CN220486477U - Lattice column for pre-welding straight thread steel bars - Google Patents

Lattice column for pre-welding straight thread steel bars Download PDF

Info

Publication number
CN220486477U
CN220486477U CN202322272059.3U CN202322272059U CN220486477U CN 220486477 U CN220486477 U CN 220486477U CN 202322272059 U CN202322272059 U CN 202322272059U CN 220486477 U CN220486477 U CN 220486477U
Authority
CN
China
Prior art keywords
lattice column
steel bars
steel bar
head
thread
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322272059.3U
Other languages
Chinese (zh)
Inventor
王森林
沈子翔
李干
闫士帅
赵祎斐
申卢晨
杨宇权
王康
季昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Technology Construction Co Ltd
Original Assignee
China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Technology Construction Co Ltd filed Critical China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority to CN202322272059.3U priority Critical patent/CN220486477U/en
Application granted granted Critical
Publication of CN220486477U publication Critical patent/CN220486477U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a lattice column, which belongs to the technical field of steel bar pre-welding, in particular to a lattice column for pre-welding straight thread steel bars, comprising a concrete supporting beam, wherein a lattice column is arranged in a fixing hole on the concrete supporting beam, a plurality of double-head thread head steel bars are arranged on the lattice column, two ends of each of the plurality of double-head thread head steel bars are respectively connected with a steel bar straight thread sleeve in a threaded manner, and the other ends of each of the plurality of steel bar straight thread sleeve are respectively connected with a single-head thread head steel bar in a threaded manner; according to the utility model, through the size of the lattice column and the aperture of the bored pile, the middle section of steel bars are double-thread head steel bars, a plurality of double-thread head steel bars are fixed on the lattice column, the construction of the lattice column is completed, the earth excavation is completed, the single-thread head steel bars are connected by the steel bar straight thread sleeve, and the installation of horizontal bars is completed, so that the problems that the existing lattice column is welded on site after excavation, the welding time is long, the operation is complex and the welding quality is difficult to guarantee are solved.

Description

Lattice column for pre-welding straight thread steel bars
Technical Field
The utility model relates to the technical field of steel bar pre-welding, in particular to a lattice column for pre-welding a straight thread steel bar.
Background
The construction of deep foundation pit often uses lattice column stand as the vertical support of concrete horizontal support or stack bridge board, and lattice column top needs anchor in the concrete supporting beam or the stack bridge, and anchor position needs welded several rows of horizontal reinforcing bars have ensured with concrete joint strength. The common practice is to excavate the ends of the structural columns in the earth and then weld the horizontal bars of the lattice columns.
Based on the above prior art findings:
the existing lattice column is subjected to field welding after excavation, the welding time is long, the operation is complex, and the welding quality is difficult to guarantee.
Disclosure of Invention
In order to solve the technical problems, the utility model provides a lattice column for pre-welding straight thread steel bars, double-thread head steel bars are fixed on the lattice column, construction of the lattice column is completed, earth excavation is completed, and single-thread head steel bars are connected by steel bar straight thread sleeve.
The technical solution for realizing the purpose of the utility model is as follows: the utility model provides a lattice column of pre-welded straight screw thread reinforcing bar, includes a concrete supporting beam, set up the fixed orifices on the concrete supporting beam, placed the lattice column in the fixed orifices, the equal fixedly connected with of four sides of lattice column a plurality of double-end screw thread silk reinforcing bars, the equal spiro union in both ends of a plurality of double-end screw thread silk reinforcing bars have the straight screw thread silk sleeve of reinforcing bar, the equal spiro union in the other end of a plurality of straight screw thread silk sleeves of reinforcing bar has the single-end screw thread silk reinforcing bar.
In some embodiments, a plurality of connecting holes are formed in the inner wall of the concrete supporting beam, and the other ends of the plurality of single-head screw thread head steel bars extend into the plurality of connecting holes.
In certain embodiments, the lattice columns are square.
In some embodiments, a plurality of said rebar straight thread sleeves are stud joints.
Compared with the prior art, the utility model, its apparent advantage is:
according to the utility model, a plurality of double-end thread head steel bars are fixed on a lattice column according to a drawing, the construction of the lattice column is completed, the earth excavation is completed, the single-end thread head steel bars are connected by a steel bar straight thread sleeve, and the installation of horizontal bars is completed;
the problems that the existing lattice column is subjected to field welding after excavation, the welding time is long, the operation is complex, and the welding quality is difficult to guarantee are solved.
Drawings
The utility model is further explained below with reference to the drawings and examples:
FIG. 1 is a schematic diagram of an overall cross-sectional structure provided in one embodiment of the present utility model;
FIG. 2 is a schematic view of a lattice column and double-ended straight thread head rebar structure provided in one embodiment of the present utility model;
fig. 3 is a schematic diagram of a double-ended straight thread head rebar and a single-ended straight thread head rebar provided in an embodiment of the utility model;
fig. 4 is a schematic structural view of a steel bar straight thread sleeve according to an embodiment of the present utility model.
Reference numerals illustrate:
1. a concrete support beam; 2. lattice columns; 3. double-end thread head steel bar; 4. single-head screw thread head steel bar; 5. a steel bar straight thread sleeve.
Detailed Description
The following detailed description of the present utility model clearly and fully describes the technical solutions of the embodiments of the present utility model, and it is apparent that the described embodiments are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
The utility model provides a lattice column for pre-welding a straight thread steel bar by improving the lattice column, which comprises the following technical scheme:
as shown in fig. 1-2, a lattice column for pre-welding straight thread steel bars comprises a concrete supporting beam 1, wherein a fixing hole is formed in the concrete supporting beam 1, a lattice column 2 is placed in the fixing hole, a plurality of double thread wire head steel bars 3 are fixedly connected to four sides of the lattice column 2, a welding mode is specifically adopted for fixing, two ends of the double thread wire head steel bars 3 are respectively and conveniently operated, a steel bar straight thread wire sleeve 5 is respectively and conveniently operated, a single thread wire head steel bar 4 is respectively and conveniently connected to the other ends of the steel bar straight thread wire sleeve 5 in a screwed mode through bolts of the steel bar straight thread wire sleeve 5; by means of the structure, the pre-welding connection of the device is achieved through the arrangement of the lattice column 2 and the double-thread head steel bar 3, and the post-bolt installation is facilitated.
As shown in fig. 1, in one embodiment, in order to ensure the connection strength with the concrete, a plurality of connection holes are formed on the inner wall of the concrete support beam 1, and the other ends of the plurality of single-head screw thread head steel bars 4 extend into the plurality of connection holes, specifically, the other ends of the single-head screw thread head steel bars 4 are placed in the concrete; by means of the structure, connection between concrete is achieved through the arrangement of the single-head thread head steel bars 4, and the lattice column 2 is firmer.
As shown in fig. 4, in one embodiment, the lattice columns 2 are square; by means of the structure, through square arrangement, the lattice column 2 is not easy to overflow when poured into concrete, and is convenient to install.
As shown in fig. 4, in one embodiment, a plurality of rebar straight thread bushings 5 are employed with a stud joint; by means of the structure, through the arrangement of the stud joint, the bolt connection between the stud wire head reinforcing steel bar 3 and the single-head stud wire head reinforcing steel bar 4 is achieved, and the operation is convenient.
The specific working method is as follows: when the horizontal rib structure is used, the length, the specification and the model of the horizontal rib welded at the upper end of the lattice column 2 are determined according to a construction drawing, then the horizontal rib structure is divided into three sections according to the size of the lattice column 2 and the aperture of a bored pile, the reinforcing steel bars at the middle section are double-thread wire head reinforcing steel bars 3, then a plurality of double-thread wire head reinforcing steel bars 3 are fixed on the lattice column 2 according to the drawing, the construction of the lattice column 2 is completed, the earth excavation is completed, the single-thread wire head reinforcing steel bars 4 are connected by the reinforcing steel bar straight thread wire sleeve 5, and the installation of the horizontal rib is completed.
The technical means disclosed by the scheme of the utility model is not limited to the technical means disclosed by the technical means, and also comprises the technical scheme consisting of the technical characteristics and the equivalent substitution. The present utility model is not limited to the prior art.

Claims (4)

1. Lattice column of pre-welded straight screw steel bar, including concrete supporting beam (1), its characterized in that: the concrete support beam (1) is provided with a fixing hole, a lattice column (2) is placed in the fixing hole, a plurality of double-end screw thread head steel bars (3) are fixedly connected to four sides of the lattice column (2), two ends of each double-end screw thread head steel bar (3) are respectively connected with a steel bar straight thread wire sleeve (5) in a threaded mode, and the other ends of each steel bar straight thread wire sleeve (5) are respectively connected with a single-end screw thread head steel bar (4) in a threaded mode.
2. A pre-welded straight rebar lattice column according to claim 1, wherein: the inner wall of the concrete supporting beam (1) is provided with a plurality of connecting holes, and the other ends of the single-head thread head reinforcing steel bars (4) extend into the connecting holes.
3. A pre-welded straight rebar lattice column according to claim 1, wherein: the lattice column (2) is square.
4. A pre-welded straight rebar lattice column according to claim 1, wherein: a plurality of the steel bar straight thread wire sleeves (5) are stud joints.
CN202322272059.3U 2023-08-23 2023-08-23 Lattice column for pre-welding straight thread steel bars Active CN220486477U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322272059.3U CN220486477U (en) 2023-08-23 2023-08-23 Lattice column for pre-welding straight thread steel bars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322272059.3U CN220486477U (en) 2023-08-23 2023-08-23 Lattice column for pre-welding straight thread steel bars

Publications (1)

Publication Number Publication Date
CN220486477U true CN220486477U (en) 2024-02-13

Family

ID=89825185

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322272059.3U Active CN220486477U (en) 2023-08-23 2023-08-23 Lattice column for pre-welding straight thread steel bars

Country Status (1)

Country Link
CN (1) CN220486477U (en)

Similar Documents

Publication Publication Date Title
CN202767252U (en) Inner separating board type concrete filled square steel tube column and H type girder semi-rigid node
CN208918018U (en) A kind of prefabricated assembled concrete shock-resistant node
CN109372129A (en) The novel full assembly concrete frame joint of one kind and its construction method
CN112112264A (en) Prefabricated column connecting joint for dry connection and construction method
CN108005267A (en) A kind of yi word pattern assembled stem steel plate shear force wall and its assembling constructing method
CN204753812U (en) Reinforced concrete frame structure
CN220486477U (en) Lattice column for pre-welding straight thread steel bars
CN212689211U (en) Prefabricated column connecting joint for dry-type connection
CN209874078U (en) Fast-spliced H-shaped steel concrete column and reinforced concrete beam connecting node
CN206737115U (en) A kind of steel core concrete column and steel beam connecting joint
CN215758594U (en) Widened pier column steel column tie beam device
CN206635801U (en) A kind of deep water waters bridge construction tower-crane foundation structure
CN204850068U (en) Connection structure of side column and crane beam tip in steel construction
CN210459181U (en) New and old ground is wall T joint design node even
CN211690803U (en) Novel rigid connection structure of H-shaped steel beam and concrete shear wall
CN103628685B (en) A kind of method and concrete pump pipe bracing means preventing concrete pump pipe lateral displacement
CN111980017A (en) Broken pile reinforcing structure and method for large-diameter cast-in-place pile
CN112609822A (en) Assembled reinforced concrete beam column node
CN218933110U (en) Anchor structure suitable for steel-pipe pile
CN214994032U (en) Recyclable foundation bolt positioning device
CN214657706U (en) Connecting device between assembled reinforced concrete column unit and node
CN218622608U (en) Connecting joint of beam steel reinforcement framework and steel column
CN219241073U (en) Steel bar connecting member in steel reinforced concrete column
CN215562538U (en) Precast pile splicing device permeates water
CN219951968U (en) Retaining plate structure between support piles

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant