CN215562538U CN202122034928.XU CN202122034928U CN215562538U CN 215562538 U CN215562538 U CN 215562538U CN 202122034928 U CN202122034928 U CN 202122034928U CN 215562538 U CN215562538 U CN 215562538U
Authority
CN
China
Prior art keywords
connecting piece
connection
spacing
wall
flow guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122034928.XU
Other languages
Chinese (zh)
Inventor
李刚
刘洁
刘永超
陆鸿宇
张阳
王玉琢
孙登峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN JIANCHENG JIYE GROUP CO Ltd
Original Assignee
TIANJIN JIANCHENG JIYE GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN JIANCHENG JIYE GROUP CO Ltd filed Critical TIANJIN JIANCHENG JIYE GROUP CO Ltd
Priority to CN202122034928.XU priority Critical patent/CN215562538U/en
Application granted granted Critical
Publication of CN215562538U publication Critical patent/CN215562538U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a water-permeable precast pile splicing device which comprises a first connecting piece, a second connecting piece, a flow guide structure and a protection structure, wherein the first connecting piece penetrates through the inner wall of the protection structure and is fixedly connected to the second connecting piece, the inner wall of the first connecting piece and the inner wall of the second connecting piece are respectively and fixedly connected to the flow guide structure, and the outer wall of the first connecting piece and the outer wall of the second connecting piece are respectively and fixedly sleeved in the protection structure. The pile splicing device for the permeable precast pile is simple in structure and reasonable in design, prefabricated parts at two ends are easy to butt joint through the first connecting piece and the second connecting piece, time and labor are saved, the connection strength can be enhanced through the flow guide structure, the inner wall of the flow guide structure is provided with the flow guide grooves, concrete is poured after pile sinking, the concrete poured in the pipe is mixed and exhausted, the phenomenon that the pipe is greatly hollow is avoided, the joints of the prefabricated parts at two ends are high in strength due to the arrangement of the protection structure, the transverse load resistance is sufficient, and the prefabricated parts at two ends are not easy to break.

Description

Precast pile splicing device permeates water
Technical Field
The utility model belongs to the technical field of precast piles, and particularly relates to a water-permeable precast pile splicing device.
Background
A precast pile is a pile (such as a wood pile, a concrete square pile, a prestressed concrete pipe pile, a steel pile and the like) made of various materials and in various forms on a co-production construction site, when in use, pile sinking equipment is used for driving the pile into the soil, pressing or vibrating the pile into the soil, wherein the concrete precast pile can bear larger load, is firm and durable and has high construction speed, and becomes one of pile types widely applied in the prior construction, but due to the influence of factors such as transportation and the like, the concrete precast pile can only be processed in sections, for the construction site using a longer precast column, the pile splicing construction of the sectioned precast pile is required in the field construction process, the prior precast pile is widely used in the field of construction, two concrete square piles which are adjacent up and down need to be connected together in the construction process, the prior art adopts the welding direction for connecting the two adjacent precast piles, in the welding process, low-carbon steel plates are embedded in the side faces and the end faces of four corners of the end parts of the upper pile and the lower pile, and the surfaces of the low-carbon steel plates are kept clean. When the lower pile is driven to the operation height convenient for welding (about 1m from the ground and the pile tip is enabled to avoid a hard soil interlayer), the upper pile is lifted by the pile frame and is aligned to the lower pile head. The verticality is corrected in two directions which mutually form 90 degrees by using an instrument, the uneven position of a joint gap is filled with an iron sheet and is firmly welded with an embedded iron plate on the end face of the pile. The inspection is errorless the back, with spot welding with four corners angle connector and pre-buried steel sheet temporary welding, inspect position and straightness back that hangs down once more, weld by two welders diagonal angle symmetry immediately, it is crooked to prevent that the node from arousing the end body because temperature stress produces welding deformation in the welding, need guarantee the coaxial coupling of both sides prefab all the time at the pile extension in-process, the precision that this kind of pile extension mode required is high, the construction degree of difficulty is big, work efficiency is low, and weld seam intensity is lower, anti transverse load is not enough, the prefab that leads to both ends takes place easily and breaks under the transverse load effect of job site, connection work at every turn needs two staff's cooperation at least in addition just can accomplish, consuming time and consuming effort, the practicality is not strong.
Disclosure of Invention
In view of this, the present invention provides a permeable precast pile splicing device to solve the problems of the prior art that precast piles are not suitable for butt joint, consume time and labor, and have poor practicability.
In order to achieve the purpose, the technical scheme of the utility model is realized as follows:
the utility model provides a precast pile splicing device permeates water, includes connecting piece, No. two connecting pieces, water conservancy diversion structure and protective structure, the one end fixed connection of a connecting piece is to the pile body No. one, and the other end passes No. two connecting pieces of protective structure inner wall fixed connection, No. two connecting piece bottom fixed connection to the pile body No. two, and a connecting piece inner wall and No. two connecting piece inner walls fixed connection to water conservancy diversion structure respectively, and a connecting piece outer wall and No. two connecting piece outer walls are fixed cup joint to in the protective structure respectively.
Further, a connecting piece includes a connection body, a spacing and a limiting plate, and a connection body is hollow structure, a connection body top fixed connection to pile body No. one, bottom fixed connection to spacing, and a protection architecture fixed connection to connecting piece top No. two is passed to the other end of spacing, a connection body bottom has seted up a draw-in groove No. one, is equipped with a limiting plate in the draw-in groove No. one, and a limiting plate is used for the connecting piece No. two of joint, and a connection body inner wall is equipped with an internal thread, and a connection body is through an internal thread fixed connection to flow structure upper portion No. one.
Further, No. two connecting pieces include No. two connection bodies, No. two spacing and No. two limiting plates, and No. two connection bodies are hollow structure, No. two connection body bottom fixed connection to No. two pile bodies, and top fixed connection to No. two spacing, No. two spacing other ends pass protection architecture fixed clamping and connect to a draw-in groove in, No. two connection bodies have inside seted up No. two draw-in grooves, are equipped with No. two limiting plates in No. two draw-in grooves, and No. two limiting plates are used for a spacing of joint, and No. two connection body inner walls are equipped with No. two internal threads, and No. two connection bodies are through No. two internal thread fixed connection to the flow structure lower part.
Further, the water conservancy diversion structure includes the water conservancy diversion body, and the water conservancy diversion body is hollow structure, and the guiding gutter has been seted up to water conservancy diversion body inside, and the guiding gutter is helical structure, and water conservancy diversion body outside is equipped with the external screw thread, and the external screw thread uses with internal thread, No. two internal screw-thread cooperations.
Further, protective structure includes a protective layer and No. two protective layers, and a protective layer, No. two protective layer structures are the same, and a protective layer both sides are fixed connection respectively to No. two protective layer both sides, and the two forms hollow cylinder structure, and the inside fixed joint of hollow cylinder structure connects body, No. two and connects the body.
Further, a protective layer includes a protection body, a joint ring, 2 a bolt board and a plurality of joint board, a protection body is the ring channel structure, a protection body both sides are equipped with a bolt board respectively, a plurality of joint boards of protection body outer wall circumference equipartition, a protection body inner wall middle part is equipped with a joint ring of a body structure, a joint ring is last to be equipped with and to set up a plurality of through-holes, a through-hole is used for using with spacing, No. two spacing cooperation.
Compared with the prior art, the water-permeable precast pile splicing device has the following advantages:
(1) the pile splicing device for the permeable precast pile is simple in structure and reasonable in design, prefabricated parts at two ends are easy to butt joint through the first connecting piece and the second connecting piece, time and labor are saved, the connection strength can be enhanced through the flow guide structure, the inner wall of the flow guide structure is provided with the flow guide grooves, concrete is poured after pile sinking, the concrete poured in the pipe is mixed and exhausted, the phenomenon that the pipe is greatly hollow is avoided, the joints of the prefabricated parts at two ends are high in strength due to the arrangement of the protection structure, the transverse load resistance is sufficient, and the prefabricated parts at two ends are not easy to break.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate an embodiment of the utility model and, together with the description, serve to explain the utility model and not to limit the utility model. In the drawings:
fig. 1 is a schematic structural diagram of a water-permeable precast pile splicing device according to an embodiment of the present invention;
fig. 2 is a cross-sectional view of the overall structure of a water-permeable precast pile splicing device according to an embodiment of the present invention;
FIG. 3 is an enlarged view of A in FIG. 2;
fig. 4 is a schematic view of a flow guiding structure of a pile splicing device for water-permeable precast piles according to an embodiment of the present invention;
fig. 5 is a sectional view of a flow guiding structure of a water permeable precast pile splicing device according to an embodiment of the present invention;
fig. 6 is a schematic view of a protection structure of a water permeable precast pile splicing device according to an embodiment of the present invention;
fig. 7 is a schematic view of a protective layer of a water permeable precast pile splicing device according to an embodiment of the present invention.
Description of reference numerals:
1. a first connecting piece; 11. the first connecting body; 111. a first card slot; 112. a first internal thread; 12. a first limit strip; 13. a first limiting plate; 131. a first baffle plate; 132. a first spring; 2. a second connecting piece; 21. the second connecting body; 211. a second card slot; 212. a second internal thread; 22. a second limit strip; 23. a second limiting plate; 231. a second baffle plate; 232. a second spring; 3. a flow guide structure; 31. a flow guide body; 311. a diversion trench; 312. an external thread; 4. a protective structure; 41. a first protective layer; 411. a protection body I; 412. a first snap ring; 413. a first bolt plate; 414. a first clamping plate; 42. a second protective layer; 5. a first pile body; 6. pile body II.
Detailed Description
It should be noted that the embodiments and features of the embodiments may be combined with each other without conflict.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on those shown in the drawings, and are used only for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present invention. Furthermore, the terms "first", "second", etc. are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first," "second," etc. may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless otherwise specified.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art through specific situations.
The present invention will be described in detail below with reference to the embodiments with reference to the attached drawings.
As shown in fig. 1 to 7, a precast pile splicing device permeates water, including connecting piece 1, No. 2, water conservancy diversion structure 3 and protective structure 4, the one end fixed welding of connecting piece 1 connects to pile body 5 No. one, and the other end passes 4 inner walls of protective structure fixed joint to No. 2 connecting piece, and No. 2 bottom fixed welding of connecting piece connects to pile body 6 No. two, and when actually connecing the stake, connecting piece 1 and pile body 5 No. one, and connecting piece 2 and pile body 6 No. two both can the welding set up, also can pass through the screw connection, prefabricate in advance when can also producing, form an organic whole structure, and connecting piece 1 inner wall and No. 2 inner walls of connecting piece are fixed welding respectively to water conservancy diversion structure 3, and connecting piece 1 outer wall and No. 2 outer walls of connecting piece are fixed welding protective structure 4 respectively. This pile extension device simple structure, reasonable in design makes the prefab at both ends dock easily through connecting piece 1, No. 2 connecting pieces of a, and 3 inner walls of its water conservancy diversion structure are equipped with the guiding gutter for pile sinking back cast concrete, mix and the exhaust the concrete of pouring in the geminate transistors, avoid causing intraductal great cavity that appears, the setting up of its protective structure 4 makes the prefab interface intensity at both ends high, and anti transverse load is sufficient, and the prefab at both ends is difficult to the emergence fracture.
In another embodiment, the first connecting piece 1 comprises a first connecting body 11, 4-6 first limiting plates 13 and 4-6 first limiting strips 12, the second connecting piece 2 comprises a second connecting body 21, 4-6 second limiting plates 23 and 4-6 second limiting strips 22, the first connecting body 11 and the second connecting body 21 are both hollow structures, the top of the first connecting body 11 is fixedly connected to the first pile body 5, the bottom of the first connecting body is circumferentially and uniformly and fixedly connected to the first limiting strips 12, the other end of the first limiting strips 12 penetrates through the protective structure 4 to be fixedly connected to the top of the second connecting piece 2, 4-6 first clamping grooves 111 are formed in the first connecting body 11, the first limiting plates 13 are respectively arranged in each first clamping groove 111, the first limiting plates 13 are used for clamping the second limiting strips 22, the inner wall of the first connecting body 11 is provided with a first internal thread 112, the first connecting body 11 is fixedly connected to the upper portion of the flow structure 3 through the first internal thread 112. No. two connection bodies 21 bottom fixed connection to pile body 6 No. two, the even fixed connection of top circumference is to No. two spacing 22, and No. two spacing 22's the other end passes protection architecture 4 fixed snap-on to be connected in draw-in groove 111, No. two connection bodies 21 are inside to have seted up 4-6 No. two draw-in grooves 211, are equipped with a No. two limiting plates 23 in every No. two draw-in grooves 211, and No. two limiting plates 23 are used for a spacing 12 of joint, and No. two connection bodies 21 inner walls are equipped with No. two internal threads 212, and No. two connection bodies 21 are through No. two internal threads 212 fixed connection to the 3 lower parts of class structure, and No. one spacing 12 and No. two spacing 22 are L type structure, No. one limiting plate 13, No. two limiting plates 23 are the arc structure, and No. one draw-in groove 111, No. two draw-in grooves 211 are the arc groove structure to be applicable to No. one spacing 12 of joint and No. two spacing 22.
Connecting piece 1 includes a connection body 11, a spacing 12 and a limiting plate 13, No. two connecting pieces 2 include No. two connection bodies 21, No. two spacing 22 and No. two limiting plates 23, and a connection body 11, No. two connection bodies 21 are hollow structure, and a connection body 11 top fixed connection to pile body 5, bottom fixed connection to a spacing 12, and the other end of a spacing 12 passes No. 4 fixed connection of protection architecture to No. 2 tops of connecting piece, a connection body 11 is inside to have seted up a draw-in groove 111, is equipped with a limiting plate 13 in a draw-in groove 111, and a limiting plate 13 is used for two spacing 22 of joint, and a connection body 11 inner wall is equipped with internal thread 112 No. one, and a connection body 11 is through internal thread 112 fixed connection to 3 upper portions of flow structure. The bottom of the second connecting body 21 is fixedly connected to the second pile body 6, the top is fixedly connected to the second limiting strip 22, the other end of the second limiting strip 22 passes through the protection structure 4 to be fixedly clamped in the first clamping groove 111, a second clamping groove 211 is formed in the second connecting body 21, a second limiting plate 23 is arranged in the second clamping groove 211, the second limiting plate 23 is used for clamping a first limiting strip 12 in a clamping mode, a second internal thread 212 is arranged on the inner wall of the second connecting body 21, the second connecting body 21 is fixedly connected to the lower portion of the flow structure 3 through the second internal thread 212, the first limiting strip 12 and the second limiting strip 22 are both hook-shaped structures, and the first clamping groove 111 and the second clamping groove 211 are both annular groove structures, so that be applicable to No. one spacing 12 of joint and No. two spacing 22, the prefab of a connecting piece 1, No. two connecting pieces 2 makes both ends butt joint easily, and joint strength is high moreover.
The first limiting plate 13 and the second limiting plate 23 are identical in structure and both are annular structures, the first limiting plate 13 comprises a first baffle 131 and a first spring 132, one end of the first spring 132 is fixed to one side of the inner wall of the first clamping groove 111, the other end of the first spring 132 is fixed to the first baffle 131, the cross section of the first baffle 13 is of a U-shaped structure, the two sides of the U-shaped structure are of the existing telescopic sleeve structure, contraction and extension of the first spring 132 are facilitated in cooperation, and in actual use, the second limiting strip 22 penetrates through the first baffle 131 to extrude the first spring 132 to contract, so that the second limiting strip 22 is clamped in the first clamping groove 111;
no. two limiting plates 23 include No. two baffles 231, No. two springs 232's one end is fixed to No. two draw-in groove 211 inner wall one sides, No. two springs 232's the other end is fixed to No. two baffles 231, No. two baffle 231 cross sections are the U-shaped structure, and the both sides of U-shaped structure are for being current telescopic sleeve structure, be convenient for cooperate No. two springs 232 shrink and extension, when the in-service use, No. 12 spacing bars pass No. two baffles 231, the shrink of No. two springs 232 of extrusion, thereby make 12 joint of spacing bars in No. two draw-in grooves 211.
The flow guide structure 3 comprises a flow guide body 31, the flow guide body 31 is of a hollow structure, a flow guide groove 311 is formed in the flow guide body 31, the flow guide groove 311 is of a spiral structure, the spiral structure is arranged to mix and exhaust concrete poured in a pipe conveniently, large hollow space in the pipe is avoided, an external thread 312 is arranged outside the flow guide body 31, the external thread 312 is matched with the internal thread 112 and the internal thread 212 to be used, the upper section of the external thread 312 is in threaded connection with the internal thread 112, and the lower section of the external thread 312 is in threaded connection with the internal thread 212.
Protection architecture 4 includes a protective layer 41 and No. two protective layers 42, and a protective layer 41, No. two protective layers 42 structure is the same, and a protective layer 41 both sides difference fixed connection to No. two protective layers 42 both sides, and the two forms hollow cylinder structure, and connecting body 11, No. two connecting body 21 of the inside fixed joint of hollow cylinder structure. The setting of protection architecture 4 makes the prefab interface intensity at both ends high, and anti transverse load is sufficient, and the prefab at both ends is difficult to the emergence fracture.
The first protective layer 41 comprises a first protective body 411, a first clamping ring 412, 2 first bolt plates 413 and 2-4 first clamping plates 414, the first protective body 411 is of an annular groove structure, two sides of the first protective body 411 are respectively provided with the first bolt plates 413, during actual production, a protection body 411 and a joint ring 412, 2 a bolt board 413, a joint board 414 both can set up as an organic whole, also can weld, a protection body 411 outer wall circumference equipartition 2-4 a joint board 414, a protection body 411 inner wall middle part fixed welding joint ring 412, be equipped with on a joint ring 412 and set up a plurality of through-holes, a through-hole is used for using with a spacing strip 12, No. two spacing strips 22 cooperation, a spacing strip 12 passes through a through-hole and fixes to No. two card grooves 211, No. two spacing strips 22 pass through a through-hole and fix to No. one card groove 111.
No. two protection bodies 42 include No. two protection bodies, No. two joint rings, No. 2 No. two bolt boards and No. 2-4 No. two joint boards, No. two protection bodies are the ring channel structure, No. two protection body both sides are equipped with a No. two bolt boards respectively, No. two protection body outer wall circumference equipartition No. 2-4 No. two joint boards, No. two protection body inner wall middle parts are equipped with No. two joint rings of a body structure, be equipped with on No. two joint rings and set up a plurality of No. two through-holes, No. two through-holes are used for cooperating with spacing 12, No. two spacing 22 and use, No. one spacing 12 passes No. two through-holes and fixes to No. two card grooves 211, No. two spacing 22 passes No. two through-holes and fixes to No. one card groove 111.
The utility model provides an installation of precast pile splicing device permeates water:
when pile splicing is actually needed, the method comprises the following steps:
s1, a worker fixedly connects the first connecting piece 1 with the first pile body 5 and fixedly connects the second connecting piece 2 with the second pile body 6;
s2, fixing and clamping the inner wall of the first pile body 5 with the flow guide structure 3 by a worker;
s3, the worker respectively clamps the first clamping ring 412 and the second clamping ring with the first connecting piece 1, and the first limiting strip 12 penetrates through the first through hole of the first clamping ring 412 (or the first limiting strip 12 penetrates through the second through hole of the second clamping ring);
s4, a worker fixedly clamps the inner wall of the second pile body 6 with the diversion structure 3, so that the first pile body 5 and the second pile body 6 are slowly connected together, meanwhile, the first limiting strip 12 is fixed into the second clamping groove 211, and the second limiting strip 22 of the second connecting piece 2 passes through the first through hole of the first clamping ring 412 and is fixed into the first clamping groove 111 (or the second limiting strip 22 passes through the second through hole of the second clamping ring and is fixed into the first clamping groove 111);
s5, fixedly connecting the first bolt plate 413 and the second bolt plate together by a screw rod, and then fastening and connecting the first pile body 5 and the second pile body 6, thereby completing the installation process of the water-permeable precast pile splicing device.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the utility model, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (6)

1. The utility model provides a precast pile splicing device permeates water which characterized in that: including connecting piece (1), No. two connecting pieces (2), water conservancy diversion structure (3) and protective structure (4), the one end fixed connection of a connecting piece (1) is a pile body (5), and the other end passes protective structure (4) inner wall fixed connection to No. two connecting pieces (2), No. two connecting piece (2) bottom fixed connection to No. two pile bodies (6), No. one connecting piece (1) inner wall and No. two connecting piece (2) inner wall fixed connection respectively to water conservancy diversion structure (3), and fixed cover is connected to protective structure (4) respectively to a connecting piece (1) outer wall and No. two connecting piece (2) outer walls.
2. A water permeable precast pile extension device according to claim 1, characterized in that: a connecting piece (1) includes a connection body (11), a spacing (12) and a limiting plate (13), and a connection body (11) is hollow structure, and a connection body (11) top fixed connection to pile body (5) No. one, bottom fixed connection to spacing (12) No. one, and the other end of a spacing (12) passes protection architecture (4) fixed connection to connecting piece (2) top No. two, No. one draw-in groove (111) has been seted up to connection body (11) bottom, is equipped with a limiting plate (13) in draw-in groove (111), and a limiting plate (13) is used for two connecting pieces of joint (2), and a connection body (11) inner wall is equipped with internal thread (112) No. one, and a connection body (11) is through internal thread (112) fixed connection to class structure upper portion No. one.
3. A water permeable precast pile extension device according to claim 2, characterized in that: no. two connecting piece (2) are including No. two connection body (21), No. two spacing (22) and No. two limiting plate (23), and No. two connection body (21) are hollow structure, and No. two connection body (21) bottom fixed connection to pile body (6) No. two, top fixed connection to No. two spacing (22), and the other end of No. two spacing (22) passes in protection architecture (4) fixed clamping connects to a draw-in groove (111), No. two connection body (21) inside has seted up No. two draw-in grooves (211), is equipped with No. two limiting plate (23) in No. two draw-in grooves (211), and No. two limiting plate (23) are used for joint a spacing (12), and No. two connection body (21) inner wall is equipped with No. two internal threads (212), and No. two connection body (21) are through No. two internal thread (212) fixed connection to class structure lower part.
4. A water permeable precast pile extension device according to claim 3, characterized in that: the flow guide structure (3) comprises a flow guide body (31), the flow guide body (31) is of a hollow structure, a flow guide groove (311) is formed in the flow guide body (31), the flow guide groove (311) is of a spiral structure, an external thread (312) is arranged outside the flow guide body (31), and the external thread (312) is matched with the first internal thread (112) and the second internal thread (212) for use.
5. A water permeable precast pile extension device according to claim 3, characterized in that: protection architecture (4) include protective layer (41) and No. two protective layers (42), and protective layer (41), No. two protective layers (42) structure are the same, and protective layer (41) both sides are fixed connection to No. two protective layer (42) both sides respectively, and the two forms the hollow cylinder structure, and body (11), No. two connection bodies (21) are connected to the inside fixed joint of hollow cylinder structure.
6. The water permeable precast pile extension device according to claim 5, characterized in that: a protective layer (41) includes a protection body (411), a joint ring (412), 2 a bolt board (413) and a plurality of joint board (414), a protection body (411) is the ring channel structure, a protection body (411) both sides are equipped with a bolt board (413) respectively, a protection body (411) outer wall circumference equipartition a plurality of joint board (414), a protection body (411) inner wall middle part is equipped with a joint ring (412) of a body structure, be equipped with on a joint ring (412) and set up a plurality of through-holes, a through-hole is used for using with a spacing (12), No. two spacing (22) cooperation.
CN202122034928.XU 2021-08-26 2021-08-26 Precast pile splicing device permeates water Active CN215562538U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122034928.XU CN215562538U (en) 2021-08-26 2021-08-26 Precast pile splicing device permeates water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122034928.XU CN215562538U (en) 2021-08-26 2021-08-26 Precast pile splicing device permeates water

Publications (1)

Publication Number Publication Date
CN215562538U true CN215562538U (en) 2022-01-18

Family

ID=79842850

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122034928.XU Active CN215562538U (en) 2021-08-26 2021-08-26 Precast pile splicing device permeates water

Country Status (1)

Country Link
CN (1) CN215562538U (en)

Similar Documents

Publication Publication Date Title
CN212078446U (en) Closed section column connecting structure
CN215562538U (en) Precast pile splicing device permeates water
CN211714001U (en) Inner supporting device for prefabricated plate moulding bed
CN112302163A (en) Connecting device for building beam and column and manufacturing method thereof
CN108166629A (en) A kind of detachable assembling type steel core concrete column-connected mode and its construction method
CN218597116U (en) Round tube body structure
CN113668703B (en) Direct-insertion type bolt-free connecting joint of closed cavity column and steel beam with three-layer ring plate structure
CN114197511B (en) Assembly type steel reinforced concrete light foundation and assembly method thereof
CN211899268U (en) Precast concrete post and pre-buried anchor slab connection structure
CN210685474U (en) Concrete underpins structure
CN211172363U (en) Vertical connecting steel node of prefabricated frame column of prefabricated concrete structure
CN210164054U (en) Quick butt joint and temporary fixing device for upper and lower layers of steel concrete composite pipe
CN113738102A (en) Template building block for civil engineering and manufacturing method and using method thereof
CN108661301B (en) Modular assembly platform for vertical frames of well frames and use method
CN210032628U (en) Supporting beam structure for building construction
CN213509708U (en) Ring beam underpinning and reinforcing structure of brick-concrete structure building
CN217027056U (en) Prefabricated PHC tubular pile connects connection structure
CN212866621U (en) Prefabricated welded steel bar net
CN217268786U (en) Sinking well scaffold anti-settling pull rod device
CN219364933U (en) Box assembled square steel tube structure module grouting anchoring node
CN219410923U (en) Side slope frame beam
CN219343162U (en) High-shear prestressed concrete pile
CN212026230U (en) Square bored concrete pile
CN214460464U (en) Assembled upright post pile
CN219156362U (en) Ladder type adduction building tower crane attachment device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant