CN220394678U CN202322326401.3U CN202322326401U CN220394678U CN 220394678 U CN220394678 U CN 220394678U CN 202322326401 U CN202322326401 U CN 202322326401U CN 220394678 U CN220394678 U CN 220394678U
Authority
CN
China
Prior art keywords
embedded
existing
steel
existing wood
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322326401.3U
Other languages
Chinese (zh)
Inventor
陈介华
黄晏林
余波
管浩
安斯杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Original Assignee
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Municipal Engineering Group Co Ltd filed Critical Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority to CN202322326401.3U priority Critical patent/CN220394678U/en
Application granted granted Critical
Publication of CN220394678U publication Critical patent/CN220394678U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to the technical field of wood structure engineering, in particular to a foundation reinforcing structure of an existing wood structure column, which comprises a steel member arranged on the existing wood structure column, wherein the steel member comprises a supporting member positioned above the ground and an embedded member embedded below the ground, the temporary supporting member is connected with the embedded member to form an integral structure, and the embedded member is embedded in concrete poured in the foundation range of the existing wood structure column. The utility model has the advantages that: the method not only can meet the demand of foundation replacement bearing capacity, but also can avoid the defect of longer concrete curing period, thereby meeting the demand of a propelling procedure, effectively improving the construction efficiency and shortening the construction time; the construction process is simple, the used components are convenient to manufacture, and the method is suitable for popularization.

Description

Existing wood structure cylinder foundation reinforcing structure
Technical Field
The utility model relates to the technical field of wood structure engineering, in particular to a foundation reinforcing structure of an existing wood structure column.
Background
At present, in the ancient building transformation process, because of the needs of transformation construction, often can need excavate ground, and the excavation then can cause timber post structure basis disturbance, for satisfying timber structure bearing stability requirement, avoids timber structure open caisson, adopts steel structure basis underpinning technical measure among the prior art often.
However, after the steel frame foundation and the ground concrete construction are completed, the wood column foundation is subjected to replacement reinforcement in situ, compared with the traditional concrete foundation replacement, the wood structure roof returning steel pipe cannot be removed in time due to the influence of the concrete curing period, the follow-up construction propulsion is affected, and the construction efficiency is low.
Disclosure of Invention
According to the defects of the prior art, the utility model provides the existing wood structure column foundation reinforcing structure, the steel structure is used for in-situ wood structure column foundation replacement, the defect of concrete curing age is avoided, and the construction progress of subsequent procedures is not influenced while the replacement of the foundation is realized.
The utility model is realized by the following technical scheme:
the utility model provides an existing wood constructs cylinder basis reinforced structure for replace the basis of existing wood constructs the cylinder, its characterized in that: the concrete pile comprises a steel member arranged on the existing wood structure column body, wherein the steel member comprises a supporting member positioned above the ground and an embedded member embedded below the ground, the supporting member is connected with the embedded member to form an integral structure, and the embedded member is embedded in concrete poured in the basic range of the existing wood structure column body.
The supporting member comprises a supporting plate and vertical channel steel, the supporting plate is arranged at the column bottom of the wood structure column body, and the vertical channel steel is arranged at the bottom of the supporting plate and connected with the embedded member.
The embedded member comprises an embedded steel box, the embedded steel box is composed of end plates on two sides and horizontal channel steel arranged between the end plates on two sides, two ends of the horizontal channel steel are respectively fixedly connected with the end plates on the corresponding sides, and the horizontal channel steel is connected with the supporting member.
And the periphery of the supporting member is filled with shrinkage grouting material or not.
And a C20 concrete cushion layer is arranged at the bottom of the concrete poured in the foundation range of the existing wood structure column body.
The support member and the embedded member are both prefabricated members.
The utility model has the advantages that: the method not only can meet the demand of foundation replacement bearing capacity, but also can avoid the defect of longer concrete curing period, thereby meeting the demand of a propelling procedure, effectively improving the construction efficiency and shortening the construction time; the construction process is simple, the used components are convenient to manufacture, and the method is suitable for popularization.
Drawings
FIG. 1 is a pillar bottom plan node map of the present utility model;
fig. 2 is a section A-A of fig. 1.
Description of the embodiments
The features of the utility model and other related features are described in further detail below by way of example in conjunction with the following figures to facilitate understanding by those skilled in the art:
as shown in fig. 1-2, the labels 1-9 are shown as: channel steel 1, existing timber construction column 2, backup pad 3, non-shrink grouting material 4, pre-buried steel box 5, C20 concrete cushion 6, expansion screw 7, once pour concrete 8, twice pour concrete 9.
Examples: as shown in fig. 1 and 2, the existing wood structure column foundation reinforcement structure in this embodiment is used for performing foundation replacement and reinforcement on the existing wood structure column 2 in the construction of ancient building reconstruction, so as to ensure the bearing performance of the existing wood structure column 2. In the present embodiment, the reconstruction construction refers to a reconstruction of the surrounding road surface (ground) of the existing wooden pillar 2, which is required for excavation construction.
Specifically, the foundation reinforcement structure in this embodiment includes a prefabricated steel member including a supporting portion mainly located on the ground and an embedded portion located below the ground, and the supporting portion is connected with the embedded portion below by its members and forms an integral stress structure, thereby ensuring that sufficient supporting effect can be provided for the existing wooden column 2.
Wherein the support part in the prefabricated steel member mainly comprises a support plate 3 and a vertically arranged channel steel 1, wherein the support plate 3 is arranged at the bottom position of the existing wood structure column 2, and the surface area of the support plate is larger than the diameter of the existing wood structure column 2, namely, the support plate 3 covers the bottom surface of the existing wood structure column 2. The vertically arranged channel steel 1 is arranged at the bottom of the supporting plate 3 and forms welded connection with the supporting plate 3.
The embedded part in the prefabricated steel component comprises an embedded steel box 5, the embedded steel box 5 comprises end plates on two sides and channel steel arranged between the end plates on two sides, the channel steel is a channel steel 1 which is horizontally arranged, two ends of the channel steel 1 are respectively connected with the end plates through expansion screws 7, and the end plates on two sides are connected and fixed to form an integral structure. In this embodiment, the channel steel vertically arranged by the supporting portion and the channel steel horizontally arranged by the embedded portion form a connection, so that the supporting portion and the embedded portion of the embedded steel member are connected to form an integral structure.
As shown in fig. 1 and 2, the foundation reinforcement structure in this embodiment further includes a secondary casting concrete 9 disposed within the foundation range of the existing timber structure column 2, where the secondary casting concrete 9 can embed the embedded steel box 5 and part of the vertically arranged channel steel 1 during casting, so as to provide support for the existing timber structure column 2.
As shown in fig. 2, in this embodiment, a C20 concrete cushion 6 is disposed below the secondary pouring concrete 9, and the C20 concrete cushion 6 mainly provides a flat pouring surface for the secondary pouring concrete 9, so as to ensure that the secondary pouring concrete 9 can be poured on a plane, and further ensure the quality of the foundation. During construction, the C20 concrete pad 9 may be placed under the foundation by excavation.
As shown in fig. 2, the outer periphery of the supporting portion of the prefabricated steel member is wrapped and filled with shrinkage grouting material 4 or not so as to protect the supporting plate 3 and the vertically arranged channel steel 1 and ensure the beautiful appearance of the outer elevation.
In the construction of this embodiment, as shown in fig. 1 and 2, the method includes the following steps:
1) After the reconstruction construction is finished, building ground concrete is poured firstly, and the building ground concrete is the one-time pouring concrete 8; during pouring, the basic range of the existing timber structure column 2 can be reserved in a mode of formwork supporting.
2) And (3) maintaining the building ground concrete (the primary pouring concrete 8) and synchronously constructing the steel member.
3) After the building ground concrete reaches the curing age, steel pipes are adopted to carry out back-roof supporting reinforcement on the wood structures around the existing wood structure columns 2, namely, related existing wood structures supported by the existing wood structure columns 2 are temporarily supported by adopting the steel pipes, so that instability and even damage of the related wood structures caused by insufficient supporting force due to the fact that the existing wood structure columns 2 carry out foundation replacement reinforcement are avoided.
4) And (5) removing the original filling soil of the foundation of the existing timber structure column 2.
5) The embedded part of the prefabricated steel member is installed at the design position and connected with the supporting part, and the pier of the existing timber structure column 2 is restored.
6) And pouring ground concrete in the basic range of the existing timber structure column 2, namely, secondarily pouring concrete 9.
7) And removing the supporting frame body of the existing timber structure column body 2.
8) And after the secondary pouring concrete 9 reaches the curing age, filling non-shrinkage grouting material 4 on the periphery of the supporting plate 3 and the vertically arranged channel steel 1.
In the embodiment, the prefabricated steel components and the staged construction mode are utilized, so that the foundation of the existing timber structure column 2 is replaced and reinforced in the construction process of the ancient building reconstruction.
The embodiment is implemented in specific manner: the primary casting concrete 8 and the secondary casting concrete 9 can be connected through transverse reinforcement to form an integral structure, so that the performance of the secondary casting concrete 9 is ensured. The transverse reinforcement is embedded in the construction of the primary casting concrete 8 and then embedded in the construction of the secondary casting concrete 9.
Although the foregoing embodiments have been described in some detail with reference to the accompanying drawings, it will be appreciated by those skilled in the art that various modifications and changes may be made thereto without departing from the scope of the utility model as defined in the appended claims, and thus are not repeated herein.

Claims (6)

1. The utility model provides an existing wood constructs cylinder basis reinforced structure for replace the basis of existing wood constructs the cylinder, its characterized in that: the concrete pile comprises a steel member arranged on the existing wood structure column body, wherein the steel member comprises a supporting member positioned above the ground and an embedded member embedded below the ground, the supporting member is connected with the embedded member to form an integral structure, and the embedded member is embedded in concrete poured in the basic range of the existing wood structure column body.
2. An existing timber column foundation stabilization structure according to claim 1, wherein: the supporting member comprises a supporting plate and vertical channel steel, the supporting plate is arranged at the column bottom of the wood structure column body, and the vertical channel steel is arranged at the bottom of the supporting plate and connected with the embedded member.
3. An existing timber column foundation stabilization structure according to claim 1, wherein: the embedded member comprises an embedded steel box, the embedded steel box is composed of end plates on two sides and horizontal channel steel arranged between the end plates on two sides, two ends of the horizontal channel steel are respectively fixedly connected with the end plates on the corresponding sides, and the horizontal channel steel is connected with the supporting member.
4. An existing timber column foundation stabilization structure according to claim 1, wherein: and the periphery of the supporting member is filled with shrinkage grouting material or not.
5. An existing timber column foundation stabilization structure according to claim 1, wherein: and a C20 concrete cushion layer is arranged at the bottom of the concrete poured in the foundation range of the existing wood structure column body.
6. An existing timber column foundation stabilization structure according to claim 1, wherein: the support member and the embedded member are both prefabricated members.
CN202322326401.3U 2023-08-29 2023-08-29 Existing wood structure cylinder foundation reinforcing structure Active CN220394678U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322326401.3U CN220394678U (en) 2023-08-29 2023-08-29 Existing wood structure cylinder foundation reinforcing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322326401.3U CN220394678U (en) 2023-08-29 2023-08-29 Existing wood structure cylinder foundation reinforcing structure

Publications (1)

Publication Number Publication Date
CN220394678U true CN220394678U (en) 2024-01-26

Family

ID=89604980

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322326401.3U Active CN220394678U (en) 2023-08-29 2023-08-29 Existing wood structure cylinder foundation reinforcing structure

Country Status (1)

Country Link
CN (1) CN220394678U (en)

Similar Documents

Publication Publication Date Title
CN107142856B (en) Abutment reconstruction method, abutment reconstruction pier and jacking reconstruction bridge
JP5666081B2 (en) Reconstruction method of existing bridge
KR100892137B1 (en) Rahmen typed underground tunnel construction method using lateral psc beam
CN107119917B (en) Increase the construction method of basement structure behind strip footing house
CN108265618B (en) Underground reverse storey-adding construction method for viaduct pier foundation
CN109594581B (en) River-crossing pipeline structure and installation method thereof
CN108589769B (en) Construction method of super-long rock-socketed T-shaped combined column plate high retaining wall
CN112411579B (en) Assembly type anchor rod frame beam structure containing EPS elastic cushion layer and suitable for expansive soil slope
CN106812359B (en) A kind of assembled underground garage and its method of construction
CN220394678U (en) Existing wood structure cylinder foundation reinforcing structure
CN108425374B (en) Integral construction method of steel suspension box cofferdam with tie beam dumbbell-shaped bearing platform under complex sea condition
KR20120100052A (en) Bridge leg correcting method using oil compressure jack and broken parts compensation structure
CN212247899U (en) Construction system for cast-in-place box girder at excavation section of existing line bridge-changing section in active service
CN211549324U (en) Bearing wall rear opening door hole structure
CN210621630U (en) Concrete panel rock-fill dam
KR102097122B1 (en) Precast mold for platform on piles system and concrete slab track construction method therewith
CN113266038A (en) Construction method for excavating underground building in foundation pit
CN105822079B (en) A kind of method for being used to control to increase structural column vertical deformation after basement
CN215857913U (en) Active retaining wall disease foam concrete repair structure
CN217810309U (en) Road and bridge crack reinforced structure based on prestressed concrete
CN114775673B (en) Construction method for pile foundation reserved pile supplementing and pile cap enlarging system
CN110820583B (en) Cast-in-place box girder support heightening foundation and construction method thereof
CN219653491U (en) Steel construction abutment suitable for steel trestle
CN112813852B (en) Repairing and reinforcing method for bridge deck subsidence of in-service bridge
CN220767747U (en) Railway basket arch bridge construction structure with large inclined span longitudinal slope underground double parallel structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant