding and the steel wire 4 during paying-off is convenient to pay-off, and the steel wire 4 is relatively smooth, and the supporting frame is high in the paying-off is easy to be located at the front of a supporting frame with high smooth 4.
The foregoing has shown and described the basic principles, principal features and advantages of the utility model. It will be understood by those skilled in the art that the present utility model is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present utility model, and various changes and modifications may be made without departing from the spirit and scope of the utility model, which is defined in the appended claims.

Claims (7)

1. An elevator installation pay-off, its characterized in that: comprises a fixing mechanism (1), a paying-off mechanism (2), a guiding mechanism (3) and a steel wire (4); the paying-off mechanism (2) is positioned at the rear of the upper end of the fixing mechanism (1), the guide mechanism (3) is positioned at the front of the upper end of the fixing mechanism (1), and the steel wire (4) is positioned in the middle of the paying-off mechanism (2);
the guide mechanism (3) comprises a supporting rod (301), a sliding rod (302), a sliding block (303) and a guide ring (304), wherein the sliding rod (302) is fixedly assembled above the inner end of the supporting rod (301), the sliding block (303) is movably installed at the outer end of the sliding rod (302), and the guide ring (304) is fixedly assembled at the lower end of the sliding block (303).
2. An elevator installation payout device as defined in claim 1, wherein: the fixing mechanism (1) comprises a base (101), pulleys (102), an inner groove (103), a crane (104) and a weighting block (105), wherein the pulleys (102) are fixedly arranged on the side of the lower end of the base (101), the inner groove (103) is fixedly arranged in the lower end of the base (101), the crane (104) is fixedly assembled on the left side and the right side of the inner end of the inner groove (103), and the weighting block (105) is movably arranged in the inner groove (103) and is fixedly connected with the upper end of the crane (104).
3. An elevator installation payout apparatus as defined in claim 2, wherein: the paying-off mechanism (2) comprises a supporting frame (201), an assembling frame (202), a motor (203), a first transmission rod (204), a driving gear (205), a driven gear (206) and a second transmission rod (207), wherein the assembling frame (202) is fixedly installed on the left side of the outer end of the supporting frame (201), the motor (203) is fixedly installed on the upper end of the assembling frame (202), the first transmission rod (204) is fixedly installed on the inner end of the motor (203), the driving gear (205) is fixedly installed on the inner end of the first transmission rod (204) and fixedly connected with the supporting frame (201), the second transmission rod (207) is fixedly installed on the outer end of the supporting frame (201) and located above the driving gear (205), and the second transmission rod (207) is fixedly installed on the inner end of the driven gear (206) and penetrates into the supporting frame (201).
4. An elevator installation payout apparatus as defined in claim 3, wherein: the paying-off mechanism (2) comprises a rotating shaft (208), a winding rod (209), an electric push rod (210), a limiting groove (211) and a control panel (212), wherein the rotating shaft (208) is fixedly assembled at the inner end of a supporting frame (201) and is connected with a second transmission rod (207), the winding rod (209) is fixedly installed at the inner end of the rotating shaft (208), the electric push rod (210) is fixedly installed at the inner end of the supporting frame (201) and is located at the upper side and the lower side of the rotating shaft (208), the limiting groove (211) is fixedly arranged inside the outer end of the winding rod (209), and the control panel (212) is fixedly installed above the outer end of the supporting frame (201).
5. The elevator installation payout device as defined in claim 4, wherein: the support rod (301) is fixedly arranged on the left side and the right side of the middle of the upper end of the base (101), the guide ring (304) is matched with the steel wire (4), and the steel wire (4) is movably arranged in the middle of the winding rod (209).
6. An elevator installation payout apparatus as defined in claim 5, wherein: the built-in groove (103) is of a T-shaped structure, and the cranes (104) are symmetrically distributed on the left side and the right side of the lower end of the weighting block (105).
7. The elevator installation payout device as defined in claim 6, wherein: the utility model discloses a wire winding pole, including support frame (201), wire winding pole (209), electric putter (210), spacing groove (211), support frame (201) fixed mounting is in the left and right sides at base (101) upper end middle part and be located the place ahead of support frame (201), driving gear (205) and driven gear (206) are the meshing and are connected, the quantity of electric putter (210) is two, electric putter (210) and spacing groove (211) looks adaptation, spacing groove (211) equidistance distributes in the inside of wire winding pole (209) outer end.
CN202322104287.XU 2023-08-07 2023-08-07 Elevator installation pay-off Active CN220502336U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322104287.XU CN220502336U (en) 2023-08-07 2023-08-07 Elevator installation pay-off

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322104287.XU CN220502336U (en) 2023-08-07 2023-08-07 Elevator installation pay-off

Publications (1)

Publication Number Publication Date
CN220502336U true CN220502336U (en) 2024-02-20

Family

ID=89875857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322104287.XU Active CN220502336U (en) 2023-08-07 2023-08-07 Elevator installation pay-off

Country Status (1)

Country Link
CN (1) CN220502336U (en)

Similar Documents

Publication Publication Date Title
CN112158686B (en) Multi-connection cable storage system
CN114542903A (en) Building monitoring device based on BIM
CN216302890U (en) Universal guide wheel wire arrangement structure and lifting device
CN220502336U (en) Elevator installation pay-off
CN113998528B (en) Paying-off device for power transmission line
CN211310729U (en) Lifting platform
CN210594734U (en) Copper line unwinding device
CN111552047B (en) Wall pipeline optical cable laying device and method
CN220485189U (en) Winch capable of accurately controlling winding speed
CN109235866B (en) Lifting basket equipment
CN220845255U (en) Disc winch with good safety
CN110790202A (en) Lifting platform
CN219730324U (en) Crane running pulley
CN213237433U (en) Linkage wire arranging wheel structure and lifting device
CN216275699U (en) Pouring device for cast-in-place pile
CN211110927U (en) Street lamp pole convenient to install
CN220815531U (en) Slidable folding maintenance cat ladder
CN220098324U (en) Hoisting frame for galvanization roll changing
CN215478970U (en) Electric cable winding and unwinding shaft bracket
CN219775296U (en) String type inverter lifting mounting bracket
CN113233322B (en) Hoisting device and method for mounting mine electromechanical equipment
CN217498538U (en) Axle pulley winding displacement structure and elevating gear
CN217264545U (en) Electric overhead installation crane of power plant
CN220351400U (en) Wire rope coils exhibition and puts device
CN220703087U (en) Winding wire rope winding device for winding drum of high-altitude hoisting lifting equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant